Presentation - RC11 & RC 16 - Slab 1 & 2 Way
Presentation - RC11 & RC 16 - Slab 1 & 2 Way
Two-Way Slabs
Design of Two-Way Slab
Moment Coefficient Method
Load Transfer from Two-Way Slab
Bar Detailing
Design Example
Slab on Ground
Mongkol JIRAVACHARADET
SURANAREE
INSTITUTE OF ENGINEERING
UNIVERSITY OF TECHNOLOGY
L
S
L
G
B
B
G
()
B
B
()
!
"
S $%
L
Simple supports
on all four edges
( L < 2S )
!" #
$% tmin :
S
Perimeter
2 (L + S)
=
10 cm
180
180
"&'!(
As RB 9 Temp. steel
Min. Spacing main steel 4/3 max agg. 2.5 cm
Max. Spacing 3 t 45 cm
d
d
1
')
!*')'+
,!!
-Ms
S/4
+Ms
+ML
-ML
-ML
S/4
-Ms
L/4
S/2
L/2
L/4
./
0
1 ( ($
$# )
2!$
#
2!$
#
2!$
!#
2!$
$#
( C )
1.0
*!+
-
-
012324!
-
-
0123
-
-
m
0.9 0.8 0.7
!
0.6
0.5
( C )
1.0
m
0.9 0.8 0.7
!
0.6
0.5
0123
- 0.058 0.066 0.074 0.082 0.090 0.098 0.058
- 0.029 0.033 0.037 0.041 0.045 0.049 0.029
0.044 0.050 0.056 0.062 0.068 0.074 0.044
014123
-
- 0.033 0.038 0.043 0.047 0.053 0.055 0.033
0.050 0.057 0.064 0.072 0.080 0.083 0.050
wS/3
wS
3
45o
w S 3 m2
3 2
wS/3(3-m2)/2
'!"&(
Sn / 4
Sn / 3
Sn / 7
Sn / 4
6*#
Sn
Ln / 4
Ln / 3
Ln / 7
Ln / 4
Ln
6*#
L =
L/5
Example: Design two-way slab as shown below to carry the live load 300-kg/m2
fc = 240 kg/cm2, fy = 2,400 kg/cm2
0.10
4.00
3.80
0.50
0.20
0.20
Cross section
Min h = 2(400+500)/180 = 10 cm
5.00
4.80
Floor plan
max = 0.75
0.85(240)(0.85)
6,120
4,000
6,120 + 4,000
= 0.0197
2!$
# (m = 0.8)
Short span
Moment coeff. C
-M(
)
+M
-M(
)
0.032
0.048
0.064
Mu
86,600
=
= 17.11 kg/cm2
2
2
b d
0.9 100 7.5
0.85fc
2Rn
1 1
= 0.0045
fy
0.85fc
max = 0.0197
OK
OK
2!$
# (m = 0.8)
Long span
Moment coeff. C
-M(
)
+M
-M(
)
0.025
0.037
0.049
Mu
66,300
=
= 17.44 kg/cm2
2
2
b d
0.9 100 7.5
0.85 fc
2Rn
1 1
fy
0.85 fc
= 0.0046
max = 0.0197
OK
OK
567689:4
!
= wuS/4 = (846)(4.0)/4
Vu
= 846
$%%
Vc
../.
../.
OK
;<
3
As,min = 0.0018(100)(10) = 1.8 cm2
Select temp. steel reinforcement DB10 @ 0.30 m (As = 2.60 cm2)
[email protected] &'&()
[email protected]
[email protected] &'&()
0.10
0.50
0.95
1.30
0.55
0.95
3.80
0.20
23
0.20
[email protected] &'&()
[email protected]
[email protected] &'&()
0.10
0.50
0.70
1.20
0.20
1.20
1.60
4.80
23!
0.20
' (Slab-On-Ground)
spacing
6
Range of
max. spacing
0
0
10
15
20
30
Slab thickness, cm
"&4 &56* (Wire mesh)
!
'"
%(
!
$
)
. 737-2531 fy = 5,000 ../5
.2
,
. 4
., 15 5
. 15 5
.
4
. 4
., 20 5
. 20 5
.
4
. 4
., 25 5
. 25 5
.
4
. 4
., 30 5
. 30 5
.
6
. 6
., 20 5
. 20 5
.
6
. 6
., 25 5
. 25 5
.
6
. 6
., 30 5
. 30 5
.
$"#
(.F!. / !.)
4 "
(./.!.)
+
0.838
0.629
0.838
0.629
1.317
0.988
0.503
0.419
0.503
0.419
0.790
0.658
1.414
1.131
0.943
1.414
1.131
0.943
2.220
1.776
1.481
FL W
2
As = "$(
1
(5
.2)
W = !
" (../
.)
L =
(
)
F =
?%@A
(1.5 B
;$)
fs = "
'""$(
(../.5
.)
?
B"$(
1
')
4
:
FL W
As =
2 fs
As =
FL (1.4 W ) FL W
=
2 fy
1.43 fy
../
.
?
B"$( 'C
As =
= 0.363 .5
./
$'C
WWR 4
! "
6
Range of
max. spacing
0
0
10
15
20
Slab thickness, cm
.
. 4
.
., 30 5
. 30 5
. (As = 0.419 .5
./
)
30
QR
QR
- '$! !" 10 + 2 F!.
- (U#
V!4 FW!
- %!V'
2!("#36
16
Design of Slabs
Types of Slabs
SURANAREE
UNIVERSITY OF TECHNOLOGY
INSTITUTE OF ENGINEERING
SCHOOL OF CIVIL ENGINEERING
Types of Slab
One-way slab
One-way slab
Flat slab
Two-way slab
Grid slab
Ln = 3.2 m
Ln = 4.4 m
Ln = 3.6 m
Ln = 8.2 m
Framing Concepts
Lets use a simple example
for our discussion
Column spacing 8 m c-c
Plan
Framing Concepts
We can first assume that
well have major girders
running in one direction
in our one-way system
Framing Concepts
We can first assume that
well have major girders
running in one direction
in our one-way system
If we span between girders
with our slab, then we have
a load path, but if the spans
are too long
Framing Concepts
We will need to shorten up
the span with additional beams
But we need to support the
load from these new beams,
so we will need additional
supporting members
Framing Concepts
Now lets go back through with
a slightly different load path.
We again assume that well
have major girders running in
one direction in our one-way
system.
This time, lets think about
shortening up the slab span by
running beams into our girders.
Our one-way slab will transfer our load to the beams.
Example
Condo Floor Plan
One-way Slab
L
m
0
.
1
Main reinforcement
1
w
1m
S
S
One end
continuous
Both ends
continuous
Cantilever
L/20
L/24
L/28
L/10
*multiplied
b
A
Moment at A:
wL2
12
wL
12
b/2
wL
2
b/2
wL
2
wL2 wL b w(b / 2 )
=
+
12
2 2
2
wL2 wLb wb 2
+
4
8
12
M =
=
+
12
6
12
12
Top bars at
exterior beams
Temperature bars
Exterior span
Interior span
Bent bar
Bottom bars
Bent bars
Temperature bars
Exterior span
Interior span
G1
A
S1 S2 S3
3 @ 8 m = 24 m
Mu
1762 100
Rn =
=
= 17.6 ksc
2
2
0.9 100 10.55
bd
0.85 f c'
=
fy
2 Rn
1 1
'
0
.
85
f
c
OK
OK
L1
4
L1
3
L1
[email protected]
.13 .
[email protected]
1.0 .
1.3 .
4.0 .
[email protected]
[email protected]
#$
.13 .
1.0 .
[email protected]
1.3 .
4.0 .
Reinforcement Steel:
As 6 mm Temp. steel
Max. Spacing 3 t 45 cm
Min. Spacing main steel 4/3 max agg. 2.5 cm
C
45o
45o
45o
wS/3 kg/m
wS 3 m 2
3 2
2 m sq.m
kg/m
%&'(
%&'
-Ms
%&'(
+Ms
+ML
-ML
%&'
%&'
S/4
-ML
S/4
-Ms
L/4
L/2
S/2
L/4
))*+
m
0.9 0.8 0.7
$%&
0.6
0.5
))*+
m
0.9 0.8 0.7
$%&
0.6
0.5
L1/7
L1/3
L1/4
L1
L2/3
L2/4
L2
L1/8
L2/3
L1/8
L1
L2
L/5
L/5
3.80
0.50
0.20
0.20
Cross section
5.00
4.80
Min h = 2(400+500)/180 = 10 cm
DL = 0.10(2,400) = 240 kg/m2
wu = 1.4(240)+1.7(300) = 846 kg/m2
m = 4.00/5.00 = 0.8
Floor plan
Short span
-M()
+M
-M()
Moment coeff. C
0.032
0.048
0.064
Mu
86, 600
2
=
=
17.11
kg/cm
bd 2 0.9 100 7.52
0.85 f c
2 Rn
=
1 1
= 0.0045
fy
0.85 f c
(
63
(718 [email protected] (As=3.90 4.2)
Long span
Moment coeff. C
-M()
+M
-M()
0.025
0.037
0.049
Mu
66,300
2
=
=
17.44
kg/cm
bd 2 0.9 100 7.52
0.85 f c
2 Rn
=
1 1
= 0.0046
fy
0.85 f c
(
63
(718 [email protected] (As=3.90 4.2)
89"8:
;
7
%
9
9(2:
Vu
= wuS/4 = (846)(4.0)/4
= 846 ./.
<(88'%
9
2 Vc = 0.85(0.53) 240 (100)(7.5)
= 5234 ./.
OK
[email protected]
#$
[email protected]
[email protected]
#$
0.10
0.50
0.95
1.30
0.55
0.95
3.80
0.20
6
0.20
[email protected]
#$
[email protected]
[email protected]
#$
0.10
0.50
0.70
1.20
0.20
1.20
1.60
4.80
0.20