Risk Register / Report
11 risks Costed Risks - Cash Flow
Risk Table
Title Key Status Description Category Pre-Rating Post-Rating Post-Cost Review Date
R Injuries onsite (1) Active Onsite injuries pose a significant risk on constructi Safety High High 5,000.00 Dec 31, 2023
R Budget Overruns (1) Active Risk of budget overruns in construction projects, a Financial/Fraud Low Very Low 0.00 Jan 31, 2024
R Quality Issues (2) Active Ensuring that the final construction meets the desi Capability High Very Low 0.00 Apr 30, 2024
R Weather-Related Delays (1) Active Adverse weather conditions such as heavy rain, sn Environment High Low 0.00 Dec 31, 2023
R Supply Chain Disruptions (1) Active Disruptions in the supply chain, such as material sh Capability High Medium 0.00
R Occupational Health and Safety Incidents (1) Active Accidents, injuries, or health issues among constru Safety Medium Very Low 0.00
R Design Changes (1) Active Changes in project design during construction can Capability Medium Very Low 0.00
R Regulatory Compliance Issues (1) Active Failure to comply with local regulations and buildin Legislative Compliance High Very Low 0.00
R Labor Shortages (1) Active Shortages in skilled labor or unexpected turnover c Financial/Fraud Very High Very Low 0.00
R Technology Failures (1) Active Failures in construction technology, such as projec Reputation Very Low Very Low 0.00
R Risk of injuries onsite (1) Active Falling objects hurt! Very High Very Low 0.00
Total Rows: 11