Cronograma Valorizado Final
Cronograma Valorizado Final
ACTIVIDAD: “MANTENIMIENTO DEL CAMINO DE HERRADURA Y LIMPIEZA DE LOS CANALES DE RIEGO EN EL SECTOR HUAYOPAMPA DEL C.P. SAN ANDRES DE RUNTU DEL DISTRITO DE SAN MARCOS-HUARI-ANCASH”.
ENTIDAD: MUNICIPALIDAD DISTRITAL DE SAN MARCOS FECHA DE INICIO : 21/08/2023
MODALIDAD: ADMINISTRACION DIRECTA FECHA DE CULMINACION PROGRAMADO : 04/10/2023
PLAZO: 45 DIAS CALENDARIOS FECHA DE CULMINACION REAL : 04/10/2023
RESP. TEC: ING. JHONATAN MARINO VILLACAQUI HENOSTROZA CIP: N° 277231 MONTO DE EJECUCION : S/ 288,104.62
INSPECTOR: ING. YORDI URBANO FLOR ALVA CIP: N° 250907 DEPARTAMENTO : ANCASH
FECHA: 16/10/2023 PROVINCIA : HUARI
PERIODO: 21/08/2023 AL 04/10/2023 DISTRITO : SAN MARCOS
CENTRO POBLADO : SAN ANDRES DE RUNTU
SECTOR : HUAYOPAMPA
PRIMER MES ( "AGOSTO" 2023 ) SEGUNDO MES ("SETIEMBRE" 2023) TERCER MES ("OCTUBRE" 2023)
PRESUPUESTO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO
ITEM DESCRIPCION
(DEL 21/08/2023 AL 31/08/2023) (DEL 21/08/2023 AL 31/08/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/10/2023 AL 04/10/2023) (DEL 01/10/2023 AL 04/10/2023)
UND METRADO P.U. VALORIZACION METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION %
01 MANTENIMIENTO DE INFRAESTRUCTURA 3,450.00 920.00 26.67% 920.00 26.67% 2,300.00 66.67% 2,300.00 66.67% 230.00 6.67% 230.00 6.67%
01.01 ALMACENERO CON CASETA PARA ALMACEN mes 1.50 2,300.00 3,450.00 0.40 920.00 26.67% 0.40 920.00 26.67% 1.00 2,300.00 66.67% 1.00 2,300.00 66.67% 0.10 230.00 6.67% 0.10 230.00 6.67%
01.02 EQUIPOS E IMPLEMENTOS DE PROTECCIÓN 16,678.00 5,503.74 33.00% 5,503.74 0.00% 11,174.26 67.00% 11,174.26 0.00% 0.00 0.00% 0.00 0.00%
01.02.01 IMPLEMENTO DE SEGURIDAD INDIVIDUAL glb 1.00 16,623.00 16,623.00 0.33 5,485.59 33.00% 0.33 5,485.59 33.00% 0.67 11,137.41 67.00% 0.67 11,137.41 67.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.02.02 EQUIPO DE PROTECCION COLECTIVA glb 1.00 55.00 55.00 0.33 18.15 33.00% 0.33 18.15 33.00% 0.67 36.85 67.00% 0.67 36.85 67.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03 SEÑALIZACIÓN 180.00 59.40 33.00% 180.00 0.00% 120.60 67.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03.01 SEÑALIZACIÓN PARA LA ACTIVIDAD glb 1.00 180.00 180.00 0.33 59.40 33.00% 1.00 180.00 100.00% 0.67 120.60 67.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04 MANTENIMIENTO DEL CAMINO DE 28,771.92 0.00 0.00% 0.00 0.00% 28,771.92 100.00% 28,771.92 0.00% 0.00 0.00% 0.00 0.00%
01.04.01 DESBROCE DE MALEZAS m2 1400.00 2.82 3,948.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,400.00 3,948.00 100.00% 1,400.00 3,948.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 675.00 5.64 3,807.00 0.00 0.00 0.00% 0.00 0.00 0.00% 675.00 3,807.00 100.00% 675.00 3,807.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.03 PERFILADO Y NIVELACION DE LA m2 650.00 5.29 3,438.50 0.00 0.00 0.00% 0.00 0.00 0.00% 650.00 3,438.50 100.00% 650.00 3,438.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
ENCAUSAMIENTO DE PEQUEÑOS CURSOS DE
01.04.04 m 100.00 4.23 423.00 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00 423.00 100.00% 100.00 423.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
AGUA
01.04.05 DESQUINCHE EN TALUDES m3 45.00 28.21 1,269.45 0.00 0.00 0.00% 0.00 0.00 0.00% 45.00 1,269.45 100.00% 45.00 1,269.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.06 REMOCION DE DERRUMBES MENORES m3 60.90 33.85 2,061.47 0.00 0.00 0.00% 0.00 0.00 0.00% 60.90 2,061.47 100.00% 60.90 2,061.47 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.07 ELIMINACION DE MATERIAL EXCEDENTE m3 221.90 42.31 9,388.59 0.00 0.00 0.00% 0.00 0.00 0.00% 221.90 9,388.59 100.00% 221.90 9,388.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.08 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 1500.00 2.82 4,230.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,500.00 4,230.00 100.00% 1,500.00 4,230.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.09 MANTENIMIENTO DE MURO SECO , L = 205.91 0.00 0.00% 0.00 0.00% 205.91 100.00% 205.91 100.00% 0.00 0.00% 0.00 0.00%
01.04.09. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 3.20 21.16 67.71 0.00 0.00 0.00% 0.00 0.00 0.00% 3.20 67.71 100.00% 3.20 67.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.09. EXCAVACION EN CONGLOMERADO m3 0.80 42.31 33.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.80 33.85 100.00% 0.80 33.85 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.09. NIVELACION Y COMPACTADO m2 4.00 3.52 14.08 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 14.08 100.00% 4.00 14.08 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.09. COLOCACIÓN DE PIEDRA EN MURO SECO m3 3.20 28.21 90.27 0.00 0.00 0.00% 0.00 0.00 0.00% 3.20 90.27 100.00% 3.20 90.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05 MANTENIMIENTO DEL CAMINO DE 42,411.90 42,411.90 100.00% 42,411.90 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.01 DESBROCE DE MALEZAS m2 2769.50 2.82 7,809.99 2,769.50 7,809.99 100.00% 2,769.50 7,809.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.02 BACHEO EN PLATAFORMA DE CAMINO m2 1350.00 5.64 7,614.00 1,350.00 7,614.00 100.00% 1,350.00 7,614.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.03 PERFILADO Y NIVELACION DE LA m2 1183.00 5.29 6,258.07 1,183.00 6,258.07 100.00% 1,183.00 6,258.07 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
ENCAUSAMIENTO DE PEQUEÑOS CURSOS DE
01.05.04 m 100.00 4.23 423.00 100.00 423.00 100.00% 100.00 423.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
AGUA
01.05.05 DESQUINCHE EN TALUDES m3 45.00 28.21 1,269.45 45.00 1,269.45 100.00% 45.00 1,269.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.06 REMOCION DE DERRUMBES MENORES m3 40.60 33.85 1,374.31 40.60 1,374.31 100.00% 40.60 1,374.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.07 ELIMINACION DE MATERIAL EXCEDENTE m3 224.08 42.31 9,480.82 224.08 9,480.82 100.00% 224.08 9,480.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.08 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 2865.00 2.82 8,079.30 2,865.00 8,079.30 100.00% 2,865.00 8,079.30 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.09 MANTENIMIENTO DE MURO SECO, L = 102.96 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.09. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.09. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.09. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.09. COLOCACIÓN DE PIEDRA EN MURO SECO m3 1.60 28.21 45.14 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
MANTENIMIENTO DEL CAMINO DE
01.06 HERRADURA (CASA DE JULIO VARGAS - YANA 10,193.11 0.00 0.00% 0.00 0.00% 10,193.11 100.00% 10,193.11 100.00% 0.00 0.00% 0.00 0.00%
AYPA), L= 319.00 m.
Página 1 de 3
PRIMER MES ( "AGOSTO" 2023 ) SEGUNDO MES ("SETIEMBRE" 2023) TERCER MES ("OCTUBRE" 2023)
PRESUPUESTO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO
ITEM DESCRIPCION
(DEL 21/08/2023 AL 31/08/2023) (DEL 21/08/2023 AL 31/08/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/10/2023 AL 04/10/2023) (DEL 01/10/2023 AL 04/10/2023)
UND METRADO P.U. VALORIZACION METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION %
01.06.01 DESBROCE DE MALEZAS m2 925.10 2.82 2,608.78 0.00 0.00 0.00% 0.00 0.00 0.00% 925.10 2,608.78 100.00% 925.10 2,608.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 420.00 5.64 2,368.80 0.00 0.00 0.00% 0.00 0.00 0.00% 420.00 2,368.80 100.00% 420.00 2,368.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.03 PERFILADO Y NIVELACION DE LA m2 456.30 5.29 2,413.83 0.00 0.00 0.00% 0.00 0.00 0.00% 456.30 2,413.83 100.00% 456.30 2,413.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.04 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 957.00 2.82 2,698.74 0.00 0.00 0.00% 0.00 0.00 0.00% 957.00 2,698.74 100.00% 957.00 2,698.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.05 MANTENIMIENTO DE MURO SECO, L = 102.96 0.00 0.00% 0.00 0.00% 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00%
01.06.05. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00%
01.06.05. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.05. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.05. COLOCACIÓN DE PIEDRA EN MURO SECO m3 1.60 28.21 45.14 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07 MANTENIMIENTO DEL CAMINO DE 12,512.18 0.00 0.00% 0.00 0.00% 12,512.18 100.00% 12,512.18 100.00% 0.00 0.00% 0.00 0.00%
01.07.01 DESBROCE DE MALEZAS m2 1142.60 2.82 3,222.13 0.00 0.00 0.00% 0.00 0.00 0.00% 1,142.60 3,222.13 100.00% 1,142.60 3,222.13 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 420.00 5.64 2,368.80 0.00 0.00 0.00% 0.00 0.00 0.00% 420.00 2,368.80 100.00% 420.00 2,368.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.03 PERFILADO Y NIVELACION DE LA m2 658.80 5.29 3,485.05 0.00 0.00 0.00% 0.00 0.00 0.00% 658.80 3,485.05 100.00% 658.80 3,485.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.04 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 1182.00 2.82 3,333.24 0.00 0.00 0.00% 0.00 0.00 0.00% 1,182.00 3,333.24 100.00% 1,182.00 3,333.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.05 MANTENIMIENTO DE MURO SECO, L = 102.96 0.00 0.00% 0.00 0.00% 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00%
01.07.05. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.05. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.05. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.05. COLOCIÓN DE PIEDRA EN MURO SECO DE m3 1.60 28.21 45.14 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08 MANTENIMIENTO DEL CAMINO DE 10,749.69 0.00 0.00% 0.00 0.00% 10,749.69 100.00% 10,749.69 100.00% 0.00 0.00% 0.00 0.00%
01.08.01 DESBROCE DE MALEZAS m2 977.30 2.82 2,755.99 0.00 0.00 0.00% 0.00 0.00 0.00% 977.30 2,755.99 100.00% 977.30 2,755.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 420.00 5.64 2,368.80 0.00 0.00 0.00% 0.00 0.00 0.00% 420.00 2,368.80 100.00% 420.00 2,368.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.03 PERFILADO Y NIVELACION DE LA m2 504.90 5.29 2,670.92 0.00 0.00 0.00% 0.00 0.00 0.00% 504.90 2,670.92 100.00% 504.90 2,670.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.04 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 1011.00 2.82 2,851.02 0.00 0.00 0.00% 0.00 0.00 0.00% 1,011.00 2,851.02 100.00% 1,011.00 2,851.02 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.05 MANTENIMIENTO DE MURO SECO, L = 5.00 102.96 0.00 0.00% 0.00 0.00% 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00%
01.08.05. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.05. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.05. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.05. COLOCIÓN DE PIEDRA EN MURO SECO DE m3 1.60 28.21 45.14 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09 MANTENIMIENTO DEL CAMINO DE 21,427.91 0.00 0.00% 0.00 0.00% 21,427.91 100.00% 21,427.91 100.00% 0.00 0.00% 0.00 0.00%
01.09.01 DESBROCE DE MALEZAS m2 1241.20 2.82 3,500.18 0.00 0.00 0.00% 0.00 0.00 0.00% 1,241.20 3,500.18 100.00% 1,241.20 3,500.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 560.00 5.64 3,158.40 0.00 0.00 0.00% 0.00 0.00 0.00% 560.00 3,158.40 100.00% 560.00 3,158.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.03 PERFILADO Y NIVELACION DE LA m2 615.60 5.29 3,256.52 0.00 0.00 0.00% 0.00 0.00 0.00% 615.60 3,256.52 100.00% 615.60 3,256.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.04 REMOCION DE DERRUMBES MENORES m3 60.90 33.85 2,061.47 0.00 0.00 0.00% 0.00 0.00 0.00% 60.90 2,061.47 100.00% 60.90 2,061.47 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.05 ELIMINACION DE MATERIAL EXCEDENTE m3 135.37 42.31 5,727.50 0.00 0.00 0.00% 0.00 0.00 0.00% 135.37 5,727.50 100.00% 135.37 5,727.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.06 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 1284.00 2.82 3,620.88 0.00 0.00 0.00% 0.00 0.00 0.00% 1,284.00 3,620.88 100.00% 1,284.00 3,620.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.07 MANTENIMIENTO DE MURO SECO, L = 102.96 0.00 0.00% 0.00 0.00% 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00%
01.09.07. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.07. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.07. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09.07. COLOCIÓN DE PIEDRA EN MURO SECO DE m3 1.60 28.21 45.14 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10 MANTENIMIENTO DEL CAMINO DE 25,557.14 0.00 0.00% 0.00 0.00% 25,557.14 100.00% 25,557.14 100.00% 0.00 0.00% 0.00 0.00%
01.10.01 DESBROCE DE MALEZAS m2 1626.90 2.82 4,587.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1,626.90 4,587.86 100.00% 1,626.90 4,587.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 700.00 5.64 3,948.00 0.00 0.00 0.00% 0.00 0.00 0.00% 700.00 3,948.00 100.00% 700.00 3,948.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.03 PERFILADO Y NIVELACION DE LA m2 839.70 5.29 4,442.01 0.00 0.00 0.00% 0.00 0.00 0.00% 839.70 4,442.01 100.00% 839.70 4,442.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.04 REMOCION DE DERRUMBES MENORES m3 101.50 33.85 3,435.78 0.00 0.00 0.00% 0.00 0.00 0.00% 101.50 3,435.78 100.00% 101.50 3,435.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.05 ELIMINACION DE MATERIAL EXCEDENTE m3 101.50 42.31 4,294.47 0.00 0.00 0.00% 0.00 0.00 0.00% 101.50 4,294.47 100.00% 101.50 4,294.47 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.06 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 1683.00 2.82 4,746.06 0.00 0.00 0.00% 0.00 0.00 0.00% 1,683.00 4,746.06 100.00% 1,683.00 4,746.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.07 MANTENIMIENTO DE MURO SECO, L = 102.96 0.00 0.00% 0.00 0.00% 102.96 100.00% 102.96 100.00% 0.00 0.00% 0.00 0.00%
01.10.07. ACOPIO Y ACARREO DE PIEDRAS D<=100M m3 1.60 21.16 33.86 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 33.86 100.00% 1.60 33.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.07. EXCAVACION EN CONGLOMERADO m3 0.40 42.31 16.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.40 16.92 100.00% 0.40 16.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.07. NIVELACION Y COMPACTADO m2 2.00 3.52 7.04 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7.04 100.00% 2.00 7.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.07. COLOCIÓN DE PIEDRA EN MURO SECO DE m3 1.60 28.21 45.14 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 45.14 100.00% 1.60 45.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11 MANTENIMIENTO DEL CAMINO DE 8,107.50 0.00 0.00% 0.00 0.00% 8,107.50 100.00% 8,107.50 100.00% 0.00 0.00% 0.00 0.00%
01.11.01 DESBROCE DE MALEZAS m2 725.00 2.82 2,044.50 0.00 0.00 0.00% 0.00 0.00 0.00% 725.00 2,044.50 100.00% 725.00 2,044.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 700.00 5.64 3,948.00 0.00 0.00 0.00% 0.00 0.00 0.00% 700.00 3,948.00 100.00% 700.00 3,948.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11.03 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 750.00 2.82 2,115.00 0.00 0.00 0.00% 0.00 0.00 0.00% 750.00 2,115.00 100.00% 750.00 2,115.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.12 MANTENIMIENTO DEL CAMINO DE 2,853.84 0.00 0.00% 0.00 0.00% 2,853.84 100.00% 2,853.84 100.00% 0.00 0.00% 0.00 0.00%
01.12.01 DESBROCE DE MALEZAS m2 255.20 2.82 719.66 0.00 0.00 0.00% 0.00 0.00 0.00% 255.20 719.66 100.00% 255.20 719.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.12.02 BACHEO DE LA PLATAFORMA DEL CAMINO m2 246.40 5.64 1,389.70 0.00 0.00 0.00% 0.00 0.00 0.00% 246.40 1,389.70 100.00% 246.40 1,389.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.12.03 LIMPIEZA FINAL DEL AREA DE TRABAJO m2 264.00 2.82 744.48 0.00 0.00 0.00% 0.00 0.00 0.00% 264.00 744.48 100.00% 264.00 744.48 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.13 MANTENIMIENTO DEL CAMINO DE LA 36,357.69 0.00 0.00% 0.00 0.00% 36,357.69 100.00% 36,357.69 100.00% 0.00 0.00% 0.00 0.00%
Página 2 de 3
PRIMER MES ( "AGOSTO" 2023 ) SEGUNDO MES ("SETIEMBRE" 2023) TERCER MES ("OCTUBRE" 2023)
PRESUPUESTO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO
ITEM DESCRIPCION
(DEL 21/08/2023 AL 31/08/2023) (DEL 21/08/2023 AL 31/08/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/09/2023 AL 30/09/2023) (DEL 01/10/2023 AL 04/10/2023) (DEL 01/10/2023 AL 04/10/2023)
UND METRADO P.U. VALORIZACION METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION % METRADO VALORIZACION %
01.13.01 DESBROCE DE MALEZAS m2 2275.20 2.82 6,416.06 0.00 0.00 0.00% 0.00 0.00 0.00% 2,275.20 6,416.06 100.00% 2,275.20 6,416.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.13.02 BACHEO DE LA PLATAFORMA DE LA m2 5308.80 5.64 29,941.63 0.00 0.00 0.00% 0.00 0.00 0.00% 5,308.80 29,941.63 100.00% 5,308.80 29,941.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14 MANTENIMIENTO DEL CANAL DE RIEGO 16,548.87 0.00 0.00% 0.00 0.00% 16,548.87 100.00% 16,548.87 100.00% 0.00 0.00% 0.00 0.00%
01.14.01 LIMPIEZA DE CANAL m 1028.00 4.23 4,348.44 0.00 0.00 0.00% 0.00 0.00 0.00% 1,028.00 4,348.44 100.00% 1,028.00 4,348.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.02 DESBROCE DE LA FRANJA MARGINAL DEL m2 514.00 4.23 2,174.22 0.00 0.00 0.00% 0.00 0.00 0.00% 514.00 2,174.22 100.00% 514.00 2,174.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.03 DESCOLMATACION DEL CANAL m3 46.26 84.62 3,914.52 0.00 0.00 0.00% 0.00 0.00 0.00% 46.26 3,914.52 100.00% 46.26 3,914.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.04 REMOCION DE DERRUMBES MENORES m3 3.15 33.85 106.63 0.00 0.00 0.00% 0.00 0.00 0.00% 3.15 106.63 100.00% 3.15 106.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.05 ELIMINACION DE MATERIAL EXCEDENTE m3 141.93 42.31 6,005.06 0.00 0.00 0.00% 0.00 0.00 0.00% 141.93 6,005.06 100.00% 141.93 6,005.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15 MANTENIMIENTO DEL CANAL DE RIEGO 10,654.42 0.00 0.00% 0.00 0.00% 10,654.42 100.00% 10,654.42 100.00% 0.00 0.00% 0.00 0.00%
01.15.01 LIMPIEZA DE CANAL m 628.00 4.23 2,656.44 0.00 0.00 0.00% 0.00 0.00 0.00% 628.00 2,656.44 100.00% 628.00 2,656.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15.02 DESBROCE DE LA FRANJA MARGINAL DEL m2 314.00 4.23 1,328.22 0.00 0.00 0.00% 0.00 0.00 0.00% 314.00 1,328.22 100.00% 314.00 1,328.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15.03 DESCOLMATACION DEL CANAL m3 28.26 84.62 2,391.36 0.00 0.00 0.00% 0.00 0.00 0.00% 28.26 2,391.36 100.00% 28.26 2,391.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15.04 REMOCION DE DERRUMBES MENORES m3 2.10 33.85 71.09 0.00 0.00 0.00% 0.00 0.00 0.00% 2.10 71.09 100.00% 2.10 71.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15.05 ELIMINACION DE MATERIAL EXCEDENTE m3 99.44 42.31 4,207.31 0.00 0.00 0.00% 0.00 0.00 0.00% 99.44 4,207.31 100.00% 99.44 4,207.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16 MANTENIMIENTO DEL CANAL DE RIEGO 4,248.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,248.58 100.00% 4,248.59 100.00% 0.00 0.00%
01.16.01 LIMPIEZA DE CANAL m 238.00 4.23 1,006.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 238.00 1,006.74 100.00% 238.00 1,006.74 100.00% 0.00 0.00 0.00%
01.16.02 DESBROCE DE LA FRANJA MARGINAL DEL m2 119.00 4.23 503.37 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 119.00 503.37 100.00% 119.00 503.37 100.00% 0.00 0.00 0.00%
01.16.03 DESCOLMATACION DEL CANAL m3 10.71 84.62 906.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.71 906.28 100.00% 10.71 906.28 100.00% 0.00 0.00 0.00%
01.16.04 REMOCION DE DERRUMBES MENORES m3 1.58 33.85 53.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.58 53.48 100.00% 1.58 53.48 100.00% 0.00 0.00 0.00%
01.16.05 ELIMINACION DE MATERIAL EXCEDENTE m3 42.04 42.31 1,778.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42.04 1,778.71 100.00% 42.04 1,778.71 100.00% 0.00 0.00 0.00%
01.17 MANTENIMIENTO DEL CANAL DE RIEGO 3,087.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,807.22 58.53% 3,087.52 100.00% 1,280.30 41.47%
01.17.01 LIMPIEZA DE CANAL m 178.00 4.23 752.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 178.00 752.94 100.00% 178.00 752.94 100.00% 0.00 0.00 0.00%
01.17.02 DESBROCE DE LA FRANJA MARGINAL DEL m2 89.00 4.23 376.47 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.00 376.47 100.00% 89.00 376.47 100.00% 0.00 0.00 0.00%
01.17.03 DESCOLMATACION DEL CANAL m3 8.01 84.62 677.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.01 677.81 100.00% 8.01 677.81 100.00% 0.00 0.00 0.00%
01.17.04 ELIMINACION DE MATERIAL EXCEDENTE m3 30.26 42.31 1,280.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.26 1,280.30 100.00% 30.26 1,280.30 100.00%
COSTO DIRECTO 253,790.27 48,895.04 19.27% 49,015.64 19.31% 197,329.13 77.75% 203,264.33 80.09% 7,566.10 2.98% 1,510.30 0.60%
GASTOS GENERALES 13.52% 34,314.35 6,610.98 19.27% 6,627.28 19.31% 26,680.38 77.75% 27,482.86 80.09% 1,022.99 2.98% 204.21 0.60%
PRESUPUESTO DE LA ACTIVIDAD 288,104.62 55,506.02 19.27% 55,642.92 19.31% 224,009.51 77.75% 230,747.19 80.09% 8,589.09 2.98% 1,714.51 0.60%
AVANCE SEMANAL 55,506.02 55,642.92 224,009.51 230,747.19 8,589.09 1,714.51
AVANCE ACUMULADO TOTAL 55,506.02 55,642.92 279,515.53 286,390.11 288,104.62 288,104.62
PORCENTAJE DE AVANCE (%) 19.27% 19.31% 77.75% 80.09% 2.98% 0.60%
PORCENTAJE DE AVANCE ACUMULADO (%) 19.27% 19.31% 97.02% 99.40% 100.00% 100.00%
Página 3 de 3