Managing Risk in Projects
Managing Risk in Projects
david hillson
cHapter
1
Table 2.1
Definitions of project
GUIDE/STANDARD Body of knowledge DEFINITION OF PROJECT a unique transient endeavour undertaken to achieve a desired outcome. a temporary endeavour undertaken to create a unique product, service or result. a temporary organisation that is created for the purpose of delivering one or more business outputs according to a specified business case. a unique process, consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective conforming to specific requirements, including constraints of time, cost and resources.
ORGANISATION association for project Management (apM) project Management institute (pMi)
bs079-:000
PROJECT
validate
BENEFITS
operate
CAPABILITY
create
DELIVERABLES
figure 2.1
execute
1
With such a long history of executing projects, one would expect that we would be very successful at it by now. Unfortunately the data suggest otherwise. The best long-term data on project success come from the Standish Group, whose CHAOS Report continues to document a high number of projects which either fail completely or are challenged (meaning that they were delivered either late or over budget or with reduced scope). Figure 2.2 presents the standish Chaos data from its origin in 1994 to the most recently available in 2006, indicating that the situation has not improved dramatically over the years. So why do so many projects fail? It is not due to lack of project management theory, tools and techniques, or trained people. We have a good understanding of project concepts, project management processes are well developed, and the people working on projects are mostly professional, committed and capable. It seems that one of the major reasons for project failure is the occurrence of unforeseen events which disrupt the smooth running of the project and cause irrecoverable deviation from the plan. As former British Prime Minister Harold Macmillan explained when asked by a journalist what was most likely to throw a government off course, Events, dear boy, events. On any given project, some of these unforeseen events were probably unforeseeable. But others are likely to have been knowable, if only someone on the project team had looked in the right place or been aware of what lay ahead. These knowable uncertainties fall under the heading of risks, as future events that, if they occurred, would affect achievement of project objectives.
figure 2.2
1
we need to understand if we are to manage risk in projects successfully. These are discussed below under three headings: 1. Common characteristics; 2. Deliberate design; 3. External environment.
Common characteristics
All projects share a range of features which inevitably introduce uncertainty. Many of these characteristics are described in the definitions of project in Table 2.1. Factors found in all projects which make them inherently risky include: Uniqueness. Every project involves at least some elements that have not been done before, and naturally there is uncertainty associated with these elements. Complexity. Projects are complex in a variety of ways, and are more than a simple list of tasks to be performed. There are various kinds of complexity in projects, including technical, commercial, interfaces or relational, each of which brings risk into the project. Assumptions and constraints. Project scoping involves making a range of guesses about the future, which usually include both assumptions (things we think will or will not happen) and constraints (things we are told to do or not do). assumptions and constraints may turn out to be wrong, and it is also likely that some will remain hidden or undisclosed, so they are a source of uncertainty in most projects. People. All projects are performed by people, including project team members and management, clients and customers, suppliers and subcontractors. all of these individuals and groups are unpredictable to some extent, and introduce uncertainty into the projects on which they work. Stakeholders. These are a particular group of people who impose requirements, expectations and objectives on the project. Stakeholder requirements can be varying, overlapping and sometimes conflicting, leading to risks in project execution and acceptance. Change. Every project is a change agent, moving from the known present into an unknown future, with all the uncertainty associated with such movement.
These risky characteristics are built into the nature of all projects and cannot be removed without changing the project. For example, a project which was not unique, had no constraints, involved no people and did not introduce change would in fact not be a project at all. Trying to remove the risky elements from a project would turn it into something else, but it would not be a project.
1
Deliberate design
The definitions of project in Table 2.1 emphasise that projects are conceived, launched and executed in order to achieve objectives which are (or should be) closely linked to corporate strategy. In the competitive business environment, organisations are seeking to get and stay ahead of the competition by making significant advances in the products and services which they offer, and by operating as efficiently and effectively as possible. Many businesses use projects as vehicles to deliver that competitive advantage. Clearly each organisation wishes to move ahead as quickly as possible, and that involves taking risk as the business exposes itself to a range of uncertainties that could affect whether or not it achieves its desired aim. This can be achieved in two ways: 1. One option might be to take small steps, making incremental changes to existing products and services, seeking continuous improvement and evolutionary change. While this strategy might appear to be less risky, it delivers smaller advantages at each increment, and relies on a constant supply of value-enhancing developments. 2. An alternative is to be revolutionary, looking for major innovations and paradigm-breaking change, trying to leapfrog the competition and get several steps ahead. This is a more risky strategy but the potential gains are larger and might be achieved more quickly. The two strategies reveal an important relationship between risk and reward: they are positively correlated. Higher-risk means potentially higher reward, though clearly there is also increased possibility of significant loss. By trying to make bigger changes more quickly, an organisation takes more risk in both dimensions, both positive and negative. This is illustrated graphically in Figure 2.3. For example, attempting to launch a new product in a new market could give first-mover advantage and be very profitable, or it could result in significant losses (shown as position A in Figure 2.3). If on the other hand the organisation plays safe and takes less risk, the potential gains are lower (position B). In project-based organisations, the role of projects is to deliver value-creating capabilities. As a result, projects are deliberately designed as risk-taking ventures. Their specific purpose is to produce maximum reward for the business while managing the associated risk. Since the existence of projects is so closely tied to reward, it is unsurprising that they are also intimately involved with risk. Organisations which understand this connection deliberately design their projects to take risk in order to deliver value. Indeed projects are undertaken in order to gain benefits while taking the associated risks in a controlled manner.
1
extreme
REWARD
e as tc es b e as dc cte pe ex
wo
LOSS
rs
tc
as
A
moderate RISK high extreme
figure 2.3
External environment
Projects are not conducted in a vacuum, but exist in an environment external to the project itself which poses a range of challenges and constraints. This includes both the wider organisation beyond the project and the environment outside the organisation, and changes which are outside the projects control can occur in both of these. Environmental factors which introduce risk into projects include: market volatility; competitor actions; emergent requirements; client organisational changes; internal organisational changes; PESTLIED (political, economic, social, technological, legal, international, environmental, demographic) factors.
Each of these factors is subject to change at an increasing rate in the modern world. Projects essentially have a fixed scope which they are required to deliver within this ever-changing environment, which naturally poses risk to the project. It is not possible to isolate most projects from their environment, so this represents a common source of risk for projects.
17
RIsks oR RIsk?
When considering risk in projects, there are two levels of interest, typified by the scope of responsibility and authority of the project manager and the project sponsor. The project manager is accountable for delivery of the project objectives, and therefore needs to be aware of any risks that could affect that delivery, either positively or negatively. Their scope of interest is focused on specific sources of uncertainty within the project. These sources are likely to be
18
particular future events or sets of circumstances or conditions which are uncertain to a greater or lesser extent, and which would have some degree of impact on the project if they occurred. The project manager asks What are the risks in my project?, and the answer is usually recorded in a Risk Register or similar document. The project sponsor on the other hand is interested in risk at a different level. They are less interested in specific risks within the project, and more in the overall picture. Their question is How risky is my project?, and the answer does not usually come from a Risk Register. Instead of wanting to know about specific risks, the project sponsor is concerned about the overall risk of the project. This represents their exposure to the effects of uncertainty across the project as a whole.
These two different perspectives reveal an important dichotomy in the nature of risk in the context of projects. A project manager is interested in risks while their sponsor wants to know about risk. While the project manager looks at the risks in the project, the project sponsor looks at the risk of the project. This distinction is described in some of the more forward-thinking approaches to project risk management. Two examples are provided in Table 2.2, from risk management guidelines published by the Association for Project Management (APM) and the Project Management Institute (PMI) respectively. Table 2.2
GUIDE project risk analysis & Management (praM) guide (apM, 00)
19
Table 2.2
GUIDE
Concluded
LOWER LEVEL RISKS Individual risks are the focus of day-to-day project risk management in order to enhance the prospects of a successful project outcome. it is important to examine individual risk events or conditions that might affect project objectives. individual risks refer to specific events or conditions that have the ability to affect project objectives positively or negatively. note that an individual risk may affect one or more project objectives, elements, or tasks. understanding individual risks can assist in determining how to apply effort and resources to enhance the chances of project success. HIGHER LEVEL RISK Overall project risk represents the effect of uncertainty on the project as a whole. overall project risk is more than the sum of individual risks on a project, since it applies to the whole project rather than individual elements or tasks. it represents the exposure of stakeholders to the implications of variations in project outcome. it is an important component of strategic decision-making, program and portfolio management, and project governance where investments are sanctioned or cancelled and priorities are set.
Given these two levels of interest, any approach to risk management in projects needs to be able to answer the questions of both project manager and project sponsor. An effective project risk management process should identify individual risk events within the project and enable them to be managed appropriately, and should also provide an indication of overall project risk exposure. This second aspect is less well developed in current thinking and practice, and is the subject of active development by leading practitioners and professional bodies.
0
effective
SU AL OR ITIC CT CR S FA ES CC
lower
figure 2.4
CR
higher
1
risk management minimises threats, maximises opportunities and optimises the achievement of project objectives. The converse is also true (as illustrated by the experience of many projects where risk management is less than fully effective). Failing to manage risks on projects will result in more problems, less benefits and a lower chance of project success. In this sense, risk management is a true CSF for projects: it is unlikely that projects will be successful without effective management of risk (it is a Critical Source of Failure), and where risk management is working properly projects have the best chance of succeeding (it is a Critical success Factor), as illustrated in Figure 2.4 opposite. Having explained why risk management matters to projects, the next question is how to do it, which is addressed in the next chapter.