TEKNIK JANAKUASA SDN BHD FIRE PROTECTION EQUIPMENT TEST REPORT
EQUIPMENT TESTED: HOSE REEL SYSTEM
INSPECTION: 3 MONTHLY
LOCATION: PLANTWIDE
DATE TESTED: 11 AUGUST 2007
1. HOSE REEL TEST AND CHECK
1.
2.
3.
4.
5.
Place DIESEL pump and ELECTRICAL pump to OFF.
Start Jockey pump MANUALLY.
Open one hose reel near the pump location to maintain minimum flow.
Proceed to test & check other hose reel cabinet.
Normalize all pump selectors after the test is completed.
CHECKLIST:
1) Cabinet & Key
2) Nozzle 1
3) Hose 1 x 30 M
NO
4) Gate valve condition
5) Drum condition
6) Piping & valve
LOCATION
KKS NO
PASS
01
02
PUMP HOUSE
WORKSHOP G/FLOOR
HR NO : 1
HR NO : 2
03
ADMIN. BLOCK G/FLOOR
HR NO : 3
04
WARE HOUSE
HR NO : 4
05
WARE HOUSE
HR NO : 5
nd
06
ADMIN. BLOCK 2 FLOOR
HR NO : 6
07
ADMIN. BLOCK 2nd FLOOR
HR NO : 7
FAIL
REMARK
08
09
10
COMMENT: All system satisfactory_______________________________________________
___________________________________________________________________________
ISOLATION:
Isolate Diesel and Electrical Pump to OFF
Time
Normalize ALL pump to AUTO
Time
Tested by: MOZZAZ VENTURE
Witnessed by (Clients Representative)
Technician Name: Azhar, Fadzrin, Hanif
Signature: ________________________
Name: _________________________
Signature: ____________________