1.0
SCOPE OF WORKS
1.1 General Description
1.2 Tools and Equipment
1.3 Ready for pre-commissioning
1.4 Commissioning Activities
2.0
APPLICABLE DOCUMENTS
3.0
RESPONSIBILITIES
4.0 EXECUTION OF COMMISSIONING ACTIVITIES
5.0.
PROCEDURES
1.0
SCOPE OF WORK
1.1General Description
This procedure describes the sequence of commissioning activities,
equipments, tools and resources required for FIRE ALARM SYSTEM
at Shedgum where in accordance with relevant sections of Saudi
Aramco Project specifications, Fire Alarm and Detection Systems
and NFPA 3. Commissioning activity will be started after completion
of equipment installation & physical inspection.
1.2 Tools and Equipment
The following Tool and equipment will be used as and when
necessary to carry out pre-commissioning activities.
Item
No.
Tools and Equipment
1
2
3
Multi meter Digital
Smoke Tester
Heat Tester
Device Testing Kit
Purpose
To check voltage and continuity
Detector Test device
Detector Test device
To check functionality of the
detectors and other devices
1.3 Ready for Pre-Commissioning
The works are ready for pre-commissioning when the company has
issued a certificate for installation completion and notification in writing
that the works is ready for pre-commissioning.
1.4 Commissioning Activities
Commissioning activities are to be performed after completion of a piece of
equipment or system to make it safe and ready for commissioning. This
includes, but not limited to
. Performance of all remaining works other than commissioning &
functional test.
The completion of all inspections.
. The items for which a defect notice are issued to be rectified and
and all defect notices shall have been closed out.
.Checking & Site Modifications
. Make available necessary tools required to carry out activities.
. Trouble Shoot the devices and modules in order to make panel normal.
. Program the panel as per Saudi Aramco requirement.
. Perform functional test of the system prior to final testing.
. Availability of trained engineers.
.Notify 24hrs in advance Saudi Aramco Engineer prior to
commencement of pre-commissioning activities.
2.0
APPLICABLE DOCUMENTS
2.1
2.2
2.3
3.0
S/N
Saudi ARAMCO Commissioning forms
NFPA 3
Manufacturers Standard & Manuals
RESPONSIBILITIES
POSITION/DESIGNATION
QTY
Commissioning Engineer
Supervisor-Electrical
Technician-Electrical
4.0
RESPONSIBLITY
In-charge
for
all
precommissioning related activities
of FAS.
To support engineer to carry
out pre-com. activities
Responsible for implementing
the activities on site
EXECUTION OF PRE-COMMISSIONING ACTIVITIES
Contractor shall complete all pre-commissioning activities in accordance
with guidelines given in Saudi ARAMCO Standards/Pre-commissioning
forms. Contractor shall write necessary procedures and obtain approval
from Company prior to commencing work and shall carry out the work
in accordance with approved procedures.
5.0
PROCEDURES
Check the completion
documents to As-built.
documents
along
with
all
design
Check detector layout, alarm bells and others accessories were
installed as per approved drawings.
Check the continuity for all the loop lines, conductor to conductor
resistance.
Make sure electric head of Novec 1230 are not connected to
cylinders.
The installed equipments will be inspected and the integrity of the
installation verified.
Mechanical test will comprise of a physical inspection
installation and termination of each cables and equipment.
of
Each field device must be individually tested to ensure that it
transmits the correct signal to FACP through loops.
Connect the loops to the panel and power the panel AC & DC.
END OF SECTION