0% found this document useful (0 votes)
546 views11 pages

Types of Construction Certificates Explained

The document defines different types of certificates issued by architects during a construction project. Interim certificates certify work done and authorize progress payments with a retention amount held back. A penultimate certificate releases half the retention and includes approved variations. A practical completion certificate marks when construction is complete minus minor defects and triggers the defects liability period. A final certificate fully releases the contractor upon agreement of the final account, which reconciles payments made against the initial contract sum with deductions and additions.

Uploaded by

ANSLEM ALBERT
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
546 views11 pages

Types of Construction Certificates Explained

The document defines different types of certificates issued by architects during a construction project. Interim certificates certify work done and authorize progress payments with a retention amount held back. A penultimate certificate releases half the retention and includes approved variations. A practical completion certificate marks when construction is complete minus minor defects and triggers the defects liability period. A final certificate fully releases the contractor upon agreement of the final account, which reconciles payments made against the initial contract sum with deductions and additions.

Uploaded by

ANSLEM ALBERT
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

CERTIFICATES

Definition
Interim Certificate
Penultimate Certificate
Practical Completion Certificate
Sectional Completion Certificate
Certificate of Making Good Defects
Final Certificate
Definition
• An architect's certificate is either a payment advice or a
confirmation of work done by the contractor.
• The Standard Form of Contract makes a payment certification
process compulsory in a building contract
• The employer and other stakeholders rely on the architects
professional judgment in this respect
• If a payment advice, the architect in turn relies on the
recommendation of the QS through a valuation
• However, the architect is not bound to accept the totality of
the QS recommendation.
• There are many types of architects certificate
Interim Payment Certificate
• This is very important in the contract process
• It ensures adequate cash flow for the contract
• It also ensures that payment is tied to work done
• However, interim certificates are payments on
account; they are not indications of total
acceptance of the work
• Interim certificates are usually prepared monthly
by the architect based on the recommendation of
the QS.
Contents of Interim Certificate
• Part 1: Serial Number, Date of Issue, Title of
Project, Name of Architect, Name and address of
contractor, Contract Sum, etc
• Part 2: Value of work done to date, Materials on
site, Materials off site, Advances, Variations,
Claims, Retention (usually 5%)
• Part 3: Certification
• Distribution: original to client, a copy each to
contractor and QS, and a copy for the file
Treatment of Down Payment
• Down payments are often made to mitigate the effect
of inflation
• It can be made without an architects certificate but
thereafter the architect should formalise the payment
through a retrospective certificate
• Down payments are treated as interest free loan to the
contractor which will be repaid with work done
• Some period of moratorium may be allowed to enable
contractor achieve reasonable level of work before
commencement of repayment
Penultimate Certificate
• This is the payment certificate before the final
certificate
• It usually follows the issuance of the
certificate of practical completion
• It usually includes the release of one moiety of
retention ie half of the retention
• It also includes all approved variations issued
to date
Practical Completion Certificate
• Practical completion is achieved when the works
as envisaged in the agreement have been
completed and free from any patent defect. Minor
defects do not negate practical completion.
• Practical completion means that the building is
ready for occupation
• When in the opinion of the architect, practical
completion is achieved, a certificate is issued to
that effect stating the date it was achieved
Implications of Practical Completion

• Commencement of Defects Liability Period


• Release of one moiety of the retention
• Commencement of period for final
measurement leading to final account
• Releases contractor from liability with respect
to the insurance of the work
• Matters for arbitration which were dependent
on practical completion can commence
Final Certificate
• Final certificate is issued after the final accounts have been
agreed
• This is a certificate that fully releases the contractor from
all obligations with respect to the contract. However, it
does not release the contractor from any action bordering
on fraud
• The final certificate is generally seen as evidence that the
parties have completed and discharged their obligations
under the contract.
• It is also intended to be the final financial statement on the
project
Final Account Procedure
• A Final Account in building contracts is the final agreed
statement of the amount of money to be paid at the end
of a building contract by the employer to the contractor.
• It is usually prepared by the Consultant QS. However, the
contractors QS can generate a draft which can then be
discussed with the Consultant QS.
• At the end of final account, both parties must agree on the
final account – the Consultant QS representing the
employer and the contractors QS representing the
contractor before the account is presented to the architect
Final Account Content
1. Initial Contract Sum
[Link]:
i. PC Sums
ii. Provisional Sums
iii. Variation (Omissions)
iv. Contingency
v. Other amounts
3. Additions
vi. Amounts for nominated subcontractors
vii. Adjusted provisional sums
[Link] (Additions)
ix. Contractors Profit and attendance on nominated subcontracts
x. Loss and Expences

You might also like