HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 19/9/2012 DAY 8:00hrs-17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Mobillazation of workers & equipment to the site Barricading of construction site site clearing & evacuation of waste out of the plant
WORK SCOPE SAFE HOURS CIVIL: TOTAL
15 120
TOTAL FROM SEPT 19= 120
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnelloading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
ssed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 20/9/2012 DAY 8:00hrs-17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Excavation of the foundation waste removal from the site
SAFE HOURS CIVIL: TOTAL
18 144
TOTAL FROM SEPT 19= 264
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel loading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
SHIFT TIME:
DAY 8:00 - 17hrs
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 21/9/2012 DAY 8:00 hrs- 17hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
continuation of Excavation of the foundation waste removal from the site Constuction of laydawn area & bending of iron rods
SAFE HOURS CIVIL: TOTAL
16 128
TOTAL FROM SEPT 19= 392
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel loading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 22/9/2012 DAY 8:00hrs- 17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
continuation of Excavation of the foundation waste removal from the site Constuction of laydawn area & bending of iron rods
SAFE HOURS CIVIL: TOTAL
13 96
TOTAL FROM SEPT 19= 488
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel loading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
of iron rods
essed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 23/9/2012 DAY 8:00hrs-17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Blinding of foundation
SAFE HOURS CIVIL: TOTAL
9 72
TOTAL FROM SEPT 19= 560
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel loading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
essed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 24/9/2012 DAY 8:00hrs-17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Completion of Foundation blinding Construction work on laydown area is ongoing
SAFE HOURS CIVIL: TOTAL
9 136
TOTAL FROM SEPT 19= 696
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel loading Tipper without wearing hard hat 2 Tools & equipment were not adequately arranged on site ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
essed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 25/9/2012 DAY 8:00hrs - 17:00 hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Setting of reiforcement Evacuation of debrils Completion of construction of Ladown Area .
SAFE HOURS CIVIL: TOTAL
12 98
TOTAL FROM SEPT 19= 794
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 1 Obstruction of Access into construction site with debrils evacuated from foundation ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
essed closed
HAND OVER REPORT
DATE SHIFT: TIME : PROJECT (S): CONTRACTOR(S): 26/9/2012 DAY 8:00-17hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
S&R
WORK SCOPE CIVIL: (S&R) work done
Setting of reinforcement continue Evacuation of debris Completion of construction of Ladown Area .
SAFE HOURS CIVIL: TOTAL
12 98
TOTAL FROM SEPT 19= 892
Unsafe behavior / unsafe Condition observed : 1 Obstruction of Access into construction site with debrils evacuated from foundation ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
essed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 27/9/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R) work done
S&R
Setting of reinforcement continue Casting of concrete
SAFE HOURS CIVIL: TOTAL
17 136
TOTAL FROM SEPT 19=1028
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 1 Obstruction of access route with mixer machine. ACTIONS: All observed unsafe behaviors & conditions were adequately addressed closed out before end of the shift . OWNER: Richard Jagunna BACK-UP: Isaac Balogun
OM SEPT 19=1028
essed closed
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 28/9/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA
CONTRACTOR(S): WORK SCOPE CIVIL: (S&R)
work done
S&R
1 2 3
Continuation of concrete casting Excavation of foundation Evacuation of debris from the work area
SAFE HOURS CIVIL: TOTAL
18 144
TOTAL FROM SEPT 19=1172
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Working tools were scattered on construction site 2 Poor housekeeping in Lay down Area ACTIONS: Feedback was given to the Site Contractor Safety Officer on both Unsafe Conditions He stopped the work briefly and ensured adequate housekeeping in the two locations OWNER: BACK-UP: Richard Jagunna Isaac Balogun
ENT STORAGE AREA
TOTAL FROM SEPT 19=1172
r on both Unsafe Conditions usekeeping in the two locations
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 29/9/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
Nil
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
1 2 3
Preparation of the wall for painting ( sand paper & brushing ) priming of wall Painting of wall
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 0 28 28
TOTAL FROM SEPT 19=1200
ACTIONS: Feedback was given to the Site Contractor Safety Officer on both Unsafe Conditions He stopped the work briefly and ensured adequate housekeeping in the two locations OWNER: BACK-UP: Richard Jagunna Isaac Balogun
GE AREA &
aper & brushing )
Unsafe Conditions in the two locations
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 30/9/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
WORK SCOPE CIVIL: (S&R)
work done
1 2 1 2 3
Continuation of concrete casting Excavation of foundation Preparation of the wall for painting ( sand paper & brushing ) priming of wall Painting of wall
CIVIL:
P.Charity
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 96 54 150
TOTAL FROM SEPT 19=1350
ACTIONS:
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
ENT STORAGE AREA &
ng ( sand paper & brushing )
TOTAL FROM SEPT 19=1350
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 1/10/1900 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
1 2 3 Continuation of concrete casting Excavation of foundation Block laying
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
1 2
priming of wall Painting of wall
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 120 12 132 Debris
1 ACTIONS:
removed from excavation yet to be evacuated out of si
Permit for waste evacuation will be renew on Tuesday morning. immediately waste permit is renewed deris will be evacuated out Richard Jagunna Isaac Balogun
OWNER: BACK-UP:
EQUIPMENT STORAGE AREA & M & STRUCTURES
TOTAL FROM SEPT 19=1482
ion yet to be evacuated out of site
be renew on Tuesday morning. wed deris will be evacuated out of site
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/2/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
1 2 3 Casting of the wall Excavation of deris from the site Block laying Nil
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: S&R 15 CIVIL: p. Charity 0 TOTAL 120 TOTAL FROM SEPT 19=1602 Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Improper arrangement of tools on site 2 poor housekeeping removed in from the lay excavation down area yet to be evacuated out of site
ACTIONS: The safety officer was given a feed back, he promised to close the two issues immediatel on checking back about an hour later the has been closed OWNER: BACK-UP: Richard Jagunna Isaac Balogun
NT STORAGE AREA &
TOTAL FROM SEPT 19=1602
120
e evacuated out of site
close the two issues immediately
3-Oct
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/3/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
1 2 3 Block laying on the wall Compaction of the floor preparation for casting of the concrete Nil 16 0 128
WORK SCOPE CIVIL: (S&R)
work done
CIVIL: P.Charity SAFE HOURS CIVIL: S&R CIVIL: p. Charity TOTAL
TOTAL FROM SEPT 19=1730
Near Miss Nil Unsafe behavior / unsafe Condition observed : 3 1 poor housekeeping ( off cuts woods ) 2 tools were not properly stored on site 3 caution tape use for brrication was lowered ACTIONS: site safety officer & engineer were informed to immediately ensured that good housekeeping are maintained on construction site always . The team closed up the issues before the end of the shfi.t OWNER: Richard Jagunna BACK-UP: Isaac Balogun
NT STORAGE AREA &
TOTAL FROM SEPT 19=1730
tely ensured that
OCT
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/4/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
1 2 Continuation of wall casting Compaction of the floor Nil 17 0 136
WORK SCOPE CIVIL: (S&R)
work done
CIVIL: P.Charity SAFE HOURS CIVIL: S&R CIVIL: p. Charity TOTAL
TOTAL FROM SEPT 19=1886
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Access route was obstructed with wooden materials 2 cement bags scattered on construction site ACTIONS: the Carpenter was informed to remove the plant from access route immediately casting crew were informed to always stored used bags of cement together The issues were closed up immediately OWNER: Richard Jagunna BACK-UP: Isaac Balogun
NT STORAGE AREA &
TOTAL FROM SEPT 19=1886
ccess route immediately of cement together
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/5/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. Charity
1 2 3 1 Building casting form welding of reinforcement ( Hot work ) setting of reinforcement Scaffold erection
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: S&R CIVIL: p. Charity TOTAL
136 12 148
TOTAL FROM SEPT 19=2034
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 the site carpenter was not properly stored his tools has planned 2 off cuts wooden materials with nails not stored as required ACTIONS: the Carpenter was given a feed back , ask to stop working and observe housekeeping He maintained good housekeeping before the continuation of his task OWNER: BACK-UP: Richard Jagunna Isaac Balogun
NT STORAGE AREA &
TOTAL FROM SEPT 19=2034
s tools has planned ed as required
g and observe housekeeping on of his task
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/6/2012 DAY 18:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 3 1 2 3 Building casting form welding of reinforcement ( Hot work ) setting of reinforcement Preparation of the structure for painting ( sand paper & brushing ) Painting of Tanks , pipes & structures Painting of MCAS fan exhaust
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 136 72 208
TOTAL FROM SEPT 19=2242
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 poor house keeping in the lay down area 2 gravel parked in lay down area are not barricaded ACTIONS: The site safety officer was informed immediately to ensure adequate housekeeping is maintained in the lay down area always. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
GE AREA &
nd paper & brushing )
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/7/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 Compaction of construction site Setting of the reinforcement bar
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 56 0 56
TOTAL FROM SEPT 19=2298
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 poor house keeping in the lay down area
ACTIONS: The site safety officer was informed immediately to ensure adequate housekeeping is maintained in the lay down area always. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
NT STORAGE AREA &
OM SEPT 19=2298
ure adequate
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/8/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 Filling of the site base with hardcore Welding of the structure base
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
NIL
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 114 0 114
TOTAL FROM SEPT 19=2412
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 2 personnel not wearing gloves when handling iron rods
ACTIONS: The personnel were corrected site immediately and safety officer wasinstructed to prov hand gloves for them. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
NT STORAGE AREA &
OM SEPT 19=2412
ng iron rods
ety officer wasinstructed to provide
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/9/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 Preparation of the formwork Casting of the pillar
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
Nil
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 96 0 96
TOTAL FROM SEPT 19=2508
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 Personnel removed caoution tape around the pile of hardcore granite in lay area while working there. 2 The debris in work are is piling up and due for evacuation. ACTIONS: The personnel were corrected, and coached immediately on the importance of cordonin off work area. The safety officer was also informed. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
NT STORAGE AREA &
OM SEPT 19=2508
e pile of hardcore granite in lay down
r evacuation. y on the importance of cordoning
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/10/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 3 Preparation of the formwork Movind hardcore granite to foundation area Block setting. Nil
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 96 0 96
TOTAL FROM SEPT 19=2700
Near Miss Nil Unsafe behavior / unsafe Condition observed : 4 1 Personnel clothes were not neatly arranged in the laydown area- poor house 2 No functional first aid box on site 3 Tools litter the work area, because there are no tool boxes 4 The debris in work are is piling up and due for evacuation.
ACTIONS: The contractor safety officer was informed and coached on the importance of housekeep need for 1st aid box , and provision of tool boxes for personnel. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
T STORAGE AREA &
OM SEPT 19=2700
n the laydown area- poor housekeeping
o tool boxes evacuation.
on the importance of housekeeping,
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/11/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 3 Evacuation of debris from work area Preparation of form work for casting Filling of foundation area with hardcore Nil
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 120 0 120
TOTAL FROM SEPT 19=2,820
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 A person walked to site without hard hat 2 No functional first aid box on site ACTIONS: The contractor safety officer was asked to provide a functional First Aid box for his site. The person that entered the area without hard hat was confronted & coached immediately. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
Aid box for his site. coached immediately.
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/12/2012 DAY 8:00hrs -17:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 Removal of formwork mould from casted concrete wall Filling of foundation area with hardcore
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
Nil
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 112 0 112
TOTAL FROM SEPT 19=2,932
Near Miss Nil Unsafe behavior / unsafe Condition observed : 2 1 A truck boy was seen at laydown area without wearing safety boot, while the truck was ofloading granite. 2 No functional first aid box on site ACTIONS: The contractor safety officer was asked to provide a functional First Aid box for his site. The truck boy was confronted & coached immediately by contractor safety officer. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
afety boot, while the truck
Aid box for his site. safety officer.
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/13/2012 DAY 8:00hrs -19:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 2 Preparation of the formwork for fooundation casting Filling of foundation area with hardcore
WORK SCOPE CIVIL: (S&R)
work done
CIVIL:
P.Charity
Painting of new day tanks room
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 96 72 168
TOTAL FROM SEPT 19=3,100
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 Hand tools litter work area 2 No functional first aid box on site
2 (P. Charity) ( S&R , P.Charity)
ACTIONS: The contractor safety officers were asked to provide functional First Aid boxes for their sites.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Aid boxes for their sites.
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): CONTRACTOR(S): 10/14/2012 DAY 8:00hrs -19:00hrs
CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA & PAINTING OF NEW TANK ROOM & STRUCTURES
S&R P. CHARITY
1 Casting of floor
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.Charity
Re-spraying & painting of pipes, beams, tank room, and electric motors
SAFE HOURS CIVIL: CIVIL: TOTAL S&R p. Charity 232 70 302
TOTAL FROM SEPT 19=3,402
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 No functional first aid box on site
ACTIONS: The contractor safety officer was asked to provide a functional First Aid box for his site. The truck boy was confronted & coached immediately by contractor safety officer. OWNER: BACK-UP: Richard Jagunna Isaac Balogun
oom, and electric motors
Aid box for his site. safety officer.
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/15/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Setting of block wall Clearing of the site
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
Nil Nil
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 80 0 0 80
TOTAL FROM SEPT 19= 3,482
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 ACTIONS: No functional first aid box on site Poor housekeeping in laydown area.
OWNER: BACK-UP:
The contractor safety officer was asked to provide a functional First Aid box for his site. The safety officer was given a feedback about the housekeeping status of his laydown area, and it was closed out. Richard Jagunna Isaac Balogun
Y TANK SITE
Aid box for his site. us of his laydown
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/16/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Setting of block wall Erection of scaffold
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
Nil Nil
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 80 0 0 80
TOTAL FROM SEPT 19= 3,562
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 ACTIONS: No functional first aid box on site Poor housekeeping in laydown area.
OWNER: BACK-UP:
The contractor safety officer was asked to provide a functional First Aid box for his site. The safety officer was given a feedback about the housekeeping status of his laydown area, and it was closed out. Richard Jagunna Isaac Balogun
Y TANK SITE
Aid box for his site. us of his laydown
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/17/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Casting of Ramp Completion of scaffold erection
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
Nil Nil
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 80 0 0 80
TOTAL FROM SEPT 19= 3,642
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 3 ACTIONS:
Handtools litter work area unlabelled jerry can containing diesel placed close to a working concrete mixer No functional first aid box on site
The contractor safety officer was asked to provide a functional First Aid box for his site. The safety officer was given a feedback about unlabelled jerrycan, and he replaced the tattered label with a new one Richard Jagunna Isaac Balogun
OWNER: BACK-UP:
Y TANK SITE
orking concrete mixer
Aid box for his site. d he replaced
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/18/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Removal of formwork from castingCasting of Ramp Erection of another scaffold General housekeeping Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 48 0 0 48
TOTAL FROM SEPT 19= 3,690
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 ACTIONS:
Some Handtools found on the pavement in work area No functional first aid box on site
The contractor safety officer was asked to provide a functional First Aid box for his site. The deadline is 48hrs.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
Aid box for his site.
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/19/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Removal of formwork from castingCasting of Ramp Erection of 3rd scaffold General housekeeping Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 48 0 0 48
TOTAL FROM SEPT 19= 3,738
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 ACTIONS:
A worker carried planks without wearing cotton hand gloves No functional first aid box on site
The personnel was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/20/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
Apply body filler on pipes, tanks, machine pars and structure Painting: Spraying brush work Nil
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL
54 0 54
TOTAL FROM SEPT 19= 3,792
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 2 ACTIONS:
trailing cable and hose from from spraying machine No functional first aid box on site
The personnel was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
and structure
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/22/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Offloading of stanchion beams to site Welding/cutting/grinding of stanchion base Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 48 0 0 48
TOTAL FROM SEPT 19= 3,840
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 trailing cable from junction box 2 No functional first aid box on site ACTIONS:
The safety officer was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/23/2012 DAY 8:00hrs -18:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Welding/cutting/grinding of stanchion base Erection of stanchion beams using HIAB Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 64 0 0 64
TOTAL FROM SEPT 19= 3,904
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 trailing cable from junction box 2 No functional first aid box on site ACTIONS:
The safety officer was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/24/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Closing up of opened section of work area perimeter fence Setting of z poline sheets for roof Welding/cutting & grinding of z poline sheets for accurate size Housekeeping Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 58 0 0 58
TOTAL FROM SEPT 19= 3,962
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 trailing cable from junction box 2 No functional first aid box on site ACTIONS:
The safety officer was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE
imeter fence
or accurate size
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/25/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC Continuation of Setting of z poline sheets for roof Welding/cutting & grinding of z poline sheets for accurate size Housekeeping Nil Nil
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL Near Miss 72 0 0 72
TOTAL FROM SEPT 19= 4034
1 An uninspected /approved electric welding machine with open guard found on S&R site 2
Unsafe behavior / unsafe Condition observed : 1 trailing cable from junction box 2 No functional first aid box on site ACTIONS:
The safety officer was given a feedback and coached immediately. An MCA shall be conducted on the near miss. Richard Jagunna Isaac Balogun
OWNER: BACK-UP:
Y TANK SITE
or accurate size
d found on S&R site
n MCA shall be conducted
HAND OVER REPORT
DATE SHIFT TIME: PROJECT (S): 10/26/2012 DAY 8:00hrs -17:00hrs
1.CONSTRUCTION OF MAMBILLA EQUIPMENT STORAGE AREA 2.PAINTING OF NEW TANK ROOM & STRUCTURES 3.ELECTRICAL CONSTRUCTION WORKS (OLD MSG DAY TANK SITE & BOILER PANEL RELOCATION)
CONTRACTOR(S):
S&R P. CHARITY
SAM ELECTRIC
WORK SCOPE CIVIL: (S&R)
CIVIL:
P.CHARITY
Nil Nil
ELECTRICAL: SAM ELECTRIC
SAFE HOURS CIVIL: S&R CIVIL: P. Charity ELECTRICAL: Sam Electric TOTAL 0 0 0 0
TOTAL FROM SEPT 19=
Near Miss Nil Unsafe behavior / unsafe Condition observed : 1 trailing cable from junction box 2 No functional first aid box on site ACTIONS:
The personnel was given a feedback and coached immediately.
OWNER: BACK-UP:
Richard Jagunna Isaac Balogun
Y TANK SITE