Installation of Sheet Pile Wall: Open-Cut & Bottom-Up Construction Method
Installation of Sheet Pile Wall: Open-Cut & Bottom-Up Construction Method
Excavation &
04 . Construction
of Underground Structure
While noise, dust and other inconveniences are inevitable during construction, LTA will
Base Slab
The underground Rapid Transit System (RTS) stations and cut-and-cover tunnels are typically constructed by the open-cut and bottom-up method. In this method, the earth is excavated to the required depth with retaining walls and struts supporting the soil at the sides. Upon the completion of excavation to the required depth, the base slab of the underground structure is cast at the bottom-most level, followed by the side walls. Casting of concrete progresses upwards, level by level till the roof of the structure is completed. Ground is then backfilled and reinstated.
Formation Level
The soil is excavated to the next strut level and the second level strut is installed. It continues till the excavation reaches the final depth or formation level. The number of strut levels depends on the excavation depth.
At formation level, the reinforced concrete slab or base slab is constructed, followed by the removal of the lowest level strut and the side walls are constructed.
05 . Construction of
Underground Structure
06 . Backfilling &
Reinstated Road
Reinstatement
Roof Slab
Backfill
The next level of slab is constructed, followed by the removal of the strut near to that slab level. This process progresses upwards till the roof slab is constructed.
After the roof slab is completed, the soil is backfilled to the first strut level before the first level strut is removed. This is followed by completely backfilling the top of the underground structure. If the retaining wall is a diaphragm wall or a bored pile wall, the top 2 metres of the wall will be removed. If it is a sheet pile wall, the sheet piles will be extracted.
Side wall
01 . Installation of
Retaining Wall
Retaining Wall
02 . Excavation &
First Level Strut
If you have any suggestions or feedback, please call our Customer Service Line: 1800 CALL LTA 1800 2255 582
August 2004
The underground retaining wall is installed before excavation commences. The retaining wall can be a concrete diaphragm wall, a concrete bored pile wall or a steel sheet pile wall; depending on the site condition, soil type and the excavation depth.
The soil is excavated to the first strut level. The first level strut is installed before the excavation proceeds further.