1. This inspection checklist is for the MV switchgear installation at Khabat Thermal Power Plant Units 1&2. It lists items to inspect including ensuring the switchgear and accessories match delivery lists, proper floor installation, correct installation per drawings, fixing to supports, cable connections and testing, earth continuity checks, torque of connections, and insulation/continuity testing. 2. The contractor is POSCO Engineering & Construction and the main subcontractor is GAMA Power Systems Engineering & Contracting for the specified switchgear areas. 3. Inspection items include verifying switchgear and accessories, floor installation, installation matches drawings, fixing to supports at set intervals, cable connections and testing, earth continuity, torque
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as RTF, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views2 pages

KP-00+++-CQ712-B7907 - F01 - Rev.B - MV Switchgear Installation Inspection Checklist1

1. This inspection checklist is for the MV switchgear installation at Khabat Thermal Power Plant Units 1&2. It lists items to inspect including ensuring the switchgear and accessories match delivery lists, proper floor installation, correct installation per drawings, fixing to supports, cable connections and testing, earth continuity checks, torque of connections, and insulation/continuity testing. 2. The contractor is POSCO Engineering & Construction and the main subcontractor is GAMA Power Systems Engineering & Contracting for the specified switchgear areas. 3. Inspection items include verifying switchgear and accessories, floor installation, installation matches drawings, fixing to supports at set intervals, cable connections and testing, earth continuity, torque
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as RTF, PDF, TXT or read online on Scribd
You are on page 1/ 2

Electrical Works(MV Switchgear Installation)

Inspection Checklist - 1

Project Name
Contractor

KHABAT THERMAL POWER


PLANT UNITS 1&2
POSCO ENGINEERING &
CONSTRUCTION CO.,
LTD.

Owner Name
Main Subcontractor

Area / Unit

SEE ATTACHED
DRAWING/CABLE LIST

Item Name / Item No


/ Description

ITP No

KP-00+++-CQ712-B7907

ITP Item

Report No

Ministry of Electricity (MOE) of


Kurdistan Regional Government
GAMA POWER SYSTEMS
ENGINEERING & CONTRACTING
INC.

1,1 /1,2 / 2 / 3,1 / 3,2 / 3,3

Date
Rev.B

Drawing No
Approximate Date/Time of Related Activity:
No.

ITEM DESCRIPTION

MV Switchgear and all accessories match with the shipping/delivery list

Floor civil works are done by civil discipline in accordance with the approved drawings

MV Switchgear and all accessories are installed in accordance with the approved
drawings

MV Switchgear and all accessories are fixed onto the suitable supports at particular
intervals as per approved drawings

Cable connections and test are done in accordance with the approved MS and ITP for
Cable Pulling Termination and Jointing

Earth continuity is checked

All connections are done with torque wrench and marked.

Overall insulation measurement and continuity test is done (optional)

Remarks / Comments

Subcontractor

GAMA

Subcontractor
Name:Date:Sign:

GAMA
Name:Date:Sign:

3rd Party / AI
Name:Date:Sign:

POSCO
Name:Date:Sign:
Doc. No: KP-00+++-CQ712-B7907-F01,
Rev.B

You might also like