0% found this document useful (0 votes)
11 views3 pages

Site Inspection

The document describes a site inspection report for a temple and ancillary building project. It lists 10 items needing work including disconnected flexible ducts, improper duct insulation cutting, and missing or improper sealant. The report provides details on the needed repairs, completion status photos, and assigns responsibility to 'OLIVEAIR' for all items.

Uploaded by

jadekvillanueva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views3 pages

Site Inspection

The document describes a site inspection report for a temple and ancillary building project. It lists 10 items needing work including disconnected flexible ducts, improper duct insulation cutting, and missing or improper sealant. The report provides details on the needed repairs, completion status photos, and assigns responsibility to 'OLIVEAIR' for all items.

Uploaded by

jadekvillanueva
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

SHINRYO (PHILIPPINES) COMPANY, INC.

Rm. 404-406 One Corporate Plaza Building, 845 A. Arnaiz


Ave.,
Makati City, Philippines 1223
Telephone: (632) 812-0083 Facsimile: (632) 812-5142/43

Project: JCLDS DAVAO Customer's Copy


Date Conducted: 18-Mar-2024 Subcon's Copy
Area: TEMPLE & ANCILLIARY BUILDING Preliminary
Final

SITE INSPECTION

COMPLETION STATUS REMARKS


ITEM
DEFINITION/DEFICIENCIES LOCATION PHOTO
NO.
PICTURE (AFTER) DATE Responsible

March 27,
TEMPLE UPPER LVL - CORRIDOR 229

2024

OLIVEAIR
Disconnected flexible
1
duct
Ancilliary - Exterion (North Side)

OLIVEAIR
Proper cutting and
2 termination of rubber
insulation
PLANT ROOM - ROOM DECK

OLIVEAIR
Sealant application on
3
duct transition
PLANT ROOM - ROOM DECK

OLIVEAIR

Install collar and apply


4 sealant on Exhaust Fan
unit
SHINRYO (PHILIPPINES) COMPANY, INC.
Rm. 404-406 One Corporate Plaza Building, 845 A. Arnaiz
Ave.,
Makati City, Philippines 1223
Telephone: (632) 812-0083 Facsimile: (632) 812-5142/43

Project: JCLDS DAVAO Customer's Copy


Date Conducted: 18-Mar-2024 Subcon's Copy
Area: TEMPLE & ANCILLIARY BUILDING Preliminary
Final

SITE INSPECTION

COMPLETION STATUS REMARKS


ITEM
DEFINITION/DEFICIENCIES LOCATION PHOTO
NO.
PICTURE (AFTER) DATE Responsible
PLANT ROOM - ROOM DECK

OLIVEAIR
Modification of screen
5
edge/connection
PLANT ROOM - ROOM DECK

Painting of corroded

OLIVEAIR
bolts, nuts and washer.
6
Installation of pvc cap
with sealant.
PLANT ROOM - ROOM DECK

OLIVEAIR
Rectify canvass tarp, too
7
stretch
PLANT ROOM - ROOM DECK

OLIVEAIR

Painting of corroded
8
panel of Exhaust Fan
PLANT ROOM - ROOM DECK

OLIVEAIR

Proper application of
9
sealant
SHINRYO (PHILIPPINES) COMPANY, INC.
Rm. 404-406 One Corporate Plaza Building, 845 A. Arnaiz
Ave.,
Makati City, Philippines 1223
Telephone: (632) 812-0083 Facsimile: (632) 812-5142/43

Project: JCLDS DAVAO Customer's Copy


Date Conducted: 18-Mar-2024 Subcon's Copy
Area: TEMPLE & ANCILLIARY BUILDING Preliminary
Final

SITE INSPECTION

COMPLETION STATUS REMARKS


ITEM
DEFINITION/DEFICIENCIES LOCATION PHOTO
NO.
PICTURE (AFTER) DATE Responsible
PLANT ROOM - ROOM DECK

OLIVEAIR
Make the same duct
10
transition

PREPARED BY: CHRISTIAN RAMIREZ


QA/QC

CHECKED BY: PHILIP GONZALO NOTED BY: ANTHONY REYES


PROJECT IN-CHARGE PROJECT MANAGER