Submittal Process
Submittal Process
SUBMITTALS Submittals are required by the contract in order to regulate the timely flow of materials to be incorporated in the work.
SUBMITTALS
Submittals are necessary to prove that the proposed materials are in compliance with the contract.
SUBMITTALS All required submittals must be provided by the contractor in time to allow for the review, approval, procurement, delivery, and performance of the preparatory phase of the 3-phases of control before it is needed for construction.
SUBMITTALS
EXAMPLE : Distribution Box needed by December 1
Dec 1 Install
PLAN AHEAD
SUBMITTALS
QC RESPONSIBILITY Submittal process is part of your QC Plan. Assure that on-site management and the designer of record (if applicable) remains attentive to submittal procedures at all times. Responsible for thorough review to ensure submittals are in full compliance with contract requirements.
SUBMITTALS
Quality Control Manager assures that work must NOT be permitted to begin without properly approved submittals.
Submittal Classifications
Government Approved (GA or G)
o
100% reviewed
Submittal Classifications
Government Approved (GA or G)
o o o o o
Extension of Design
Critical Materials O&M Manuals Equipment that must be checked for compatibility with the entire system Variations
Submittals required Whether each requires Government approval (GA) Submittals are grouped by submittal descriptions (SDs)
A approved B approved, except as noted C approved, except as noted, must resubmit E disapproved, must resubmit
F receipt acknowledged FX received, does not comply with specs, must resubmit
You also see a drop-down list when you are making a transmittal form.
Submittal Types
SD-01 Preconstruction Submittals include:
(cost-loaded) Initial Submittal Register (generated in QCS) Accident Prevention Plan Quality Control Plan (construction and design) Environmental Protection Plan
Submittal Types
SD-02 Shop Drawing Submittals include:
o o o o
Drawings Schedules Diagrams Other data prepared specifically for the contract by contractor or through subcontractor, manufacturer, supplier, distributor.
Submittal Types
SD-03 Product Data Submittals include:
o
o
o o o
Manufacturers Descriptive Literature Catalog Data Brochures Pre-printed material not prepared exclusively for the contract. Can include samples of warranty language when the contract requires extended product warranties.
A submittal register is produced when all data is input into QCS and RMS
Submittal Register
Design-Bid-Build
o o
Govt. supplies the submittal register The register is nearly complete at the beginning of the project
Design-Build
o
o
Submittal Register
Submittal activities may be required to be incorporated into the construction schedule in order that the submittal progress can be tracked in conjunction with the overall progress.
Care must be taken that the schedule accurately reflects the status on the submittal register.
Submittal Register
Submittal Review
Typically 14 days
Submittal reviews must be coordinated with your Corps field office (COR)
o
o
Govt. will compare submittals to project specifications, to include referenced building codes and standards
Transmittal Form
Transmittal Form
Transmittal Numbers
o
Spec. Section - #
e.g. 01451-1, 01451-2, 01451-3,
A transmittal can include multiple items, but all items should be from the same Specification Section
Technical Specifications
Unified Facilities Guide Specification (UFGS)
o
1995
2004
49 Divisions
http://si.ksc.nasa.gov/sidownloads/ufgs/UFGSMF95MF04Conv.htm
Websites
Conversion from 1995 Specifications to 2004
http://si.ksc.nasa.gov/sidownloads/ufgs/UFGSMF95mf04Conv.htm
Preparing a Transmittal