Electrical Works(MV Switchgear Installation)
Inspection Checklist - 1
Project Name
Contractor
KHABAT THERMAL POWER
PLANT UNITS 1&2
POSCO ENGINEERING &
CONSTRUCTION CO.,
LTD.
Owner Name
Main Subcontractor
Area / Unit
SEE ATTACHED
DRAWING/CABLE LIST
Item Name / Item No
/ Description
ITP No
KP-00+++-CQ712-B7907
ITP Item
Report No
Ministry of Electricity (MOE) of
Kurdistan Regional Government
GAMA POWER SYSTEMS
ENGINEERING & CONTRACTING
INC.
1,1 /1,2 / 2 / 3,1 / 3,2 / 3,3
Date
Rev.B
Drawing No
Approximate Date/Time of Related Activity:
No.
ITEM DESCRIPTION
MV Switchgear and all accessories match with the shipping/delivery list
Floor civil works are done by civil discipline in accordance with the approved drawings
MV Switchgear and all accessories are installed in accordance with the approved
drawings
MV Switchgear and all accessories are fixed onto the suitable supports at particular
intervals as per approved drawings
Cable connections and test are done in accordance with the approved MS and ITP for
Cable Pulling Termination and Jointing
Earth continuity is checked
All connections are done with torque wrench and marked.
Overall insulation measurement and continuity test is done (optional)
Remarks / Comments