ID Task Name Duration Start Finish PROGRAMADO EJECUTADO 4 Aug '22 21 Aug '22 28 Aug '22 4 Sep '22
MADO EJECUTADO 4 Aug '22 21 Aug '22 28 Aug '22 4 Sep '22 11 Sep '22 18 Sep '22 25 Sep '22 2 Oct '22 9 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 6 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 DISEÑO DEL MEJORAMIENTO DE LAS RUTAS 270 days Wed Sat 13/5/23 100% 100%
CHA29EB, CHA29EC Y CHA32S, DEPARTAMENTO DE 17/8/22
CHALATENANGO
2 ORDEN DE INICIO 0 days Wed 17/8/22 Wed 17/8/22 100% 100% 17/8
3 EJECUCIÓN DE LOS ESTUDIOS Y TRABJOS DE LA 270 days Wed Sat 13/5/23 100% 100%
CONSULTORÍA 17/8/22
4 Topografía 227 days Wed 17/8/22Fri 31/3/23 100% 100%
5 Reconocimiento de la Zona 5 days Wed 17/8/22 Sun 21/8/22 100% 100%
6 Monumentación 15 days Fri 19/8/22 Fri 2/9/22 100% 100%
7 Redes de Replanteo 10 days Mon 29/8/22 Wed 7/9/22 100% 100%
8 Procesamiento de la Red de Control 10 days Sun 4/9/22 Tue 13/9/22 100% 100%
9 Nivelación Geodésica 10 days Sun 11/9/22 Tue 20/9/22 100% 100%
10 Nivelación Diferencial 10 days Sun 18/9/22 Tue 27/9/22 100% 100%
11 Informe de Resultados 5 days Sun 25/9/22 Thu 29/9/22 100% 100%
12 Poligonales Cerradas 10 days Tue 27/9/22 Thu 6/10/22 100% 100%
13 Levantamiento de Detalles 75 days Mon 16/1/23 Fri 31/3/23 100% 100%
14 Estudio Geotécnico 227 days Wed 17/8/22Fri 31/3/23 100% 100%
15 Planificación de proyecto 6 days Wed 17/8/22 Mon 22/8/22 100% 100%
16 Procesamiento de datos para primer informe 27 days Mon 5/9/22 Sat 1/10/22 100% 100%
17 Entrega de primer informe de resultados 0 days Sun 2/10/22 Sun 2/10/22 100% 100% 2/10
geotécnia
18 Procesamiento de datos para segundo inform23 days Mon 10/10/2 Tue 1/11/22 100% 100%
19 Entrega de segundo informe de resultados 0 days Wed Wed 100% 100% 2/11
geotécnia 2/11/22 2/11/22
20 Procesamiento de datos para tercer informe 144 days Tue 8/11/22 Fri 31/3/23 100% 100%
21 Entrega de tercer informe de resultados 113 days Tue 8/11/22 Tue 28/2/23 100% 100%
geotécnia
22 Procesamiento de datos para informe final 128 days Tue 8/11/22 Wed 15/3/23 100% 100%
23 Entrega de informe final de estudio geotécnic89 days Mon 2/1/23 Fri 31/3/23 100% 100%
24 Fase de campo (Toma de muestras y 177 days Mon 5/9/22 Tue 28/2/23 100% 100%
ensayos de campo)
25 Movilización 5 days Sun 4/9/22 Thu 8/9/22 100% 100%
26 Instalación de laboratorio provisional 5 days Sun 4/9/22 Thu 8/9/22 100% 100%
27 Calibración de equipo de laboratorio 1 day Fri 9/9/22 Fri 9/9/22 100% 100%
28 Exploraciones Pozos a Cielo Abierto 28 days Fri 9/9/22 Thu 6/10/22 100% 100%
29 Movilización de muestras (Fase 1) 0 days Fri 14/10/22 Fri 14/10/22 100% 100% 14/10
30 Movilización de muestras (Fase 2) 0 days Wed 19/10/2 Wed 19/10/2 100% 100% 19/10
31 Movilización de muestras (Fase 3) 0 days Fri 21/10/22 Fri 21/10/22 100% 100% 21/10
32 Densidades de campo con densimetro nucl 28 days Fri 9/9/22 Thu 6/10/22 100% 100%
33 Perforaciones rotativas 10 days Fri 14/10/22 Sun 23/10/22 100% 100%
34 Ensayos de penetración estandar (SPT) 107 days Mon 14/11/2 Tue 28/2/23 100% 100%
35 Fase de laboratorio (Ensayos de laboratorio) 85 days Sat 1/10/22 Sat 24/12/22 100% 100%
36 Clasificación de suelos para propositos de i 72 days Fri 14/10/22 Sat 24/12/22 100% 100%
37 Determinación del contenido de humedad 72 days Fri 14/10/22 Sat 24/12/22 100% 100%
38 Limites de contracción de suelos plasticos (72 days Sat 1/10/22 Sun 11/12/22 100% 100%
39 Ensayos CBR (Laboratorio externo) 45 days Tue 11/10/22Thu 24/11/22 100% 100%
40 Contenido de materia organica (Laboratorio45 days Tue 11/10/22Thu 24/11/22 100% 100%
41 Estudio de Derechos de Vía 270 days Wed 17/8/22Sat 13/5/23 100% 100%
42 Reconocimiento de Área de Proyecto 15 days Wed 17/8/22 Wed 31/8/22 100% 100%
43 Envío de Formatos para Aprobación del Propi 60 days Mon 22/8/22 Thu 20/10/22 100% 100%
44 Recopilación de Información de Propietarios, 75 days Mon 22/8/22 Fri 4/11/22 100% 100%
45 Solicitud de Permisos de Medición y Estudios 82 days Thu 1/9/22 Mon 21/11/2 100% 100%
46 Elaboración de Planos Generales y Matrices 255 days Thu 1/9/22 Sat 13/5/23 100% 100%
de Seguimiento
47 Elaboración de Estudios Prediales (Escrituras, 225 days Thu 1/9/22 Thu 13/4/23 100% 100%
48 Estudios Registrales 225 days Thu 1/9/22 Thu 13/4/23 100% 100%
49 Investigación de Comparables para Elaboració30 days Tue 15/11/22Wed 14/12/2 100% 100%
50 Presupuesto de Afectaciones 75 days Wed 14/12/2 Sun 26/2/23 100% 100%
51 Diagnóstico de Problemas Legales 120 days Wed 14/12/2 Wed 12/4/23 100% 100%
52 Trámites y Solución de Problemas Legales 120 days Sat 14/1/23 Sat 13/5/23 100% 100%
53 Elaboración de Planos Individuales 60 days Fri 13/1/23 Mon 13/3/23 100% 100%
54 Elaboración de Valúos 60 days Tue 28/2/23 Fri 28/4/23 100% 100%
55 Tramite de Segregaciones Simples en Catastro60 days Wed 15/3/23 Sat 13/5/23 100% 100%
56 Elaboración de Documentos Legales 75 days Tue 28/2/23 Sat 13/5/23 100% 100%
(Certificaciones de Afectación, Vistos
57 Presentación de Expedientes Técnicos para 60 days Wed Sat 13/5/23 100% 100%
Visto Bueno 15/3/23
58 Notificación de Valúos a Propietarios 120 days Sat 14/1/23 Sat 13/5/23 100% 100%
59 Seguimiento de Casos de Expropiación 30 days Fri 14/4/23 Sat 13/5/23 100% 100%
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: PROGRAMA DE TRABA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 15/5/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 1
ID Task Name Duration Start Finish PROGRAMADO EJECUTADO 4 Aug '22 21 Aug '22 28 Aug '22 4 Sep '22 11 Sep '22 18 Sep '22 25 Sep '22 2 Oct '22 9 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 6 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
60 Elaboración de Acuerdos Ministeriales y 30 days Fri 14/4/23 Sat 13/5/23 100% 100%
Proyectos de Escrituración
61 Conformación De Expedientes Finales 15 days Sat 29/4/23 Sat 13/5/23 100% 100%
62 Estudio Hidrológico ‐ Hidráulico 243 days Wed 31/8/22Sun 30/4/23 100% 100%
63 Estudio de Climatología 30 days Wed 31/8/22Thu 29/9/22 100% 100%
64 Levatamiento de Drenajes Existentes 45 days Fri 16/9/22 Sun 30/10/22 100% 100%
65 Estudio de la Definición de Cuencas 30 days Mon 31/10/2 Tue 29/11/22 100% 100%
66 Cálculo de Caudales 122 days Wed 30/11/2Fri 31/3/23 100% 100%
67 Diseño de Drenajes Menores y Mayores 153 days Tue 29/11/22Sun 30/4/23 100% 100%
68 Estudio de Tráfico 120 days Sun 6/11/22 Sun 5/3/23 100% 100%
69 Diseño de Estructuras 136 days Fri 16/12/22 Sun 30/4/23 100% 100%
70 Diseño Geométrico de la Vía 226 days Sat 17/9/22 Sun 30/4/23 100% 100%
71 Diseño de Pavimentos 106 days Sun 15/1/23 Sun 30/4/23 100% 100%
72 Componente Medio Ambiental 176 days Sun 6/11/22 Sun 30/4/23 100% 100%
73 Costos y Presupuestos 120 days Sat 14/1/23 Sat 13/5/23 100% 100%
74 Especificaciones Técnicas 120 days Sat 14/1/23 Sat 13/5/23 100% 100%
75 Programación de Obra 60 days Wed 15/3/23Sat 13/5/23 100% 100%
76 PRESENTACIÓN DE DOCUMENTOS A FOVIAL 256 days Tue 30/8/22 Sat 13/5/23 100% 100%
77 INFORME PRELIMINAR 0 days Tue 30/8/22 Tue 30/8/22 100% 100% 30/8
78 INFORME MENSUAL 1 0 days Thu 15/9/22 Thu 15/9/22 100% 100% 15/9
79 INFORME MENSUAL 2 0 days Sat 15/10/22 Sat 15/10/22 100% 100% 15/10
80 INFORME MENSUAL 3 0 days Mon 14/11/2 Mon 14/11/2 100% 100% 14/11
81 INFORME MENSUAL 4 0 days Wed 14/12/2Wed 14/12/2 100% 100%
82 INFORME MENSUAL 5 0 days Fri 13/1/23 Fri 13/1/23 100% 100%
83 INFORME MENSUAL 6 0 days Sun 12/2/23 Sun 12/2/23 100% 100%
84 INFORME MENSUAL 7 0 days Tue 14/3/23 Tue 14/3/23 100% 100%
85 INFORME MENSUAL 8 0 days Thu 13/4/23 Thu 13/4/23 100% 100%
86 INFORME MENSUAL 9 0 days Sat 13/5/23 Sat 13/5/23 100% 100%
87 ENTREGA FINAL 0 days Sat 13/5/23 Sat 13/5/23 100% 100%
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: PROGRAMA DE TRABA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 15/5/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 2
'22 4 Dec '22 11 Dec '22 18 Dec '22 25 Dec '22 1 Jan '23 8 Jan '23 15 Jan '23 22 Jan '23 29 Jan '23 5 Feb '23 12 Feb '23 19 Feb '23 26 Feb '23 5 Mar '23 12 Mar '23 19 Mar '23 26 Mar '23 2 Apr '23 9 Apr '23 16 Apr '23 23 Apr '23 30 Apr '23 7 May '23 14 May '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: PROGRAMA DE TRABA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 15/5/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 3
'22 4 Dec '22 11 Dec '22 18 Dec '22 25 Dec '22 1 Jan '23 8 Jan '23 15 Jan '23 22 Jan '23 29 Jan '23 5 Feb '23 12 Feb '23 19 Feb '23 26 Feb '23 5 Mar '23 12 Mar '23 19 Mar '23 26 Mar '23 2 Apr '23 9 Apr '23 16 Apr '23 23 Apr '23 30 Apr '23 7 May '23 14 May '2
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
14/12
13/1
12/2
14/3
13/4
13/5
13/5
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: PROGRAMA DE TRABA
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 15/5/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 4