Korba Coalfields: Power from Washery Rejects

The document discusses using coal washery rejects for power generation at Korba coalfields in India. Over 22 million tonnes of raw coal is washed annually by two companies, producing 4-4.5 million tonnes of rejects with 57-62% ash content. Aryan Coal Beneficiations has decided to upgrade these rejects for power generation. The rejects will be reprocessed using jig cleaning to produce clean coal for a planned 2x135MW power plant, with performance data showing the jig process reduces ash content significantly. Using washery rejects for power generation addresses the challenges of storing and disposing of large volumes of reject material.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views14 pages

Korba Coalfields: Power from Washery Rejects

The document discusses using coal washery rejects for power generation at Korba coalfields in India. Over 22 million tonnes of raw coal is washed annually by two companies, producing 4-4.5 million tonnes of rejects with 57-62% ash content. Aryan Coal Beneficiations has decided to upgrade these rejects for power generation. The rejects will be reprocessed using jig cleaning to produce clean coal for a planned 2x135MW power plant, with performance data showing the jig process reduces ash content significantly. Using washery rejects for power generation addresses the challenges of storing and disposing of large volumes of reject material.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 14

Use of Coal

Washery Rejects for


Power Generation

A CASE STUDY OF
KORBA COALFIELDS
Shri. G. C. Mrig
Managing Director
Aryan Coal Benefications Pvt. Ltd
GROUP
INTRODUCTION GROUP

There is great emphasis on coal


washing because of the MoEF, Govt.
of India’s stipulations for use of
washed coal for Power Houses.

The Coal of Korba coalfields is being


extensively washed for Power Houses
of Gujarat, Rajasthan, Punjab and
Maharashtra.

10th India Power Forum & 7th Non-Fossil Energy


2
Sep, 2007 New Delhi
GROUP

Total Raw Coal washed on account of the


above Power Houses is as below:-
COMPANY CAPACITY
(MTPA)
Aryan Coal Benefications Pvt. Ltd. 16.0
Spectrum Coal and Power 6.0
Total (Million Tonnes Per Annum) 22.0

10th India Power Forum & 7th Non-Fossil Energy


3
Sep, 2007 New Delhi
GROUP

When 22 MTPA Raw Coal is washed,


it produces rejects of about 4-4.5
MTPA having an ash of 57-62%.

The problem of handling such large


quantities of rejects in an
environmental friendly manner is one
of the biggest challenge being faced
by the washery operator.

10th India Power Forum & 7th Non-Fossil Energy


4
Sep, 2007 New Delhi
Washery rejects GROUP

CoalBeneficiation plants produces, 15-


20% of rejects.

Washery rejects contain 15-20% carbon


and 1600-2200 GCV.

Huge stocks of washery rejects have


been created in almost all the
beneficiation plants.

10th India Power Forum & 7th Non-Fossil Energy


Sep, 2007 New Delhi 5
GROUP

Coal rejects heaps are aesthetically


offensive and environmentally
contaminating.

Accumulation of rejects consume lot of


land which could have been used
gainfully otherwise.

There are incidences of fire in the


rejects stocks which further endanger
the environment.
10th India Power Forum & 7th Non-Fossil Energy
Sep, 2007 New Delhi 6
GROUP

POWER GENERATION FROM REJECTS:


Aryan Coal Benefications has taken a
policy decision to use these vast
reserves of washery rejects for Power
Generation.

The rejects from washeries of Aryan


Coal Benefications Pvt. Ltd and
Spectrum washery in Korba are
proposed to be upgraded for
utilisation for power generation.
10th India Power Forum & 7th Non-Fossil Energy
7
Sep, 2007 New Delhi
The process GROUP

10th India Power Forum & 7th Non-Fossil Energy


8
Sep, 2007 New Delhi
GROUP

10th India Power Forum & 7th Non-Fossil Energy 9


Sep, 2007 New Delhi
REJECT REPROCESSING FLOW SHEET
GROUP

10th India Power Forum & 7th Non-Fossil Energy


Sep, 2007 New Delhi 10
Jig Cleans:
GROUP

Jigcleans are proposed to be used in


2x135MW Power House

Aryan signed an agreement with Gujarat


Urja Vikas Nigam Limited for putting up a
2x135 MW Coal Reject based Thermal
Power Plant for GVUNL.

10th India Power Forum & 7th Non-Fossil Energy


Sep, 2007 New Delhi 11
PERFORMANCE OF JIG WITH BARREL REJECTS GROUP

Month Jig Feed ( +6mm to 20mm)

Qty ARB Ash ARB CV K.Cal./Kg


( Tone) %
June,07 113521.75 59.38 2365.8

July,07 133064.28 58.74 2471.8


August,07 114044.98 57.62 2571.2

Month Jig Clean (+6mm to 20mm)

Qty ARB Ash ARB CV


(Tone) % K.Cal/Kg

June ‘07 52355.14 46.39 3184.8


July ‘07 66573.8 44.77 3304.0
Aug ‘07 56136.53 44.21 3375.2

10th India Power Forum & 7th Non-Fossil Energy Sep, 2007 New Delhi 12
GROUP

Month Jig Fines ( -6mm)

Qty ARB Ash ARB CV


( Tonne) % K.Cal. /Kg

June, 07 18719.66 47.46 2922.1

July, 07 14825.81 45.46 3158.8


August, 07 9893.80 42.82 3388.9

Month Jig Rejects

Qty ARB Ash ARB CV K.Cal /Kg


( Tonne) %
June ‘07 42446.95 71.72 1344.5

July ‘07 51664.68 70.46 1429.8

August ‘07 48614.65 69.99 1456.4

10th India Power Forum & 7th Non-Fossil Energy


13
Sep, 2007 New Delhi
GROUP

10th India Power Forum & 7th Non-Fossil 14


Energy Sep, 2007 New Delhi

You might also like