50mc Ugt Boq

This document provides a summary sheet and bill of quantities for construction of an employee house. The summary sheet lists the substructure and superstructure amounts. The bill of quantities includes 8 sections: A) Substructure including excavation and earth works, concrete work, and masonry work totaling Rs. 606,144. B) Superstructure including concrete work, roofing and cladding work, steel work, metal work, finishing, glazing, and sanitary works totaling Rs. 1,136,091. The total cost is Rs. 1,742,235. Takeoff sheets provide further itemized details on quantities and costs for individual construction

Uploaded by

haftamuTekle
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
442 views

50mc Ugt Boq

This document provides a summary sheet and bill of quantities for construction of an employee house. The summary sheet lists the substructure and superstructure amounts. The bill of quantities includes 8 sections: A) Substructure including excavation and earth works, concrete work, and masonry work totaling Rs. 606,144. B) Superstructure including concrete work, roofing and cladding work, steel work, metal work, finishing, glazing, and sanitary works totaling Rs. 1,136,091. The total cost is Rs. 1,742,235. Takeoff sheets provide further itemized details on quantities and costs for individual construction

Uploaded by

haftamuTekle
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 7

SUMMARY SHEET FOR EMPLOYEE HOUSE

ITEM

DESCRIPTION OF WORKS A. SUB STRUCTURE


1 EXCAVATION AND EARTH WORK 2 CONCRETE WORK 3 MASONRY WORK

AMOUNT

606,144.00

SUB TOTAL "A" B. SUPER STRUCTURE


1 CONCRETE WORK 2 BLOCK AND MASONRY WORK 3 ROOFING & CLADDING WORK 4 STEEL WORK 5 METAL WORK 6 FINISHING 7 GLAZING WORK 8 SANITARY WORK 9 ELECTRICAL WORKS

606,144.00

#REF! #REF! #REF! 1,136,091.00 #REF! #REF! #REF!

SUB TOTAL "B" TOTAL SUM (A + B)

#REF! #REF!

Specification and Bill of Quantity for EMPLOYEE Building (8 PCS EH 1 TO EH8)


ITEM DESCRIPTION A. SUBSTRUCTURE 1.EXCAVATION AND EARTH WORK Clear the site to remove top soil to an average depth of 1.1 20 cm Bulk excavation to an average depth of 50 cm to remove all black cotton soil over the entire area of the tank as 1.2 per the instruction of the engineer Pit Excavation for Under ground tank (UGT) in normal soil to a depth not exceeding 150 cm from reduced 1.3 ground level. Pit Excavation for Under ground tank (UGT) in normal soil to a depth exceeding 150 cm but not exceeding 1.4 500cm from reduced ground level. Pit Excavation for Under ground tank (UGT) in weathered rock to a depth not exceeding 150 cm from 1.5 reduced ground level. Pit Excavation for Under ground tank (UGT) in weathered rock to a depth exceeding 150 cm but not 1.6 exceeding 500cm from reduced ground level. Pit Excavation for Under ground tank (UGT) in Hard rock to a depth not exceeding 500cm from reduced 1.7 ground level. Back fill under UGT with red ash or river sand brought from outside and well compacted in layers not exceeding 1.8 20cm thick. Cart away surplus excavated material and spread on a chosen site at a distance not exceeding 5 km from site. m m
2

unit

Qty

Unit Price

Amount

75.00 37.50

m3

33.75

m3

67.50

33.75

m3

67.50

m3

60.00

m3

110.20

255.00

1.9

Hard basaltic or equivalent stone hard core well rolled consolidated and blinded with crushed stone to a finished 1.10 thickness of 25 cm Total carried to summary 2. CONCRETE WORK 5cm thick lean concrete in class C-10 with minimum 3 2.1 cement content of 240 kg/m under RC Beam. Reinforced concrete in class C-25 with minimum cement content of 360 kg/m3 filled in to form work and vibrated around reinforcement bar. (form work and reinforcement 2.2 bar measured separately). a. In RC beam (30 x 25) b. Manhole beam c. In 50 cm thick concrete floor slab. d. in mass concrete base Provide, cut and fix in position Wooden or metal form 2.3 work for: a. Beams b. Floor slab Provide and place steel reinforcement bars according to structural drawings. Price includes cutting, bending, 2.4 placing in position and tying wires. a. Diam. 6 mm deformed bar b. Diam10mm deformed bar c. Diam 20mm plain bar price includes with proper top & bottom anchorage length not greater than 4m as per the drawing & instruction of the engineer Total carried to summary

m2

m2

6.35

m3 m3 m3 m3 1.10 0.60 20.00 0.30 m m2


2

16.65 14.00

kg kg pcs

47.10 79.65 4.00

Specification and Bill of Quantity for EMPLOYEE Building (8 PCS EH 1 TO EH8)


ITEM DESCRIPTION 3. MASONRY WORK 50cm thick hard trachytic stone foundation masonry wall bedded in cement sand mortar of mix ratio1:4 below 3.1 NGL. Ditto as Item 3.1 but semi-dressed stone masonry wall above N.G.L. external side left for pointing. (Price includes pointing to external side of the wall with cement 3.2 sand mortar of ratio 1:2) Total carried to summary 4. Finishing Finishing works shall include all surface pre-cleaning, preparation and application of finishing and cleaning at the end of finishing works Apply 50mm thick cement & sand screed to floor finish to receive ceremic tile. 4.1 300*300mm non slippery porcelain ceramic flooring tiles on & including 44mm thick cement sand screed (1.3)mix 4.2 & joints pointed in cement mortal (1.3)mix.. Total carried to summery Grand Total m2 963.54 500.00 481,770.00 529,947.00 1,136,091.00 m
2

unit

Qty

Unit Price

Amount

221.76

1,600.00

354,816.00

m3

147.84

1,700.00

251,328.00

606,144.00

963.54

50.00

48,177.00

No _1

Take-off sheet
Project :Location :50MC UGT

No size

QTY

Description
A. SUB STRUCTURE 1. Excavation and Earth works

No size
4 0.4 0.25 1.5

QTY

Description

5 15

75 1.1 Site Clearing


1

0.6 Manhole beam 1 15 5 0.5 4 10 0.5 20 1 10 4.5 1.5

37.5 1.2 Bulk excavation

2.3. Form work 67.5 1.3 Pit Excavation for UGT not exceeding 150cm
6 0.3 4.25 7.65 8 1.4 Pit Excavation for UGT exceeding 150cm but 135 not exceeding 500cm 2 14 0.5 14 162 1.5 0.25 3 10.65 a.) In beams a.) beam

10 4.5 3

3.6 10 4.5

5.95 8.7 51.765

Deduction

110.235 1.8 Backfilling with red ash

255 1.9 cart away


3 4.7 0.45

2. Concrete works 6.345 0 6.345 2.1. 5cm C10 lean concrete

0.3 0.25 4.5

2.2 C-25 Concrete

1.0125 RC Beam

contractor ______________

supervisor _____________

No _2

Take-off sheet
Project :Location :EMPLOYEE (One pcs)

No size
1

QTY

Description

No size
2 15.15 3.2

QTY

Description

15.15 7.95 120.4425 2.2.C 15cm concrete floor slab

96.96 2.3. Form work


8 15.15 0.25 30.3 12 4.35 0.25 13.05 a.) In grade beam 2 3 3.2 2 2.34 3.2 2 12.15 3.2

77.76

14.976

43.35 Total
24 0.25 1.65 0.25 1 3 Footing pad 12 5.2

19.2 356.324 Total

b) footing 9.9 Column

15.2

3.2. G28 metal gutter

12

30.4 Total
3.3. down pipe

62.4 Total
0 Footing pad

4.Steel structure
16 3.2 51.2 4.1. wall post unit weigt 32.37kg/m 1657.344 Total 30.3 4.2. Roof beam UW 32.37kg/m 980.811 47.7 4.3. Roof end beam UW 32.37kg/m 1544.049 121.2 4.4. Purlin UW 5.87kg/m 711.444 38.4 4.5. bracing wire uw 0.888kg/m 34.0992 16 4.6. embedde plates 16 64 4.7. embedde bolts 64

12.9 Total 3.0 Masonary work


1 46.2 1.2 0.5 46.2 0.8 0.5 2 3.1 Masonary below NGL 15.15

27.72 Total
1 6 3.2 Masonary above NGL 7.95

18.48 Total A. SUPPER STRUCTURE 3. Roofing


1 8.45 15.15 7.95 4.12 3.1. 80mm thick polystyrene sandwich color steel plate (with coating) Roof cover

15.15

12

3.2

128.0175 Total
2 3.1. 80mm thick polystyrene sandwich color steel plate (with coating) wall cladding

16

65.508
8 3.2 3.2

16

81.92

No _3

Take-off sheet
Project :Location :EMPLOYEE (One pcs)

No size

QTY
5. Metal work
8 4 1 8 4

Description
a) Door 90 x 240 b.) Door 70 x 240 C.) Door 120 x 240 D) window 100 x 120 E) window70 x50

No size

QTY

Description

6. finishing
1 15.15 7.95 6.1. 50mm thick cement screed

120.4425 Total
1 15.15 7.95 6.2. 300 x 300 mm porciline ceramic

120.4425 Total 6. Glazing


8 0.9 2.4

17.28
4 0.7 2.4

6.72
1 1.2 2.4

2.88
8 1 1.2

9.6
4 0.7 0.5

1.4 37.88 Total

contractor ______________

TAKEOFF SHEET FOR REINFORCEMENT BARS Page:_1_____ No of Bars in mem a Length ber mem. 4.5 2 1 1.1 15.75 1.4 8.55 1.4 15.15 7.95 3 4 3 4 4 4 4 3 1 1 4 4 31 11 4 76 4 41 41 76 Length of bars

S. No 1 Beams

Description

Dia. 10 10 6 6 14 8 14 8 8 8

Shape

total 12 16 93 44 16 304 16 123 41 76

= 6mm

=12mm = 10mm = 16mm =20mm =24mm 54 32

2 Manhole Beams 3 Beam stirrap 4 manhole Beam stirrap 5 Grade beam main bar 6 Grade beam stirrap 7 Grade beam main bar 8 Grade beam stirrap 9 Floor slab 10 Floor slab

93 48.4

Total length of bars in m Unit wt. Of bars Total Weight Of bars in Kg Contractor :____________________

141.4 0.222 31.4

0 0.888 0

86 0.618 53.1

0 1.579 0

0 2.467 0

0 3.552 0

Supervisor:__________________