Nigel Supply Chain Scope & Process: PO Received & DJ Released
Nigel Supply Chain Scope & Process: PO Received & DJ Released
Shortage
Trigger procurement Expedite shipment Assembly Job Completion
on gated materials with supplier
Test
Nigel Supply Chain Scope & Process
* Forecast received & triggering material purchase.
Forecast
MRP report
Blanket PO
Check SC
inventory
ASCP Run MRP Plan
Raise PO to
direct supplier
NO
Report – Material Handler
• After release of DJ, extract report from Brio to pull all the shortage material
DJ Shortage Report after deducting production line on hand quantity (OHQ).
• With the shortage report, deduct the warehouse OHQ to get the actual
gated material which will affect shipment.
• If sufficient stock in warehouse,
Nigel DJ Shortage Report • Proceed with Move Order.
• If insufficient stock,
• Expedite with procurement to place PO or pull in for the material for
open PO.
Forecast Vs Actual
• To identify between actual build order to Forecast Vs Actual
Waterfall Chart
• Forecast trend from M-6 for all Nigel product models. Identify upside & downside.
DJ Tracking
• A tracking report of all the DJ created.
Shipment Performance
• To measure OTD for all Nigel’s shipment and causes of shipment delays.
Capacity Planning
• To identify resource shortages to meet demand, and define and implement strategies to close the
gap. Tabulate man-hour shortage to allocate OT hours.