Project Management Standard Operating Procedures
Project Management Standard Operating Procedures
Standard Operating
Procedure
For
Project Management
Document Number:
24001
Audience:
Project Management
Author:
Sybil Jennings
Effective Date:
4/3/03
Version: 1.2
Accept........................................................................................................... 3
I. Manager Accepts Project ................................................................. 3
II. PM Accepts Project ........................................................................ 4
Define ........................................................................................................... 5
I. Preparation ......................................................................................... 5
II. Preliminary Meetings ..................................................................... 6
III. Documentation ................................................................................ 7
Plan ............................................................................................................... 7
I. Preparation ....................................... Error! Bookmark not defined.
II. Kick Off Meeting ............................................................................. 8
III. Service Orders ................................................................................ 8
IV. Weekly Status/Readiness Meetings............................................ 9
V. Customer Communication ............................................................ 9
VI. Documentation .............................................................................. 10
Implement ................................................................................................. 10
I. Preparation ....................................................................................... 10
II. Customer Communication .......................................................... 11
III. Internal Communication .............................................................. 11
IV. Documentation .............................................................................. 11
Close ........................................................................................................... 12
I. Project Closure ................................................................................. 12
Team Norms ............................................ Error! Bookmark not defined.
Project Management Document Index ......................................... 13
Reference Document Index ............................................................... 14
ACCEPT
* Acceptance of project from Manager and Project Manager.
ORB Review
Note: If there is an ORB associated with a project, the Product Manager will schedule a meeting
to review the ORB prior to start of the project. The participants are as follows.
A. Product Manager
B. Manager – PM Team
C. Project Manager
D. CE
E. SE (possibly)
F. Process
DEFINE
* PM gathers all necessary information to correctly define and manage project.
Goal for Definition stage is to have a complete and accurate SOW
I. Preparation
A. Review order packet for an understanding based on Service Definition/ORB.
B. Review SLA’s, processes and all other project documents as appropriate
C. Talk with any subject matter experts available. (e.g. PM’s, SE’s, CE)
D. Verify design with equipment code on SID with equipment list (location listed in index).
E. Create Project Binder (if PM determines binder is necessary) Binder consists of:
a. Project Checklist
b. Team Roster
c. Internal Communication Plan (including Change Control)
d. Scope of Work
e. Project Plan
f. Issues Register
g. Project Book
i. Expectations & Success Criteria
ii. Customer Communication Plan (including Change Control)
iii. Customer Risk Analysis
h. Internal Risk Analysis
i. Product Documentation
j. Converged Services Checklist
k. Order Tracking Documents
l. Action Items
m. Status Reports
n. PM Transition Plan
o. Project Schedule
p. Project Audits
q. Lessons Learned
r. Copy of Welcome Letter
s. Project Closure & Billing Document
t. Project Hand Off Document
u. Agendas/Meeting Minutes
v. Emails
w. Any other project documents
F. Create the Scope of Work, preliminary Project Schedule and preliminary Project Plan.
III. Orders
A. Send email to PC and Equipment Manager to place network and equipment orders.
Copy the Sales Engineer involved with the order.
IV. Documentation
B. Update all project documents on a daily basis and add most recent versions to Project
Binder.
C. Complete Project Audit document for Definition Phase and submit to Manager.
D. Enter the following dates in the Project Database:
a. Initial Customer Contact
b. Complete Define Stage (SOW)
c. Order Given to LCA
PLAN
* PM works with customer and project team to plan all project action items.
Goal for Planning is to have the Project Planned thoroughly and Timeline created.
I. Planning
A. Review SOW and design
B. Review Voice Worksheet
C. Review Site Requirements and timeline frame to complete work
D. Review Customer Expectations, Requirements, Measurement of Success
E. Identify resource requirements (skill sets)
F. Build a tentative Timeline (review calendars for Holidays)
G. Plan training dates for Voice Training, if applicable
H. Plan required meetings for the project
I. Review and plan Customer Communication Plan
J. Outline known Risks associate with the project (always anticipate the unknown)
K. Review the Logins and Passwords customer will require
L. Review IP requirements
M. Review LOA requirements
N. Review Listing requirements (Voice)
V. Customer Communication
A. Follow the Communication Plan developed jointly with the customer
B. Review and confirm Project Book with customer (Customer Implementation Review).
a. Detailed Design
b. Install/Transition Plan
c. Site Requirements
d. Risk Analysis
C. Send Customer Implementation Review date (from A) to LCA for HP Openview tracking.
D. Send customer weekly status updates.
E. Ensure customer action items are completed.
F. Review Site Requirements Form with customer.
G. Provide customer with Orange Sticker to mark location of Demarc.
H. Report major project milestones.
I. Address lessons learned.
J. Review escalation procedures.
K. Review billing information.
L. Provide Zone and/or Softswitch Username and Password to customer.
M. Set up Softswitch Training date and time with customer (reference the Training Calendar
in outlook to ensure resource availability).
N. Obtain completed Voice Worksheet from customer and send to PNOC LCA.
VI. Documentation
A. Update all project documents on a daily basis and add most recent versions to Project
Binder.
B. Complete Project Audit document for Planning Phase and review with Manager.
C. Enter the following dates in the Project Database:
a. Project Manager Plans Project
b. Estimated Install
c. Estimated Transition
IMPLEMENT
* Install circuits and customer equipment. Train customer. Install and transition services.
Goal of Implementation Phase is to implement the Plan that the project team developed.
I. Preparation
A. Confirm the Plan is complete and all necessary documents have been completed and
reviewed.
B. Verify all project team members have completed the necessary preparation, and have the
necessary information, training and tools for implementation.
C. Send out updated and finalized Install/Transition Plan to project team 2 weeks prior to
implementation.
D. Confirm the Project team knows the Communication/Escalation Plan
IV. Documentation
A. Update all project documents on a daily basis and add most recent versions to Project
Binder.
CLOSE
* Administrative and internal closure of project.
I. Project Closure
F. Conduct closure meeting with customer (utilize the Closure Meeting Agenda
Template).
a. Ensure customer expectations have been met (review Expectations_Success
Criteria document).
b. Communicate billing start date to customer.
c. Review lessons learned from customer’s point of view.
d. Document all customer feedback for final project audit.
e. Review Support and Processes
B. Complete Project Audit document for Implementation Phase and review with Manager.
C. Enter the following dates in the Project Database:
a. Actual Install
b. Actual Transition
c. Estimated Project Closure
A. Estimated Bill
D. Send Project Closure document to “Project Closure” distribution list in Outlook (add
Account Manager, Sales Engineer, Bill Keenan and Mary Zins). This document will
prompt the LCA to complete billing system entry.
E. Send customer Welcome Letter.
F. Complete Project Binder with complete and updated documents.
G. Schedule first bill review with customer and LCA. During this meeting, the project will
formally be handed off from the Project Manager to the LCA for service assurance.
H. Complete Project Audit document for Closure Phase and review with Manager.
I. Enter the following dates in the Project Database:
a. Actual Project Closure
b. Actual Bill