Sewer Dist Works covered up or in any way made unavailable for inspection before the submission of the Notice of Inspection Required form or the Engineer‟s approval to proceed shall be uncovered at the Contractor‟s expense. 5 Prior to inspection, the Contractor shall submit his Quality Control plan (QC plan) / Inspection and Test Plan (ITP) in accordance with Section 1 Clause 7.6.3. 1.3.5 CCTV Survey 1 The Contractor shall on written instruction of the Engineer undertake a CCTV survey on designated lengths of pipelines laid during the execution of the Works, including pipeline cleaning where necessary and submission of a Survey Report, as part of the final inspection of the Works. 2 The Certificate of Completion for the Works or part thereof shall not be issued until the CCTV Survey, including provision of the Survey Report, and any subsequent sewer remedial works have been completed to the satisfaction of the Engineer. 3 Should any length of the surveyed between adjacent manholes
Sewer Dist Works covered up or in any way made unavailable for inspection before the submission of the Notice of Inspection Required form or the Engineer‟s approval to proceed shall be uncovered at the Contractor‟s expense. 5 Prior to inspection, the Contractor shall submit his Quality Control plan (QC plan) / Inspection and Test Plan (ITP) in accordance with Section 1 Clause 7.6.3. 1.3.5 CCTV Survey 1 The Contractor shall on written instruction of the Engineer undertake a CCTV survey on designated lengths of pipelines laid during the execution of the Works, including pipeline cleaning where necessary and submission of a Survey Report, as part of the final inspection of the Works. 2 The Certificate of Completion for the Works or part thereof shall not be issued until the CCTV Survey, including provision of the Survey Report, and any subsequent sewer remedial works have been completed to the satisfaction of the Engineer. 3 Should any length of the surveyed between adjacent manholes
Manhole Spacing
TABLE "13"
Pipe Size 8-inch to 24-inch 27-inch to 42-inch 48-inch and larger Maximum Manhole Spacing Maximum Manhole Spacing 400 feet 600 feet 600 feet, unless otherwise approved by WSSC
c. Minimum Spacing Between Manholes. 1) Outside diameter (OD) of adjacent manholes (including the bottom slabs) should have minimum of five (5) feet horizontal clearance. Example: 8-inch sewer pipeline connecting to a four (4) foot diameter manhole, provide ten (10) feet horizontal distance between the centerline of manholes to achieve the 5 foot outside horizontal clearance.
2008
S-13.1