Item No. Description Quantity: Summary of Financial Proposal
Item No. Description Quantity: Summary of Financial Proposal
PROJECT:
LOCATION:
ITEM NO.
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
DESCRIPTION
QUANTITY
MOBILIZATION/DEMOBILIZATION
EARTHWORKS
CONCRETE WORKS
REINFORCING STEEL WORKS
FORMWORKS
MASONRY WORKS
STEEL WORKS
TINSMITHRY WORKS
ELECTRICAL WORKS
PLUMBING AND DRAINAGE SYSTEM
DOORS AND WINDOWS
PAINTING WORKS
1.00
367.61
111.76
10,606.01
2,400.00
1,172.66
330.00
330.00
1.00
1.00
45.00
980.00
GRAND TO
Prepared by:
Reviewed by:
ANCIAL PROPOSAL
CONTRACTOR:
Contract days: 120 Calendar days
UNIT
lot
cu.m.
cu.m.
kgs.
bdft
sq.m.
ln.m.
ln.m.
sys
lot
sq.m.
sq.m.
UNIT COST
44,840.00
238.55
3,963.37
736,747.53
719,066.44
615.98
706.42
928.57
54,192.53
6,046.32
160.84
GRAND TOTAL
AMOUNT
44,840.00
87,692.68
442,946.62
736,747.53
719,066.44
722,334.28
233,119.60
306,429.47
54,192.53
272,084.40
157,624.40
3,777,077.94
Noted:
:
:
Contractor :
I. MOBILIZATION/DEMOBILIZATION
Mob/Demob
II. EARTHWORKS
109.40
77.27
52.80
-
112.572 cu.m.
20.03
5.74
3.04
26.40
19.04
12.14
5.44
8.55
2.20
Materials:
Portland Cement
Screened Coarse Aggregates
Cleaned Fine Aggregates
V. FORMWORKS
Good Lumber (Total)
cu.m.
cu.m.
cu.m.
cu.m.
sq.m.
@
@
@
@
@
239.47cu.m.
Excavation Works
Backfill and Compaction
Mixed Gravel & Sand Fill and Compaction
Gravel Bedding
Soil Treatment
lot
903.44
100.38
50.19
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
bags
cu.m.
cu.m.
@
@
@
12,680.00 kgs
Beam
Roof Beam
Parapet Wall
Concrete Gutter
Corbel
120.00
253.00
312.00
1,497.00
95.24
2,400.00
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
kgs
bdft
@
@
@
@
@
@
@
@
@
2. PLASTERING
Portland Cement
Fine Sand
3. STONE AGE
1/2" Concrete Nail
#16 ATW
9,480.37
239.00
5.37
3.00
bdft
bdft
pcs
kg
roll
@
@
@
@
@
386.55 sq.m.
7,183.00
911.00
50.00
532.00
19.21
pcs
pcs
bags
cu.m.
pcs
kgs
@
@
@
@
@
@
773.11 sq.m.
249.00
13.79
pcs
pcs
@
@
sq.m.
kgs
kgs
@
@
@
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
kg
pails
pails
pcs
pcs
@
@
@
@
@
@
@
@
@
@
@
@
@
@
@
@
ln.m
pcs
pcs
pcs
@
@
@
@
13.00
2.00
3.00
27.00
32.00
4.00
21.00
21.00
16.00
4.00
150.00
2.00
4.00
3.00
3.00
330 LN.M.
264.00
21.00
22.00
824.00
1,256.00
9.00
X. PLUMBING WORKS
6" Diameter PVC Pipe
4"dia PVC Pipe
2" dia PVC
Downspout Strainer, Bronze
Catch Basin
pcs
pcs
ltrs
@
@
@
set
set
set
set
pcs
pcs
@
@
@
@
@
@
set
set
pcs
pcs
pcs
pcs
pcs
pcs
boxes
boxes
ln.m
pcs
@
@
@
@
@
@
@
36.00
3.00
14.00
18.00
14.00
pcs
pcs
pcs
pcs
sets
@
@
@
@
@
2.00
6.00
7.00
sets
sets
sets
@
@
@
sq.m.
sq.m.
@
@
19.20
12.00
@
@
574.00
6.00
6.00
10.00
12.00
sq.m.
pail
pail
pail
gal
@
@
@
@
775.57
9.00
9.00
9.00
14.00
60.00
60.00
2.00
5.00
5.00
sq.m.
lit
pail
lit
pail
sq.ft.
sq.ft.
sets
pcs
pcs
@
@
@
@
@
@
@
@
@
SUMMARY:
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
Prepared By:
2,440,652.45
757,645.83
3,198,298.28
159,355.23
191,226.28
228,198.15
3,777,077.93
Reviewed by:
Noted:
NOTE: OCM, PROFIT, TAXES VARIES. DEPENDS ON HOW THE OWNER WILL IMPLEMENT THE CONSTRUCTION. IT MAY BE B
OR BY BIDDING, WHEREIN THE LOWEST BIDDER USUALLY WINS AND WILL IMPLEMENT THE PROJECT.
38,000.00
Total Direct Cost
OCM
Profit
Taxes
Total Cost
38,000.00
38,000.00
1,900.00
2,280.00
2,660.00
44,840.00
245.00
245.00
245.00
440.00
60.00
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
26,803.00
18,931.15
12,936.00
5,033.60
17,969.60
52,023.50
69,993.10
3,499.66
4,199.59
10,000.33
87,692.68
100.38
230.00
480.00
440.00
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
207,790.74
48,183.36
22,084.04
278,058.14
97,320.35
375,378.49
18,768.92
22,522.71
26,276.49
442,946.62
845.00
545.00
445.00
345.00
290.00
240.00
210.00
135.00
65.00
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
101,400.00
87,285.00
65,520.00
202,095.00
6,190.60
462,490.60
161,871.71
624,362.31
31,218.12
37,461.74
43,705.36
736,747.53
705,529.41
28.00
28.00
695.00
2,800.00
1,600.00
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
265,450.36
166,105.00
15,036.00
4,800.00
451,391.36
157,986.98
609,378.34
30,468.92
36,562.70
42,656.48
719,066.44
12.00
10.00
230.00
440.00
135.00
65.00
86,196.00
209,530.00
22,000.00
71,820.00
1,248.65
390,794.65
230.00
390.00
57,270.00
5,378.10
62,648.10
1,150.00
90.00
70.00
14,950.00
180.00
210.00
Sub-Total
Sub-Total
Sub-Total
Material cost
Labor Cost
Direct Cost
OCM
Profit
Taxes
Total Cost
453,442.75
158,704.96
612,147.71
30,607.38
36,728.85
42,850.34
722,334.28
1,290.00
1,120.00
955.00
785.00
390.00
210.00
370.00
205.00
1,150.00
78.00
5,000.00
85.00
2,200.00
820.00
85.00
55.00
Material Cost
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
34,830.00
35,840.00
3,820.00
8,190.00
4,410.00
18,400.00
20,000.00
12,750.00
4,400.00
3,280.00
255.00
165.00
146,340.00
51,219.00
197,559.00
9,877.94
11,853.53
13,829.13
233,119.60
640.00
455.00
455.00
455.00
168,960.00
9,555.00
10,010.00
1.00
1.00
195.00
Material Cost ,
Labor Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
824.00
1,256.00
1,755.00
192,360.00
67,326.00
259,686.00
12,984.30
15,581.16
18,178.01
306,429.47
4,400.00
12,600.00
1,500.00
5,500.00
185.00
185.00
120.00
170.00
185.00
145.00
60.00
60.00
55.00
75.00
3,000.00
4,200.00
282.00
40.00
Material Cost
Labor Cost
Direct Cost
OCM
Profit
Taxes
Total Cost
390.00
180.00
60.00
390.00
1,000.00
Material Cost
Labor Cost
Direct Cost
OCM
Profit
Taxes
Total Cost
14,040.00
540.00
840.00
7,020.00
14,000.00
36,440.00
11,193.33
47,633.33
1,822.00
2,186.40
2,550.80
54,192.53
22,000.00
11,500.00
2,500.00
44,000.00
69,000.00
17,500.00
3,400.00
2,900.00
65,280.00
34,800.00
Material Cost
Total Direct Cost
OCM
Profit
Taxes
Total Cost
230,580.00
230,580.00
11,529.00
13,834.80
16,140.60
272,084.40
VERIFY!
1080
324
1404
70.2
84.24
98.28
1656.72
0.03
2,450.00
1,950.00
2,500.00
810.00
14,700.00
11,700.00
25,000.00
9,720.00
110.00
2,450.00
1,200.00
2,500.00
30.00
15.00
110.00
85.00
55.00
Material Cost
990.00
22,050.00
10,800.00
35,000.00
1,800.00
900.00
220.00
425.00
275.00
133,580.00
133,580.00
6,679.00
8,014.80
9,350.60
157,624.40
Err:520
300
15