NOTE:
ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN METERS EXCEPT OTHERWISE. ALL REQUIRED COORDINATION WITH AUTHORITIES INCLUDING TRAFFIC REROUTING IF NECESSARY TO BE DONE BY MAIN CONTRACTOR {AS PER SUB-CONTRACT AGREEMENT}. REFER TO GEOMETRY SHOP DRAWING FOR PIER & FOUNDATION - LEVEL AND HEIGHT.
00
JCB
FIRST ISSUE
1-10-2012
Rev. CLIENT
DRAWN BY:
DESCRIPTION
DATE
NAME OF PROJECT :
HARAMAIN HIGH SPEED RAIL
CONSULTANT :
MAIN DESIGNER:
CONTRACTOR :
TITLE :
HARAMAIN HIGH SPEED RAIL RAIL BRIDGE AT STATION 445+547.832 Sheet No. Revision
Contract Drw. No.
Drawing Number:
3 of 3
Scale :
As Shown
00
Drawn by: JCB Date: 1-10-2012
Checked by: JC
Drawing Status Sub No.: Sub Date:
P.M. Sign