Calculating Total Power Requirements For Data Centers-En
Calculating Total Power Requirements For Data Centers-En
White Paper 3
Revision 1
by Richard L. Sawyer
Contents
Click on a section to jump to it
Introduction Needs assessment Determining the electrical power capacity needed Final electrical capacity computation Conclusion Resources
2 2 2 5 9 10
white papers are now part of the Schneider Electric white paper library produced by Schneider Electrics Data Center Science Center [email protected]
Introduction
With the adoption of scalable pay as you grow uninterruptible power supply (UPS) architectures, its becoming easier to install these systems. It allows the data center manager to simply add modules as the needs of the data center grow. However, it is easy to lose sight of the future electrical needs of the data center or data room within a larger facility. Sizing the electrical service for a data center or data room requires an understanding of the amount of electricity required by the cooling system, the UPS system, and the critical IT loads. The power requirements of these elements may vary substantially from each other, but can be accurately estimated using simple rules once the power requirements of the planned IT load are determined. In addition to estimating the size of the electrical service, these elements can be used to estimate the power output capacity of a standby generator system, if one is required for the data center loads.
Needs assessment
Related resource
White Paper 75
Comparing UPS System Design Configurations
Any initiative to improve the capabilities of a data center environment, no matter the size or scale, must begin with a needs assessment. The needs assessment essentially establishes the availability needs of the business applications being processed by the IT equipment. A business process that is not time sensitive, or is batch process driven may dictate power and air conditioning for the load in an N configuration, with no internal redundancies to increase availability. More time sensitive sites may require a degree of redundancy in key component systems and have configurations of an N+1 topology. Every key system element would have a redundant piece of equipment so that if one of the units fails, the system could still maintain its function for the IT critical load. The most critical data center applications requiring total availability (7x24) would have a 2N topology where critical systems would be completely redundant. One critical system could fail, but another would maintain operational loads. This also provides for a degree of concurrent maintainability whereby maintenance could be performed on one system while another supplies the load. For more information on the different types of system configurations see White Paper 75, Comparing UPS System Design Configurations. No matter what the actual UPS system design configuration is (N, N+1, 2N), the core issue of providing sufficient power to the critical load and keeping it cool is the same, and must be carefully addressed. Underestimating the required capacity may result in future power disruptions when forced to increase capacity, and over estimating leads to excessive initial installation costs and higher ongoing maintenance expenses.
Most data centers are part of a larger building. The steps in determining the electrical capacity described below will assist in estimating the capacity required for that portion of the building dedicated to the data center or data room. The difference between the steady state power and the peak power is important when calculating power capacity requirements and is noted throughout this paper. For more information on why power variations exist read White Paper 43, Dynamic Power Variations in Data Centers and Network Rooms. For installations where critical components like air conditioning, chillers, or standby generators are shared and used to supply other loads beyond the data center, the sizing of the system requires a more complete and complex analysis by a consulting engineer. Figure 1 illustrates a typical breakdown of how the electrical capacity is divided among the various loads in a data center. This breakdown assumes 5,000 ft2, (465 m2) data center with an initial steady state critical load of 50 kW, plus a future steady state load of 50 kW. The cooling system is assumed to be direct expansion (DX) and the utility voltage is 480 volts AC.
Related resource
White Paper 43
Dynamic Power Variations in Data Centers and Network Rooms
White Paper 3
Rev 1
Figure 1
Breakdown of data center electrical requirements
Critical loads
A proper planning exercise in developing a data center, from a single rack sized environment to a full scale data center begins with determining the size of the critical load that must be served and protected. The critical load is all of the IT hardware components that make up the IT business architecture: servers, routers, computers, storage devices, telecommunications equipment, etc., as well as the security systems, fire and monitoring systems that protect them. This process begins with a list of all such devices, with their nameplate power rating, their voltage requirements, and whether they are single phase or three phase devices. The nameplate information must then be adjusted to reflect the true anticipated load. The nameplate power requirements are the worst-case power consumption numbers required by Underwriters Laboratory and in almost all cases, are well above the expected operating power level. Studies conducted by reputable consulting engineering firms and power supply manufacturers indicate that the nameplate rating of most IT devices is well in excess of the actual running load by a factor of at least 33%. The U.S. National Electrical Code (NEC) and similar worldwide regulatory bodies also recognize this fact and allow electrical system planners to add up nameplate data for anticipated loads and multiply by a diversity factor, anticipating that not all devices are running at full load 100% of the time. Alternatively, an advanced sizing calculator may be used such as the one found at the website below. Calculators such as this one gather power consumption data from a wide range of manufactures and further specify various equipment configurations. UPS Selector At this site an IT professional can configure a representative racks worth of servers based on brand-name ingredients. This tool works behind the scenes to add up the known power requirements of each component within a given servers configuration. For example, when a user specifies a server, they will also be asked to record the quantity of CPU and other details within the box. Given the users inputs, the UPS Selector will calculate the total power required for the rack. (The power will be stated in volt-amps or VA) Also included in the tool are important facts about the manufacturers intended input voltage and power plug. With the list of anticipated components comprising the critical load, the base load can be established by using a sizing calculator. For IT equipment unlisted in calculators as well as the power requirement for fire, security and monitoring systems, the following process should be used:
1. Add up the nameplate power of the anticipated loads. If the wattage is not listed on
the device, it can be determined by multiplying the current (amps) by the voltage of the
White Paper 3
Rev 1
2. Multiply the anticipated VA number by 0.67 to estimate the actual power, in watts, that
the critical load will represent.
3. Divide the number by 1,000 to establish the kilowatt (kW) load level of the anticipated
critical load.
Future loads
Data Center loads are not static. Once built or established, the IT equipment will be under an almost constant state of change during the lifetime of the data center. IT refreshes will, at a minimum, have a 3 year cycle where new, more powerful or efficient devices will be installed with, or replace the devices on the initial planning list. A realistic assessment of the scope and timing of future changes and upgrades should be developed by the IT organization to allow proper planning for the initial determination of power requirements. The downstream elements of the electrical power and distribution system can be scaled, or adjusted to known loads and future loading (See White Paper 37, Avoiding Costs from Oversizing Data Center and Network Room Infrastructure), but the electrical power service supplying the data center physical infrastructure (DCPI) components has to be sufficiently sized to carry the known load at start-up and future loads, or provision has to be made for installing additional capacity without incurring excessive downtime that would adversely affect the availability expected by the IT customer. Once an estimate is made for the amount of future loading, it is added to the base loading information developed above to establish the electrical critical load number in kW.
Related resource
White Paper 37
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure
UPS loads
Assuming that the availability determination in the needs assessment, explained above, requires the inclusion of UPS power (in almost all cases this is true), the total electrical load power must include a factor for the inefficiency of the UPS system as well as the additional power required for battery charging. UPS efficiency varies between product models and varies dramatically depending on the loading of the UPS. UPS are rarely run at the operating points where their advertised efficiency is provided. A realistic and sufficiently accurate value for UPS efficiency in a typical installation is 88%. Battery charging is a significant but intermittent power consumer. Under normal operation with a charged battery the battery charging load is negligible. However, when a battery has been partially or completely discharged the battery charging power can be on the order of 20% of the rated UPS load. Although this load only rarely occurs, the generator and service entrance must be sized for this load.
Lighting loads
Weather Lighting loads account for all the lighting in the data center portion of the building and are a function of the data center floor area. A good rule of thumb for this type of load is 2 watts per square foot or 21.5 watts per square meter.
Related resource
White Paper 25
Calculating Total Cooling Requirements for Data Centers
Cooling loads
Refer to White Paper 25, Calculating Total Cooling Requirements for Data Centers, for a detailed discussion of heat loads in data center environments. The paper provides a table to help calculate the cooling required for the heat generated by the IT equipment. It also allows the planner to establish the amount of cooling required to support a planned critical load.
White Paper 3
Rev 1
Once the total electrical capacity is estimated in kW from the process described above, two critical determinations can be made: the first is an estimate of the electrical service needed to supply the data center, and the second is the size of any standby power generator capacity that may be needed to achieve the desired availability.
1. Take the total electrical capacity required in kilowatts and multiply by 125% to meet
the requirements of the National Electrical Code and similar regulatory bodies.
2. Determine the three phase AC voltage of the service entrance to be supplied by the
utility company. Typically this is 480 Volts AC in the United States and 230 Volts AC in most other parts of the world.
3. Use the following formula to determine the electrical service size to supply the data
center, in Amps: Amps = (kW x1000) / (Volts x 1.73) This provides an estimate of the electrical service capacity required to support the critical load, cooling, and the building functions for a data center. Using the same assumptions of Figure 1, Figure 2 emphasizes the important distinction between rated (peak) power and steady state power by comparing the electrical service requirements for both. It must be noted that this is only an estimate, and that the final determination of the service size is highly dependent on accurate site specific information. It is strongly recommended that the services of a qualified professional consulting engineer be retained to verify the initial estimate and develop the final data center electrical supply design. Table 1, located at the end of the paper, can be used as a worksheet that assists in summarizing the discussion above.
White Paper 3
Rev 1
Figure 2
kW
250
Air Conditioner Load
Rated vs. steady-state electrical service power for a typical 100 kW critical load. Electrical service rating is almost 4X the steady state critical load value
200 150
UPS Load
100 50 0 Electric Service Rated Critical Load Air Conditioner Load Lighting Load Electrial Service Derating
Critical Load
UPS Load
Critical Load
Utility
Generator
Transfer Switch
Figure 3
Typical generator system
Emergency Bus
UPS
Critical IT Load
White Paper 3
Rev 1
Related resource
White Paper 15
Watts and Volt-Amps: Powerful Confusion
Figure 4
kW
250 200 150 100 50 0 Generator Rated Critical Load UPS Load Oversizing due to Critical loads Generator Steady State Lighting Load Air Conditioner Load Oversizing due to Cooling loads
Critical Load Air Conditioner Load Air Conditioner Load
UPS Load
Rated vs. steady-state electrical generator power for a typical 100 kW critical load. Electrical service rating is over 4X the steady state critical load value
UPS Load
Critical Load
White Paper 3
Rev 1
Table 1
Data center power requirement estimate calculation worksheet
Item
Power requirement electrical
Critical load- sizing calculator value from Schneider Electric website For equipment not listed in the sizing calculator, critical load nameplate Future Loads Peak power draw due to variation in critical loads UPS inefficiency and battery charging Lighting Total power to support electrical demands
Data required
Calculation
Subtotal kW
# 1 _______________kW
Subtotal VA (include fire, security and monitoring systems) VA of nameplate of each anticipated IT device Total steady state critical load power draw Actual Load + Future Loads (in kW) Total floor area associated with the data center Total from # 4, # 5, and # 6 above
( Subtotal VA x .67 ) / 1000 [ (Add VA rating of future devices) x .67 ] / 1000 ( # 1 + # 2 + # 3 ) x .1.05 ( # 1 + # 2 + # 3 ) x 0.32 0.002 x floor area (sq ft), or 0.0215 x floor area (sq m) #4+#5+#6
# 2 _______________kW
__________________Amps
*WARNING: The 1.3 variable applies to fully power factor corrected UPS. A 3.0 multiplier must be used when using traditional double conversion UPS with input harmonic filters.
White Paper 3
Rev 1
Conclusion
Assessing the electrical power required to support and cool the critical loads within the data center is essential in planning for the development of a facility that will meet the end users availability expectations. By employing the process described above, a reasonable estimate of the power requirements can be made. This will help specify the size of the Data center physical infrastructure components that will achieve the availability determined by the needs assessment. Once the sizing determination is made, conceptual and detailed planning can go forward with the assistance of a competent DCPI systems supplier or, in the case of larger scale data centers, a consulting engineer. Cost estimation can then be made based on the size and reliability configuration determined from the power needs assessment process described above.
Acknowledgements
Special thanks to Richard L. Sawyer for authoring the original content of this white paper.
White Paper 3
Rev 1
Resources
Click on icon to link to resource
Avoiding Costs from Oversizing Data Center and Network Room Infrastructure
White Paper 37
Contact us
For feedback and comments about the content of this white paper: Data Center Science Center [email protected] If you are a customer and have questions specific to your data center project: Contact your Schneider Electric representative
White Paper 3
Rev 1
10