11 Chapter Model
11 Chapter Model
5/6/13 9:38 PM
2/15/2006
NET PRESENT VALUE & INTERNAL RATE OF RETURN (Sections 11.3 & 11.4)
The Net Present Value (NPV) method estimates how much a potential project contributes to shareholder wealth and is the primary capital budgeting decision criterion. While other capital budgeting tools are important and provide valuable information, the NPV is clearly the dominant metric used to evaluate projects. We use cash flow data for two projects (S and L) to illustrate NPV concepts and calculate NPV and IRR. Project S's cash flows come in sooner than Ls. We assume that the projects are equally risky and that the end-of-year net cash flows have been adjusted to reflect taxes, depreciation, and salvage values.
Project S
Project L
These cash flows (either in table or time line form) can be used to quickly solve for NPV by finding the PV of each cash flow, or by using the NPV function. To find the internal rate of return, you must use Excel's IRR function.
Year (t) 0 1 2 3 4 WACC = 10% 0 | -$1,000 $454.55 $330.58 $225.39 $68.30 $78.82
Project S
1 | $500
2 | $400
3 | $300
4 | $100
NPV =
Using Excel's NPV function: NPV = Using Excel's IRR function: IRR =
Project L
NPV =
1 | $100
Using Excel's NPV function: NPV = Using Excel's IRR function: IRR =
An NPV profile is a graph that plots a projects NPV against the discount rate. To create an NPV profile, first we construct a data table that calculates NPV at various costs of capital. Notice, we have used increments of 5% and added Project S's IRR.
200
IRRS =
100
When comparing mutually exclusive projects whose cash flows differ with respect to size or timing, conflicts arise between the NPV and IRR methods (as indicated by calculations above). NPV profiles of two such projects would intersect at some point. The cost of capital at which the profiles cross (and the projects have the same NPV) is called the crossover rate . A data table and graph below shows results for Projects S and L. Again, increments of 5% are used, but the IRR for each project and the crossover rate between the projects are used. The crossover rate is calculated immediately below the figure, but for now assume it is correct.
L S
At r = 10%, NPVL > NPVS, but IRRS > IRRL, so there is a conflict.
IRRS
15%
20%
Year (t) 0 1 2 3 4
Expected After-Tax Net Cash Flows, CFt Project S Project L -$1,000 -$1,000 500 100 400 300 300 400 100 675 11.97%
Crossover rate =
NPV ($)
Data for the Graph: -$0.77 0% -$1.60 10% -$0.77 20% -$0.21 30% $0.18 50% $0.62 100% $0.90 200% $0.62 300% $0.28 400% $0.00 500% -$0.21
1.5 1.0 0.5 0.0 -0.5 -1.0 -1.5 -2.0 0% 100% 200% 300% 400% 500%
Cost of capital
The NPV profile crosses the x-axis, so there are two IRRs. To find each IRR, we must calculate the IRR twice, but the second calculation will insert a very high value for a guess (to find the higher IRR shown above). IRR1 = IRR2 = 25% 400%
Project S
PV(costs) =
TV =
Using the RATE function: MIRR = Using the MIRR function: MIRR =
Project L
0 | -$1,000
1 | $100
3 | $400
PV(costs) =
TV =
Using the RATE function: MIRR = Using the MIRR function: MIRR =
Project L
1 | 100 -900
2 | 300 -600
3 | 400 -200
4 | 675 475
Payback L =
3 + 200/675
However, the payback period ignores cash flows occurring after the cost is recovered and it ignores the time value of money. In an effort to alleviate the second concern, the discounted payback was developed, which incorporates the present value of cash flows received.
Project L
1 | 100 91 -909
SECTION 11.3
SOLUTIONS TO SELF-TEST QUESTIONS 2 What are the NPVs of Projects SS and LL if both have a 10% cost of capital and the indicated cash flows? WACC 10% Expected After-Tax Net Cash Flows, CFt Project SS Project LL -$700 -$700 500 100 300 300 100 600
SECTION 11.4
SOLUTIONS TO SELF-TEST QUESTIONS 2 What are the NPVs of Projects SS and LL if both have a 10% cost of capital and the indicated cash flows? Expected After-Tax Net Cash Flows, CFt Project SS Project LL -$700 -$700 500 100 300 300 100 600
SECTION 11.6
SOLUTIONS TO SELF-TEST QUESTIONS
2 Project MM has the cash flows shown below. Calculate MMs NPV at discount rates of 0%, 10%,12.2258%, 25%, 122.1470%, and 150%. What are MMs IRRs? If the cost of capital were 10%, should the project be accepted or rejected? Project MM CFs -$1,000 2,000 2,000 -3,350 -$350.00 -$45.83 $0.00 $164.80 $0.00 -$94.40 WACCs 0% 10% 12.23% 25% 122.15% 150%
Year (t) 0 1 2 3 NPVMM (0%) = NPVMM (10%) = NPVMM (12.2258%) = NPVMM (25%) = NPVMM (122.1470%) = NPVMM (150%) = IRRMM,1 = IRRMM,2 = 12.23% 122.15%
*** A quick scatter plot graph shows a sketch of the NPV profile of MM and its two IRRs.
NPV ($) 200 100 0 -100 -200 -300 -400 Cost of capital 0% 50% 100% 150%
SECTION 11.7
SOLUTIONS TO SELF-TEST QUESTIONS
4 Projects S and L have the following cash flows, and their cost of capital is 10%. What are the projects IRRs, MIRRs, and NPVs? Which project would each method select? WACC 10% Expected After-Tax Net Cash Flows, CFt Project SS Project LL $ (1,000) $ (1,000) 1,150 100 100 1,300 Proj L 19.1% 18.7% $165.29 Accept? Accept S Accept L Accept L
SECTION 11.8
SOLUTIONS TO SELF-TEST QUESTIONS 3 Project P has a cost of $1,000 and cash flows of $300 per year for 3 years plus another $1,000 in Year 4. The projects cost of capital is 15%. What are Ps regular and discounted paybacks? If the company requires a payback of 3 years or less, would the project be accepted? Would this be a good accept/reject decision, considering the NPV and/or the IRR?
Regular payback
Years Cash Flow Cumulative Cash Flow 0 | -1,000 -1,000 1 | 300 -700 2 | 300 -400 3 | 300 -100 4 | 1,000 900
Reg PB =
3.10
Discounted payback
WACC 15% Years Cash Flow Discounted Cash Flow Cumulative Discounted CF Disc PB = NPV = IRR = 3.55 $256.72 24.78% 0 | -1,000 -1,000 -1,000 1 | 300 261 -739 2 | 300 227 -512 3 | 300 197 -315 4 | 1,000 572 257
The payback rule of 3 years leads to a reject decision, which would conflict with both the NPV and IRR criteria, which would suggest accepting the project.