FABRICATION OF OFFSHORE PLATFORM
Presented by Mr. Therasap Rattanapat
Platform Configuration In Thailand
The 4-legged Jacket Conventional-bracing jacket comprises of elevated panels with batter in both directions 6-20 Drill Slot Water Depth : 70-80m. Approximately Equipped with Boat-landing and Riser 4 Piles Installation by Crane Lifting / Upending Flooding Syatem is required for Free Floating of JK in the Sea before Upending
Jacket :
Platform Configuration In Thailand
the integrated 4-column structure comprises of several Elevation deck panels ie; Drain Deck Panel Lower Deck Panel Upper Deck Panel He-li Deck Vent Boom / Flare Boom Crane Platform Piping, Mechanical Electrical and Instrument Safety Equipment Installation by Single Lift using of Derrick Crane Barge
Topside :
Welding Process
Structural Welding Process
SMAW SAW FCAW Gas Shield FCAW Self Shield TIG
Control of Welding Quality
WPS
All welding shall be followed the approved Welding Procedure Specification (WPS)
Control of Welding Quality
WPQT
Relating to the specific WPS, The welding procedure qualification test (WPQT) is also required in order to proved that the WPS to be used is qualified in the strength, quality point of view. The base metal, consumable and other parameters ie preheating and temperature to be used / control in the WPQT shall be comply or equivalent to the actual used of fabrication.
Control of Welding Quality
PQR
During the test, all necessary parameter shall be recorded in the PQR (Procedure Qualification Record) format. After Completed the testing, visual inspection in according to ASME or AWS D1.1 shall be done, whichever is applicable, then followed by NDE (24Hr for Mild steel, 48hr for High Strength Steel). The completed welded testing specimen shall be sent to the qualified laboratory for mechanical testing, which will be consist of Tensile Test, bend test, Impact Test, hardness test for each heat effect zone.
Example of WPS, WPQT, PQR
Example of WPS, WPQT, PQR
Welder Qualification Test
Welder Qualification Test (WQT)
All welder shall be qualified before allow to assigned to the project. The qualification of welder shall be done at the same requirement specified in the WPS. The completed test specimen shall be visual inspection and follow by NDE as below - 100% RT for all butt joing that is qualified for 6GR, 6G, 3G/4G, 1G - 100% UT for 6GR and SAW-1G - MPI for Fillet Welded - Macro for acute angle
Example of WQT
Welding Examination
All welding shall be 100% visual inspection after completion of welding before release for NDE and painting. NDE shall not be carried out until 24Hr for Mild steel and 48hr for high strength steel.
Welding Examination
Material Control
All Materials shall be control throughout each stage of fabrication to ensure the following. All material shall be checked during receiving stage to ensure that theyre traceable to mill certificate After receiving of material, all material shall be numbering anf containing to heat number and piece number from manufacture. All structural member shall be full traceability by hard stamp during material marking (material verification) before material cutting process.
Corrosion Protection
2 Process are normally be selected to protect the structure from the corrosion. -Catholic Protection, Anode -Coating (Painting) -Normally the structure which located under splash zone will be protect from corrosion by using of Anode. -The structure located at and above splash zone will be protect from corrosion by using of coating / paint process. -The painting system and designed of Anode shall be complied with the designed lift of platform 9ie. 20Years or other life.
Fabrication Yard Layout Plan
Fabrication Yard Layout Plan (Pre-Fabrication)
Fabrication Yard Layout Plan
Fabrication Yard Layout Plan (Final Space Assembly)
Fabrication / Loadout Support Plan
Jacket Fabrication and Loadout Support Plan
Fabrication / Loadout Support Plan
Topside Fabrication and Loadout Support Plan
Fabrication Sequence for Jacket
Jacket Fabrication Flow Chart
Fabrication Sequence for Jacket
Jacket Elevation Panel Pre-Fabrication (TYP)
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Jacket
Jacket General Fabrication Sequence
Fabrication Sequence for Topside
Deck Fabrication Flow Chart
Fabrication Sequence for Topside
Deck Panel Pre-Fabrication
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence
Fabrication Sequence for Topside
Deck General Fabrication Sequence