PROCESS OF CONTROLLING
RECIPROCAL RELATIONSHIP AIDS PLANNING BY
ATTENTION TO AREAS THAT NEED NEW PLANS PROVIDES DATA TO BASE THE NEW PLAN
PROCESS OF CONTROLLING
DESIRE D PERFOR MANCE IMPLEM ENTATIO N OF PLAN CORRE CTIVE ACTION PLAN ANALYSI S OF CASUSE S OF DEVIATI ON
PROCESS OF CONTROLLING
TOP MANAGEMENT PERFORMANCE STANDARDS
ORGANIZATIONAL STANDARDS
FUNCTIONAL STANDARDS
DEPARTMENTAL STANDARDS
POSITION STANDARDS
PROCESS OF CONTROLLING
MARKET CONTROL
PRICE COMPETITION MARKET SHARE
BUREAUCRATIC CONTROL
STRICT RULES FORMAL CONTROL RIGID TOP DOWN APPROACH
CLAN CONTROL
SHARED VALUES NORMS & TRADITIONS OF ORG. CULTURE
TECHNIQUES OF CONTROLLING
FINANCIAL CONTROL BUDGET CONTROL MARKETING CONTROL PERFORMANCE MANAGEMENT COMPUTERS AND INFORMATION CONTROLS
Gantt and PERT charts are both CPM (Critical Path Method) tools to: manage the tasks involved in big and complex projects let project managers organise time, people, equipment and money ensure the right people and equipment are in the right place and the right time to monitor the allow managers progress of a project
Gantt Basics
Basically, a timeline with tasks that can be connected to each other Note the spelling! It is not all-capitals! Can be created with simple tools like Excel, but specialised tools like Microsoft Project make life easier
10
11
Step 3 add dependencies (which tasks cannot start before another task finishes)
12
Notes
The arrows indicate dependencies. Task 1 is a predecessor of task 2 i.e. task 2 cannot start before task 1 ends. Task 3 is dependent on task 2. Task 7 is dependent on two other tasks Electrics, plumbing and landscaping are concurrent tasks and can happen at the same time, so they overlap on the chart. All 3 can start after task 4 ends. Painting must wait for both electrics and plumbing to be finished. Task 9 has zero duration, and is a milestone
13
14
PERT basics
PERT is an acronym so its in capital letters Gantt is a name, so only has an initial capital In Gantt chart, the length of a tasks bar is proportional to the length of the task. This rarely applies to PERT charts. There are a few different flavours of PERT and Gantt charts
15
PERT charts
This PERT chart follows the Activity on Arrow style. The tasks are shown by arrows. Task name are shown by letters, in this case. The circles are called nodes. The nodes indicate the start or end of tasks. Task durations are the shown by the numbers.
16
Activity on Node is a different flavour of PERT: this time the nodes are tasks, and the arrows are merely connectors. We will use Activity on Arrows, with the nodes merely connecting points. Its a style issue!
17
1: Which tasks are on the critical path? 2: What is the slack time for tasks C, D and G? 3: Task C is delayed by one day. What impact would this have on the completion date of the project? Why? 4: Task A will be delayed by 2 days because some equipment has arrived late. If the project manager wants to finish the project on time he will need to shorten the duration of one or more of the tasks. How can he achieve this? 5: The project manager reduces the durations of tasks D and F by one day each. How will this affect the finishing date of the project?
18
ANSWER: A,B,D,F,I