ATC REPORT
Activity: AUDIT/PROCESS
China / Huaibei Plant
KILN AUDIT
by: ATC P&E Team
04~08Dec2007
Distribution:
Region
BU
Plant
ATC
Other
Codification
Rosy Wang /Wang ZhiHonh( for plant distribution)
Renaud de Belmont // G.Benveniste
TSP/HUA400/NQI/20080205/HUA kiln audit
Table of Content
A.
Executive Summary............................................................................................................... 2
B. Main Report............................................................................................................................ 4
B.1. Introduction......................................................................................................................... 4
B.2. Work Done:........................................................................................................................ 4
B.3. Analysis / Argument / Conclusions.....................................................................................5
B.3.1
Safety alert.................................................................................................................5
B.3.2
Plant information.........................................................................................................5
B.3.3
Heat and mass balance..............................................................................................8
B.3.4
Cooler performance..................................................................................................10
B.3.5
Preheater and precalciner inspection........................................................................12
B.3.6
Gas analyzer and false air........................................................................................15
B.3.7
NOx and SO2........................................................................................................... 18
B.3.8
Burner audit.............................................................................................................. 19
B.3.9
Volatile balance.........................................................................................................22
B.3.10 Fan efficiency............................................................................................................ 24
B.3.11
Operation.................................................................................................................. 25
B.3.12 Quality and Sample analysis.....................................................................................26
B.4. Recommendations............................................................................................................ 27
B.5. Acknowledgements.......................................................................................................... 29
B.6. References....................................................................................................................... 29
B.7. Appendices....................................................................................................................... 29
A.
Executive Summary
Objectives
Training of Lafarge ATC P&E engineers
Make an extensive kiln heat and mass balance
Run tests of general interest for technical assistance in LSO
NOx abatement Environmental protection standards
A 7 day report was sent after the audit based on the [presentation given to the plant (see
attachment)
Results and Findings
Global heat consumption was 777kcal/kg-ck @ clinker production 1145.5tpd. Main KPIs are as
following:
Kiln parameters:
actual
target
clinker production
1145.5 tpd
Clinker C3S & clinker CaOl
777kcal/kg-k
specific heat consumption
730
efficiency of top cyclones
94.9%
>92%
ID fan power consumption
12.45kWh/t-k
ID fan efficiency
53%
>70%
kiln/calciner ratio
38.6 : 62.4
>40% at kiln
Decarbonation
90~95%
primary air ratio
16%
12%
total false air (based C1
18.31%
<10%
outlet)efficiency
Cooler
recovery ratio:
0.67
0.70
cooling efficiency:
0.94
0.95
k-factor:
1.39
1.30
138kcal/kgck
Cooler loss:
<120
45.82t/m2.d
cooler load
<45
2.19N3/kg-k
cooling air specific
~2.2
The kiln operates at full capacity. The bottlenecks are ID fan (PH pressure drop), precalciner size
(1.4s residence time), EP Fan (false air).
Improvement Opportunities
Through implementation of following actions about 44kcal/kg-ck heat loss could be saved.
Table of actions:
No.
Action
Priority
Light the blower room of coal workshop
Fix the air cannon inlet valve at kiln inlet chamber
Reduce NOx and increase free lime by reducing overburning
Changing the TAD refractory
Reduce primary air of kiln burner, apply new burner
Arrest false air along the kiln, preheater and raw mill line.
Optimize cooler operation
ID fan optimize
prepare SOP for operators
10
10 rules of kiln operation
1
Page 2 of 31
Based these recommendations, the plant should establish a detailed action plan going through
priority level, actions, and expected results, starting and finishing dates, resources/ responsibilities.
In report recommendation chapter, one page indicates for each action ATC point of view regarding
objectives, way to implement, reference documents, persons in charge, cost and expected results.
Emergency Actions
None
Further Work
As part of the de-bottlenecking project, it is recommended to use the de-bottlenecking tool.
As ARL analysis could not be sent on time, an addendum will be written later taking into
account the finding of the analysis.
Miscellaneous topics
The plant has stated that one of their bottlenecks is the kiln drive capacity. We thus suggest testing
increasing the kiln filling rate (thus reducing the ratio kiln speed/kiln feed) to reduce the torque
induced by the materials.
Mainly due to limited residence time in the precalciner, the plant has got high CO at preheater
outlet, thus negatively impacting heat consumption. We have to consider increasing the coal feed at
kiln (thus decreasing coal feed at precal), although this is linked to various other issues (IDfan
capacity, pressure drop in the preheater).
Page 3 of 31
B.
Main Report
B.1. Introduction
The Huaibei plant kiln audit was carried out during 3-7Dec, 2007. ATC & Plant process team, DJY
process manager, and Shunfa process engineers participated. This report focuses only the HUA
plant related results.
Objectives of audit
- Training of Lafarge ATC P&E engineers
Make an extensive kiln heat and mass balance, including:
Dust weigh-check, clinker drop test
Volatile balance
Clinker temperature using calorimetric box
Secondary air temperature mapping in the kiln hood
Preheater survey
Run tests of general interest for technical assistance in LSO:
Test Chinese-made gas analyzer
Challenge ATC BO Process measurement techniques and equipment
Get data for on-going plant issues:
Preheater survey Preheater modification
NOx abatement Environmental protection standards
ID fan efficiency De-bottlenecking
Agenda of audit
- Monday (preparation)
-
Tuesday (heat and mass balance)
Wednesday (PH survey, Dust sampling perturbated because kiln condition)
Thursday (PH survey, Preca Efficiency, Volatile Balance, False Air, Analysers benchmark)
Friday (quick report and debriefing)
B.2. Work Done:
Field measurement
Fan efficiency
Preheater survey
Temperature, pressure, and gas flow of the pyro-system
Cooler survey
Sample analyses
Raw mix (raw mill outlet)
K1450 (burnability)
Various chemical analyses (pyretic S, C, alkalis, Cl)
Preheater feed
C5 outlet material (hot meal dry // wet)
SO3, alkalis, Cl, unburnt C
Clinker
Microscopy
DX-Rietweld method
BB10 (grind ability)
Page 4 of 31
Various chemical analyses
Coal
Ultimate analysis
Remarks
Possibility to benchmark plan lab and ARL on some analyses
Opportunity for the plant to get some non-frequently carried out analyses results (pyretic
sulfur)
More comprehensive result interpretation can be done once results are received
B.3. Analysis / Argument / Conclusions
B.3.1 Safety alert
Safety alert 1
Theres no lamp in the blower section of coal mill workshop. During the day, its dark
inside the room.
Recommendation: Identify the reason, and then take corresponding measures to make
the room with sufficient light. Since it is in a coal grinding shop, we must have the
appropriate sealed light.
Safety alert 2
At the kiln inlet chamber, compressed air inlet
valve of air cannon cant be locked (see photo
on the right)
Recommendation:
Improve
LOTOTO
according to Lafarges Safety Regulation.
B.3.2 Plant information
Main equipments of Huaibei plant pyro system
Table 3.2.1: main equipments of pyro system
Equipments
ID fan
Preheater
Kiln
Cooler
Cooler EP fan
Specification
Flow 168000 170000m /h, Pressure 7840Pa, Temp.340C , gas density
1.4kg/Nm3, Motor YR4504, 560KW, 1500r/min
TC F7 type // 5 stage preheater: C1(x2): 3400mm, C2&3: 4500mm,
C4&5: 4800mm
PC: 4400mm, TAD: 1800mm
=3m, L=48M // Slope: 3.5 // speed 0.696~4.8rpm // auxiliary speed
0.2189rpm
2.13m (width) 13.5m (length) // 3.41~13.64strokes/min // moving distance
127mm // eff. Area 25m2 // Tinlet=13001400C, Toutlet=70Cambient
Fan: Y47311, NO18D // anti.45C, 145000m3/htotal pressure 1529Pa
Motor Y315M28
3
Page 5 of 31
Production during the audit days (plant information)
- Monday
Operation as normal, clinker output was 1180 t.
during kiln audit, decrease wind power out of the 5th cooler fan
- Tuesday
Operation as normal, clinker output was 1192t [Note: drop test:1145.5tpd].
During kiln audit, decrease wind power out of the 5th cooler fan
- Wednesday
Kiln main motor halted at 10:36; renewed feed in kiln at 11:43.
Decreased feed in kiln, from 14:00 to 16:30 (coal mill main motor)
Kiln feed get back 75t at 19:00.
Clinker output: 0:00-8:00 400t; 8:00-16:00 204t; 16:00-24:00 316t
Variation of operation was observed when shift changing.
- Thursday
Operation as normal, clinker output was1154t
During kiln audit, decrease wind power out of the 5th cooler fan.
Variation of operation was observed when shift changing
Notes:
- Raw material stagnate at preheater tube stack, air blaster was not opened to clean it for
auditors safety. (abnormal)
Fig 3.2.1: Kiln operation trends on 3 Dec
Page 6 of 31
Fig 3.2.2: Kiln operation trends on 4 Dec
Fig 3.2.3 : Kiln operation trends on 5 Dec
Page 7 of 31
Fig 3.2.4: Kiln operation trends on 6 Dec
We can see that Dec 3rd and 4th production was steady, but a stoppage of kiln happened in
Dec 5th. Hence, it is consider that the conditions of operation were representative on Tuesday
4th during the heat and mass balance.
B.3.3 Heat and mass balance
The production of Dec 4th is 1192tpd as recorded. But, by drop testing, the kiln production during the
audit (Dec 4th) was 1145.5tpd. Discrepancy is 4%.
The global heat balance was 777kcal/kg-ck during the audit (to be updated till the coal ultimate
analysis will be carried out). And it is higher for a 5-stage precalciner kiln.
Coal feed was 127 kg/t-ck during the audit and fuel split was 38.6% to the kiln and 62.4% to the
calciner.
Table 3.3.1: Mass and Heat Balance
Global Balance
input
cooling air
raw feed
wet content
coal feed
wet content
primary air
false air
SHC
Sum
Nm3/kg-k
2.196
0.070
0.275
kg/kg-k
2.839
1.645
0.003
0.122
0.005
0.091
0.356
kcal/kg.C kcal/kg-k output
0.240
6.82
clinker
0.192
18.95 vent air
1.001
0.21
ph exit gas
0.263
0.87
ph fly dust
0.999
0.14
wall loss
0.240
0.59
vaporisation
0.240
0.86
clinkerisation
777.1
805.56 Sum
10
60
60
27
27
27
10
5.061
Nm3/kg-k
1.397
1.479
kg/kg-k
1.000
1.806
2.140
0.115
120
260
315
315
0.003
5.061
kcal/kg.C kcal/kg-k
0.190
22.84
0.243
114.03
0.253
170.56
0.229
8.27
71.50
596
2.06
418.63
807.90
Main reasons for high SHC include:
- Higher wall losses
Especially the TAD surface temperature got 174C, which leads 7.22 kcal/kg-ck increase of heat
loss offsetting that at the surface temperature being 90C. ATC will provide a short note on this
issue.
Table 3.3.2: TAD surface temperature
C1
C2
C3
C4
C5
PC
TAD
Kiln
cooler
Wall losses
HUA
63
58
67
98
94
94
174
251
68
8.85%
HCN
102
52
66
74
80
90
90
265
65
4.58%
Page 8 of 31
Table 3.3.3: Heat loss of the TAD
Diameter
Length
Surface
Shell surface
Ambient t
Wind velocity
Heat loss
kcal/kgCk
1.70m
53m
283m2
174C
8C
2.5m/s
686159kcal/h
14.28
53m
90C
8C
2.5m/s
338946 kcal/h
7.06
1.70m
283m
- High CO at preheater outlet
Higher CO reflects an incomplete combustion until top cyclones of the preheater. 2400ppm CO
would cause more heat loss of about 10.7kcal/kgCk. As stated at table 3.3.5, CO at PH outlet was
higher than C5, is related to the precalciner combustion condition due to less resident time(1.4sec),
and maybe due to carbon content in the raw mix (to be checked by raw mix chemical analyze).
However, C5 CO is high because low residence time in precalciner.
Table 3.3.4: Gas analysis at Dec 4
Huabei Audit
Heat lost with CO
Dec-07
CO Dunbar
ppm
% v/v
Nm3/h CO kcal/h CO
CO PH
2400
0.24%
168.8
509817
CO Kiln
500
0.050%
10.0
30200
PH Nm3/h
70339
Kiln Nm3/h
20000
Pkcal/Nm3 CO
3020
CO + 1/2O2 --> CO2 + 67.6kcal/mol
kg/h ck
47708.33
kcal/kgck
10.69
0.63
Table 3.3.5: Gas analysis at Dec 4
Measurement at 4th Dec
Content
O2 %
CO ppm
NOx ppm
Kiln back end
3.15
500
2650
C5 outlet
3.37
1280
850
ID fan inlet
4.67
2400
800
- High O2 at preheater outlet
Also more oxygen (4.7%) in the exhaust gas, it is well known that the more the excessive air, the
more the heat loss. If the oxygen density be less (3%), the heat loss would be reduced by about
10kcal/kg-ck. One reason of the high O2 concentration is theres too much false air along the kiln
and preheater (18.6% based on preheater outlet gas). And about 7.2% comes from the preheater,
and 11.4% comes from kiln back end and kiln hood.
It was observed that O2 at preheat exit reduced to about 3.5% in the last two days of the audit,
since ID fan speed slow down a little from 13971388rpm.
Table 3.3.6: Total input air volume to kiln and preheater
items
flow
unit
Comments
Kiln Primary air
0.055
Nm3/kg-ck
15.85% based on PA & SA
Secondary air
0.292
Nm3/kg-ck
Calciner Primary
air
0.016
Nm3/kg-ck
Tertiary air
0.506
Nm3/kg-ck
False air of PH
0.106
Nm3/kg-ck
7.2% based on PH gas flow 1.479Nm3/kg-ck
False air of kiln
0.169
Nm3/kg-ck
11.4% based on PH gas flow1.479Nm3/kg-ck
- Higher cooler vent air temperature
Cooler vent air temperature was 260C. Its higher than normal figure (<240C). Thus the excessive
heat loss would be about 9kcal/kgck. Causes to be discussed later in cooler performance.
Page 9 of 31
Table 3.3.7: Heat loss due to vent air
Nm3/kg-k
kg/kg-k
kcal/kg.C
kcal/kg-k
vent air
1.396
1.805
260
0.243
113.94
vent air
1.396
1.805
240
0.242
105.01
8.93
- Higher clinker temperature
Clinker temperature at the bucket conveyer was measured ranging between 61~111C, average
85C, but the clinker pile temperature at silo side was 120C. In the calculation of heat balance we
took the 120C, and If we took 85C, the heat saving would be about 7.01kcal/kg-ck.
Recommendation
Based on the above analyze, total heat loss could be saved by about 44 kcal/kg-ck, and thus SHC
would be 730~735kcal/kg-ck, if following recommendations were implemented:
Reduce the TAD surface temperature to 90C through changing the TAD refractory with
Calcium Silicate Board + refractory brick.
Reduce O2: match the ID fan speed with raw feed so that reducing the O2 at PH top (~3%),
and false air as stated in the Gas analyzer and false air.
Reduce CO through: precalciner size to be checked to make sure resident time is enough
(>3.5sec)also debottlenecking project, and carbon content in raw mix to be valuated to
see if it is have relation with high CO.
Reduce cooler vent air temperature to below 240C, through optimizing operation.
Reduce clinker temperature to 70C + ambient. To be discussed following in cooler
performance.
B.3.4 Cooler performance
Findings:
Overall cooler heat loss is high 138kcal/kg-ck (see table 1.3.4.1). The heat loss that oversteps
average level comes from high clinker temperature (120C vs 85C), cooler vent air high
temperature. Other parameters see table 1.3.4.2.
Table 3.4.1: Cooler heat and mass balance
Table 3.4.2: Cooler efficiency:
Items
actual
Standard
recovery ratio
0.67
0.70
cooling efficiency
0.94
0.95
k-factor
1.39
Cooler loss
138.3
cooler load
45.8
cooling air specific
2.19
1.30
Comments
High PA to be reduced and
blowing
density
to
be
optimized
kcal/kg-ck
<120
t/m2.d
<45
OK
N3/kg-k
~2.2
OK
Reasons for the heat loss could be:
Too much blowing density in the cooling side of cooler which is related to the high
temperature of vent air, and less blowing density in the recuperating side of cooler. Cooler
blowing density is as table 3.4.3.
Page 10 of 31
High clinker temperature 120C is the silo side, but at bucket conveyer it ranged between
61~111C, average 85C.
And meanwhile, too much kiln primary air is related to the heat loss in cooler: much primary
air less secondary air much vent airmuch heat loss.
Room of improvement
As showing of the blowing density, blowing density need improving through enlarging the
fans in chamber 1# and 2# as table 3.4.3 indicated.
And re-adjust the blowing density as recommendation curve to be close to the
recommendation curve.
Reduce kiln primary air as stated in section Burner audit.
Table 3.4.4: Cooler blowing density
Table 3.4.3: Cooler fans measurement and recommendation
Items
Measurement
Recommenda
tion
Flow [m3/h]
Fan 1#
Fan 2#
Fan 3#
Fan 4#
Fan 5#
Sum
15319
17524
22943
24658
24393
104836
3664
3340
2800
1778
28771
20814
18823
17022
Pressure [Pa]
Flow [m3/h]
19575
Pressure [Pa]
Page 11 of 31
105004
B.3.5 Preheater and precalciner inspection
Preheater survey
Very high pressure loss, preheater top 818mmWG. below is the pressure drop for each
stage of the cyclones. C3, C4and C5 have high pressure drop in the cyclones.
Table 3.5.1: Preheater pressure drop
C1
C2
C3
C4
C5
Cyclone (mmWG)
58
61
100
101
94
Riser duct (mmWG)
81
83
73
65
72
Very high cyclone loading ~110 tpd/m2 (shall be <90)
False Air Control in the PH itself is very good sealing. Total false air 8.4%. But between
C4~C5 4.2%, see also the kiln inlet dust hopper connected to dust reclaiming system without
flaps (see photo Gas analyzer and false air)
No by-passes (material or gas) were detected (high velocities and very tight flaps. See table
3.5.5
De-bottlenecking to be done but only C3 is easily possible. For C3, roof can be risen by 1m;
For other cyclones, because of beam, it is not possible to rise the position of the splash box
and as a result rising the cyclone roof is difficult
Very High CO in gas - Calciner volume too small: <1.4 s (to be calculated).
Kiln outlet CO:170~555ppm. Good
C5 outlet CO: 390~3400ppm. High variability of CO.
It can be observed carbon burning in the hot meal (C5)
Raw mix carbon to be done by ARL.
Table 3.5.2: Preheater gasflow (to be updated)
Gasflow Tempe.
Cyclone 1
Cyclone 2
Cyclone 3
Cyclone 4
Cyclone 5
Calciner
TAD
kiln
Gasflow
Pressure
Size (m2)
velocity (m/s)
Nm3/kg-ck
mmWG
m3/h
m3/s
inlet
cyclone
outlet
inlet
cyclone
outlet
1.479
1.442
1.410
1.391
1.256
1.256
0.506
0.447
318
460
583
739
878
850
945
969
-818
-717
-507
-377
-226
-170
-112
-20
168726
202030
225623
259787
262552
254728
110703
98817
47
56
63
72
73
71
31
27
2.00
2.52
2.52
2.86
2.86
100.00m3
1.33
4.51
13.20
12.56
12.56
14.51
14.51
2.40
2.77
2.77
3.14
3.14
23.43
22.27
24.87
25.23
25.50
1.41sec
23.18
6.09
3.55
4.47
4.99
4.97
5.02
19.50
20.23
22.59
22.98
23.23
Precalciner Efficiency
Poor temperature profile in the riser duct; one side goes high to 950C, and the other side
just stays less than 800C.
The hot core touches the refractory in the front of the burner. To be further investigated
(transport air velocity, position ) :
Temperature profile OK in the vortex
Samples analyze to be done by ARL.
Precalciner efficiency & mapping still waiting for un-burnt carbon measurement
Decarbonation of hot meal is between 90~95%. And SO3 is steady.
Table 3.5.3: hot meal
Hours
11:00
13:00
15:00
17:00
19:00
SO3
1.73
1.64
1.67
1.68
1.68
LOI
4.83
4.14
5.2
3.74
2.58
Page 12 of 31
Decarbonation
90.78%
92.2%
90.0%
92.9%
95.2%
Table 3.5.4: Preheater survey
Page 13 of 31
Table 3.5.5: Gas by-pass and meal by-pass checking
Page 14 of 31
Fig 3.5.1: Riser Duct Mapping
Fig 3.5.2: Vertex chamber mapping
B.3.6 Gas analyzer and false air
During the kiln audit, we measured the preheater and stack gas analysis. And below is the result:
Page 15 of 31
Table 3.6.1: Gas analysis at 6th Dec. with the TESTO350pro analyzer
Content
O2
CO
NOx
Unit
ppm
ppm
Kiln back end
2.5
353
2770
C5 outlet
2.18
1380
850
ID fan inlet
3.65
2400
810
raw mill bagfilter inlet
8.97
1500
570
Bagfilter fan inlet
10.9
1570
465
Findings
False air was 7.8%in preheater above C5 outlet. Its OK.
False air was 42% between ID fan and bag filter fan. It is high, and O2 should be less than
7.5%~8.5% at bag filter fan inlet.
False air in the bagfilter was 16%. And before it 30.7% in the raw mill system.
Hence, the power consumption of EP fan to be reduced by 44kW, thats 0.94kwh/t-ck.
Table 3.6.2: power saving by reducing false air
O2
O2
False air
coefficient
ID fan -- Bagfilter outlet
3.65
10.9
41.8%
ID fan Bagfilter inlet
3.65
8.97
30.66%
Bagfilter inlet--outlet
8.97
10.9
16.04%
Future
3.65
25.1%
Power
consumption
(kW)
199
155
Recommendation
Inspect along the kiln, preheater and raw mill system and make mark of the false air when the kiln
and raw mill starting, and repair them when shutting down. See Fig 3.6.2 and fig 3.6.3
Fig 3.6.1: False air survey
Page 16 of 31
Fig 3.6.3: False in raw mill system
Page 17 of 31
Fig 3.6.2: False Air in PH
To be added flap
damper to seal fasle
air to KBE
B.3.7 NOx and SO2
Findings
NOx at kiln back end is high, 2707ppm.
Looking to NOx concentration figures, it looks as though there is post-combustion in
precalciner. Actually, the NOx reduction from kiln back-end to precalciner outlet is due to gas
dilution (more gas at precalciner outlet than at kiln back-end). In terms of kg of NOx per kg of
clinker, it does not change. CO in precalciner does not contribute to NOx reduction because
of too low residence time in the precalciner.
NOx concentration in the stack is 1108mg/Nm3 vs. 500mg/Nm3 as per Chinese standard
SO2 was not detected from KBE and preheater. Low SO2 at KBE is difficult to explain. It can
be explained by the fact that SO3/alk ratio is low. It has to be highlighted that TESTO
supplier participated to the audit with brand new equipment and still could not detect SO2
neither. This measurement shall be further confirmed once ATC gets accurate SO2
monitoring equipment.
Room for improvement
Reduce NOx at kiln BE by avoiding over-burning.
Include multistage combustion in new de-bottle necking project.
Investigate SNCR in the future.
SNCR-- Selective Non-Catalytic Reduction
Page 18 of 31
Table 1.3.6.9: NOx concentration mapping
Figure 1.3.6.1: NOx Mapping in ppm
B.3.8 Burner audit
Finding
Now the burner stands for 3 months of life time with its tip. Reason was due to wearing from
high transport air tip velocity (67 m/s).
High clinker temperature at kiln discharge (1488C) and High NOx (2770ppm KBE) was also
detected. The cause could be the high burner Specific Impulse (7.67Nh/Gcal) due to high air
velocity at burner tip. Also the high burning zone temperature resulted in high Sulfur
Volatilization factor (85%).
Table3.8.1: Kiln primary air
axial air :
0.019Nm3/kg-k
5.52%
radial :
0.013Nm3/kg-k
3.69%
transport :
0.023Nm3/kg-k
6.65%
Total :
0.055Nm3/kg-k
15.86%
Table3.8.2: gas analysis at KBE
Gas Analyzing
Kiln back end
O2
CO
NOx
ppm
ppm
2.5
353
2770
Recommendation
A new burner is suggested and the design has been done.
Page 19 of 31
The coal transportation air velocity will be reduced to 26 m/s. This will reduce the wear
degree of burner tip dramatically.
The coal transportation pipe diameter will be 105 mm.
The coal transportation air content will be reduced from 9 % to 3.5 %. This will also
contribute to SHC, NOx and Is reduction.
Fig 3.8.1: Kiln main burner calculation present operation
IMPULSION AND SWIRL CALCULATION
Plant : Huabei
Date : 04.12.2007
Name : ATCBOTeam/Yang J inBiao / Qian Feng
IMPULSION - Version on 10/04/95
CLV / Stphane THIERS
COMMENTS :
Actual Operation
OUTLET SURFACES
diameter
(mm)
198
182
AXIAL AIR
856
surface reduction %
Ext.diam. : 245
thIckness 9
227
273 m/s
210 m/s
mm2
152
120
COAL AIR
6836
180
39 m/s
67 m/s
mm2
121
100
82
78 m/s
Waste fuel
1. J acket Tube/Waste pipe
2. J acket Tube/Waste pipe
Name
Solid waste
Dia (mm)
80
Pipe speed (m/s)
0
DETAIL OF THE NOZZLE
Swirl
angle ()
35
Fins
number
12
Orifices
width
16.2
16.2
RADIAL AIR
76 m/s
15.3 (head)
10.9 (base)
Axial (if holes)
Number of holes :
Base data
Kiln system :
Fins
width
9.7 (head)
5.3 (base)
10.6
10.6
10
Fins radial
gap (mm)
0.5
Diameter :
AS
SP : no calciner, AT : air through, AS : separated air.
Heat consumption th/T KK :
1175
0.96
Inside kiln shell diameter (m) :
LCV
Kcal/kg
6100
0
Therm.energy
Gcal/h
15.27
0.00
0.00
0.00
Total (Gcal/h) :
AERAULIC MEASUREMENTS
Stat. press. in the burner (mmWG)
T in the burner (C)
Theoretical flow (Nm3/h)
Adopted flow (Nm3/h)
Bias coefficient :
Atmospheric pressure (mmWG)
Inlet air temperature
Inlet flow (m3/h)
Axial
4500
100
655
655
1.00
10204
20
703
10
PRODUCTION (T CK /j) :
% of fuel to the pre-heater :
Flow
kg/h
2503
0
rayon
raccord.
1
Total neutral combustion air (Nm3/kg CK) :
780
Heat consumption
to the main burner
Petcoke
Solid waste
194
7
133
6
16 m/s
Ext.diam. : 76
thIckness 8
1476
mm2
(surface area normal to the flow)
Radial (constant width for orifices)
Radial (constant width for orifices)
Radial (constant width for fins)
Radial (constant width for fins)
16 m/s
Ext.diam. :
thIckness
Ext.diam. :
thIckness
60
3.00
Recalculated heat consumption :
780
OK
th/T KK
15.27
Radial
400
30
379
360
0.95
Transport
2000
50
1638
Solid waste
2000
50
20
387
20
1758
20
0
RESULTS
SPEEDS
Type of flow
Axial
Radial
Transport air
subsonic
subsonic
speed
273
78
39.4
Outlet speed (m/s)
MAP/MAS
2.87
Is
N.h/Gcal
7.67
Table3.8.3: Burner air suggestion
Content of axial air
4.6%
radial
3.9%
Page 20 of 31
transport
3.7%
Total
12.2%
Swirl
0.024
Fig 3.8.2: Kiln main burner calculation New burner Design
IMPULSION AND SWIRL CALCULATION
Plant : Huaibei
Date : 16.05.2007
Name : Chandrasekar J ayaraman
IMPULSION - Version on 10/04/95
CLV / Stphane THIERS
COMMENTS :
New Lafarge Burner - Coal
OUTLET SURFACES
diameter
(mm)
surface reduction %
Ext.diam. : 295
thIckness 9
277
AXIAL AIR
223 m/s
1810
188 m/s
mm2
215
180
COAL AIR
10858
215
26 m/s
26 m/s
mm2
160
156
136
150 m/s
Waste fuel
1. J acket Tube/Waste pipe
2. J acket Tube/Waste pipe
Name
Solid waste
Dia (mm)
80
Pipe speed (m/s)
0
DETAIL OF THE NOZZLE
Swirl
angle ()
35
Fins
number
17
Orifices
width
14
14
RADIAL AIR
133 m/s
15.8 (head)
12.3 (base)
Axial (if holes)
Base data
Kiln system :
Number of holes :
Heat consumption th/T KK :
Fins
width
14.6 (head)
11.1 (base)
12.8
12.8
16
Fins radial
gap (mm)
0.5
12.00
PRODUCTION (T CK /j) :
1300
Total neutral combustion air (Nm3/kg CK) :
0.95
770
% of fuel to the pre-heater :
Inside kiln shell diameter (m) :
Heat consumption
to the main burner
Coal
Solid waste
Flow
kg/h
3077
0
LCV
Kcal/kg
6100
0
Total (Gcal/h) :
AERAULIC MEASUREMENTS
Stat. press. in the burner (mmWG)
T in the burner (C)
Theoretical flow (Nm3/h)
Adopted flow (Nm3/h)
Bias coefficient :
Atmospheric pressure (mmWG)
Inlet air temperature
Inlet flow (m3/h)
Axial
2700
100
1070
1070
1.00
10000
20
1149
rayon
raccord.
1
Diameter :
AS
SP : no calciner, AT : air through, AS : separated air.
245
15
180
10
31 m/s
Ext.diam. : 121
thIckness 8
2045
mm2
(surface area normal to the flow)
Radial (constant width for orifices)
Radial (constant width for orifices)
Radial (constant width for fins)
Radial (constant width for fins)
25 m/s
Ext.diam. :
thIckness
Ext.diam. :
thIckness
Therm.energy
Gcal/h
18.77
0.00
0.00
0.00
55
3.00
Recalculated heat consumption :
770
OK
th/T KK
18.77
Radial
1800
60
1048
891
0.85
Transport
600
60
850
Solid waste
0
50
20
956
20
912
20
0
RESULTS
SPEEDS
Type of flow
Outlet speed (m/s)
Axial
Radial
Transport air
subsonic
subsonic
speed
223
150
25.8
Objectives
to
obtain:
Fuel-Oil
Coal
Petrol coke
Content of axial air : 4.63%
radial : 3.85%
transport : 3.68%
J acket Tubes/Waste pipes 0.00%
Content of primary air 12.16%
Page 21 of 31
MAP/MAS
2.07
Is
N.h/Gcal
7.11
5
6
>7
Swirl
0.155
0.15
0.15
0.15
B.3.9 Volatile balance
Main finding
The Volatilization Factor is high 85% comparing with normal Volatilization Factor 55% of
Precalciner kiln. However, this high ratio comes from high SO3 content I the dust escaping
the kiln.
SO3 content in clinker is only 0.3% due to low SO3 in the raw meal.
The NOx in kiln backend gas is very high (average 2400ppm, max 3600 ppm). These results
indicate a high temperature in burning zone. This is confirmed by the low free lime (0.5 to
0.7%).
And sometimes material rings and clinker balls appeared in kiln from plant report, which
means plant needs take some actions to reduce volatile re-circulating in kiln. See fig 3 hereafter.
The plant reports build up in riser duct as well as seldom ring/ball formation. This can be
caused by cold false air entering through the dust reclaiming system, carbon content in C5
meal, burner flame adjustment (see November 2007 ring formation) or high alkali.
Recommendations
For short term steps, keep proper O2 content (2.5-3%) at the kiln backend, and adjust the
burner, so that decrease kiln burning zone temperature (step by step following the clinker
quality).
Try to control a short flame by new burner design and primary air adjustment through new
burner design.
Further investigations at kiln back end (iso kinetic sampling and SO2 measurement) to cross
check the information.
Table 3.9.1: The HuaiBei plant sampler data in Volatile balance 20071207 1
2 ways of dust collecting in gas was taken: one is suction pump and another is scoop.
Obviously, the SO3 content is too low in kiln dust by scoop method, maybe some material from
C5 mixed in the sample. So we discarded the sample results by scoop method.
Page 22 of 31
Table 3.9.2: The calculation of HuaiBei kiln sulphur balance 20071207
The ratio 0.15kgdust/kgck is a standard figure (see vademecum, considering that the kiln is closed
to its max capacity. Velocity was ~16m/s).
Photo 3.9.1: The volatile check area in HuaiBei kiln audit 20071207
Photo 3.9.2: The kiln backend gas dust sampling method in HuaiBei plant 20071207
Page 23 of 31
Photo 3.9.3: The Volatilization and its consequences
B.3.10Fan efficiency
Findings
The efficiency of ID fan and EP fan was inspected during the audit. And findings are:
The ID fan efficiency is too low around 53%.
To increase the efficiency to be 75%, power consumption can be reduced by 174kW, or
3.65kWh/t-ck.
As a result, specific power consumption of the ID fan is high12.5kWh/tck;
ID Fan is current kiln bottleneck.
The EP fan efficiency is ok 74%.
False air is relatively controlled in PH outlet.
Actual fan rpm was 1420 rpm compare with 1394 rpm at CCR.
The pressure drop at fan inlet damper was ~ 50 mm H2O.
Fan power was 594 kW. Motor rated power was 630 kW.
Improvement actions
Junction box at ID fan outlet tapping to coal and raw mill from this box
Supplier to check why internal recirculation (ATC can support)
Check diffuser at outlet
Remove the damper or at least one by one damper blades (check electrical and mechanical
aspect of it): potential saving 5mbar.
Fill and send Flackt fan questionnary (see in annex)
Fig 3.10.1: ID fan and EP fan measurement
Page 24 of 31
Table 3.9.1: Quick Win Fan Efficiency Calculations (ID fan)
Items
Measured,
actual
Fan speed
1420
rpm
Fan Inlet Static Pressure
-877
mmWg
Fan Outlet Static Pressure
-270
mmWg
Fan Inlet Volume
169119
m3/hr
Gas Temperature
315
Motor Power Consumed
594
Total Loss
10%
Shaft Power (calculated)
534.6
Static Pressure Difference across Fan
607
Power output
314.8
314.8
kW
Fan Efficiency (Static - Calculated)
53%
75%
To be
unit
419.8
kW
%
377.8
kW
mmWg
Table 3.9.2: Quick Win Fan Efficiency Calculations (EP fan)
Items
Measured, actual
Fan rpm
1082
rpm
Fan Inlet Static Pressure
-465
mmWg
Fan Outlet Static Pressure
-97
mmWg
Fan Inlet Volume
183250
m3/hr
Gas Temperature
151
OC
Motor Power Consumed
280
kW
Total Loss
10%
SPRS Recovery (Power Recovery)
kW
Shaft Power (calculated)
252
kW
Static Pressure Difference across Fan
367.98
mmWg
Fan Efficiency (Static - Calculated)
74%
B.3.11 Operation
SOP
-
Finding:
The plant said that they have hot kiln feeding SOP and follow it. But there is not SOP
manuals on operating desk in CCR.
The plant claims (see WXH monthly report) that it follows 6 SOPs.
- Recommendation:
Prepare SOPs and set on operating desk for operators reference by Plant kiln coach.
10 rules
- Finding:
Kiln load volume----there is not operating table between kiln speed and feeding.
Cooler clinker bed depth----O.K. is controlled through under grate pressure by manual.
Cooler cooling fan predefined table----? there is no air flow indicator on operating screen.
Kiln hood slightly negative pressure----? there is slightly positive pressure by manual
Constant oxygen in kiln back end----O.K. is between 2~4% by manual.
Constant oxygen in PH outlet----O.K. it is between 3~5% by manual.
Page 25 of 31
Constant ID fan outlet pressure----O.K. it is 150~300Pa by manual.
Fuel amount proportional to kiln feeding----? They have implemented but there is no
operating table.
Constant calcinations----O.K. Temperature on pre-calciner outlet is controlled by coal
feeding to pre-calciner manually.
Maximize production and minimize heat consumption----O.K. Maximization production is
80 t/h of raw meal.
The kiln filling rate is 12.4% (see table 3.11.1).
Table 3.11.1: kiln filling rate
Recommendation
Prepare an operation table of kiln and cooler on CCR.
Try to keep kiln hood under slight negative pressure about 0.2mbar and to observe which
changes.
Install 3 auto controlling PID loops between kiln hood pressure and cooler venting fan
speed, cooler grate speed and under grate pressure of 2nd chamber, PH ID fan outlet
pressure and EP ID fan speed. Recovery using PID loop between precalciner coal
feeding and precalciner outlet temperature.
B.3.12Quality and Sample analysis
All the samples taken for the audit were analyzed at the plant laboratory (where possible) and Asian
Regional Laboratory(to be analyzed), including some specific analyses such as Organic carbon on
raw mix and ultimate analyses of fuel.
- Clinker and raw mix chemical analysis
Clinker f-CaO mostly between 0.5%~0.7%.
Steady burning in the kiln
Over burning in the kiln
- SO3/(K2O+Na2O) of Clinker
S/K is low
Contribute to ring formation in kiln and build-ups at KBE.
- C5 hot meal
SO3 between 1.6~1.7%
LOI and decarbonation is steady
Table 3.12.1: chemical analyses of clinker and raw feed
Page 26 of 31
LOI
SiO2
AL2O3
Fe2O3
CaO
MgO
K2O
Na2O
SO3
SUM
fCaO
clinker
22.77
4.12
2.87
66.47
1.85
0.84
0.13
0.25
99.29
0.65
raw feed
35.55
14.32
2.64
1.78
43.14
1.26
0.56
0.08
0.06
99.38
35.61
Table 3.12.2: Clinker S/K
%
kgmol
Mol
K2O
0.84
94.20
0.0089
Na2O
0.13
62.00
0.0021
SO3
0.25
80.00
0.0031
SO3/(K2O+Na2O)
0.2785
Table 3.12.3: C5 hotmeal analysis
C5 hot meal
SO3
LOI
2007-12-4 10:00
1.68
2.24
2007-12-4 11:00
2007-12-4 13:00
1.73
1.64
4.83
4.14
90.76%
92.16%
2007-12-4 15:00
2007-12-4 17:00
1.67
1.68
5.2
3.74
90.03%
92.94%
2007-12-4 19:00
1.68
2.58
95.21%
2007-12-6 10:00
1.27
4.65
91.18%
2007-12-6 13:00
Average
1.59
3.26
1.62
3.83
93.91%
92.31%
Decatbonation rate
B.4. Recommendations
Action N1: light the blower room of coal workshop
Objective: work in the room with sufficient brightness
Way to implement: inspect electricity line and fix bright lamps
Reference documents: No
Plant or BU responsible: Plant maintenance team
Expected result: work with sufficient brightness.
Action N2: fix the air cannon inlet valve at kiln inlet chamber
Objective: avoid hazard to people when operating there
Way to implement: check the valve and change it with new one.
Reference documents: no
Plant or BU responsible: plant maintenance team
Expected result: the valve can be shut down completely
Action N3: Reduce NOx at kiln back end.
Objective: avoid hazard to environment regulation and overburning
Way to implement: replace new kiln burner and operate according to 10 rules
Reference documents: None
Plant or BU responsible: ATC & Plant
Expected result: Reduce NOx at KBE by 50% and meet demand of environment
regulation.
Action N4: heat preservation of the TAD
Objective: reduce the TAD surface temperature to below 100C
Way to implement: to be see further in separate report.
Reference documents: none
Page 27 of 31
Plant or BU responsible: plant process and production team
Expected result: save ~7 kcal/kg-ck of heat loss
Action N5: Reduce primary air of kiln burner and apply new lafarge burner
Objective: reduce primary air
Way to implement: new burner design
Reference documents:
PR-PYR P06-02 How
to optimize a burner final.pdf
Plant or BU responsible: ATC & Plant
Expected result: Primary air decrease to 12%
Action N6: arrest false air along the kiln, preheater and raw mill line.
Objective: reduce false air in kiln hood and backend to be <15% and false air in the raw
mill system to be <40%.
Way to implement: identify the false air source (refer to fig 3.6.1 and 3.6.2), and make
action plan. After action re-measure the false air to check the results.
Reference documents:
PR-PYR P06-09 How R-PYR 0P06-10 How
to control false air
to in
measure
the preheater.pdf
false air.pdf
Plant or BU responsible: Plant
Expected result: to reduce heat loss 10.7kcal/kg-ck and power consumption 0.94kWh/t-ck
Action N7: Optimize cooler operation
Objective: to reduce vent air temperature to <240C and clinker temperature
<70C+ambient temperature
Way to implement: install piezo ring, adjust the cooling fans ventilation and clinker depth
according to cooling air blowing density
Reference documents:
PR-PYR P06-08 How
to adjust cooling air level & distribution.pdf
Plant or BU responsible: plant
Expected result: save heat loss for 15.94kcal/kg-ck
Action N8: ID fan optimize
Objective: to increase the ID fan efficiency >75%, and save 500Pa pressure drop.
Way to implement: check the internal recirculation and diffuser at outlet and damper at
inlet.( refer to FLAKT questionnaire)
Reference documents: no
Plant or BU responsible: Plant (ATC can help)
Expected result: reduce power consumption by 3.65kWh/t-ck
Action N9: SOP prepare
Objective: uniform the kiln operation
Way to implement: prepare SOPs and place them in the CCR
Reference documents: no
Plant or BU responsible: kiln coach
Expected result: keep the kiln stable
Page 28 of 31
Action N10: 10 rules of kiln operation
Objective: stably operation of kiln
Way to implement: set kiln operation sheets for operator references.
Reference documents: SOP & 10 rules of kiln operation
Plant or BU responsible: kiln coach
Expected result: make the kiln operation stably.
B.5. Acknowledgements
Great thanks of the HUA process team, esp. Mr Wang ZhiHong and Mr Han Li, for their great
support in the kiln audit and organization.
And thanks also to the Plant manager Mrs. Wang, for her kindly help.
B.6. References
analysis for
Mass & heat
0712klin demarcate.xls
balance 0201.xls
B.7. Appendices
Fan FLAKT.doc
Flaktwoods fan
data A.jpg
Page 29 of 31