Reply to Queries:
S.No
Clause No. / Page
No.
Comment
Cl. No.- 2.1 / (f),
Page no.-6
All three pumps as
there are three
pumps not two
Cl. No.- 2.1 / (h),
Page no.-6
MCC / VFD panels
should be placed at
Pump House E Room
Cl. No.- 2.1 / (t),
Page no.-8
Are Cleaning up at
site of all debris and
temporary structures
in the contractors
scope
Reply
Accepted. But at any given
point of time only two pumps
are required to operate and
the third will be a standby
Accepted, The Motor control
centre (MCC) shall be housed
in the pump house Electrical
room (E room)
Yes, This is in contractors
scope.