CA02-Change Routing End User Procedures: Business Process
CA02-Change Routing End User Procedures: Business Process
End User
Procedures
Routing - Change
A routing is a description of which operations (process steps) have to be carried out and in which order to
produce a material (product). In addition to information about the operations and the order in which they
are carried out, a routing also contains details about the work centers at which they are carried out as well
as about the required production resources and tools (includes jigs and fixtures). Standard values for the
execution of individual operations are also saved in routings.
Activity
1. Follow the SAP menu as shown, or type the transaction code CA02 in the command field.
Page 1 of 3
Business Process
End User
Procedures
Plant: Enter (3000) Plant Number or Select from Pull-Down Window for other plants.
Sales Document Item: Enter sales document line number for KMAT materials only.
Key Date: Defaults to Current date. Enter validity date if not Current date.
Plant: NO ENTRY REQUIRED This is the Key that identifies the Plant in which routings
plans or reference operation sets to be selected are valid.
Task List Status: NO ENTRY REQUIRED Key that specifies the processing status of
the task list. Enter task list status, or pull down menu if desired
Profile: NO ENTRY REQUIRED Key to group of default settings Enter Profile Key or
select from Pull Down menu if desired.
Page 2 of 3
Business Process
End User
Procedures
3. To enter the Change Routing: Operation Overview press the Enter key.
From this point forward, navigation and field content is identical to that described within the Routing
Create procedure.
Note: Data fields that exist with a white background may be changed. Fields with a blue
background may not.
4. Click the save button
are complete.
or key the enter key to save the completed routing when all changes
Page 3 of 3