Hose Reel Test Report

The document provides a fire protection equipment test report for a hose reel system at multiple locations of a plant. It details the steps taken to test the hose reel system, including placing pumps in off positions, manually starting the jockey pump, opening a hose reel near the pump to maintain flow, and proceeding to test other hose reel cabinets. A checklist is provided to inspect cabinet components, hoses, and piping/valves at 10 different locations across the plant. All systems were found to be satisfactory with no failures reported. Times were recorded for isolating pumps to off positions and then normalizing all pumps to auto.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
67% found this document useful (3 votes)
9K views1 page

Hose Reel Test Report

The document provides a fire protection equipment test report for a hose reel system at multiple locations of a plant. It details the steps taken to test the hose reel system, including placing pumps in off positions, manually starting the jockey pump, opening a hose reel near the pump to maintain flow, and proceeding to test other hose reel cabinets. A checklist is provided to inspect cabinet components, hoses, and piping/valves at 10 different locations across the plant. All systems were found to be satisfactory with no failures reported. Times were recorded for isolating pumps to off positions and then normalizing all pumps to auto.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

TEKNIK JANAKUASA SDN BHD FIRE PROTECTION EQUIPMENT TEST REPORT

EQUIPMENT TESTED: HOSE REEL SYSTEM

INSPECTION: 3 MONTHLY

LOCATION: PLANTWIDE

DATE TESTED: 11 AUGUST 2007

1. HOSE REEL TEST AND CHECK


1.
2.
3.
4.
5.

Place DIESEL pump and ELECTRICAL pump to OFF.


Start Jockey pump MANUALLY.
Open one hose reel near the pump location to maintain minimum flow.
Proceed to test & check other hose reel cabinet.
Normalize all pump selectors after the test is completed.

CHECKLIST:
1) Cabinet & Key
2) Nozzle 1
3) Hose 1 x 30 M
NO

4) Gate valve condition


5) Drum condition
6) Piping & valve

LOCATION

KKS NO

PASS

01
02

PUMP HOUSE
WORKSHOP G/FLOOR

HR NO : 1
HR NO : 2

03

ADMIN. BLOCK G/FLOOR

HR NO : 3

04

WARE HOUSE

HR NO : 4

05

WARE HOUSE

HR NO : 5

nd

06

ADMIN. BLOCK 2 FLOOR

HR NO : 6

07

ADMIN. BLOCK 2nd FLOOR

HR NO : 7

FAIL

REMARK

08
09
10
COMMENT: All system satisfactory_______________________________________________
___________________________________________________________________________

ISOLATION:
Isolate Diesel and Electrical Pump to OFF

Time

Normalize ALL pump to AUTO

Time

Tested by: MOZZAZ VENTURE

Witnessed by (Clients Representative)

Technician Name: Azhar, Fadzrin, Hanif

Signature: ________________________

Name: _________________________

Signature: ____________________