Status Report

The project plan outlines various activities scheduled from July 2 to July 30, 2020, with a focus on completing functional specifications, development, testing, and user acceptance. Key tasks include customer acceptance and data migration, both of which are currently at 0% completion. The document also highlights accomplishments and mentions open risks and issues without specific details provided.

Uploaded by

Zeynep Beyhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views1 page

Status Report

The project plan outlines various activities scheduled from July 2 to July 30, 2020, with a focus on completing functional specifications, development, testing, and user acceptance. Key tasks include customer acceptance and data migration, both of which are currently at 0% completion. The document also highlights accomplishments and mentions open risks and issues without specific details provided.

Uploaded by

Zeynep Beyhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

Project title

Project Title Plan June July


Activity Start End %
Report Date CR - Func Spec approval 02.07.2020 03.07.2020 100%

% Complete % Project Status RAG CR approval 02.07.2020 03.07.2020 100%


CR development & Internal
06.07.2020 10.07.2020 100%
Baseline Delivery Date Projected Delivery Date tests
Dry Run 2 & Fixes 13.07.2020 15.07.2020 100%
Project Summary Dress Rehearsal 1 & Fixes 16.07.2020 17.07.2020 100%

UAT 20.07.2020 23.07.2020 90%

Customer Acceptance 24.07.2020 27.07.2020 0%


Updated Manual & Training
Videos
08.07.2020 09.07.2020 100%
Status/Accomplishments this week Super User Training 13.07.2020 15.07.2020 100%
Activity Date Update/Result Data Migration & Cutover 30.07.2020 30.07.2020 0%

1
2
Next Key Tasks/Activities planned next week
Activity Owner Start Date
3

Open Risks/Issues
Detail Impact Mitigation Action General Comments
1