ROURKELA STEEL PLANT
INSTALLATION OF HOT STRIP MILL 
FEASIBILITY REPORT   
STEEL AUTHORITY OF INDIA LIMITED 
CENTRE FOR ENGINEERING &TECHNOLOGY 
RANCHI - 834 002   
MARCH 2012  CET/05/RN/3379/FR/RF/01/R-0   
RSP  CONTENTS CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 1 of 3  
CONTENTS - CHAPTERS  
Chapter no.  
Description  
Page no. 
1.  Summary  1.1-1.3 
2.  Background  2.1-2.11 
3.  Selection of Alternatives   3.1-3.3 
4.  Project Description  4.1-4. 74 
5.  Project Implementation  5.1-5.1 
6.  Financial Analysis  6.1-6.5 
7.  Recommendation  7.1-7.1 
  Annexures   
  Drawings    
RSP  CONTENTS CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2 OF 3  
CONTENTS - ANNEXURES  
ANNEXURE 
NO. 
DESCRIPTION  NO. OF 
PAGES 
2.6.2-1  Copy of Letter for Assignment From RSP  1 
4.2-1  Tentative Product Mix   
5.1-1  Implementation Schedule (Pre- Ordering Activities)  1 
5.1-2  Implementation Schedule (After Stage-II Approval)  1 
6.1.1-1  Capital Cost Estimate  Summary  1 
6.1.1-2  Detailed Capital Cost Estimate  3 
6.1.1-3  Basis Of Capital Cost Estimate  4 
6.1.1-4  Volume Of Work  for Capital Cost Estimate  1 
6.5.1.6-1  Works Cost Of Production   1 
6.5.2.2-1  Gross Margin Calculation  1 
6.6.1-1  Cash Flow Statement  6 
6.6.2-1  Financial Analysis  1   
RSP  CONTENTS CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 3 of 3  
CONTENTS - DRAWINGS  
Sl. no.  Drawing no.  Description 
1    CET RN 3379 CEO 00 001 R=0   General Layout of HSM Location 
2    CET RN 3379 RF1 00 003 R=0  Layout of Proposed Hot Strip mill 
3    CET RN 3379 RF1 00 004 R=0  Layout of sheet shearing Line 
  4  CET RN 3379 EE1 00 001 R=0  Single  Line  diagram  of  Power 
distribution Scheme    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 1.1    
1  SUMMARY  
1.1  Rourkela  Steel  Plant  (RSP)  produces  a  large  variety  of  steel 
products  which  include Hot  Rolled  Coils/Sheets,  Heavy Plates,  Cold 
Rolled Products, Pipes and Cold Rolled Non-Oriented Products. RSP 
is currently modernizing/expanding their facilities. After completion of 
the  ongoing  modernization,  the  crude  steel  production  of  RSP  is 
envisaged to be 4.2 Mtpa. The saleable products after completion of 
the modernization is envisaged to be 3.99 Mtpa which includes 0.82 
Mtpa of slabs.  
1.2  The  distribution  of  slabs  after  the  ongoing  expansion  has  been 
considered as follows : 
Hot Strip Mill   :  1.85 Mtpa 
Existing Plate Mill  :  0.53 Mtpa 
New Plate Mill  :  1.00 Mtpa 
Sales/IPT    :  0.82 Mtpa 
Total slabs    :  4.20 Mtpa 
1.3  Hot  Strip  Mill  is  the  major  consuming  unit  of  slabs  at  RSP  which 
produces HR coils for sale and also for feed material to downstream  
production  units  of  RSP  like  Pipe  Plants,  Cold  Rolling  Mills  and 
Silicon  Steel  Mill.  The  existing  Hot  Strip  Mill  of  RSP  is  an  old  mill 
commissioned  in  mid  1960s.  This  mill  has  been  modernized  three 
times  in  last  two  and  half  decades.  The  rated  capacity  after  the  last 
modernisation was 1.65 Mtpa. The mill is designed for producing hot 
rolled  coils  with  strip  thickness  range  of  1.6-18  mm,  strip  width  of 
700-1550  mm  and  maximum  coil  weight  of  17  t.  The  average 
production  for  last  five  years  through  this  mill  is  around  1.55  Mtpa 
(input slabs 1.593 Mtpa) with the best production of 1.61 Mtpa (input 
slab 1.648 Mtpa) in the year 2007-08. 
1.4  As per the ongoing expansion of RSP, the existing Hot Strip Mill will 
have  to  process  1.85  mt  of  slabs  per  year.  With  ageing  of  the 
equipment  that  were  not  modernized  earlier  and  in  view  of 
obsolescence  of  such  equipment,  the  productivity  of  Hot  strip  mill  is 
low.  No  modernisation  of  the  existing  Hot  Strip  Mill  has  been 
envisaged  in  the  ongoing  modernisation.  Hence,  with  the  present 
status, the Hot Strip Mill will have difficulty in processing 1.85 Mtpa of 
slabs  without  substantial  investment.  Even  after  processing  1.85 
Mtpa  form  the  existing  Hot  Strip  Mill,  0.82  Mtpa  of  slabs  remains 
which will have to be sold as semis. The quality of the products, viz., 
the  thickness  tolerance,  width  tolerance,  profile  &  shape  and 
metallurgical  properties  are  inferior  to  those  produced  from  modern  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 1.2  
mills.  The  mill  has  been  designed  for  lower  strip  width  (upto  1550 
mm)  and  lower  coil  weight  (upto  17  t).  Higher  strength  of  HR  coils 
cannot  be  produced  through  this  mill  due  to  limitations  in  the  mill. 
The  mill  will  also  require  regular  investment  as  some  sustenance 
schemes. 
1.5  The  quality  of  products  from  the  existing  Hot  Strip  Mill  can  be 
improved to some extent by extensive modernisation of the mill. The 
capacity  can  also  be  raised  marginally  through  the  modernisation. 
This will require investment of around Rs 1200 to 1500 Crore and a 
shut down of around 60 days.  
1.6  Even  after  such  investment,  many  of  the  limitations  of  the  existing 
Hot  Strip  Mill  will  remain.  Around  0.67  Mtpa  of  slabs  from  RSP  will 
remain  as  semis.  Maximum  strip  width  will  be  upto  1550  mm  and 
maximum  coil  weight  will  be  17  t  only.   Higher grades  like  API  X-80 
cannot  be  rolled  through  this  mill.  The  equipment,  which  will  be 
retained, will be older and may prove as weaker areas. 
1.7  In  view  of  processing  the  required  tonnage  of  slabs  which  will  be 
available  after  the  ongoing  modernisation  of  RSP  and  to  enrich  the 
product range with wider strip, higher coil weight &  excellent product 
quality,  it  is  envisaged  to  install  a  new  Hot  Strip  Mill  3.0  Mtpa 
capacity with state of the art facilities. The existing Hot Strip Mill will 
be phased out after stabilisation of the new Hot Strip Mill. 
1.8  The envisaged Hot Strip mill will be located near the slag granulation 
plant  after  necessary  site  development.  The  Hot  Strip  Mill  will  have 
following broad parameters : 
Strip thickness  :  1.2 - 25.4 mm 
Strip width    :  725 - 2100 mm 
Max. Coil weight  :  35 t 
Specific Coil weight :  20 t/mm (max) 
1.9  Major  facilities  in  the  Hot  Strip  Mill  will  include,  two  nos.  of  Walking 
Beam  type  Reheating  Furnaces,  High  pressure  desclaing,  a  4-high 
Reversing Roughing Stand with Edger, Passive covers, Crop Shear, 
six nos. of 4-high finishing stands, Laminar cooling system, two nos. 
of  down  coilers,  coil  conveying  system,  etc.  The  mill  will  have 
modern  control  system  including  automatic  strip  width  control, 
thickness  control,  profile  &  shape  control,  metallurgical  properties, 
etc. to produce hot rolled coils of excellent quality. A Roll shop will be 
provided adjacent to the Mill to cater to the requirements of the new 
mill.  A  Sheet  shearing  Line  of  400,000  tpa  capacity  will  also  be 
installed  for  making  sheets/plates  from  the  HR  coils  produced    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 1.3    
through  the  new  mill.  The  existing  Dividing  Line  will  also  be  utilised 
for  producing  hot  rolled  sheets.  Supporting  facilities  and 
infrastructures  including  power  supply,  Water  &  utilities,  road  &  rail 
network will also be provided at the proposed Hot Strip Mill area.  
1.10  It  is  estimated  that  the  project  will  be  completed  in  42  months  from 
the  date  of  sanction  and  36  months  from  the  date  of  stage-II 
approval.  The  project  will  be  implemented  under four  packages,  viz. 
soil Investigation & survey package, Site development package, Rail 
Network package and the Mill package. 
1.11    The  capital  cost  estimate  for  the  New  Hot  Strip  Mill,  RSP  has  been 
estimated to be Rs. 3879.42 Crore, net of cenvat credit of Rs. 356.03 
Crore and inclusive of IDC component of Rs 192.06 crore.  
1.12  Techoeconomic parameters of the project areindicated below : 
  Gross Margin      :  Rs 931.18 Crore 
IRR (Pre tax)       :  21.36% 
IRR (Post tax)      :  18.08% 
NPV at 10% discount (pre tax)  :  Rs 2875.83 Crore 
NPV at 10% discount (post tax)  :  Rs 1782.92 Crore 
If only inhouse  slabs  (2.67  Mtpa)  are  considered, the  IRR  (post  tax) 
works out to be 16.41%. 
1.13    A  new  Hot  Strip  Mill  with  modern  features  is  required  to  roll  the 
required volume of slabs available after the ongoing modernisation of 
RSP  and  to  avoid  sales  of  semis  as  slabs.  Market  requirements  of 
higher  coil  weight,  wider  strip,  higher  strength  grades,  excellent 
product qualities, etc. will be met through the new Hot Strip Mill.  
The project is technically feasible and technoeconomically viable and 
hence recommended for implementation.     
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.1 
2  BACKGROUND 
2.1  Rourkela  Steel  Plant  (RSP)  produces  variety  of  saleable  products 
which  include  hot  rolled  coils  &  sheets,  heavy  plates,  pipes,  cold 
rolled coated & uncoated coils/sheets and electrical steel (cold rolled 
non oriented steel). Rolling & processing facilities at RSP to produce 
these products consist of the following complexes : 
  Hot Strip Mill 
  Plate Mill 
  ERW Pipe Plant 
  SW Pipe Plant 
  Cold Rolling Mills 
  Silicon Steel Mill 
A new Plate Mill of 1.0 Mtpa capacity is also under installation.  
The  feed  material  to  the  Hot  Strip  Mill  and  the  Plate  Mill  are  cast 
slabs whereas the feed materials to the other mills are hot rolled coils 
produced from the Hot Strip Mill.  
2.2    Existing Hot Strip Mill 
2.2.1    The  1700  mm  Hot  Strip  Mill  (HSM)  of  Rourkela  Steel  Plant  was 
installed  in  mid  1960s  for  producing  1.15  Mtpa  of  Hot  rolled  (HR) 
coils mostly of normal carbon steels. This mill has been modernized 
three  (3)  times  in  last  two  and  half  decades.  The  modernization 
activities  were  carried  out  with  different  objectives  related  to 
improvements  in  productivity  and  product  quality.  In  the  last 
modernization,  carried  out  in  early  1990s,  the  production  capacity 
was enhanced to 1.65 Mtpa.  
2.2.2    The  existing  1700  mm  Semi-Continuous  Hot  Strip  Mill  broadly 
comprises of the following facilities : 
- 225 t/h walking beam type reheating furnaces  2 nos. 
- Primary descaler 
- 2-Hi reversing rougher (R0) with vertical edger (V0) 
- 4-Hi reversing rougher (R1) with attached edger (E1)  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2.2  
- 4-Hi single pass rougher (R2) with attached edger (E2) 
- Coil box 
- Rotary crop shear 
- Pinch roll scale breaker 
- Finishing train comprising of six 4-Hi stands (F1  F6) with hydraulic 
AGC in stands F3  F6 
- Run-out table with laminar strip cooling system 
.- Two downcoilers (C4 & C5) 
- Coil conveying system with coil weighing, banding and marking 
facilities 
- Hot rolled strip shearing line 
2.2.3    Main Parameters 
The  existing  Hot  strip  mill  is  presently  rolling  Low  carbon  steels, 
CRNO steels, API grade steels up to X-65. The input slab sizes and 
rolled coil parameters, as designed, are as follows: 
Slab Dimensions : 
Parameters    Designed      Actual 
Thickness   :   180  210 mm    180  220 mm 
Width    :   700  1550 mm    740  1450 mm 
Length   :   3500  8600 mm    6000  8900 mm 
Weight   :   17 t max      17 t max 
Transfer bar Dimensions : 
Thickness   :     20  32 mm    20  32 mm 
Coils/Strip Dimensions :   
Thickness     :   1.6  18 mm    1.9  12 mm 
Width      :   700  1550 mm  740  1450 mm 
Inner diameter   :   760 mm    760 mm    
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.3 
Outer diameter   :  1700 mm max.  1700 mm 
Weight     :   17 t max.    17 t max 
Specific Weight   :   13 kg/mm max. 
Designed mill capacity : 1,650,000 tpa 
Best  achieved  production  in  the  mill  was  1.61  MT  in  the  year  2007-
08. Average of last 5 years production is 1.555 Mtpa of HR coils.  
2.2.4  A  part  of  the  HR  products  of  the  existing  HSM  is  used  as  input 
material in the down stream units, viz, Cold Rolling Mill, Silicon Steel 
Mill, Spiral welded pipe plant and ERW pipe plant. Balance is sold as 
HR coils or HR sheets.  
2.3    Ongoing Expansion/Modernisation of RSP 
2.3.1    Rourkela  Steel  Plant  is  already  under  expansion  &  modernization. 
Following  facilities  are  being  added/expanded  during  the  ongoing 
modernization : 
  A 67.7 m new Coke Oven battery  
  A 4060 m
3
 new Blast Furnace  
  A new 150 t BOF at SMS-II 
  Secondary  Refining  units  (1  Ladle  Furnace  and  1  RH-OB)  at 
SMS-II 
  A single strand Slab Caster at SMS-II 
  A  new  Plate  mill  of  1  Mtpa  capacity  (expandable  upto  1.8 
Mtpa in future) 
After  completion  of  the  ongoing  expansion/modernization,  the 
production level at various processing steps of RSP will be as follows 
: 
Hot Metal  :  4.5 Mtpa 
Crude Steel  :  4.2 Mtpa 
Saleable: 
Plates from Existing Plate Mill  :  0.4890 Mtpa 
Plates from new Plate Mill    :  0.9295 Mtpa  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2.4  
Hot Rolled Coils/Sheets    :  1.2454 Mtpa 
Cold rolled products     :  0.3017 Mtpa 
Pipes          :  0.1300 Mtpa 
CRNO coils/sheets      :  0.075 Mtpa 
Total finished products    :  3.1706 Mtpa 
Semis (Slabs)      :  0.8200 Mtpa 
Total saleables (including semis)  :  3.9906 Mtpa 
2.3.2    Distribution of Slabs 
The  distribution  of  slabs  after  the  ongoing  expansion  has  been 
considered as follows : 
Hot Strip Mill   :  1.8500 Mtpa 
Existing Plate Mill  :  0.5300 Mtpa 
New Plate Mill  :  1.0000 Mtpa 
Sales/IPT    :  0.8200 Mtpa 
2.4    Limitations of Existing Hot Strip Mill 
2.4.1    As per the ongoing expansion of RSP, the existing Hot Strip Mill will 
have  to  process  1.85  Mt  of  slabs  per  year.  With  ageing  of  the 
equipment  that  were  not  modernized  earlier  and  in  view  of 
obsolescence  of  such  equipment,  the  productivity  of  Hot  strip  mill  is 
low. It was envisaged to process 1.65 Mtpa of slabs through this mill 
during the last modernization in 1992. The best throughput in this mill 
was 1.648 MT in the financial year 2007-08. Average throughput for 
last five years is 1.593 Mtpa. Hence, with the present status, the Hot 
Strip Mill will have difficulty in processing 1.85 Mtpa of slabs without 
substantial  investment.  The  quality  of  the  products  from  this  mill  is 
inferior to those produced from modern mills.  
2.4.2    Limitations  of  the  existing  Hot  Strip  Mill  of  RSP  can  be  summarized 
as follows : 
  Production capability 
The  capacity  of  the  mill,  after  last  modernization,  was  rated  as 
1.65  Mtpa.  The  cycle  time  in  roughing  mill  area  is  high  due  to 
the  present  layout  and  limitations  in  existing  roughing  mill.  The    
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.5 
old roughing stands R1 and R2 have become weaker with time, 
resulting  in  low  drafting  and  speed  capabilities.  Also,  the 
drafting and speed capabilities of R1 and R2 are much lower as 
compared  to  present  day  roughing  stands  limiting  the 
possibilities of higher production.  
The cycle time of finishing stands is also high because of drive 
power  limitations.  Further,  the  load  on  finishing  mill  is  higher 
due  to  less  drafting  from  the  roughing  mill.  Work  roll  changing 
time  in  this  mill  is  more  than  30  minutes  whereas  modern  mill 
has  work  roll  change  time  of  around  5  to  7  minutes  only.  The 
combination of these factors restricts higher production from the 
existing Hot Strip Mill.  
  Product sizes 
The mill is designed to produce HR coils with maximum width of 
1550  mm.  Demand  for  higher  width  HR  coils  is  increasing 
especially  for  API  grades.  New  mills  are  coming  which  can 
produce  strip  upto  2100  mm  width  and  hence  will  have 
advantage  on  account  of  this.  The  Mill  is  designed  to  roll  strip 
with  thickness  range  of  1.6  mm  18  mm.  However,  a  strip 
thickness range of 1.9 mm to 12.5 mm is being rolled from this 
mill  due  to  constraints  in  roughing  and  finishing  mills.  Modern 
Hot  Strip  Mills  can  produce  HR  coils  with  minimum  strip 
thickness  upto  0.8-1.2  mm  which  find  applications  as  a 
substitute  of  CR  coils  at  various  applications.  Also,  HR  coils  of 
higher thickness  are in demand.  
  Grades of HR coils 
The  old  roughing  stands R1 and R2 have become weaker with 
time,  resulting  in  low  drafting  and  speed  capabilities.  Also,  the 
drafting and speed capabilities of R1 and R2 are much lower as 
compared  to  present  day  roughing  stands  limiting  the 
possibilities  of  higher  production  and  rolling  of  stronger  Higher 
strength HR coils cannot be produced through existing mill due 
to limitations in drive power, poor health of equipment and other 
factors. Demand of stronger material upto API X-80 is rising.  
  Lower Coil weight 
The  existing  Hot  Strip  Mill  is  designed  for  maximum  17  t  coil 
weight  (Specific  Coil  Weight  13  kg/mm).  Higher  coil  wt.  (upto 
30-35 t) is preferred and is available from other mills. 
  Product Quality  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2.6  
The basic parameters that determine the quality of HR coils are  
-  Width  tolerance  :  The  mill  lacks  Automatic  Width  Control 
(AWC)  system  and  there  are  variations  in  width  of  the  rolled 
strip. Width variations of the strip are of the order of +20 to 30 
mm,  whereas  products  form  competitors  are  having  width 
tolerance  within  0,  +5  mm.  Head  end  fishtails  are  also 
observed in coils produced through the existing mill.  
-  Thickness  tolerance  :  Thickness  tolerance  achieved  in  the 
products  from  this  mill  is  more  than    100  m  where  as  a 
thickness  tolerance  of  25    50  microns  are  achieved  at  other 
modern  mill.  HAGC  was  provided  in  finishing  stands  from  F3 
to  F6  only.  The  existing  HAGC  is  of  older  design,  has  poor 
resolution  and  repeatability.  The  controls  &  automation  level 
are outdated. Hence the thickness tolerance achieved through 
this mill is quite wide.  
-  Strip  Profile:  No  provision  for  strip  profile  control  has  been 
provided  with  the  mill.  Strip  Profile  of  all  the  strip  cannot  be 
measured  as  there  is  no  profile  measuring  gauge  installed  at 
the mill. In general, the profile achieved from this mill is of the 
level  of    100  micron  whereas modern  mill  achieve  a  level  of 
Profile 40  60 micron. 
-  Strip  Shape  &  flatness:  No  provision  has  been  provided  for 
measurement  and  shape  control  and  the  shape  of  the  strip 
achieved through this mill is poor. 
-  Strip  surface  quality:  Surface  quality  of  the  rolled  strip  is  also 
not  up  the  mark  as  no  provision  for  anti-peeling  /oxide 
suppression has been provided.  
-  Metallurgical  properties  of  finished  strip:  The  existing  laminar 
cooling  system  is of  older  open-loop  design.  The  settings  are 
based  on  operator  experience  only  and  has  a  poor 
repeatability.  Hence  the  required  metallurgical  properties  are 
not  achieved.  Further,  for  better  metallurgical  properties,  the 
finishing  mill  needs  a  good  temperature  regime  that  can  be 
achieved with higher transfer bar thickness. With limitations of 
drive  powers  in  the  finishing  stands,  the  possibilities  are 
limited. 
It  can  be  inferred  from the above  that  the  present  quality 
of  HR  coils  from  RSP  Hot  strip  mill  falls  far  below  the 
present  market  demand  and  the  HR  coils  available  from 
competitors.    
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.7 
  Health of equipment 
Health  of  various  equipment  which  has  not  been  modernized 
during last modernization, is poor and unpredictable breakdown 
occurs.  These  equipment  need  to  be  revamped/replaced  for 
long time sustenance.  
2.5    Necessary Modernisation required in Existing Mill 
2.5.1    A part of the mentioned limitations can be overcome by modernizing 
the  existing  Hot  Strip  Mill.  Major  areas  required  of 
modernization/revamping will include the following. 
  Roughing Mill Area 
No  modernization  has  been  carried  out  in  the  existing 
roughing  stands  R1  and  R2  and  the  stand  equipment  has 
inability  to  roll  at  designed  speeds  and  drafting  capability  is 
low.  The  existing  roughing  stands  R1  and  R2  need  to  be 
replaced  with  a  new  heavy  roughing  stand  alongwith  edgers 
with  higher  drafting  and  speed  capabilities  and  automatic 
width control. 
The  roller  tables  are  inadequately  powered  w.r.t.  the 
increased slab weight. The roller tables are prone to frequent 
breakdowns. Most of the roller tables, which are old and have 
not been modernized earlier, will have to be replaced with new 
roller table assemblies along with new individual AC drives.  
The existing crop shear will have be modified to facilitate quick 
shear blade change and to have provisions for optimization of 
crop ends. 
  Finishing Mill Area 
The finishing mill stands are operated at lower speed of rolling 
than  designed  due  to  its  limitations  in  drive  system.  There  is 
no  provision  for  hydraulic  AGC  in  F1  &  F2.  There  is  no 
provision  of  profile  &  flatness  control  facility.  Roll  changing 
time  is  high.  Load  cells  have  erroneous  performance. 
Thyristor  control  systems  of  existing  DC  motors  are  old  and 
have  poor  controllability.  Existing  DC  drives  of  Finishing 
stands  are  not  sufficient  for  higher  productivity.    Also  existing 
drive    motors  are  prone  to  break  down  and  availability  of 
spares  is  becoming  difficult.  Inter-stand  loopers  have  high 
inertia,  low  response  and  not  able  to  generate  tension  for 
higher thickness strips.  Existing inter-stand guides & strippers  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2.8  
are  prone  to  frequent  break  downs.  Absence  of  inter-stand 
strip cooling, oxide suppression affect strip quality 
The  finishing  mill  area  need  to  be  up-graded  thoroughly  for 
higher  power  and  modern  quality  control  features  so  as  to 
achieve high productivity and better product quality.  
Drive  system  of  finishing  stands  need  to  be  replaced  with 
higher  power  AC  drives.  Existing  screw-down  system  and 
hydraulic  cylinders  need  to  be  replaced  with  long  stroke 
cylinders  for  achieving  better  thickness  tolerance  and 
reduction in in work roll change time. Replacement of old load 
cells with new load cells for better and more accurate roll force 
measurement  and  for  facilitating  better  AGC  operations  is 
required.  Roll  bending  and  shifting  system  alongwith  housing 
blocks  need  to  be  provided  at  all  stands  for  achieving  better 
profile  and  shape  of  the  rolled  product.  Existing  mechanical 
mill entry guides have to be replaced with new hydraulic entry 
guides  and  strippers  having  better  operation  and  easier 
maintainability.  Replacement  of  existing  roll  cooling  system 
with  new  roll  cooling  system  is  required  alongwith  inter-stand 
strip  cooling  system  and  anti-peeling  system  for  better  strip 
quality  and  higher  roll  life.  Existing  low  response  electro-
mechanical  loppers  with  high  response  hydraulic  loopers  and 
tensiometer  is  required  for  better  control  of  inter-stand  strip 
tension  and  to  eliminate  width  variation  (Necking)  in  the 
finishing  stands.  New  state  of the  art  automation  system  with 
mathematical  models  will  have  to  be  implemented  for  better 
quality of the products.  
  Laminar cooling 
Existing  laminar  cooling  system  is  open-loop  and  is  of  older 
design  with  no  edge  masking.  The  existing  laminar  cooling 
system  will  have  to  be  replaced  by  a  new  laminar  cooling 
system of latest design with edge masking facilities to achieve 
uniform  and  better  metallurgical  properties  of  strip  and  to 
achieve  better  coiling  temperature  control.  ROT  Roll  cooling 
facilities  will  also  have  be  provided.  The  new  laminar  cooling 
system will be linked with the microstructure control models.  
  Strip Measuring gauges 
A new gauge house will have to be provided at the exit of the 
finishing  mill  train  with  strip  thickness,  width,  profile  and 
flatness  instrumentation  for  measurement  and  control  of  strip 
quality.    
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.9 
  Down coilers  
Existing  entry  guides  will  have  to  be  replaced  with  new 
hydraulic  entry  guides  for  better  guiding  of  strip  and  better 
coiling in the down coiler. Replacement of existing down coiler 
pinch rolls with new wear resistant pinch rolls is also required 
to  reduce  down  time  for  replacement  of  pinch  rolls  and 
enabling  coiling  of  higher  strength  strip.  Existing  down  coiler 
wrapper  rolls  need  to  be  replaced  with  new  wear  resistant 
wrapper rolls to reduce down time for replacement of wrapper 
rolls. Modification of existing automatic jump control system of 
wrapper rolls is also needed.  
  Coil conveying 
Augmentation  of  existing  coil  conveyors  is  required  for 
handling higher production rate and to restore health. 
  Roll shop 
Augmentation  of  roll  shop  is  required  for  handling  new  work 
rolls and to match higher production requirements 
  Electrics 
Latest state of art electrical equipment, drives and controls for 
all the facilities to match with the technological requirement of 
modernization  scheme  will  be  required.  They  broadly  include 
new  AC  drive  system  for  the  new  roughing  stand  &  edger, 
finishing  stands,  roller  tables,  replacement  of  existing  drive 
regulation system with digital drive regulation system.  
  Automation System 
State  of  Art  level  II  automation  and  computer  facilities 
alongwith required instruments & actuators are required in the 
Hot  Strip  Mill  for  optimizing  and  controlling  the  various 
parameters  for  better  quality  of  the  products.  Modules 
required  in  the  mill  includes,  Mill  Tracking,  Mill  racing, 
Rougher  &  Finishing  mill  setup,  temperature  set  up  model, 
laminar  cooling  model,  Microstructure  model,  Profile  & 
Flatness control, Slab & coil yard mapping, etc.  
  Sustenance schemes under AMR 
Besides  the  modernization  of  the  above  mentioned  areas, 
other  AMR  schemes  are  also  required  to  restore  the  overall  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 2.10  
health  of  the  equipment  and  debottlenecking  which  are  under 
process by RSP.  
If the above mentioned schemes are implemented, following benefits 
are expected : 
  The product qualities, viz thickness tolerance, profile & shape, 
width tolerance and metallurgical properties will improve. 
  Capacity of the mill will increase marginally. 
2.5.2    Limitations to be remained after modernisation 
Implementation  of  the  schemes  indicated  in  the  preceding 
paragraphs  will  require  a  capital  cost  of  around  1200  to  1500  crore. 
Even  after  the  modernization,  following  limitations  will  remain  with 
the existing Hot Strip Mill.  
  The  mill  cannot  accommodate  the  required  tonnage  of  slabs 
which  will  be  produced  at  RSP  after  the  ongoing 
modernization.  Approximately  0.70  Mtpa  of  slabs  will  remain 
as  semis  even  after  complete  modernization  of  the  existing 
Hot Strip Mill. 
  Maximum strip width will remain to be lower (upto 1550 mm) 
  Coil weight will remain to be lower (17 t max). 
  Higher grades like API X-80 cannot be rolled in this mill. 
  The  equipment,  which  will  be  retained,  will  be  older  and  may 
prove  as  weaker  areas  in  getting  full  benefits  of  the 
modernization.  
2.6    Plan for New Hot Strip Mill 
2.6.1    The  existing  Hot  Strip  Mill  has  limitations  in  accommodating  the 
required  quantity  of  slabs  which  will  be  available  after  the  ongoing 
modernization of RSP. The mill is designed for lower width and lower 
coil  weight.  Higher  strength  HR  coils  cannot  be  produced  through 
this  mill  due  to  limitations  in  Roughing  &  Finishing  mill.  The 
equipment condition is not up to the mark due to its age. Many of the 
equipment  is  becoming  obsolete  and  spares  availability  is  getting 
difficult.  Electrics,  control  and  automation  system  is  outdated. 
Products  quality  w.r.t.  dimensional  tolerances  and  metallurgical 
properties are inferior to those available from competitors.    
RSP    CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 2.11 
A  thorough  modernisation  of  the  existing  Hot  Strip  Mill  will  be 
required to improve the quality, specially the dimensional tolerances, 
of  the  rolled  products  and to  restore  the health  of  the  equipment  for 
long  term  sustenance.  Productivity  of  the  mill  can  also  be  raised 
marginally  with  the  modernisation  and  the  mill.  The  investment 
required for this modernisation will be around Rs 1200 to 1500 crore 
However,  around  0.70  Mtpa  of  slabs  of  RSP  will  remain  as  semis 
even  after  the  massive  modernisation.  Other  basic  limitations  of  the 
mill  like  lower  width,  thickness  limitations,  coil  weight,  limitation  of 
producing higher strength coils, etc. will remain. 
In  view  of  the  above,  RSP  plans  to  install  a  new  Hot  Strip  Mill  with 
wider  product  range  (strip  width  upto  2100  mm  and  strip  thickness 
from  1.2 mm to 25.4  mm)  with  state  of the art facilities. The mill will 
have  the  capacity  of  3.0  Mtpa  of  slabs  rolling  Out  of  the  total  3.0 
Mtpa,  2.67  Mtpa  will  be  inhouse  slabs  and  balance  0.33  Mtpa  of 
slabs will be purchased/IPT.  
The  existing  Hot  Strip  Mill  will  be  closed  after  commissioning 
and stabilization of the new Hot Strip Mill. However, the existing 
Sheet  Shearing  Line  (Dividing  Line)  will  be  retained  for 
producing  the  sheets/plates  from  the  HR  coils  produced 
through the proposed Hot Strip Mill. 
2.6.2    CET  has  been  assigned  vide  RSP  letter  no.  AMR-
M&SC/Consulatancy/15/433-37  dated  17.03.2011  (copy  enclosed 
Annexure 2.6.2-1) for feasibility study of the proposed Hot strip Mill. 
Accordingly,  draft  feasibility  report  was  submitted  by  CET  in  August 
2011. Subsequently, discussions with RSP on the draft FR was held 
in February 2012 and the FR has been finalised accordingly. 
2.6.3    The co-operation provided by RSP and other agencies in preparation 
of this report is gratefully acknowledged.      
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 3.1    
3  SELECTION OF ALTERNATIVE 
3.1    Approximately 1200 m x 600 m area will be required for installation of 
the  Hot  Strip  Mill.  Following  two  alternatives  were  considered  for 
location of the proposed facilities : 
Alternative-I :Near Hanuman Vati 
Under  this  alternative,  the  proposed  Hot  Strip  Mill  will  be  located 
outside the existing plant boundary near Hanuman Vati.  
This  site  is  farther  from  the  existing  RSP  boundary.  All  the 
infrastructures will have to be created at this site. Longer network of 
railways  tracks,  longer  gas  and  water  pipelines,  etc.  will  be  required 
at this site. There is a water lagoon between the existing boundary of 
RSP  and  this  site  which  has  to  be  taken  care  for  making  the 
infrastructure. Power corridor is also passing through this site. 
Alternative-II: Near Slag Granulation Plant 
Under  this  alternative,  the  proposed  Hot  Strip  Mill  will  be  installed 
near  the  slag  granulation  plant.  This  site  was  earlier  used  for 
dumping Blast Furnace slag which is not in use at present. This site 
is  adjacent  to  the  existing  plant  boundary.  The  facilities  for  the 
proposed mill will be partly inside and partly outside the existing plant 
boundary  (major  area  will  be  outside  the  existing  plant  boundary). 
The location is indicated in Drawing no. CET RN 3379 CE0 00 001 
R=0. 
A  road  is  passing  between  RSPs  existing  boundary  and  this  site 
which  will  have  to  be  diverted.  Rail  network  is  already  existing  near 
this  site  which  will  have  to  be  further  extended/strengthened. 
Creating infrastructures will be easier at this location. 
Selection of alternative 
Site  under  alternative-II  is  adjacent  to  the  existing  plant  boundary 
and  it  will  be  easier  to  create  required  infrastructures  for  the 
proposed  Hot  Strip  Mill.  Hence,  this  site  is  more  suitable  and  is 
selected. for the proposed Hot Strip Mill.     
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.1    
4.  PROJECT DESCRIPTION 
4.1    It  is  envisaged  to  install  a  Hot  Strip  Mill  alongwith  a  Sheet  Shearing 
Line  at  Rourkela  Steel  Plant.  The  Hot  Strip  Mill  will  be  designed  for 
rolling  3.0  Mtpa  of  slabs.  A  new  sheet  shearing  line  of  0.40  Mtpa 
capacity  will  also  be  installed  within  the  proposed  Hot  Strip  Mill 
Complex.  The  existing  Sheet  Shearing  Line  (Dividing  Line)  will  also 
be retained and will be utilized for production of sheets from the HR 
coils produced through he proposed Hot Strip Mill.  
The proposed Hot Strip Mill will be located near the Slag Granulation 
Plant. Location of the proposed mill is indicated in Drawing no. CET 
RN 3379 CE0 00 001 R=0. 
4.2    Main Parameters 
Broad Parameters of the proposed Hot Strip mill will be as follows: 
Slab dimensions 
Slab thickness  :  200  300 mm carbon steel 
Slab width    :  725  2100 mm 
Slab length    :  5000  11000 mm 
Slab weight, max  :  35 t  
Strip dimensions 
Strip thickness  :  1.2  25.4 mm 
Strip width    :  725  2 100 mm 
Coil weight, max  :  35  t 
Spec. coil weight  :  max. 20 kg/mm 
Rated Production Capacity :  3.00 Mtpa (Input slabs) 
          2.94 Mtpa (HR coils) 
Main Steel grades 
Carbon structural steels 
HSLA 
Low carbon steels 
High strength steels 
LPG cylinder steel 
Line pipe steels up to API 5L X80 
Steels for Automotive applications 
Boiler and pressure vessel quality  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.2  
DDQ and EDDQ - steels 
CQ  steels 
CRNO 
A tentative size wise product mix is indicated at Annexure-4.2-1. 
The  new  Hot  Strip  Mill  will  be  equipped  with  advanced  control 
systems  in  roughing  and  finishing  mill  for  rolling  of  strips  with  best 
tolerances  for  strip  thickness,  strip  profile,  strip  flatness,  strip  width, 
final rolling and coiling temperature.  
Layout of the Hot Strip Mill is indicated in Drawing no. CET RN 3379 
RF1 00 003 R=1. 
4.3    TECHNOLOGICAL FACILITIES 
4.3.1    SLAB YARD 
Slabs  coming  from  the  Steel  Melting  Shops  will  transported  by 
railway  wagons.to  the  Hot  Strip  Mill  and  will  be  stored  in  the  slab 
storage  yards.  The  slab  yards  will  have  storage  capacity  for 
approximately  five  days.  The  slabs  stacked  in  the  slab  yard  will  be 
picked  up  by  overhead  crane  and  placed  onto  the  slab  yard  roller 
table. Slabs will be weighed and measured before transported further 
on to the charging roller table in front of the furnaces.  
4.3.2    REHEATING FURNACES 
Two  nos.  of  reheating  furnaces  will  be  provided  to  heat  &  soak  the 
input  slabs  to  the  required  rolling  temperature.  The  reheat  furnaces 
will be of walking beam type. 
4.3.2.1  Charging & Discharging Equipment 
Slabs  as  received  will  be  perfectly  aligned  automatically  and 
positioned  in  front  of  furnace  and  then  pushed  into  the  furnace  with 
the help of pusher. The pushed slab will be carried to discharge side 
with  the  help  of  walking  beam  mechanism.  From  discharge  position 
the extractor will lift the slab and put down the same on discharge roll 
table 
4.3.2.2  Reheating Furnace 
The  envisaged  major  technological  parameters  are  as  mentioned 
below :  
Type  Walking  Beam  Furnace  with  two  row 
charging 
Capacity  300 tph based on cold slabs (for reference    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.3    
size) 
Quantity(No. of Furnaces)  2 nos. 
Reference slab size  Length : 6-10m 
Width: 1500 mm 
Thickness :  250 mm 
Fuel gas  Duel  Fired  Furnace  with  provision  of 
firing  with    Furnace  Oil  (LCV  -9500 
kcal/kg)    &  Mixed  Gas  (LCV  -3600 
kcal/Nm3) 
Input material   
Charging temperature  20
o 
C (cold) 
Discharge temperature  1280
o 
C max. 
Temperature  difference 
(surface and core) 
25 
0
C max. 
Specific fuel consumption   0.3  Gcal/t  (on  yearly  average  basis)  at 
furnace discharge 
Skid cooling  Water 
Charging  by pusher 
Discharging  by extractor 
Walking  beam  furnace  skids  will  of  high  temperature  and  wear 
resistant  steel  with  high  rigidity.  The  furnace  will  be  packed  from 
inside with refractory and insulation material to limit the furnace skin 
temperature  to  about  500  C  above  ambient  temperature.  The 
movement of the walking beams will be hydraulic. A pair of movable 
skids  walking  beam  will  have  central  driving  mechanism.  One  cycle 
of  operation  consists  of  lifting,  forward  movement,  lowering  and 
reverse  movements  of  walking  beams  during  which  slabs  will  be 
advanced by predetermined distances. Hydraulic power pack will be 
provided for the movement of the walking beams. Centralised grease 
lubrication system will also be provided for the furnaces 
Combustion System 
The combustion system will include the following: 
1)  Burners  
2)  Combustion air piping 
3)  Mixed Gas & Furnace Oil Piping 
4)  Combustion air blower 
5)  Metallic recuperator for air preheating 
Three  nos.  of  Combustion  Air  Blowers  (2W+1S)  with  VVVF  drive 
have been envisaged for furnace.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.4  
Air Recuperator 
A metallic recuperator will be installed in the flue channel to preheat 
the  combustion  air  to  about  650  oC.  The  recuperator  will  be  cross-
counter flow type. Dilution air fan & Hot Air Bleed will be provided for 
protection of recuperator 
Waste Gas Flue Exhaust System 
Waste  gases  from  furnace  will  be  taken  out  through  the  opening 
provided  on  the  charging  end,  and  will  be  exhausted  to atmosphere 
through    underground  tunnel  with  forced  draft  fan  &  chimney  of 
adequate  height.  The  system  will  be  so  designed  that  waste  gas 
temperature at the base of the chimney will be kept around 250 deg 
C. 
Combustion System 
The combustion system will include the following: 
1)  Burners  
2)  Combustion air piping 
3)  Synthetic Gas Piping 
4)  Combustion air blower 
5)  Metallic recuperator for air preheating 
Three  nos.  of  Combustion  Air  Blowers  (2W+1S)  with  VVVF  drive 
have been envisaged for furnace. 
Air Recuperator 
A metallic recuperator will be installed in the flue channel to preheat 
the  combustion  air  to  about  550 
o
C.  The  recuperator  will  be  cross-
counter flow type. Dilution air fan & Hot Air Bleed will be provided for 
protection of recuperator.  
Waste Gas Flue Exhaust System 
Waste  gases  from  furnace  will  be  taken  out  through  the  opening 
provided  on  the  charging  end,  and  will  be  exhausted  to atmosphere 
through    underground  tunnel  with  forced  draft  fan  &  chimney  of 
adequate height. 
4.3.3    HIGH-PRESSURE WATER PRIMARY DESCALER 
Once  the  slabs  have  exited  the  reheat  furnace,  they  will  be 
transported  via  a  roller  table  into  a  high  pressure  water  descaling 
unit. During the reheating process an oxide layer (scale) will form on 
the  slab,  which,  if  not  removed,  will  be  rolled  into  the  surface  of  the 
product  causing  surface  defects  and  reduced  product  quality.  In    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.5    
order  to  ensure  optimum  product  quality,  the  slabs  are  descaled  to 
remove the oxide layer.  
The  process  of  scale  removal  will  broadly  consist  four  adjustable 
headers (two top, two bottom) with flat-jet nozzles delivering water at 
high  pressure  and  suitable  flows.  Two  of  the  headers  will  be 
operational and two of the headers will be standby. The headers are 
enclosed  in  a  descaler  hood  to  collect  the  water  and  scale.  Chain 
curtain  will  be  provided  at  entry  &  exit  of  the  descaler.  Main 
parameters of the primary descaler are indicate below : 
Number on top headers     :  2 
Number of bottom headers   :  2 
Operating pressure      :  240 bar  
4.3.4    ROUGHING MILL AREA 
The  Roughing  mill  area  will  consist  of  a  4-high  Reversing  Roughing 
stand.  A  vertical  edging  stand  will  be  provided  at  the  entry  side  of 
each Roughing mill stand.  
4.3.4.1  Vertical Edger 
The Edger will be capable of taking a maximum draft of up to about 
100  mm.  It  will  be  equipped  with  Hydraulic  Automatic  Width  Control 
(HAWC)  to  permit  quick  width  taper  adjustments  during  rolling. 
Spindle  change  device  for  splined  cardan  shafts  will  be  provided. 
The  Edger  will  improve  finished  width  tolerance,  minimize  plan  view 
shape errors and enhance edge quality. 
Parameters of edgers 
Roll Diameter (grooved rolls)     :  1200 / 1100 mm 
Maximum roll separating force     :  700 t 
Maximum width reduction       :  100 mm 
4.3.4.2  Roughing Stand 
The  4-high  Roughing  mill  stand  will  be  situated  directly  after  the 
edger and the work rolls are driven by AC drive with two motors with 
ski control. Work roll bearings will be four rows tapered bearing. Back 
up roll bearings will be keyless type oil film bearings. Top backup roll 
will  be  hydraulically  balanced  by  cylinder  located  in  housing 
separator.  For  work  rolls  balancing,  hydraulic  cylinders  will  be 
located  in  maewest  blocks.  Back  up  roll  balancing  cylinders  will  be 
mounted  on  the  top  of  the  housing.  Spindle  of  cardan  shaft  design  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.6  
with  spindle  balance  and  spindle  head  holding  device  will  be 
provided.  Mill  window  liners  of  duplex  material  will  be  provided  with 
greasing system, The stand will be provided with electro-mechanical 
screw  down  system  and  hydraulic  roll  force  cylinders  and  control 
system.  Two  nos.  of  hydraulic  roll  force  cylinders  (one  at  operator 
side  and  one  at  drive  side)  will  be  mounted  on  the  top  of  the  mill 
window. Hydraulic roll force cylinders will be equipped with pressure 
and  position  transducers.  The  Automatic  Gauge  Control  (AGC)  in 
conjunction  with  roll  allignment  control  will  be  provided  to  control 
thickness,  wedge  and  camber.  The  roll  force  hydraulic  cylinders  will 
be  fed  by  high  pressure  hydraulic  system.  Other  hydraulic  cylinders 
will  be  fed  by  low  pressure  hydraulic  system.  Roll  cooling  headers 
The entry and exit side of the stand will be provided with roll cooling 
headers.  Hydraulically  operated  Entry  guide  ledges  will  be  provided 
at each side of the stand to centre the slab. Mechanised Quick Work 
Change System will be provided for work roll changing. Back-up roll 
change is carried out by means of a hydraulic cylinder. The work rolls 
and  the  back-up  rolls  are  placed  by  crane  onto  the  roll  transfer  car 
which transports the rolls to the roll shop.  
Oxide  removal  headers  (top  &  bottom)  will  be  provided  at  entry  and 
delivery guides to direct water to top and bottom of the strip surface 
to remove oxide dust. Descaling headers will also be provided at the 
roughing stand. 
Load  cells  will  be  installed  between the sledge and the bottom back 
up roll chocks.   
4-high roughing stand parameters 
Mill configuration      :  4-high 
Work roll diameter       :  1250 mm  1130 mm 
Work roll barrel length    :  2250 mm 
Back-up roll diameter     :  1600 mm  1440 mm 
Roll separating force    :  5500 t 
4.3.4.3  Delay Table and Passive Cover 
After the final roughing pass the transfer bar is transported along the 
delay  table,  which  comprises  the  heat  retaining  passive  cover 
system.  Passive cover serves  for  saving temperature of the transfer 
bar  and  for  reduced  temperature  drop  between  head  end  and  tail 
end.  Consequently,  passive  cover  helps  to  achieve  a  smaller 
minimum  strip  thickness  and  more  consistent  final  material 
properties.  The  passive  cover  will  consist  of  a  group  of  insulating    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.7    
panel  located  on  the  delay  roller  table  after  the  4-high  roughing 
stand.  Each  module  of  the  passive  cover  can  be  lifted  hydraulically. 
Suitable protection will be provided at the entry of the passive cover 
to protect it from the curved transfer bar ends. 
4.3.4.4  Transfer Bar Reject System 
Bar  reject  device  will  be  provided  between  the  roughing  stand  and 
the  finishing  stand  to  reject  transfer  bar,  if  required.  The  system  will 
mainly  consist  of  suitable  nos.  of  pushing  devices  actuated  by 
hydraulic  cylinder.  Rejected  transfer  bar,  pushed  of  the  rolling  line, 
will be positioned on skid mounted supports aside the rolling line.   
4.3.5    CROP SHEAR 
Behind  the  passive  covers,  a  drum-type  crop  shear  will  be  provided 
to  shear  and  square  off  the  head  and  tail  ends  of  the  transfer  bar. 
The  crop  shear  will  consist  of  drum  housing,  drums  with  shear 
knives, knife drums bearings and the drums AC drive system. Knives 
will  be  locked  on  drums  with  hydraulic  quick  unlocking  device.  The 
crop  shear  is  equipped  with  a  crop  optimization  system  to  minimize 
the yield loss.  
The scrap produced will be disposed into scrap buckets via a chute.  
Hydraulically adjustable entry guide will be provided at the entry of 
crop shear to guide the transfer bar into the crop shear and keep it 
centered. Feed rollers will be provided at entry and exit of the crop 
shear. 
Broad parameters of the crop shear are indicated below : 
Shear Type        :  Start-stop Rotary Drum-type 
Maximum bar cross section   :  2,100 x 76  mm (API X 80) 
4.3.6    FINISHING MILL AREA 
4.3.6.1  Secondary Descaler 
A  secondary  descaler  alongwith  pinch  rolls  will  be  provided  before 
the  finishing  mill  for  descaling  the  transfer  bar  before  entering  into 
the  finishing  mill.  The  pinch  rolls  will  drive  the  transfer  bar  through 
the  water  nozzles  at  uniform  speed  and  will  also  stop  water  from 
flowing back on the transfer bar and prevent chilling.  
The  secondary  descaler  will  consist  of  two  nos.  of  top  and  two  nos. 
of  bottom  headers  with  flat  type  nozzles  housed  in  a  spray  hood, 
solenoid operated valves, etc. Descaling system pressure will be 200 
bars  (indicative).  The  spray  hood  will  have  flaps  with  replaceable  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.8  
wearing  plates  driven  by  pneumatic  cylinder  to  stop  high  pressure 
water from spray backwards. 
4.3.6.2  Finishing Mill Train 
The  finishing  mill  will consist of six  4-high,  fully hydraulic mill stands 
(F1F6).  Finishing  mill  train  will  mainly  comprise  of  the  following 
facilities : 
Guides 
Entry  and  exit  guides  arranged  ahead  and  at  back  of  the  stands 
afford guiding action to the strip as it passes the stands 
Mill stands 
Six nos. of finishing stands will be installed in the finishing mill. Each 
stand will be of 4-high configuration.  
Mill  drive  with  AC  motors,  reduction  gear  box  and  pinion  stands  will 
be  provided.  Cardan  shaft/  geared  spindles  with  spindle  balancing 
and  head  holder  will  be  provided.  Work  roll  bearings  will  be  four 
tapered  roller  bearing.  Back  up  roll  bearings  will  be  keyless  type  oil 
film  bearings.  Top  backup  roll  will  be  hydraulically  balanced  by 
cylinders  mounted  at  the  housing  top.  Work  rolls  will  also  be 
hydraulically balanced by cylinders mounted in Maewest blocks. Mill 
window  liners  of  duplex  material  will  be  provided  with  greasing 
system. Two nos. of long stroke hydraulic roll force cylinders (one at 
operator side and one at drive side) will be mounted on the top of the 
mill  window.  Hydraulic  roll  force  cylinders  will  be  equipped  with 
pressure  and  position  transducers.  The  initial  roll  gap  setting  and 
automatic Gauge Control (AGC) is provided via hydraulic gap setting 
cylinders  The  roll  force  cylinders  will  be  fed  by  high  pressure 
hydraulic  system.  Other  hydraulic  cylinders  will  be  fed  by  low 
pressure  hydraulic  system.  Load  cells  will  be  provided  between  the 
sledge and the bottom back up chocks. 
The finishing stands will use shaped work rolls (contoured rolls) with 
roll  bending  and  shifting  mechanism  for  control  of  strip  profile  and 
flatness for the strip. Hydraulic cylinders for positive work roll bending 
will  be  mounted  in  the  Maewest  blocks.  The  positive  work  roll 
bending  cylinders  will  also  serve  for  work  roll  balancing.  Hydraulic 
cylinders  for  negative  work  roll  bending  will  be  mounted  in  back  up 
roll  chocks.  Further,  hydraulic  cylinders  will  also  be  provided  at  the 
maewest blocks for work roll shifting.  
Stripper will be provided at entry and exit of each mill stand so as to 
guide the transfer bar head and also to prevent the contact between 
the  cooling  water  and  the  strip  surface.  These  strippers  will  be    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.9    
adjusted by pneumatic cylinders. The entry and exit side of the stand 
will be provided with roll cooling headers.  
Quick  Work  Roll  Change  system  will  be  provided  for  work  roll 
changing  in  all  the  stands.  Steel  sledge  for  back  up  roll  change  will 
be  located  between  the  bottom  back  up  roll  chocks  and  the  mill 
housing bed plate. 
Work Roll cooling headers will be provided at entry and exit sides of 
each rolling stand. Work Roll Cooling header on the entry side will be 
located only in top position, while in exit side are located on top and 
bottom  position.  All  headers  will  be  mounted  on  guides.  Backup  roll 
header  will  be  located  on  entry  side  on  top  position.  Further,  anti-
peeling  cooling  sprays  will  be  provided  at  entry  side  of  the  stands 
which will cool the strip in proximity of the roll bite to avoid damage of 
the chromium oxide of the work roll. 
Roll  bite  lubrication  will  be  applied  at  first  four  finishing  stands  to 
reduce friction and therefore to reduce separating force and limit roll 
wear. The roll bite lubrication system will premix and store a mixture 
of lube and water in right proportion to feed a spray system. This oil-
water  dispersion  will  be  sprayed  at  the  roll  bite  through  auxiliary 
headers  &  nozzles.  One  no.  of  header  will  be  provided  at  top  and 
bottom  work  roll  each.  Each  header  will  be  divided  into  different 
spraying  zones  so  as  to  optimize  oil  consumption  as  per  the  strip 
width. 
The  mill  stands  F1  to  F4  are  equipped  with  roll  gap  lubrication 
devices.  
Parallel  neck  taper  roller  bearing  alongwith,  thrust  bearing  at  the 
operator side will be considered. Keeper plate will be swevelling type 
mounted  on  shifting  cylinder  barrel.  Pass  line  adjustments  will  be 
through shims. 
Main parameters (Indicative) 
Number of mill stands    :  6 
Mill configuration      :  Type 4-high 
Work roll diameter (F1-F4)   :   850  750 mm 
Work roll diameter (F5-F6)   :  720  620 mm 
Work roll barrel length     :  2550 mm 
Back-up roll diameter     :  1600  1440 mm 
Back-up roll barrel length     :  2250 mm  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.10  
Back-Up roll bearing     :  Keyless oil-film type  
Mill stand force (F1-F4)    :  5000 t (max) 
Max. mill stand force F5-F6)  :  4000 t (max) 
Drive Power        :  10,000 kW  
Work roll bending (each chock)  :  200 t max ( F1-F4). 
Work roll bending (each chock)   :  160 t max (F5-F6).  
Work roll shifting stroke    :  +/- 150 mm (max) 
Maximum rolling speed     :  20 m/s 
Roll force cylinders max stroke  :  200 mm 
Inter stand loopers 
Low-inertia  hydraulic  looper  will  be  provided  between  the  finishing 
mill stands to ensure constant strip tension between two successive 
stands  and  a  stable  rolling  process.  Hydraulic  actuators  will  be 
directly  connected  to  the  loopers  arms.  Each  looper  system  will 
comprise of a looper table assembly , idle roller, hydraulic cylinder & 
servo  valve  for  tilting  the  looper  table.  Each  looper  will  be  equipped 
with  two  load  cells,  mounted  at  each  side  of  the  idle  roll  for 
measurement  of  strip  tension  at  drive  and  operating  side  for  the 
control  of the strip tension and levelling control.  
Oxide blowing system 
Top  and  bottom  spraying  headers  will  be  provided  on  mill  stands 
delivery guides to direct water to top & bottom at strip surface close 
to  the  roll  bite  in  order  to  avoid  mill  scale  powder  formation  and 
consequently scale fume emissions.  
4.3.7    RUN OUT ROLLER TABLE WITH LAMINAR STRIP COOLING 
SYSTEM  
The  run-out  table  will  be  provided  downstream  of  the  finishing  mill 
and  serves  to  convey  the strip  through the  laminar  cooling  line.  The 
run out roller table will have hollow rollers individually motor driven. 
A run out laminar strip cooling system will be provided in the area of 
run-out  table  for  cooling  the  strip  down  to  the  required  coiling 
temperature  in order to ensure the required metallurgical properties. 
The  laminar  strip  cooling  system  is  equipped  with  upper  and  lower 
cooling  headers  for  cooling  both  the  top  and  bottom  strip  surface. 
The  run  out  cooling  system  will  be  a  U-tubes  banks  on  the  top  and    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.11    
blanks  of  multiple  nozzles  headers  on  the  bottom.  Bottom  strip 
cooling  headers  will  also  be  utilized  to  cool  roller  table  rollers.  The 
header will be closed/opened by proportional valves according to the 
strip  thickness,  speed  and  temperature  at  inlet,  so  as  to  assure  the 
metallurgical  properties  of  the  end  product.  The  top  headers  can  be 
hydraulically raised in emergency cases.  
The laminar cooling section will have different zones so that different 
cooling  strategies  can  be  applied  for  various  steel  grades  of  the 
product  mix.  Different  zones  will  work  in  combination  with 
microstructure control model. 
4.3.8    ROLLER TABLES 
Roller tables at all locations will consist of roller tables frames, apron 
with  guides,  roll  assemblies  with  individually  driven  AC  drives,  roller 
cooling system, and automatic bearing lubrication. 
4.3.9    DOWN COILER EQUIPMENT 
At  the  end  of  the  run-out  roller  table,  two  nos.  of  down  coilers  with 
the pinch roll units will be provided for coiling the hot rolled strip.  
A  hydraulically  operated  side  guide  will  be  provided  before  each 
pinch roll unit to position the strip.  
The  pinch  roll  unit  feeds  the  strip  into  the  coiler  and  generates  the 
strip  tension  required  for  the  coiling  operation.  The  pinch  roll  gap  is 
set  by  position  controlled  hydraulic  cylinders  according  to  the 
relevant  incoming  strip  gage.  After  threading  the  strip  into  the  pinch 
roll gap, the cylinders are switched to pressure control mode to apply 
the  necessary  force  to  the  strip  (depending  on  strip  gauge  and 
material).  
The  coiler  will  be  designed  as  a  3  or  4  hydraulically  operated 
wrapper rollers with step control.  
Pinch  roll  polisher  will  be  provided  for  online  polishing/grinding  of 
pinch rolls. 
Main parameters of down coilers (Indicative) 
Type         :  3 or 4 roller type, hydraulically 
actuated 
Maximum coil weight   :  35 t 
Specific coil weight    :  20 kg/mm  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.12  
A  strip  catcher  will  be  provided  downstream  of  down  coiler  no.  2  to 
stop  the  strip  head  end  for  safety  in  case  of  failure  of  the  pinch  roll 
and down coiler. The strip catcher will consist of a steel curve chute 
and carry over apron. 
4.3.10   COIL HANDLING AND TRANSPORT SYSTEM 
From  the  coiler  the  coils  will  be  removed  by  a  coil  car  and 
transported to a coil banding station. One coil car will be provided for 
each  down  coiler.  Traverse  of  the  coil  car  will  be  through  hydraulic 
motor. Elevation of the coil cars rollers will be done hydraulically. At 
the  coil  banding  station,  circumferential  strapping  of  the  coil  will  be 
done  with  the  help  of  banding  machine.  An  automatic  coil  marking 
unit will also be provided. 
After  this,  the  coils  are  transported  to  walking  beam  type  coil 
conveyors.  The  walking  beam  coil  conveyor  will  consist  of  a  fixed 
supporting  frame  and  a  walking  beam  which  through  a  rectangular 
motion,  lifts  and  transfers  the  coil  from  one  saddle  to  the  next  one. 
Coil  tilters,  lifting  mechanism,  turn  table  will  be  provided  as 
necessary.  
Sample  collection  and  inspection  station  will  be  located  at  the 
walking  beam  conveyor.  Coil  will  be  picked  up  by  a  coil  transfer  car 
and  positioned  on  the  coil  rotating  rig.  Sample  will  be  cut  with  the 
help of robotic cutting arm.  
Strapping  station  will  also  be  provided  along  the  walking  beam 
conveyor.  Circumferential  and  radial  strapping  of  the  coils  will  be 
done  at  the  coil  strapping  station.  A  strapping  machine  will  be 
provided each for circumferential strapping and radial strapping. The 
strapping machine will broadly consist of the machine car running on 
rails,  strap  chute,  strap  dispenser  and  pneumatic  &  hydraulic 
components. The strap dispenser will be actuated pneumatically.  
A  coil  weighing  station  will  be  provided  along  the  coil  conveyor 
downstream of strapping station..  
4.3.11   COIL STORAGE 
The  coils  from  the  walking  beam  conveyor  will  be  picked  up  by 
overhead  cranes  and  placed  in  the  coil  storage  yards.  Coil  saddles 
will  be  provided  to  support  the  coils  and  allow  to  dispose  them  on 
multiple  rows.  The  coil  storage  yards  will  have  the  capacity  to  store 
the coils of one week production. Facilities for automated loading and 
storage will be provided in the coil yard.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.13    
4.3.12   SHEET SHEARING LINE 
4.3.12.1  A Sheet Shearing Line of 400,000 tpa capacity will be installed within 
the  proposed  Hot  Strip  Mill  Complex  to  produce  sheets/plates  from 
the HR coils produced. The sheet Shearing Line will be installed in a 
separate  bay  parallel  to  the  coil  storage  bays.  The  sheets/plates 
produced  through  this  line  will  be  dispatched  from  the  same  bay 
(shearing line bay).  
4.3.12.2  Main Parameters  
Main parameters of the Sheet shearing Line are indicated below : 
Inner dia of input coils    :  762 mm 
Outer dia of input coils     :  1,2002,150 mm 
Maximum coil weight    :   35 t 
Hot strip thickness      :  5.0 - 25.4 mm 
Hot strip width      :  1000 - 2100 mm 
Max. sheet length      :  5000 mm 
Maximum        :  10 t 
Maximum Line speed    :   40 m/min 
Max threading speed    :  15 m/min 
4.3.12.3  Description of technological facilities 
The  technological  layout  of  the  Sheet  Shearing  Line  is  indicated  in 
Drawing  no.  CET  RN  3379  RF1  00  004  R=0.The  input coils will  be 
placed onto the coil loading skids by overhead crane. Three skids will 
be  provided  for  storing  the  input  coils  to  be  fed  to  the  pay-of  reel. 
From the skids, a coil car will pick up the coil and will transport to the 
payoff  reel.  The  pay-off  reel  and  processor  roll  are  equipped  with  a 
strip  centering  control  system  for  proper  centred  strip  guiding  within 
the line. The two pressure rolls will be used for the strip threading as 
well  as  to  prevent  back-turning  of  the  pressure  roll  due  to  back-
pushing of the strip during coil opening procedure. The processor roll 
will  be  used  for  threading  and  processing  during  strip  unwinding, 
horizontally and vertically adjustable as a function of strip gauge and 
material strength A pinch roll unit will transport the strip to the leveler 
and  also  provide  the  required  strip  tension.  The  pinch  rolls  will  be 
hydraulically  adjusted  in  accordance  with  strip  thickness,  strip  width 
and material strength. Side guides will be provided before the leveler.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.14  
Two multi roll strip levelers will be provided to improve the flatness of 
the  strip.  The  strip  leveller  will  be  equipped  with  multiple  levelling 
rolls,  backed-up  by  supporting  rollers.  Top  levelling  rolls  are 
adjustable  under  levelling  load  by  means  of  hydraulic  cylinders. 
Hydraulic adjustment of the top levelling rolls is provided with super-
imposed  levelling  gap  control.  Compensation  of  the  crossbeam 
deflection is provided by means of a pre-bending system for the top 
levelling rolls. With the pre-bending system better levelling results of 
plates  with  wavy  edges  or  centre  buckles  can  be  achieved. 
Individually adjustable bottom rolls are provided in order to allow the 
required  shape  of  the  levelling  gap  to  be  obtained  as  a  function  of 
strip gauge and material strength.  
The  strip,  after  leveler,  will  be  fed  to  the  flying  cross  cut  shear 
through  pinch  rolls.  Cutting  of  strip  through  the  flying  shear  will  be 
achieved mechanically by a flywheel. The top blade will be fixed and 
bottom blade moves up and cutting method will be downside up Gap 
between the blades can be adjusted by motor. Change of blades will 
be  done  by  cartridge  mode  extraction  of  blade  holders.  Two 
measuring  rolls  coupled  with  encoders  will  be  provided  for 
measurement  of  length  for  shearing  action.  An  expandable  runout 
conveyor  will  be  provided  to  co-ordinate  the  motion  of  the  flying 
shear  with  the  line.  This  will  be  a  driven  by  AC  motor  belt  type 
conveyor.  The  conveyor  will  automatically  adapt  its  length  to  the 
motion of the flying shear.  
A paint marking machine will be provided for marking the finished 
plates during transfer on the roller table to the piler. 
The piler will comprise of two piling positions and will be arranged for 
automatic  plate  pile  changing  for  plates  up  to  eight  meter  length. 
Another piler  will be  provided for stacking  rejected sheets. The Piler 
will  be  provided  with  tiltable  roller  conveyors  for  providing  straight-
sided  plate  piles  in  longitudinal  direction.  The  piler  will  be  equipped 
with  stops  for  head  and  tail  end  of  the  plates  for  proper  piling.  Two 
hydraulically  operated  lifting  tables  will  be  located  under  the  piler. 
Two  separate  pile  transfers  will  be  used  for  transport  of  the  plate 
piles  from  the  two  piling  sections  to  the  discharge  roller  table.  Two 
lifting  tables  will  hand  over  the  packages  from  the  pile  transfers  to 
the  discharge  roller  table  sections.  The  pile  weighing  system  will  be 
incorporated  in  the  discharge  lifting  tables.  The  weighing  system 
incorporates  a  weight  card  printer  and  a  data  memory  for  data 
transfer. Discharge roller tables will be provided for further transfer of 
the piles. Mechanised strapping system will be provided to make the 
packets.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.15    
4.3.13   ROLL SHOP 
    A  Roll  Grinding  and  repair  shop  will  be  provided  adjacent  to  the 
proposed Hot Strip Mill. The roll shop will be utilized to grind the work 
& back up rolls of the new mill, grinding of the shear blades, repair of 
the  bearings  and  other  associated  services.  The  Roll  shop  will 
comprise of the following main facilities : 
-  CNC Roll Grinders (5 nos.) 
-  Roll cooling stands 
-  Roll  handling  tackles  for  handling  single/double  rolls  with 
chocks 
-  Back up and Work rolls chock extractors (2 nos.) 
-  Roll chock tilter 
-  Back  up  roll  chock  washing  station  with  high  pressure  hydro 
washer 
-  Work roll chock & bearing cleaning tank 
-  Roll washing machine 
-  Set of roll racks 
-  Rack for grinding disks 
-  Storage rack for knives 
-  Jib cranes at required locations. 
-  Set  of  instruments  including,  Portable  digital  thermometer, 
Portable internal & external micrometers, Filler gauges, Depth 
gauges, vernier caliper, BUR neck taper measurement gauge-
Bevel  measurement,  Portable  Ultrasonic  Crack  Tester 
Portable Hardness tester Portable Roughness tester 
All the roll grinding machines will be CNC controlled. Out of the total 
5  grinding  machines,  three  will  be  designed  for  grinding  finishing 
stands  work  rolls,  shear  knives  and  edger  rolls.  Balance  two  will  be 
designed  for  grinding  Finishing  mill  back  up  &  work  rolls  and 
Roughing  stand  back  up  &  work  rolls.  Grinding  of  work  rolls  can  be 
performed with chocks with the rolls.  
A workshop will also be provided with adequate numbers of machine 
tools.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.16  
4.3.14   EOT CRANES AND MATERIAL HANDLING 
Overhead  EOT  cranes  will  be  provided  at  different  locations  of  the 
Hot Strip Mill as indicated below : 
Slabs Yards      :  4 nos. (2 in each bay) 
Furnace Charging    :  2 no. 
Furnace bay      :  1 no. 
Mill bay      :   3 nos. 
Roughing stand motor bay :  1 no. 
Finishing stands motor bay:  1 no. 
Coil storage & dispatch bays:  6 nos. (3 nos. in each bay) 
Sheet Shearing Line & dispatch:  3 nos. 
Roll shop      :  3 nos.  
Scale Pit      :  2 no. 
Suitable  handling  facilities  will  be  provided  at  other  auxiliary  areas 
including pump house, compressor, etc. 
Two  transfer  cars  will  be  provided  between  the  mill  bay  and  the  roll 
shop for inter bay transfer of rolls. A transfer car will also be provided 
between mill bay to motor house. 
4.3.15   HYDRAULICS & LUBRICATION 
4.3.15.1    Oil-Hydraulic System 
Broad details oil hydraulic system will be as below: 
i)  The flow and pressure for the systems will be selected by the 
Bidder, based on the system requirement. 
ii)  Filters  used  will  be  duplex  type  with  electrical  clogging 
indicators.    rating  of  the  filters  will  be  as  per  system 
requirement.    ratio  will  be    200.  Flow  capacity  of  pressure 
line  filters  will  be  2  times  the  maximum  flow  rate  of  pumps 
and flow capacity of return line filters will be 3 times the total 
flow rate of pumps. 
iii)  Mineral oil will be used. 
iv)  The  tank  capacity  will  be  minimum  5  times  the  capacity  of 
main pump.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.17    
v)  The  different  velocities  to  be  considered  for  the  system  will 
be as below:- 
For suction lines  1.0 m/s (maximum) 
For pressure lines  5.0 m/s (maximum) 
For return lines  3.5 m/s (maximum) 
vi)  For the pipelines, size up to DN 30, inside diameter will be as 
per  DIN  2391/C.  Connection  will  be  by  welding  cone  screw 
coupling  with  O-ring  seals  according  to  DIN  2353.  For  sizes 
above  DN  30,  inside  diameter  will  be  as  per  DIN  2448  and 
will be connected by flanges. Pipelines and fittings will be as 
per system requirement. 
vii)  The air breathers will be desiccant type. 
viii)  The  system  will  be  designed  with  oil  level  monitoring  in  the 
tank,  pressure  monitoring  in  the  system,  temperature 
monitoring etc. 
ix)  The  Power  Pack  will  be  provided  with  tray  at  the  bottom  for 
taking care of leakage of oil. 
x)  Off-line filtering-cum-cooling system will be provided. Capacity 
of pump (lpm) will be 1/10
th
 of tank capacity 
xi) The number of standby pumps will be as below: 
Number of normally 
operating pumps 
Number of standby pumps
1 - 4  1 
5 - 8  2   
4.3.15.2    Grease Lubrication System 
Broad details for Grease Lubrication System will be as below: 
i)  Centralised motorised dual line grease lubrication system  
ii)  The system will be 1 No. working and 1 No. standby for main 
pumps  with  reservoirs,  filters,  relief  valves,  change  over 
valves etc. 
iii)  Refilling  pump,  main  pumps,  change  over  valves  will  be 
electric motor operated. 
iv)  Pipe  sizing  will  be  carried  out  based  on  actual  pressure  drop 
calculations. However, minimum pipe sizes will be as below: 
Pipe Zone  Pipe OD (mm) x 
pipe thickness 
(mm) 
Material of pipe  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.18  
Pipe Zone  Pipe OD (mm) x 
pipe thickness 
(mm) 
Material of pipe 
Main header   30 x 3  DIN 2391 C 
Branch  lines  from  main 
header  up  to  inlet  of 
distributors 
20 x 2  DIN 2391 C 
Feed  lines  from 
distributors  up  to  inlet  of 
bearing points 
10 x 2  DIN 2391 C 
v)  The system will be operated based on end pressure relays as 
well as timers. 
vi)  Reservoirs for main pumps will have minimum capacity of 100 
litres. 
vii)  1 No. grease refilling pump with provision of easy taking out or 
putting  in  of  the  refilling  pump  inside  the  barrel,  like  provision 
of a hand operated winch, will be provided. 
viii)  Operating period will be considered as 24 hours per day. 
4.4    UTILITY FACILITIES 
4.4.1  Compressed Air System: 
Compressed  Air  will  be  required  for  pneumatic  valve  actuation, 
camera  cooling  etc  for  furnace  and  mills  as  well  as  for  furnace  oil 
atomization  in  the  furnace.  The  approximate  requirement  for  the 
same will be 
Mill including Reheating Furnaces -  1000 Nm3/h 
Furnace Oil atomization      -  5000 Nm3/h  
The  compressed  air  for  oil  atomization  will  be  utilized  occasionally 
when  furnace  will  be  fired  by  furnace  oil.  Above  mentioned 
requirement for Compressed Air will be tapped from the grid near the 
old  HSM.  The  compressed  air  system  will  be  complete  with  driers 
and compressed air piping to different consumers 
4.4.2    Fuel Oil System 
For normal operation Furnace will be fired by Mixed Gas. However in 
case of occasional gas shortage the Reheating Furnace will also be    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.19    
capable of firing through Furnace Oil. Furnace oil for the purpose will 
be  brought  from  old  HSM  through  pumping.  For  this  purpose  a 
furnace oil pump house will be installed at old HSM. To maintain the 
flow  ability  of  furnace  oil  electric  tracing  of  oil  pipelines  have  been 
envisaged. A day tank of 100 kl capacity will be installed in the new 
HSM along with oil supply system to the Reheating Furnace. 
4.4.3    Other Utilities 
Nitrogen  for  purging  of  gas  line  will  be  tapped  from  existing  DN600 
header  near  column  no.  B-71.  Oxygen  required  for  general  purpose 
cutting  etc  at  a  pressure  of  18-20  bar  will  also  be  tapped  near 
column  B-71.  All  the  utility  pipelines  will  be  laid  on  new  trestles  as 
there are no existing utility pipe supporting system available between 
old HSM & new HSM. 
4.5    WATER SYSTEM  
4.5.1    The  water  system  envisaged  for  various  requirements  of  proposed 
Hot  Strip  Mill  (HSM)  will  be  re-circulating  type  and  will  be  designed 
with zero discharge concepts. Only make-up water will be taken from 
the  existing  Lagoon  of  RSP  with  adequate  treatment  and  pumping 
facilities. 
The proposed water system for the Mill will consist of following types 
of water systems: 
1.  Reheating Furnace Cooling Water System  
2.  De-scaling Water System 
3.  Mill Equipment Cooling Water System 
4.  Laminar Cooling Water System 
5.  Strip Cooling Water System 
6.  Mill Auxiliaries & Motor Cooling Water System 
7.  Make-up water system 
8.  Cable tunnel dewatering facilities 
All critical equipments and equipments related to contaminated scale 
water  will  have 100%  standby.  Other  equipments  like  cooling  tower, 
heat  exchanger,  filters,  settling  tanks,  water  softeners  will  have 
minimum one standby. 
All  underground  pipes  will  be  routed  through  ventilated  and 
illuminated pipe cellars with adequate space for inspection and future 
pipe replacement. 
All  pumping  stations  and  equipment  buildings  will  have  pendant 
operated handling facilities like cranes/ hoists.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.20  
All  cooling  towers  will  be  of  RCC  structure,  over-ground  basin,  FRP 
fan  and  covered  hot  water  basin.  Cooling  towers  of  each  circuit  will 
have 10% side stream filtration facilities. 
All auto control valves will be electrically operated gate valves and all 
manual valves more than DN300 size will be gear operated. 
There will be common maintenance workshop with adequate working 
space  and  a  small  manufacturing  area  with  basic  machines  like 
centre  lathe,  drilling  machine,  power  saw,  bench  grinding,  welding 
etc. 
At  present,  the  makeup  water  pipe  line  of  size  DN250  is  going 
underground to SGP through the proposed HSM area. This line is to 
be suitably rerouted without affecting production of SGP. 
Each  water  circuit  will  have  flow,  pressure,  temperature 
measurements and also have indication in the main control room. 
All water tanks/sumps will have adequate manual cleaning facilities. 
Wherever  applicable,  the  on-line type  quality monitoring  instruments 
like pH meter, Turbidity meter, TDS, Hardness etc. to be provided. 
4.5.1.1  Reheating Furnace Cooling Water System 
Soft  water  is  envisaged  for  skid  cooling  of  the  Reheating  Furnaces. 
The envisaged flow rate is 1600m3/h at a pressure of 40mWC at the 
consumer  end.  It  is  proposed  to  install  a  dedicated  Soft  water 
generation  &  re-circulation  system  for  the  proposed  Reheating 
furnace  with  all  its  associated  facilities  like  Soft  Water  Plant,  Soft 
water  sump,  Emergency  overhead  soft  water  tank,  Chemical  dosing 
unit,  Pumps,  filters,  heat  exchangers,  pipes,  valves,  fittings, 
instruments  etc.  However,  100%  standby  soft  water  plant  and  soft 
water pumps are envisaged. 
A Pipeline will be laid from the Pump delivery header, installed in the 
Mill  Pump  House  upto  the  Reheating  furnace  header  with  all  valves 
and  fittings. After  cooling the  skids, the  hot water will be returned to 
the heat exchangers for cooling. A water filter will be provided in the 
supply line to ensure that no foreign material enters the water-cooling 
elements. Makeup to this re-circulating system will be taken from the 
proposed  Soft  Water  Plant.  The  industrial  water  required  for  Soft 
Water  Plant  will  be  tapped  from  the  proposed  makeup  water 
network. 
To  take  care  the  emergency  situation  arising  out  of  pump  failure  or 
power  failure,  an  Emergency  Overhead  Water  Tank  is  envisaged  to 
supply cooling water for half an hour. Provision of emergency power 
supply will also be there.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.21    
Industrial  water  is  envisaged  as  secondary  water  for  heat 
exchangers.  A  separate  water  system  (industrial  quality)  is  to  be 
installed  for  the  purpose  with  all  its  associated  facilities  like  Pumps, 
Cooling tower, filters, valves, pipes, fittings etc. A Pipeline will be laid 
from the Pump delivery header, installed in the Mill Pump House up 
to  heat  exchangers  and  from  heat  exchangers  to  top  of  the  cooling 
tower to carry hot water from Heat exchanger with all valves, fittings, 
instruments etc. The makeup water required for re-circulation cooling 
water  system  will  be  tapped  from  the  proposed  makeup  water 
network. 
Filtered water is envisaged as cooling water for direct cooling system 
of  reheating  furnace.  The  water  will  be  tapped  from  delivery  header 
of filtered water pumps. 
4.5.1.2  De-scaling Water System 
Filtered  water  is  envisaged  to  be  used  for  de-scaling  purpose.  De-
scaling  system  for  roughing  mill  and  finishing  mill  will  be  at  different 
pressure.  The  envisaged  flow  rate  for  roughing  mill  is  700m3/h  at  a 
pressure of 2400mWC and for finishing mill is 120m3/h at a pressure 
of 3800mWC. A Common Filtered Water system is to be installed for 
the purpose with all its associated facilities like Settling tank, Settled 
water  sump,  Settled  water  pumps,  Pressure  filters,  Filtered  water 
sump,  Filtered  water  pumps,  Cooling  towers,  Duplex  water  filter, 
valves,  pipes,  fittings,  instruments  etc.  Two  groups of pumps  will  be 
installed,  one  group  will  consists  of  settled  water  pumps  to  supply 
water to Pressure filters and other group will consist of filtered water 
pumps  to  supply  water  to  De-scaling  system  through  filters.  Return 
water  from  de-scaling  system  will  go  directly  to  the  settling  tank 
through  scale  channel.  Arrangement  for  removal  and  transportation 
of mill scale and oil from scale pit and settling tanks will be there. The 
makeup water required for re-circulation water system will be tapped 
from the proposed makeup water network. 
Air  blowers  and  filter  backwash  pumps  are  envisaged  for 
backwashing of pressure filters. 
4.5.1.3  Mill Equipment Cooling Water System 
Mill  Equipment  consists  of  two  parts,  one  is  high  pressure  (HP)  roll 
cooling  and  other  is  low  pressure  (LP)  roll  cooling.  Filtered  water  is 
envisaged  as  cooling  water  for  Mill  Equipment.  The  envisaged  flow 
rate at the consumer end is 2070m3/h at a pressure of 120mWC for 
HP Roll Cooling and 1730m3/h at a pressure of 60mWC for LP Roll 
Cooling  system.  For  HP  roll  cooling  filtered  water  will  be  pumped 
from  the  common  filtered  water  sump  by  a  group  of  pumps  with 
associated  piping,  instruments  etc.  For  LP  roll  cooling,  water  will  be 
tapped from de-scaling water circuit. Return water from Roll Cooling 
will go directly to scale channel for scale flushing.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.22  
Two  groups  of  pumps  will  be  installed  for  scale  flushing,  one  group 
will consist of flushing water pumps to supply water for scale flushing 
and  other  group  will  consist  of  scale  water  pumps  to  transfer  water 
from  scale  pit  to  settling  tank.  MOC  of  scale  water  pumps  will  be  of 
abrasive resistant material of minimum hardness 600 BHN and MOC 
of  valves,  fittings  will  be  of  wear  resistant  material.  Scale  water 
pumps will have two parallel headers up to settling tanks each having 
100%  capacity  to  facilitate  repair.  Scale  water  channels,  pipes  will 
have  inside  coated  with  abrasive  resistant  basalt/  ceramic  linings. 
The  envisaged  flow  rate  at  the  consumer  end  is  100m3/h  at  a 
pressure of 45mWC for scale flushing. 
The  makeup  water  required  for  re-circulation  water  system  will  be 
tapped from the proposed makeup water network. 
4.5.1.4  Laminar Cooling Water System 
Filtered  water  is  envisaged  to  be  used  for  Laminar  Cooling.  The 
envisaged  flow  rate  is  6760m3/h  at  a  pressure  of  5mWC  at  the 
consumer  end.  Filtered  water  will  be  tapped  from  the  common 
filtered  water  sump.  The  system  will  consist  with  all  its  associated 
facilities  like  pumps,  filters,  valves,  pipes,  fittings,  instruments  etc. 
Return  water  from  the  system  will  go  directly  to  a  common  sump 
through suitable water channel. The common sump will collect return 
water  from  both  laminar  cooling  &  strip  cooling  system.  From  the 
sump  water  will  be  pumped  to  settled  water  sump  through  solid 
separator.  The  makeup  water  required  for  re-circulation  water 
system will be tapped from the proposed makeup water network. 
4.5.1.5  Strip Cooling Water System 
Filtered  water  is  envisaged  to  be  used  for  Strip  Cooling.  The 
envisaged flow rate is 1150m3/h at a pressure of 150mWC. Filtered 
water  will  be  tapped  from  the  common  filtered  water  sump.  The 
system will consist with all its associated facilities like pumps, filters, 
valves, pipes, fittings, instruments etc. Return water from the system 
will go directly to a the common sump through suitable water channel 
and  from  the  sump  water  will  be  pumped  to  settled  water  sump 
through solid separator. The makeup water required for re-circulation 
water  system  will  be  tapped  from  the  proposed  makeup  water 
network. 
4.5.1.6  Mill Auxiliaries & Motor Cooling Water System 
Industrial water is envisaged as cooling water for Mill Auxiliaries and 
Motor  cooling.  The  envisaged  flow  rate  is  500m3/h  at  a  pressure  of 
35mWC.  For  this  Cooling  Water  System  water  will  be  tapped  from 
cooling  tower  of  secondary  water  circuit  of  heat  exchanger  cooling. 
Only one group of pumps is to be installed for the purpose with all its 
associated facilities and piping. A Pipeline will be laid from the Pump 
delivery header, installed in the Mill Pump House up to the consumer 
points with all valves, fittings, instruments etc. Return water lines will    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.23    
be laid from consumer points to top of the cooling tower to carry hot 
water. 
4.5.1.7  Make-up Water System 
Make-up  water  is  required  for  all  re-circulating  water  systems. 
Estimated make up water requirement for the proposed mill will be to 
the tune of 1000m
3
/h. 
The  required  makeup  water  will  be  available  from  the  existing 
Lagoon  of  RSP.  Lagoon  water  will  be  treated  to  industrial  makeup 
water  quality  and  pumped  to  an  overhead  makeup  water  tank  at 
proposed  Mill  area.  Adequate  treatment  facilities  have  been 
envisaged.  All  industrial  makeup  water  consumers  will  avail  water 
from  the  proposed  makeup  water  tank  through  a  suitable  piping 
network.  The  water  treatment  plant  will  be  installed  on  the  space 
available  in  between  the  Lagoon  and  National  Highway.  Area 
requirement will be to the tune of 100x200m, which will be developed 
accordingly.  The  electric  power  requirement  will  be  to  the  tune  of 
1000kW maximum demand & 1750kW connected load. 
The  quality  and  other  parameters  of  Lagoon  water  is  as  specified 
below: 
pH  6.98  7.8 
TSS  108 - 794 ppm 
Oil & grease  2  4 ppm 
Iron  2.5  4.2 ppm 
Ammonical nitrogen (NH
3
-N)  4.8  15.5 ppm 
Phenol  0.05  0.09 ppm 
Cyanide   0.05  0.2 ppm 
BOD  10  18 ppm 
COD  44  92 ppm 
Water temperature  32 
o
C 
Tapping point  Near  discharging  point  from 
Lagoon. 
Distance  between  Tapping 
point and proposed Mill 
1500m. approx. 
Proposed make up water pipe 
routing 
Underground  along  the  existing 
and proposed road 
Make  up  to  soft  water  system  will  be  provided  by  a  new  soft  water 
plant  through  a  soft  water  storage  tank.  For  soft  water  plant, 
industrial water will be tapped from the proposed makeup water line  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.24  
and  supply  water  to  soft  water  plant  through  adequate  pipe  size  for 
smooth operation of the soft water system. 
For  industrial  water  system  make-up  water  will  be  tapped  from 
existing makeup water ring main and supply water to Cooling Tower 
basin. The water flow will be controlled by the level of cooling tower 
basin. 
For  direct  water  (filtered  water)  system  make-up  water  will  be 
supplied to Filtered water sump. The water flow will be controlled by 
the level of the sump. 
Each  makeup  water  consumer  will  have  a  venturi/  orifice  type  flow 
transmitter in the line with flow indication in the main control room. 
4.5.1.8.  Cable tunnel dewatering facilities 
For  dewatering  the  underground  cable/pipe  tunnel  12  no  pits  will  be 
provided  with  12nos  sump  pump  sets  alongwith  pipes,  hoses  etc. 
The water from cable/ pipe tunnel will go to the recovery water tank. 
4.5.2.    Control Philosophy 
The cooling water system will be fully automatic with PLC. However, 
facility  for  local  start/stop  will  also  be  provided  for  each  individual 
drive. All electrically operated valves will have position indicator. 
There  will  be  one  main  control  room  for  all  water  systems  with  all 
operational parameters, warning signals, instrument readings etc. will 
be  displayed.  There  will  be  local  operation  stations  also.  MMI  with 
display monitors will be installed in main control room for continuous 
display,  monitoring  and  recording  of  all  the  important  parameters  of 
water systems. 
4.6    AIR CONDITIONING & VENTILATION SYSTEM 
Following  types  of  Air  Conditioning  &  Ventilation  System  are 
envisaged for proposed Mill: 
4.6.1    Chilled water based Central Air Conditioning system will be installed 
in a central AC plant building for various Control Rooms, PLC rooms, 
MCC  rooms  housing  intelligent  MCCs,  digital  drive  rooms,  weighing 
electronic rooms, Office Spaces, etc. 
The proposed Chilled water system will consist of the following major 
equipment: 
1)  Water cooled chiller units with accessories 
2)  FRP cooling towers for closed circuit condenser cooling 
system    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.25    
3)  Necessary chilled water pumps (with 100% stand by), 
Condenser cooling pumps (with 100% stand by), piping, 
valves, etc. 
4.6.2  Dry  pressurized  ventilation  system  will  be  installed  for  switch  gear 
rooms and MCC rooms having non-intelligent MCCs. 
4.6.3  Push-pull  type  ventilation  system  will  be  provided  for  cable 
tunnel/cellar and cable basements. 
4.6.4  Exhaust  ventilation  system  will  be  provided  for  compressor  house, 
battery  rooms,  chiller  plant  room,  transformer  rooms,  pump  houses, 
store, toilets, etc. 
4.7    FIRE FIGHTING SYSTEM 
4.7.1  A comprehensive fire fighting System has been envisaged for entire 
area of the Hot Strip mill. It consists of the following: 
  Portable Fire Extinguishers as first aid Fire Fighting System 
  Water based Fire Fighting System 
  Automatic Fire Extinguishing System 
i)  High Velocity Water Spray System(HVWSS)/ Medium Velocity 
Water Spray System (MVWSS) 
ii)  Gas based Fire Fighting System 
  Passive Fire Protection 
4.7.2  Portable Fire Extinguishers 
Portable  fire  extinguishers  will  be  provided  as  per  TAC  norms  to  all 
the  covered  area  in  the  HSM.  This  includes  but  not  limited  to  new 
buildings,  shops,  electrical  rooms,  cable  vaults,  ventilation  shafts, 
junction houses.   
4.7.3  Water based fire Fighting System 
1)  A  pump  house  will  be  provided  to  accommodate  the  envisaged 
for  fire  fighting  equipments,  like  electrically  operated  main  fire 
pumps, diesel driven  100% standby  diesel engine driven pumps, 
two  jockey  pumps  i.e.  working  as  well  as  standby,  envisaged  in 
this  package.  The  minimum  pumping  capacity  of  the  main  fire 
water  pump  has  been  envisaged  as  546m3/h.  These  pumps  are 
complete with all accessories as per TAC norm.  The facilities for 
automatic  starting,  stoppage  and  interlocks  of  the  pumps  will  be 
provided  depending  upon  the  line  pressure.  A  material  handling 
facility  like  under  slung  crane  will  be  provided.  An  electrical 
control  room  will  be  provided  to  accommodate  the  control  panel 
along  with  electrics.  A  covered  tank  with  a  partition  wall  will  be 
provided  for  storage  of  fire  water  for  two  hours  of  pumping  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.26  
capacity.  The  line  pressure  should  be  kept  as  per  TAC  norm 
however it should not less than 8.8 Kg/cm
2
. Water will be tapped 
(DN150)  from  the  proposed  makeup  water  line.  The  facilities  will 
be provided for refilling of fire water to both the compartments of 
the  tank  with  the  level  switches  and  motorized  valves.  The 
tapping point will also be provided with gate valve for isolation.  
2)  Ring  main  based  pipe  header  (DN300)  to  be  provided  to  entire 
HSM  area  along  the  road  to  cater  the  fire  water  requirement. 
External  hydrant  will  be  provided  for  ever  45m  spacing  whereas 
internal  hydrants  will  be  provided  at  every  30m  spacing.  Every 
landing  platform  will  be  provided  with  landing  valves.  Each 
internal hydrant will be provided with hose box complete with two 
numbers  of  fifteen  meter  hose,  coupling,  nozzles.  The 
underground  pipeline  will  be  provided  with  wrapping  and  coating 
as per IS to protect it from corrosion..   
3)  Manual  type  water  spray  system  will  be  provided  in  the  entire 
length of conveyor galleries. Each conveyor gallery will be divided 
not  more  than  50m  segment  for  water  spray.  Each  segment  will 
be fed water from the riser connected to the Fire water header. A 
gate valve will be provided to each riser for isolation.  
4.7.4    Automatic Fire Extinguishing System 
1)  High  Velocity  Water  Spray  System  (HVWSS)/  Medium  Velocity 
Water Spray System (MVWSS): 
High velocity water spray system(HVWS) for transformers (above 10 
MVA or having oil more than 2000 lt.) and Medium velocity water 
spray  system  (MVWS)  for  cable  tunnels/cable  galleries/  cable 
cellar/ cable vaults etc in the HSM complex. These system will be 
automatic and controlled by delude valve. 
2)  For protection of Computer rooms/ PLC rooms/ important Critical 
Control  rooms  including  false  floor  and  false  ceiling,  automatic 
clean  agent  fixed  fire  extinguishing  system  (IG-541)  will  be 
provided.  The  system  will  be  designed  according to  NFPA 2001. 
100%  reserve  cylinders  filled  with  gas  and  accessories  will  be 
provided  for  all  systems.  There  will  be  provision  for  switch  over 
from  main  to  reserve  cylinders  automatically  from  the  panel  as 
well as through toggle button. 
4.7.5    Passive Fire Protection 
Fire  Retardant  Compound  and  Fire  Barriers  will  be  provided  in 
electrical  cable  runs  as  passive  fire  protection.  The 
compartmentalization of cable tunnels will be done as per IS:12459-
1988. Fire check doors will be provided at each compartment. 
4.8    INSTRUMENTATION, PROCESS CONTROL & AUTOMATION 
The  Control  and  Automation  systems  are  envisaged  to  provide 
complete  control  and  monitoring  of  the  following  proposed  areas.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.27    
The  areas  to  be  covered  will  be  broadly  consist  of  Slab  Yard, 
Reheating  Furnaces,  Roughing  Mills,  Passive  Heat  Shield,  Crop 
Optimization  System,  Finishing  Mills,  Cooling,  Coilers  &  Coil 
Conveying  Systems,  Coil  yard,  Roll  Shop,  Hydraulic  Systems,  Drive 
Systems  etc.  Various  process  of  Hot  Strip  Mill  will  be  controlled  by 
the  operator  from  the  respective  Control  Pulpits  housing  Control 
Desks,  HMIs,  CCTV  monitor,  Display  and  Alarm  devices,  etc.  In 
order to monitor and control the complete process of Hot Strip Mill in 
an integrated way all process control equipment at Level-0, Level-1 & 
Level-2  will  be  fully  integrated  to  form  a  unified  control  system 
transparent  to  the  operators.  The  system  will  be  reliable,  efficient, 
less  maintenance  oriented,  and  easy  to  operate.  Level-3 
Manufacturing  Execution  System  (MES)  will  be  executed  at  HSM  to 
manage  manufacturing  information.  The  MES  will  integrate  all  the 
functions  and  services,  customers  need  for  sustained  maximization 
of the plant performance. 
4.8.1    Level of Automation 
The  proposed  system  will  be  based  on  micro-processor  based 
network  compatible  field  instruments  with  hierarchical  control 
philosophy  consisting  of  field  instruments,  field  sensors,  electro-
pneumatic  control  valves,  electrics,  final  control  elements,  gauges 
etc.  at  Level-0  ,  Process  Control  Systems  consisting  of  multi-
processor  based  Technological  Control  Systems  (TCS)  with  Data 
Acquisition  System  (DAS)  at  Level-1.  Material  tracking  from  Slab 
yard  to  Coil  yard  will  be  part  of  automation  system.  Process 
Optimization Servers for Slab yard, Furnace, Roughing Mill, Finishing 
Mill,  Cooling  &  Coiler,  Roll  Shop  etc.  along  with  process 
mathematical  models  will  be  provided  for  process  optimization 
functions  at  Level-2.  Fuzzy  logic/Neural  network  will  be  used  for 
optimization  functions.  The  proposed  automation  system  will  be 
interfaced with the existing plant wide network for receipt of slab PDI 
(primary  data  inputs-  width,  weight,  thickness,  length,  steel  grade 
etc.).  There  will  be  interfacing  between  servers  of  various  areas  for 
exchange  of  input  and  output  data.  The  automation  system  will  be 
ERP  compatible.  Besides  process  optimization;  process  &  plant 
simulation  during  installation  &  commissioning,  computerized 
maintenance  management  system,  roll  shop  management  system, 
etc. will be considered. Storage Area Network (SAN) will be provided 
for  archival  data  management  like  slab  data.  coil  data,  quality  data 
etc. Level-3 Manufacturing Execution System (MES) will be executed 
at  HSM  to  manage  manufacturing  information  like  management  of 
product,  resources,  scheduling,  dispatching,  execution  of  production 
orders,  collection  of production  data, production  tracking, production 
performance  analysis  etc.  and  interfacing  with  Level-4  system  like 
production  planning  control,  plant  ERP  system  etc.  The  software 
modules  of MES will be based on ISA S95 to optimize all horizontal 
production  processes  from  slab  to  strip;  vertically  integrate  the  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.28  
information flow from end to end for better decision making, assured 
maintenance and further development over the entire life cycle of the 
plant. 
4.8.2    Slab Yard Management 
Slabs coming from the continuous casting machines will either be fed 
into  the  slab  yard  ROT  or  stored  in  slab  yard.  There  will  be  slab 
marking  and  slab  reading  system.  The  reader  will  send  the  slab  id 
data  wireless  to  the  automation  system.  The  slabs  intermediately 
stored  in  the  slab  yard  will  be  picked  up  by  overhead  crane  and 
placed  onto  the  slab  yard  roller  table.  Automatic  positioning  of  EOT 
cranes  will  be  part  of  the  slab  yard  management  system.  Slabs  will 
be  weighed  at  ROT.  Also,  length  measurements  of  the  slab  will  be 
done at ROT through a photo array system. Slab thickness/width will 
be measured through a laser based system at ROT. These data will 
be  sent  to  the  automation  system  for  validation  of  slab  data.  There 
will  be  a  control  pulpit  with  Operator  Console/  HMI  at  slab  yard  for 
data  entry  of  slab  storage  in  the  yard.  Level-2  system  with  a 
dedicated  Server  will  be  provided  for  keeping  slab  PDI,  slab  yard 
management  and  slab  archival  functions.  Slab  Yard  mapping  in  all 
the three axis will be done to show the location of desired slab in the 
console/HMI.  Storage  Area  Network  (SAN)  will  be  provided  for 
archival data management like slab data.  
4.8.3    Reheating Furnace Management 
Walking-beam furnaces with sufficient capacity for cold charging will 
be  provided  for  heating  up  the  slabs.  The  slabs  will  be  charged 
through the furnace in one row. Slab mapping inside the furnace with 
time  stamping  will  be  made  and  will  be  displayed  at  Operator 
consoles. Reheating will have separate charging pulpit and will have 
Furnace  Control  Pulpit  for  controlling  and  monitoring  of  furnace 
parameters.  Slab  discharge  from  furnace  will  be  carried  out  from 
Furnace Control Pulpit. There will be provision of taking into account 
discarded slabs in automation system. 
4.8.3.1    Basic functions of Furnace Automation 
1)  Automation of Level-0 
The functions of level-0 automation system will be: 
  To send all data coming from the field like pressure, 
temperature, flow etc. 
  To actuate various drives like valves, motors etc. 
2)  Automation of Level-1 
Control  &  automation  system  of  level-1  will  monitor  operational 
conditions  of  the  furnace,  analyses  the  information  and  control  the 
heating  as  well  as  other  technological  parameters  and  will  be 
performed in a PLC system.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.29    
The basic functions of the complete system will be: 
  Digital control of burners/ Fuel-air ratio control 
  Supervision of process variable: Monitoring and control of 
process parameters as per technological requirement. 
  Combustion control: Adjustment of heating rate in each zone of 
the furnace in response to change in the production rate, quality, 
process parameters, operational irregularities, etc. 
  Heat balance calculation. 
  Graphical display of process information 
  Diagnostic and alarm generation 
  Events and report generation for MIS 
  Gas mixing and Booster control and monitoring  
  Pump house for cooling water system  
3)  Automation of Level-2 
Level-2  system  with  a  dedicated  server  for  furnace  process 
optimization  will  be  provided  for  two  nos.  of  reheating  furnaces. 
Furnace  mapping  will  be  done  to  show  the  location  of  slabs  inside 
furnace  with  time  stamp  in  the  console/HMI.  The  purpose  of  the 
level-2 system will be to fix the temperature set points in the various 
zones  of  the  furnace  using  mathematical  models  so  that  each 
product  can  be  discharged  from  the  furnace  with  its  required 
discharge  temperature  in  a  precise  and  repetitive  manner.  This  will 
be  done  over  the  whole  operating  range  of  the  furnace  and  during 
delays  and  for  wide  range  of  steel  grades,  discharge  temperatures, 
product sizes etc. The objective of the optimization system will be as 
follows: 
  Predictive  thermal  modeling:  Predicting  slab  discharge 
temperature  and  making  automatic  corrections  for  zonal 
temperature  set-points  by  actual  slab  temperature 
measurements. 
  Real  time  thermal  modeling  :Thermal  behavior  of  slab  in  any 
zone of the reheating furnace 
  Slab temperature gradient calculation 
  Automatic  zonal  temperature  set-point  calculation  for  level-1 
control  
  Calculation of heating and soaking time 
  Self adaptive and self tuning features based on historical data. 
  Fuel  optimization  and  automatic  handling  of  temperature  set-
points during scheduled and un-scheduled delays.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.30  
  Historical logging of Level-2 information/data 
4.8.4    Mill Management 
4.8.4.1    Mill Automation (Roughing, Finishing, Cooling & Coiler) 
1)  L2 process control server systems will be provided for Roughing mill, 
Finishing  mill,  Cooling  &  Coiler  operation.  There  will  be  minimum 
three number servers for process optimization, model calculation and 
cooling.  Also,  there  will  be  warm  backup  server  with  both  servers 
sharing  raid  disk  arrays  configured  on  the  SAN  (Storage  area 
network).  Server  system  will  be  complete  with  hardware,  software 
and  mathematical  models  to  carry  out  process  control  and 
optimization functions.  
2)  Server will carry out process optimization functions for pass schedule 
calculation, automatic thickness control, Automatic width control etc. 
for  stand  R2  of  roughing  mill.  Optimization  functions  for  pass 
schedule calculation, profile control, flatness control etc. for stand F1 
to F6 of finishing mill to be carried out. Process server will also carry 
out  optimization  functions  for  laminar  cooling  and  two  nos.  coilers. 
Inheritance  and  adaptive  control  will  also  be  part  of  the  function. 
There  will  be  short  term  and  long  term  adaptation  with  predictive 
controls. Following control & optimization functions will be carried out 
in Level-2 process server: 
  Strip temperature 
  Strip rolling 
  Width calculation & control 
  Pass schedule calculation for RM & FM 
  Profile & flatness control 
  Laminar cooling etc. 
  Coiler functions 
3)  Following  artificial  Neural  Network  based  mathematical  models  will 
be considered for the mill. 
  Roll thermal & crown model 
  Pass to pass adoption 
  Temperature model over lengthy & thickness 
  Rolling model 
  Mechanical, Yield stress & Friction models 
  Strip thickness model 
  Model of elastic mill stand & roll stack deformation 
  Ferritic rolling 
  Microstructure cooling 
  Adoption of the models etc.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.31    
4)  Laminar cooling based control will be used for microstructural target 
cooling  in  the  rolled  strip.  Physical  modeling  of  the  steel 
transformation  will  be  used  to  compute  temperature  and  phase 
fractions along the entire cooling section in real time. The cooling will 
enable  changes  in  the  microstructure  properties  of  the  strip.  The 
models will be suitable for all types of steel including modern grades 
such  as  dual  phase  and  complex  phase.  The  advance  control  will 
provide flexible selection of targets and strategies based on temporal 
cooling courses. Precise control of temporal cooling along the entire 
cooling  section  as  well  as  selection  of  coiling  temperature  will  be 
provided. 
5)  Data  like  mechanical  properties  such  as  tensile  strength  and 
elongation  will  be  available  in  Microstructure  monitor  at  FM  control 
pulpit. System will be flexible to provide wide range of cooling power. 
6)  The proposed automation system will be continuously sharing data of 
primary slab, transfer bar parameters after Furnace and overall strip 
tracking  in  the  mill  through  other  computer  systems  like  slab  yard, 
furnace computer systems etc. 
7)  The  above  system  supply  will  also  include  necessary  system 
software,  programming  software,  application  software,  mathematical 
models  and  development  of  necessary  protocol  for  interfacing  to 
different systems. 
8)  All  functionality  of  the  mill  except  plant  safety  will  be  carried  out 
through Technological Control Systems (TCS). The TCS used for mill 
function  will  be  same  make  and  of  same  family.  Each  mill  stand  of 
the mill will be controlled through minimum on number TCS system. 
Technological  Control  Systems  (TCS)  will  be  proposed  to  carry  out 
technological  functions for roughing mill (RM) R2, finishing mill (FM) 
F1 to F6, media, laminar cooling, two number coilers etc. . Each TCS 
system  will  have  requisite  number  of  multitasking  controllers  and 
process  I/Os  with  suitable  interfaces  to  PLC  and  Drive  systems  of 
the  mill.  These  controllers  will  be  equipped  with  CPUs,  memory 
modules,  communication  system,  process  I/Os,  power  supplies, 
racks,  panels  &  interface  modules  along  with  requisite  application 
software  which  will  be  used  for  carrying  out  the  process  control 
functions  such  as  HAGC  control  in  all  stands,  speed  control,  AWC, 
ATC,  camber  control,  centerline  control,  roll  force  control,  skew 
control, cobble protection control, profile control, flatness control, roll 
bending,  roll  shifting/CVC,  laminar  cooling,  coiler  control  etc.  TCS 
also  will  be  used  for  carrying  out  sequential,  interlocking  and  alarm 
functions  of  mill  &  auxiliaries,  hydraulics,  emulsion,  descaler,  mill 
entry  &  exit,  mill  readiness,  etc.  All  TCS  will  be  connected  through 
high  speed  dedicated  control  bus  for  exchange  of  data  between 
controllers.   
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.32  
9)  Passive  heat  shield  temperature  sensors  will  be  monitored.  Passive 
heat  shield  will  be  operated  through  TCS  system  from  finishing  mill 
pulpit. 
10) PC  based  necessary  development  tools;  engineering  stations, 
programming unit etc. and other accessories for computer system & 
TCS will be considered in the scope of work. 
11) New  Local  Control  Stations  (LCS)  will  be  installed at the  mill  stands 
consisting of selector switches, push buttons, indicating lamps; digital 
display,  soft-key  &  LCD  monitor  etc.  with  necessary  protections  for 
localized  mill  functions  like  roll  changing,  screw  down  operation  etc. 
LCS with soft-key and touch screen type monitors will be provided for 
new  hydraulics  &  lubrication  system  of  the  mill.  The  LCS  will  be 
interfacing with the PLC system. 
12) Process Data Acquisition (PDA) 
This  will  be  used  for  high-speed  acquisition  of  process  data,  on  line 
display  of  analog  and  digital  variables,  other  discreet  analog  and 
binary  signals  from  the  plant.  PDA  system  is  a  powerful  tool  for 
maintenance  personnel  for  commissioning,  mill  setup, 
troubleshooting,  data  and  failure  analysis.  PDA's  will  be  hooked  up 
directly  to  the  real  time  reflective  memory  of  the  controllers.  There 
will be minimum two licenses for the PDA system for the mill and will 
be housed at TCS rooms. 
PDA system will record all system variables online and save in user-
defined  files.  The  on  line  display  of  the  selected  channels  will  occur 
at user defines time base. For acquisition of data, required selection 
of  data  (say  tension,  control,  speed,  drive  parameters  etc.),  range 
clock rate etc. will be entered by the user. Measurement session will 
be saved in a user defines file. The representation function is off line 
display  and  it  will  contain  an  overview  function  for  fast  review  of  all 
the channels  in various  modes.  It  will  be  possible  to print or convert 
the selected curves for further analysis. It will be possible for integral 
/ differential calculations, log conversions etc. System will permit fast 
Fourier  transformation  and  auto  /  cross  correlation.  The  PDA  will 
perform the following minimum functions: 
  Synchronous monitoring & recording of all system variables 
  Powerful on line monitoring 
  Quick & easy configuration within integrated I/O Manager 
  Mass storage 
  Off line display and analysis 
  Export of data to Microsoft office (Excel) 
4.8.4.2  Mill Instrumentation    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.33    
1)  Roll force measurement system will use strain gauge type load cells 
for each mill stand. Slab type/ washer type load cells (2 nos. for each 
mechanism)  will  be  used  for  measuring  roll  force.  Each  load  will  be 
hermetically  sealed  to  prevent  any  internal  damage  due  to  the 
presence of water and other solvents used in the mill. Load cells are 
compression  force  transducers  for  measuring  force  or  weight. 
Pressure  transducers  of  hydraulic  circuit  will  be  used  as  back  up  of 
roll force measurement. 
2)  Pressure  Transducers  will  be  used  for  static  and  dynamic  pressure 
measurement and remote pressure control. This will be used for roll 
force  and  roll  bending  pressure  measurement.  In  the  present 
application  strain  gauge  type  pressure  transducers  are  envisaged. 
Quantity  and  rated  pressure  of  pressure  transducers  will  be  as  per 
control & design parameter. 
3)  Multi  point  gauge  for  thickness,  profile,  width  &  flatness  will  be 
provided  at  the  exit  of  F6.  Profibus  DP/  Ethernet  interface  and  fiber 
optics signal transmission to the automation for display will be done. 
4)  Non-contact  type  two  number  line  scan  CCD  camera  based  width 
gauge  will  be  provided  at  the  exit  of  R2.  Profibus  DP/  Ethernet 
interface and fiber optics signal transmission to the regulation system 
and for display will be done.  
5)  Lasser  Doppler  Velocimeter  (LDV)  based  Length  Measurement 
system 
LDV  based  length  measurement  system  of  strip  length  will  be 
installed at the exit of R2 for Crop Optimization system. The LDV will 
be  installed  before  the  hot  crop  shear.  Necessary  terminal  display 
will be made available at FM main control pulpit and crop pulpit. The 
signals  will  interface  with  automation  system  and  crop  regulation 
system. 
6)  Magnetostrictive  Position  Sensors  (Temposonic  type)  or  Installation 
of  absolute/  incremental  encoders  based  position  transducers  with 
Profibus  DP/  Ethernet/Modbus  interface  and  fiber  optics  signal 
transmission for Hyd AGC in R1 & R2 mill stands. 
7)  Position  Sensors  (Sony  magnescale  type)  based  position 
transducers  with  Profibus  DP/  Ethernet/Modbus  interface  and  fiber 
optics  signal  transmission  for  Hyd  AGC  in  R2  and  F1  to  F6  mill 
stands. 
8)  Installation  of  position  transducers  for  the  QWRC  system  work  roll 
pull  out  arrangement  &  QWRC  system  side  shifter  unit  will  be 
provided.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.34  
9)  Installation of position transducers for the proposed CVC system side 
shifter unit work roll shifting arrangement 
10) HMD with hot standby arrangement will be considered for the mill at 
various  locations  like  entry to  mill stands,  ROT, passive heat shield, 
crop  shear  etc.  for  material  tracking.  Photo-relays  will  be  used  as 
HMDs to detect presence of hot material. 
11) Ratio  Pyrometer/  Dual  temperature  measuring  instruments  (2  color 
infra-red  ratio  type  Pyrometers  with  complete  system)  will  be 
considered  at  important  locations.  Five  number  spot  measuring 
pyrometer will be provided at Furnace exit, RM exit, FM entry, exit & 
before  coiling.  Two  number  scanning  pyrometer  (across  the  strip 
width) at FM exit and before coiling will be provided. 
12) Differential tension measurement device between last loopers of FM 
will be provided for tension control between FM mill stands. 
13) Load  cell  based  Tensiometer  Looper  will  be  provide  at  the  FM  last 
mill stand for tension measurement for flatness control. 
14) Sensing  devices  such  as  angle  transducers,  opto-digital  encoders, 
combination  tachometers,  photoelectric  switches,  loop  sensors, 
programmable  limit  switches,  proximity  switches,  strip  speed 
measurement devices, light barriers, etc. will be in the scope of work. 
15) Interfacing  of  electrics  &  automation  with  Passive  heat  shield  & 
Hydraulic AGC in F1 to F6 Mill Stands will be considered. 
16) Single  frame  Jumbo  7-segment  displays  (250mm)  will  be  provided 
for  display  of  input  and  output  gauges  of  the  strip  thickness, 
thickness deviation, etc., at appropriate places in the mill proper. 
17) Field mounted devices, sensors, transducers etc. including mounting 
brackets,  socket  outlets,  couplers  &  utility  connections  will  also  be 
considered. 
18) Strip Surface Inspection System 
Online  non-contact  Strip  Surface  Inspection  will  be  carried  out  for 
both  sides  of  the  rolled  strip  through  camera  based  measurement. 
The  system  will  be  based  on  white  LED  illumination  and  12  bit 
resolution  cameras  four  numbers  per  each  surface  with  highly 
elaborate techniques and algorithms through image processing. The 
system will include state of the art image based classification builder, 
follow  up  indicators  and  image  enhancing  capability.  The 
measurement system will be located near down coiler. 
The  system  will  have  software  capability  to  verify  that  the  product 
meets  the  specification  in  terms  of  surface  quality.  The  system  will    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.35    
work as a watchdog warning the operator about processing problems 
in  a  strip.  HMI  will  be  provided  for  viewing  surface  faults  as  well  as 
surface  inspection  report  in  a  continuous  manner.  The  archival  data 
will  be  stored  in  SAN.  Adaptive  control  and  inheritance  will  build  a 
strong  database  to  help  in  better  understanding  the  product  surface 
quality.  
19) Utility:  Industrial  water  and  instrument  air  will  be  provided  at  take 
over points for various sensors for cooling, purging, cleaning etc.  
4.8.4.3  Mill Visualization System 
1)  There  will  be  Client  server  based  Visualization  system.  Hot  standby 
Database  HMI  Server  for  Process  Supervision  and  Monitoring 
System  will  be  considered.  HMIs  for  Visualization  System, 
Engineering Station, Developmental Consoles, Programming station, 
Plant simulation station etc. will be considered for the mill. There will 
be plant wide data communication network based on OFC on TCP/IP 
protocol  with  common  global  database.  Visualization  system  will  be 
connected  to  suitable  communication  network  (LAN)  linking  various 
mill locations like Control room, Computer Room, Centralized Control 
Pulpits, Local control stations etc. for integrated control.  
2)  Consumption  of  utilities  and  power  will  be  considered  in  the  Data 
Acquisition System (DAS) package. 
3)  File server, Web server etc. will be provided for mail massaging and 
remote  monitoring  of  data  and  CCTV  images.  Firewall,  password 
protection, antivirus software will also be considered. 
4)  The  scope  will  also  include  supply  of  Operator  stations/  Human-
Machine  Interfaces  (HMIs)  with  21  TFT  colour  monitor  for  down-
loading  of  rolling  schedules  and  set-points,  process  supervisory 
functions,  visualization  of  process  parameters  &  process  trends, 
reports and status, fault logging, trending, etc. There will be common 
HMIs for L1 and L2 client preferably. 
5)  The  control  desks  will  be  ergonomically  designed  and  will  be 
provided  with  control  elements  such  as  selector  switches,  push 
buttons,  indicating  lamps;  digital  display,  analogue  meters  etc.  LCS 
will be positioned near mill stand for local control and visualization. 
4.8.4.4  Mill Networking 
1)  There will be a common bus based on FOC with TCP/IP protocol to 
which  HMIs  and  servers  will  be  connected.  All  TCS  systems  along 
with PDA system will be connected through a dedicated fast bus for 
exchange of critical data between controllers. There will be industrial 
Ethernet  bus  connecting  to  TCS  systems  for  transmission  of  critical 
field  data  of  hydraulic  servo  valves,  pressure  transducers,  roll  force 
data  etc.  R  I/O,  Drive  systems  etc.  will  be  connected  through  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.36  
Profibus DP. Network switches will be provided at Server room, TCS 
room,  ECR,  Instrumentation  room,  Control  rooms/pulpits  etc. 
Ethernet  network  will  be  designed  with  a  fibre  optic,  Gigabit  bus 
based  type  backbone  with  ring/star/mesh  topology.  Redundancy  in 
Switches  and  FOC  will  be  provided  as  per  requirements,  allowing 
communication  to  take  place  in  case  of  fault  at  one  switch.  All  the 
core  switches  will  be  manageable  type.  Client  HMIs,  HMI  database 
server  and  software  development  station  will  be  equipped  with 
double  LAN  adapters  and  will  be  connected  to  both  the  redundant 
network. 
2)  Communication with Plant ERP system 
The  Level-2  automation  system  and  Level-3  MES  system  will 
establish  communication  with  TCP/IP  based  plant  network. 
Production  data  and  any  other  necessary  information  will  be 
transmitted  to  the  proposed  Level-4  ERP  system.  The  L2  &  L3 
system hardware, OS & RDBMS will be compatible with ERP. 
3)  Twisted  pair  cable  will  be  laid  inside  the  control  room  and  FO  cable 
will be laid for outside premise for communication. FO cable will also 
be laid between each remote I/O unit and the main processor.  
4)  Interface  (both  hardware  and  software)  with  internal  systems,  like 
power  distribution  system,  automation  system,  Passive  Heat  Shield 
controller,  Auxiliaries  (hydraulic,  grease,  compressor  etc.)  systems, 
Furnace, Gas boosting stations, Water systems, Fire alarm systems, 
communication  systems,  Slab  yard,  Roll  shop  management  system 
etc.  will  be  considered.  CCTV  system,  communication  system,  fire 
alarm system will have separate network. 
5)  Interface  (both  hardware  and  software)  with  external  systems,  PPC 
Level-3  system,  CCD  computer  system,  SMS,  Laboratory  and 
connection with Plant network will be included. 
6)  Network  management  software  will  be  provided  for  diagnostic  and 
network management. 
4.8.4.5  Mill Tracking 
T.O.P.  for  material  tracking  will  start  from  the  Slab  charging  roller 
table  at  slab  yard  upto  coil  dispatch  at  coil  yard.  Interfacing  of  mill 
sensors  signals  like  HMDs,  mill  gauges,  roll  bites  etc.  will  be  done 
with automation system for material tracking.  
1)  The  material  tracking  function  will maintain a  queue of the materials 
in the HSM.  
2)  Material tracking system in the mill from slab yard and up to the coil 
conveying system of HSM exit, so that process control & monitoring    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.37    
of  the  coil  is  carried  out,  as  desired,  in  different  sections  for  the mill 
process  line.  Material  tracking  data  will  be  displays  at  HMIs  as  per 
process requirements. 
3)  Segment Tracking 
Segment  tracking  will  be  carried  out  for  finished  coil  for  thickness, 
temperature,  hardness  etc.  at  regular  intervals  and  the  data  will  be 
stored for archival. For the current rolled material a segment tracking 
will  be  performed,  which  will  be  based  on  the  actual  process  data 
transmitted  from  the  basic  automation  system.  External  storage  for 
data archival of 5000 rolled coils measured parameters with 8 traces 
stored at approx. 3m interval will be provided. 
4)  Roll Tracking 
Roll  tracking  between  mill  and  roll  shop  will  be  provided  for 
identification  of  rolls  and  for  information  like  tonnage  rolled,  roll 
machine history and for roll inventory management. The last used roll 
diameters  for  1000  rolls  will  be  maintained  in  the  Level  2  system, 
thus allowing complete roll histories (diameter, crown) to be tracked. 
This data will be used as a verification check on operator entered roll 
diameters for a particular ID of a roll. The proposed system will have 
provision that once a roll is changed in the particular stand, date and 
time  when  roll  has  been  inserted/  removed  and  the  rolled  tonnage 
and length will be stored in the database. 
4.8.4.6  Crop Optimization System 
The use of latest state of the art technology in the area of crop shear 
operation  will  be  proposed,  which  will  make  a  substantial 
improvement  in  reduction  of  quantity  of  crop  ends.  It  will  have 
calculations  done  in  real  time  basis  for individual  tasks  and  to  down 
load  the  calculated  set  values  so  as  to  co-ordinate  the  drive  level 
functions  and  technological  functions  being  performed  by  the 
controllers. 
1)  Crop Visualization System 
The optimization system will receive sets of information like the crop 
cutting  strategy,  the  bar  identification  and  the  bar  thickness  etc.  for 
each transfer bar from the host computer as the bar approaches the 
last roughing stand. Upon receipt of the signal of last pass, the vision 
system will capture head and tail end images. 
Two  number  solid  state  line  scan  area  array  CCD  camera  of  high 
resolution will be mounted above the transfer table at the exit of R2. 
High-speed pattern recognition software will intelligently analyses the 
image and precisely determines the complete profile of the head and 
tail end and width of the strip.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.38  
An optimal cut point will be determined in accordance with the unique 
shape of the head end. The image of the head end of the strip, with 
the  cut  line  superimposed  will  be  displayed  for  the  operator  in  a 
operator station at FM control pulpit monitor. The system will transmit 
the  information  about  optimal  or  desired crop  cut  and  other  relevant 
data to crop shear controller (TCS).  
2)  Crop Communication System 
Crop  optimization  system  will be  hooked  to  LAN, for communication 
to  the  host  computer  system.  The  strip  numbers,  thickness,  strip 
width, temperature etc. associated with the next strip to pass through 
the last rougher will be input to the crop optimization system through 
this  link.  Crop  cut  length,  weight,  width  (optional),  length  of  the  bar 
(optional) etc., information and alarm messages will be transmitted to 
host  computer  over  the  same  link.  Following  MIS  functions  will  be 
carried out: 
  Crop Statistics Display 
  Crop Statistics 
  Camber Statistics 
  Strip Width 
3)  Strip Tracking  
This  vision  system  will  follow  the  strip  as  it  moves  from  the  last 
rougher to the crop shear. The camera will capture the image of the 
head  and  tail  end  of  the  strip.  The  material  will  be  tracked  and  the 
speed  of  the  strip  will  be  measured  through  encoders,  hot  metal 
detectors, laser velocimeter positioned in strategic places. 
4.8.5  Plant Emergency System 
Emergency functions for complete mill will be designed according to 
the international norms, standards and regulations and will have the 
following features. 
1)  Fail safe PLC under certification will be provided for carrying out 
Plant Emergency System. 
2)  Emergency Stop (E-Stop Category-1): Emergency stop (E-Stop) 
is a safety operation, required for dangerous situations or as a 
designed safety reaction to equipment failure or malfunction. 
3)  Quick Stop (Stop Category 2): Quick-stop-mode will require all 
drives in the associated Quick-Stop-Area to be stopped 
synchronously as quickly as possible. 
4.8.6  Condition Monitoring System 
The condition monitoring system with Diagnostic server will include 
following:    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.39    
1)  Temperature  monitoring  complete  with  PT100  sensors,  Local 
cabinet  with  necessary  multiplexer  and  intermediate  amplifier, 
signal  conversion  and  signal  processing  module  etc.  will  be 
offered  for  the  following  drives.  Also,  LAN  interface  will  be 
provided  to  super  co-ordinate  Diagnostic  server  for  necessary 
data storage/ analysis. 
  Main drive motors (R2 & V2) with air to water heat exchanger 
if any. 
  Bearings  of  main  drives  and  Large  aux.  drive  motors,  pinion 
stand of main stands / TMB/FFB, HT motors 
  Water-cooled main drive converters if used. 
2)  Vibration  monitoring  of  gearboxes  for  motors  greater  than 
1000  KW  rating  will  be  provided.  This  will  include  necessary 
Industrial  universal-axial  vibration  /  acceleration  sensors  with 
its  pre-processing  units,  IP55  local  cabinet,  Analysis  and 
diagnostic software package for defect detection system, Data 
&  signal  management,  condition  evaluation  and  monitoring, 
Maintenance  and  service  interface,  with  its  PC,  19  inch 
monitor,  software  etc.  Also,  LAN  interface  will  be  provided  to 
super  co-ordinate  Diagnostic  server  for  configuration  of 
individual  vibration  channel,  data  storage  and  frequency 
analysis.  The  measuring  devices  complete  with  its  protective 
housing will be suitable for rolling mill environment. 
3)  Torque  condition  monitoring  of  R2  main  drive  spindles  etc. 
complete  with  heavily  protected  strain  gauges,  telemetry  (non 
contact  power  supply  &  signal  transmission), signal  evaluation 
(Analog/digital  signal  conversion),  IP55  cabinet,  Stator 
electronics,  bending  compensation,  pre-processing  unit,  data 
&  signal  management,  condition  evaluation  &  monitoring, 
maintenance  &  service  interface,  Interface  with  other  systems 
etc.  Also,  LAN  interface  will  be  provided  to  super  co-ordinate 
Diagnostic server for necessary data storage / analysis.  
Two  nos.  sensor  system  for  top  &  bottom  spindle  of  R2  each 
with  individual  torque  analyzing  system,  required  nos.  of 
preprocessing  units  and  local  cabinets,  spare  channels  and 
necessary interface with other systems (like main drive speed, 
current and load cells etc.). 
4)  Complete  CMS  including  server  &  PC's,  networking 
components,  software  along  with  intelligent  local  data 
capturing  devices  &  interface  with  Level-1  system,  on-line 
monitoring,  of/off  line  analysis  of  acquired  parameters  with 
generation of necessary screens and reports. 
4.8.7  Coil Yard Management 
Coils coming from the mill will be brought to the coil yard through coil 
conveying  systems.  Weighment  of coil  and  Eye strapping of the coil 
will be carried out in the coil yard. There will be coil marking and coil 
reading system. The reader will send the coil id data wireless to the  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.40  
automation  system.  There  will  be  a  control  pulpit  with  Operator 
Console/  HMI  at  coil  yard  for  data  entry  of  coil  storage  in  the  yard. 
Automatic  crane  positioning  system  will  be  considered  for  coil  yard 
management.  Level-2  system  with  Server  will  be  provided  for 
keeping  coil  PDI,  coil  yard  management  and  coil  archival  functions. 
Coil  Yard  mapping  in  all  the  three  axis  will  be  done  to  show  the 
location  of  desired  coil  in  the  console/HMI.  Storage  Area  Network 
(SAN)  will  be  provided  for  archival  data  management  like  coil  data, 
quality  data  etc.  The  Coil  yard  management  system  will  provide 
following benefits: 
  Better yard utilization 
  Faster coil retrieval & feeding 
  Real time display of inventory & order progress 
  Minimum coil handling 
  Optimum crane utilization 
  Avoid of wrong dispatch of coils to customer 
  Mix up coils can be identified 
4.8.8  Roll Shop Management System 
Roll shop management will be part of the scope of work. Roll shop 
management will  minimize  number of rolls in production; optimize 
production, optimized shop logistic etc. Roll data management will 
contain  roll  history.  Information  exchange  with  roll  shop  must  be 
comprehensive  and  suitable  for  both  way  communications.  Roll 
shop management will usher following advantages: 
  High quality assemblies 
  Optimizing roll machining process 
  Dimension information on chocks 
  Optimum use of bearings 
  Transparency of the system 
The RSMS is a server based software system to manage roll shop 
equipment  such  as  grinders,  rolls,  chocks,  bearings  etc.  RSMS 
will  also  provide  historical  data,  inventory,  tracking  and 
maintenance  information.  A  client  server  based  complete 
Information  system  comprising  of  server,  required  number  of  PC 
workstations,  networking  as  well  as  standard  and  application 
software,  as  needed,  will  be  supplied.  The  functions  to  be 
performed by RSMS will include but not be limited to the following:  
  Maintain a database containing all information related to rolls, 
chocks, bearings, roll/bearing/chock assembly  
  Tracking of rolls, chocks, bearings  
  Display status of rolls, chocks, bearings  
  Generation of grinding schedules based on production schedule 
for roll change and mill setup  
  Storage of grinding profiles for all rolls to be used in the mill line  
  Data gathering from linked grinding processes     
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.41    
  Input screens for data entry for de-chocking and re-chocking 
process  
  Generation of reports for all possible combination of stored data  
  Generation of purchase orders and requisitions to track costing 
information on the inventory  
  Establishment of link with mill Level 2 system for necessary data 
exchange related to tonnage rolled, rolls status etc.  
  Establishment of link to higher level systems via mill Level 2 
system, as required  
4.8.9    Computerized Maintenance Management System 
The  Computerized  Maintenance  management  System  will  be 
suitable  for  any  level  of  user  and  will  be  customized  for  the  mill. 
The activities handled by CMMS will be the following: 
  Equipment & Facilities Management 
  Planning, Scheduling, Preventive Maintenance operation 
  Job plan & work order management 
  Resource management 
  Inventory management 
  Report & Analysis 
CMMS  will  store/  find  equipment/  asset  information,  i.e.  technical 
specifications,  work  outstanding,  cost  of  ownership  etc.  It  will  build 
comprehensive  and  detailed  library  of  jobs  for  each  planned  and 
unplanned jobs/routines. It will have plans for jobs forthcoming week, 
month,  year  or  any  other  time  interval.  It  will  quickly  and  easily 
provide  complete  history  of  each  equipment  and  their  depreciation 
value. Necessary hardware and software will be provided for CMMS. 
4.8.10    Process & Plant Simulation System 
Safe  &  quick  commissioning  and  the  quick  attainment  of  full 
production capacity is of prime importance. The commissioning of 
the  mill  takes  much  of  the  time  because  set  up,  testing  and 
implementation  of  the  electrical  &  automation  system  starts  after 
mechanical  components  had  been  installed  on  the  site.  Long 
commissioning  time  happens  due  to  technical  interfaces  between 
individual  modules  of  the  electrical  &  automation  system 
(technological  control  system,  L2 automation  system  etc.)  as  well 
as  integrated  system  for  the  plant.  These  will  show  kinematic  & 
dynamic behavior of the mill. Also, it will help in reliable quick start 
up  and  secure  take  over  reducing  mill  commissioning  time  and 
quickly  realizing  full  potential  of  the  mill.  To  commission  the 
system quickly the following methodologies will be used: 
  Plug  &  Work  Test  Process:  The  core  of  the  process  is  testing 
against  a  virtual  production  sequence.  By  means  of  simulations, 
the  automation  system  will  be  tested  under  practical  production  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.42  
conditions. This will help in deriving fault free pre optimized plant 
solution.  These  will  allow  the  testing  of  the  actual  hardware  & 
software under almost real plant condition. 
  Virtual production test: The customer specific construction models 
are  used  as  a  basis  and  the  relevant  geometrical  data,  the 
kinematic  and  dynamic  behavior  of  the  plant  unit  in  question  as 
well  as  function  of  the  field  instrument  located  on  the  unit  are 
transferred  to  the  simulation  model  in  a  more  or  less  automated 
layout process. 
  Test  facilities:  The  entire  software  and  hardware  of  the  scope  of 
supply  is  installed  to  judge  the  completeness  and  workability  of 
the system as a result commissioning is significantly accelerated. 
Process  and  plant  simulation  will  be  conducted  at  the  mill 
automation  supplier  premises  in  presence  of  the  Purchaser. 
Mill  operators  will  be  given  training  in  near  mill  operating 
conditions for all the steel grades enabling training in real time 
environment. 
4.8.11   Manufacturing Execution System (MES) 
MES will integrate all the functions and services of customer need for 
sustained  maximization  of  plant  performances.  MES  of  HSM  will 
ensure  a  seamless  and  transparent  flow  of  data  vertically  from  the 
process  to  the  management  level  and  horizontally  from  the  delivery 
of  raw  materials  to  the  finished  product.  The  software  modules  of 
MES  will  optimize  all  horizontal  production  processes,  from  slab  to 
strip  and  vertically  integrate  the  plants  information  flow  end-to-end, 
helping  the  management  to  make  better-founded  decisions;  and 
assure  maintenance  and  further  development  over  the  entire  life 
cycle of the HSM plant.  
All necessary hardware of server systems, networking hardware and 
software  like  OS,  Application  development  software,  application 
software modules for MES will be considered for MES. Interfacing to 
plant server and HSM server will also be considered for exchange of 
MES information. Various modules for HSM MES are given below. 
1)  Production management 
MES  production  management  module  will  provide  the  relevant  key 
information  on  the  status  of  production,  the  status  and  location  of 
every  material  unit  and  of  all  relevant  resources  for  the  entire  plant 
HSM.  The  software  module  of  Production  Modeling  will  accurately 
describe  the  entire  production  process  including  production  rules  in 
each production step. Material and order tracking will continuously be 
updated and checked using production rules. 
2)  Information management 
This module will provide reliable information on the current status of 
the production operation and its metrics. From predefined structures    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.43    
in  a  database  and  a  data  warehouse,  all  information  is  extracted, 
processed,  and  made  available  in  a  format  that  can  easily  be 
evaluated.  In  addition  to  predefined  standard  reports  by  powerful 
Web  Reporting  Tools,  the  system  delivers  up-to-date  graphically 
enhanced  Key  Performance  Indicators  for  the  key  matrices  of  the 
production. 
3)  Material management 
The  coil  yard  management  system  is  a  solution that  unifies  material 
and  information  flow  across  the  entire  system  from  the  sensor  to 
control room. The module will have innovative tools such as material 
and order scheduling, web connection and service support. 
4)  Production planning 
The  module  will  provide  optimum  capacity  and  production  path 
planning  based  on  technological  plant  limits,  plant  conditions  and 
scheduled  availability.  These  will  also  maximize  production  across 
the  entire  process-  with  the  global  optimum  taking  precedence  over 
the  local  optimum.  The  optimized  production  sequences  created  by 
Production  Planning  also  minimize  set-up  efforts  thus  improving 
product quality resulting faster and more reliable planning even in the 
event  of  fault  conditions. There  will  be  different  scheduling solutions 
or the plant. Also overall planning functions will be available to create 
production orders based on new customer orders. 
5)  Quality management 
Quality  management  module  will  assess  quality  and  develop 
appropriate  strategies  to  overcome  quality  defects  without  infringing 
production  process  in  any  way.  Here,  early  detection  of  fault  will 
allow  the  plant  to  act  quickly  and  securely to limit  damage,  avoiding 
costly returns and loss of reputation. Quality control functions will be 
available  based  on  flexible  specification  management  of  all 
production  steps.  Online  production  rules  will  be  checked 
continuously  to  check  if  production  is  running  properly  in  specified 
limits.  There  will  be  a  seamless  integration  between  the  modules  of 
quality  control,  production  order  management  and  production 
scheduling  to  ensure  the  best  balance  between  plant  utilization, 
product quality and customer order due dates. 
6)  Logistics management 
Storing  and  retrieving  raw  materials,  intermediate  goods  or  final 
products take up a significant amount of the production and delivery 
time.  Optimized  slab  yard  and  coil  yard  logistics  will  provide 
significant  advantage  by  reducing  costs  and  increasing  the 
competitive  edge.  The  module  will  efficiently  support  stock  keeping, 
quality planning and product dispatching. 
7)  Laboratory management 
The  module  will  collect  and  manage  all  quality  data  in  a  central  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.44  
database and configure quality workflows and analysis in the lab and 
on  production  line.  This  will  include  automatic  validation  and  alarm 
handling for management. 
8)  Maintenance & Equipment management 
The performance of the plant greatly depends on the effectiveness of 
its  maintenance  system.  The  maintenance  module  will  help  to 
increase  availability  while  supporting  the  competitiveness  of  the 
production. The functionality of the module ranges from maintenance 
planning  using  standardized  work  schedules  to  the  initiation  of 
maintenance orders based on defined criteria and the collection and 
archiving  of  all  incurred  costs  to  fulfill  the  technological  and  process 
needs of the plant.  
9)  Energy management 
Total  cost  of  energy  for  HSM  is  very  large  of  the  total  production 
costs. The energy module will show transparency for revealing actual 
energy consumption. The module functions in recording consumption 
data,  allocating  energy  charges,  planning,  energy  forecasting, 
generating energy balances etc. The module will be configurable and 
scalable for the different automation levels and production units. 
4.8.12   Modes of Operation 
The proposed mill will have three modes of operation for RM & FM. 
1)  Manual mode 
There  will  be  no  rolling  in  this  mode.  The  operator  through  HMI/ 
switches  provided  in  main  control  pulpit  will  have  facility  of  manual 
and auto calibration of hydraulic screw downs. The individual system 
will be tested during maintenance using manual mode. 
2)  Automatic mode with process computer 
In  this  mode,  the  process  computer  will  send  the  set  points 
calculated  from  the  pass  schedule  to  the  Level-1  system.  All  rolling 
parameters  except  tension  will  be  dynamically  calculated  and  down 
loaded  to  Level-1  system  based  on  the  actual  feed  of  rolling 
parameters  from  Level-1  system.  Any  change  in  entry  thickness 
during  threading  will  cause  new  preset  value  down  loading  to  the 
Level-1 system.  
4.8.13   UPS Systems 
New UPS systems will be used for the proposed automation system 
consisting  of  Severs,  Networking  hardware,  TCS,  PLC  and  process 
supervision  &  monitoring  system,  process  instrumentation, 
telecommunication,  fire  detection  &  alarm  system,  etc.  Each  UPS 
systems  will  be  in  parallel  redundant  configuration  with  50%  load 
sharing.  The  Rectifier  and  Inverter  of  UPS  system  will  be  IGBT 
based.  The  UPS  system  will  have  battery  back  up  time  of  minimum 
one  hour.  Separate  UPS  systems  will  be  provide  for  Automation    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.45    
Building  and  various  control  pulpit,  TCS  rooms,  Instrumentation 
rooms,  PLC  rooms  depending  upon  locations  The  centralized  UPS 
systems will be distributed as per requirement. PDB will be provided 
for distribution of UPS power. 
4.8.14   Digital Video Management System (DVMS) 
The HSM will be equipped with DVMS system in order to cater to 
video  surveillance  and  plant  operational  requirements.  The 
system  will  have  its  dedicated  communication  bus  enabling 
surveillance,  alarm  and  event  activated  recordings.  The  video  of 
both the cause of the event and the results of the event captured 
will  allow  for  proper  diagnostic  &  analysis.  The  control  room 
operator  can  not  only  view  &  control  all  the  cameras  from  the  
main  control  rooms  from  the  TV  monitors.  The  plant  operators 
will monitor and control the process with the aid of live videos. 
The Digital Video Recording & Management System will include: 
  DVM Database & Camera Servers 
  Network connected cameras (IP based) and/or network 
connected camera streamers 
  Network infrastructure 
  System software 
The CCTV cameras will be located at different strategic locations 
from Slab yard to Furnace to Mill to Coil Yard. 
4.8.14.1  System Requirement  
The  camera  will  be  suitable  for  day  and  night  operations.  The 
camera  will  be  IP  based  with  digital  output  signals.  Each  of  the 
TV cameras will be hooked up to the network. Remote viewing of 
camer5as  will  be  provided.  The  monitors  along  with  its  controls 
and  its  associated  equipment  will  be  installed  at  main  control 
pulpit.  All  control  functions  related  to  CCTV  systems  comprising 
of Cameras, Monitors, Water cooling jacket, blower unit and wipe 
& wash unit of the weather proof housing will be affected from the 
control unit to be installed in pulpit & main control room. 
The  CCTV  system  will  comprise  of  colour  TV  cameras  with 
manual  and  motorized  zoom  lenses  as  required,  camera 
mounting  platforms/  structure  as  required  at  site,  Water  cooling 
jackets, complete with wipe & wash units, Remote controlled Pan 
& tilt units, Control console with control units for complete control 
of  cameras  and  associated  devices,  colour  TV  TFT  monitors, 
Interconnecting  video  &  control  cables,  UPS  system,  Video 
distribution  amplifier/  Video  cable  equalizers,  Camera streamers  , 
DVM Database & Camera Servers etc. as per requirements. All other  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.46  
auxiliary  equipment,  connectors,  erection  accessories  etc.  will  be 
provided as required. 
4.8.15  Intelligent Automatic Fire Detection System 
Intelligent  type  digitally  addressable  Fire  Alarm  System  will  contain 
one  or  more  Intelligent  type  addressable  Fire  Alarm  panel(s)  and 
Intelligent  type  addressable  detector  and  multi  criterion  devices  and 
Linear  Heat  Detection  (LHD)  cables.  All  the  panel  must  have  in  a 
strong  networking  system.  There  must  be  a  Life  Safety  Colour  Text 
and  Graphics  Annunciation  connected  in  the  network.  The 
description,  feature  and  specification  of  all  the  system  components 
are as described below: 
Standard  Regulation:  Automatic  Fire  detection  &  Alarm  System  will 
be  designed,  manufactured,  supplied,  erected  and  tested  as  per 
requirement  laid  in  Fire  Protection  manual  issued  by  Tariff  Advisory 
Committee  of  India  and  relevant  Indian  Standard  specification  / 
IPSS. In absence of relevant standards, the system will be designed 
in  accordance  with  requirement  of  National  Fire  Practice,  Fire 
officers  committee,  UK  and  other  International  Standards,  Codes 
and  regulations.  All  imported  items  will  bear  under-writers 
laboratories  (UL),  USA/Factory  manual  (FM),  USA/Fire  Officers 
Committee  (FOC),  UK  approvals  and  TAC,  India  Standard  approval 
certificate for any Indian Supply. 
Each Intelligent type addressable smoke detectors sensitivity will be 
capable  of  being  programmed  individually  as  most  sensitive,  more 
sensitive,  normal  less  sensitive  or  lest  sensitive.  In  addition  to  the 
five  sensitivity  levels  the  detector  will  provide  a  pre-alarm  sensitivity 
setting,  which  will  be  settable  in  5%  increments  of  the  detectors 
alarm sensitivity value. 
An alternate alarm sensitivity level will be provided for each detector, 
which can be se of any of the five (5) sensitivity settings manually or 
automatically  using  a  time  of  day  event.  In  addition  to  the  five 
alternate  sensitivity  levels  the  detector  will  provide  an  alternate  pre-
alarm  sensitivity  setting,  which  will  be  settable  in  5%  increments  of 
the detectors alternate alarm sensitivity value. 
The  detector  will  be  able  to  differentiate  between  a  long  drift  above 
the pre-alarm threshold and fast rise above the threshold. 
The  detectors  sensing  element  reference  point  will  automatically 
adjust,  compensating  for  background  environmental  conditions  such 
as  dust,  temperature,  and  pressure.  Periodically,  the  sensing 
element  real-time  analog  value  will  be  compared  against  its 
reference value. The detector will provide a maintenance alert signal 
that  75%  to  99%  compensation  has  been  used.  The  detector  will 
provide  a  dirty  fault  signal  that  100%  or  greater  compensation  has 
been used.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.47    
The  system  will  allow  for  changing  of  detector  types  for  service 
purposes  without  the  need  to  reprogram  the  system.  The 
replacement detector type will automatically continue to operate with 
the  same  programmed  sensitivity  levels  and  functions  as  the 
detector it replaced. System will display an off-normal condition until 
the  proper  detector  type  has  been  installed  or  change  in  the 
application program profile has been made. 
The  areas  to  be  covered  under  Intelligent  Fire  Detection  &  Alarm 
system  will  include  the  following  installation  installed  new  pertaining 
to this project: 
  ECR & Transfer Rooms 
  Cable Tunnels 
  Server, TCS & PLC Rooms 
  UPS Rooms 
  Control Pulpits 
  Hydraulic/ lubrication rooms 
The system will comprise of main control panel, manual call stations, 
repeater  panels,  response  indicators,  various  type  of  detectors, 
electronics,  hooters,  power  supply  units  complete  with  back  up 
power supply system etc. 
4.8.16  Cables & Accessories 
All  power,  control,  screened  and  special  cables  along  with  cabling 
accessories  required  for  interconnection  of  all  the  equipment  under 
the scope of the work. The following cables will be used for:  
  Interconnection of I/Os for PLC and TCS systems 
  Incomers and power distribution for automation system 
  Cables for panel illumination and lighting 
  Interconnection between computers and its peripherals, 
HMI/ Operators stations, IO systems and other field 
sensors/ devices, etc. 
  FOC and twisted pair cables 
  Telecommunication cables 
  Special cables etc. 
4.8.17  Telecommunication System 
4.8.17.1  Press to talk type loud speaker communication system 
  Press  to  talk  type  Loudspeaker  Inter-communication  System  will  be 
used  to  provide  quick  and  reliable  communication  facility  among 
various strategic location in the mill. 
 The  system  will  be  flexible  as  far  as  expansion  and  system 
configuration is concerned.  
 Depending upon the requirement, the subscriber stations will be desk 
or wall mounting type.   
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.48  
4.8.17.2  Plant Telephone System 
The  plant  telephone  facility  will  be  extended  to  the  new  locations  to 
the  mill  areas  including  the  above  locations  where  press  to  talk 
system  is  being  envisaged.  Suitable  telephone  sets  along  with 
EPBAX system are being envisaged.  
4.8.17.3  Walkie talkie sets  
Walkie  talkie  sets  are  also  being  envisaged  for  efficient  and  reliable 
communication. 
4.8.18  Access Control system 
Biometric  based  Access  control  system  is  being  envisaged  for 
regulating  access/entry  to  various  important  rooms  like  Process 
computer  room,  MES  room  and  control  pulpits.  The  access  control 
system will include automatic attendance management features. The 
system  will  be  installed  at  different  locations  to  facilitate  the 
attendance of employees. The system will have a centralized server 
to  store  all  the  access and attendance  records  and  will also  provide 
various reports. 
4.9    ELECTRICAL SYSTEM AND DRIVE AUTOMATION 
4.9.1    Power Requirement 
The  estimated  power  requirement  for  the  new  3.0  Mt  Hot  Strip  Mill 
(HSM) is as follows:- 
Maximum  Demand  (  15 
minutes) 
190 MVA 
Average Demand  135 MVA 
4.9.2    Present power distribution system 
Presently, Rourkela Steel Plant is receiving power from the following 
three sources: 
  Orissa  Power  Transmission  Corporation  Limited  (OPTCL)  is 
supplying power from Tarkera Sub-station at 132kV level 
  NSPCL is supplying power at 132kV level 
  RSP is generating own power at 33kV level through CPP-1.  
At present the average power demand of RSP is around 175MW and 
peak demand is around 220MW.  
After  on-going  modernization,  average  demand  of  RSP  is  expected 
to  increase to 315 MW. Additional Power will be drawn from 220 kV 
Tarkera  sub-station  through  2  nos.  220  kV  lines  at  MSDS-IV 
substation.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.49    
4.9.3    Power Distribution network of the proposed Mill 
4.9.3.1    As the existing 220 kV transmission line from OPTCL to RSP is not able 
to  take  additional  load  of  the  proposed  Hot  Strip  Mill  (HSM).  The 
following are proposed: 
  Construction  of  2  nos.  220  kV  bays  at  Tarkera  grid  sub-
station,  extension  of  the  control  room,  boundary  wall  and 
associated jobs 
  It  is  proposed  to  tap  the  bulk  power  at  220  kV  level  through 
transmission  lines/  cables  (part)  from  Tarkera  grid  substation 
for  catering  to  power  demand  of  the  proposed  HSM  and  its 
associated auxiliaries. 
4.9.3.2    Addition  of  2  nos.  220  kV  bays  at  NSPCL  new  unit  S/s.  Connectivity 
with  the  proposed  250  MW  NSPCL  power  plant  with  new  MSDS-VII 
through transmission lines.  
4.9.3.3  All  transmission  lines  have  been  considered  with  optical  ground  wire 
(OPGW). 
A  new  Main  Step  Down  substation,  i.e.  MSDS-VII  is  planned  to  be  set 
up  in  the  vicinity  of  HSM  site  at  a  strategic  location  and  will  broadly 
consist of the following:    
  220  kV  double  circuit  power  from  Tarkera  through  overhead 
transmission lines/ cables (part) will be brought to MSDS-VII  
  220 kV indoor Gas Insulated Substation (GIS) 
  Three nos. 160/ 140 MVA, 220/ 33 kV ONAF/ ONAN outdoor 
power transformers 
  33  kV  indoor  GIS  for  feeding  mill  drives  and  power  supply  to 
for 33/ 6.6 kV substations 
4.9.3.2  The  power  supply  at  220  kV  from  Tarkera  OPTCL  substation  will  be 
brought through transmission lines. A route survey is to be conducted to 
establish  the  route  of  transmission  line.  Cable  routing  in  short  span, 
wherever necessary depending upon route survey will be considered. 
4.9.3.3  Two  nos.  33kV/6.6  kV  HT  substations  1  &  2  are  also  envisaged  to  be 
set  up  at  strategic  load  centres. 33  kV  incoming power  supply  to these 
HT substations will be fed from 33 kV GIS to be installed at MSDS VII. 
4.9.4    Necessary approval and sanction for additional power requirement from 
OPTCL is to be taken up by RSP separately. 
4.9.5    Total  power  requirement  of  new  HSM  is  proposed  to  be  met  from  the 
following two substations:  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.50  
a.  Main Step Down Substation (MSDS-VII) to be located near HSM 
for the following purpose: 
  To  receive  power  at  220  kV  level  from  Tarkera  substation 
and in future also from new NSPCL/ MSDS-IV 
  To step down from 220 kV to 33 kV level for catering to major 
mill  loads.  Roughing  Stand  motors  and  to  Finishing  Stand 
motors shall be fed through Converter transformers 33kV/6.6 
kV HT substation no. 1: To step down from 33 kV to 6.6 kV level for 
catering to mill and auxiliary loads. 
c. 33 kV/ 6.6 kV HT Substation no. 2 for RH Furnace and auxiliaries 
is  proposed  to  be  located  near  Re-Heating  Furnaces  for  catering  to 
Re-Heating Furnace loads 
4.9.6    Emergency power: 
Critical loads (Category I) including for illumination has been considered 
as 1 MVA. This will be met from CPP-I through new plate mill 6.6 kV HT 
Board.  One  6.6  kV  emergency  HT  board  has  been  considered  in  Re-
Heating  furnace  switchgear  room.  This  6.6  kV  HT  Board  will  be  fed  by 
two nos. 6.6 kV incomers, one from new MSDS  VII and another from 
existing  CPP-I  through  new  plate  mill  substation.  Auto  changeover 
facility has been considered. Existing 6.6 kV HT Board in new Plate mill 
will  be  extended  by  one  panel  for  the  purpose  of  tapping  power  for  6.6 
kV  emergency  HT  Board.  Cable  route  of  1  kM  distance  has  been 
considered  from  new  Plate  mill  to  the  proposed  6.6  kV  emergency  HT 
Board  for  new  HSM.  All  category  I  loads,  mainly  pump  motors  for  Re-
heating furnaces and complete illumination, will be fed directly from this 
emergency  6.6  kV  HT  Board.  Same  make  of  6.6  kV  HT  breaker  as 
considered for new plate mill 6.6 kV HT Board will be preferred. 
4.9.7    MSDS-VII will consist of the following:  
a.  Indoor  type  double  bus  configuration  220  kV  Gas  Insulated 
Substation (GIS) 
b.  Three  nos.  of  outdoor  160  MVA/  140  MVA,  220  kV/  33  kV  each 
ONAF/ ONAN transformers 
c.  Switchyard  to  220  kV  GIS  and  from  GIS  to  transformer  connection 
will be through SF6 bus-duct 
d.  Indoor type double bus configuration 33 kV GIS HT Board for catering 
to major mill loads, HT substation no. 1 & 2 for mill auxiliaries and Re-
heating  furnaces,  respectively  and  also  for  start  up  of  Coal 
gasification plant     
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.51    
e.  Substation  automation  system.  SAS  will  be  integrated  with  the 
existing  SCADA  at  MSDS-IV.  Necesssary  hardware  and  software 
have  been  considered.  Necessary  number  of  OPC  gateways  will  be 
provided  in  the  SAS  for  down  loading  required  data  to  process 
automation. 
f.  Nitrogen  injection  based  fire  protection  system  for  above  mentioned 
transformers 
g.  On line condition monitoring for above mentioned transformers 
h.  Hydrant system for outdoor switchgear equipment protection 
i.  All protection relays will be numerical type and communicable on IEC 
61850 protocol 
4.9.8    33 kV/6.6 kV HT Substation No.1 
The above substation is proposed to be installed close to the Finishing Mill 
zone and will be catering power supply to Finishing mill equipment, coilers, 
transfer  bed  and  auxiliaries.  The  substation  will  broadly  consist  of  the 
following: 
a.  2x31.5  MVA,  33  kV/  6.6  kV  HT  substation  to  be  fed  from  33  kV  HT 
Board in MSDS-VII through cables for Mill equipment.  
b.  Substation automation system 
c.  Nitrogen  injection  based  fire  protection  system  for  above  mentioned 
transformers 
d.  On line condition monitoring for above mentioned transformers. 
e.  All  oil  filled  transformer  will  be  kept  in  a  separate  room  with 
independent inlet & outlet ventilation for each transformer room 
f.  Static VAR compensator with detuned filter at 6.6 kV level 
4.9.9    33 kV/6.6 kV HT Substation No.2  
The  above  substation  is  proposed  to  be  installed  close  to  the  Reheating 
furnace  and  will  be  catering  power  supply  to  Reheating  furnace.  The 
substation will broadly consist of the following: 
a.  2x31.5    MVA,  33  kV/  6.6  kV  HT  substation  to  be  fed  from  33  kV  HT 
Board in MSDS-VII through cables for RH Furnace  
b.  Nitrogen  injection  based  fire  protection  system  for  above  mentioned 
transformers  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.52  
c.  On line condition monitoring for above mentioned transformers 
d.  Hydrant system for outdoor switchgear equipment protection 
e.  33 kV feeders for start-up of Coal gasification plant. 
f.  All  oil  filled  transformer  will  be  kept  in  a  separate  room  with 
independent inlet & outlet ventilation for each transformer room. 
4.9.10   Brief  description  of  the  power  distribution  scheme  is  indicated  in  the 
enclosed  Single  Line  Diagram,  drg.  No.  CET  RN  3379  EE1  00  001, 
R=0.  The  SLD  is  indicative.  Smaller  6.6  kV  substations  for  sub-plant 
units like Furnace, Coiler, Pump House, Dividing line, etc. to be located 
nearer to the load will be considered during TS finalisation.  
4.9.11   Around  1000  m3/h  of  make  up  water  will  be  required  for  the  proposed 
HSM. The same will be taken from the existing Lagoon outside the plant 
boundary. Tentative power requirement for necessary treatment facilities 
is around 1000 kW at 415 V. Power at 6.6 kV level for the purpose will 
be tapped from the existing spare 2 nos. feeders of 6.6 kV board of new 
substation at Tarkera pump house. 
4.9.12   Design considerations 
The power distribution network has been designed as a simple radial 
system, with two alternative supply feeders to each load centre. The 
design  of  power  distribution  system  and  selection  of  equipment  will 
be  based  on  the  main  consideration  of  simplicity,  safety,  reliability 
and  ease  of  operation  &  maintenance  as  well  as  convenience  of 
future expansion. 
The  equipment  will  conform  to  relevant  IS/IEC  specifications  and 
code of practice to meet the operational requirements and to ensure 
reliable and trouble free service in the plant. 
4.9.12.1  Basic Design Criteria  
The electrical system is proposed to be designed to suit the following 
power system parameters: 
Sl.No.  Description  Technical parameters 
1.  HT  Power 
supply  
220  kV(  +/-)10%,  50  Hz(  +/-  5%),  15000 
MVA, 
Solidly grounded system 
2.  HT  Power 
supply  
33kV(  +/-)10%,  50  Hz(  +/-  5%),  1800 
MVA    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.53    
Solidly grounded system 
3.  HT  Power 
supply  
6.6kV( +/-)10%, 50 Hz( +/- 5%), 450 MVA
Resistance grounded system  
4.9.12.2  Power supply to various HT & LT Loads / load centres  
1.  All  the  stand  motors 
including  of  Roughing 
Train,  Vertical  Edgers, 
Finishing  stand  motors    & 
all  other  motors  above 
2000 KW 
33kV,  3  ph,  50Hz  as  primary 
source  to  the  different 
converter  transformers  (i.e. 
through unit transformer). 
2.  Motors rated above 200kW 
and up to 2000kW 
6.6 kV, 3 ph, 50 Hz 
3.  Motor  rated  above  90kW 
and  up to 200kW Fed from 
direct  Power  Control 
Centres (PCCs) 
415V, 3 ph, 50 Hz 
4.  Motor  rated  up  to  90  kW 
feed from MCCs 
415V, 3 ph, 50 Hz 
5.  Illumination  and  small 
power 
240 V, 1 ph. 50 Hz 
6.  Control  power  supply  AC 
for  LT  switchgear,  MCC, 
etc. 
240  V,  1  ph,  50  Hz  through 
control transformers 
7.  Control  power  supply  DC 
for HT switchgear 
220V  DC  through  Battery 
bank  
4.9.13   LT Sub-Station 
4.9.13.1  Transformers 
LT substations complete with double ended 1600 / 2000 kVA, 6.6 kv/ 
433 V power distribution transformers, power control centers (PCCs) 
have been envisaged for meeting the power requirements of furnace 
drives, mill auxiliaries, cooling system, air compressors, EOT cranes, 
ACVS  equipment,  illumination  and  welding  network  workshop  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.54  
facilities, water facilities, etc. the proposed power transformers will be 
dry  type  (AN),  winding  insulation  classF  and  will  conform  to  IS-
11171.  
It  is  also  envisaged  that  no  transformers  will  be  placed  in  the  shop 
floor.  All  transformers  will  be  placed  in  rooms  with  approach  road 
suitable for movement of vehicle for transportation of transformers.   
4.9.13.2  6.6 kV HT Isolators  
6.6  kv,  630A  load  break  type  HT  isolators  at  the  primary  side  of 
power  transformers  are  considered.  Further  HT  stop  push  buttons 
will  also  be  provided  in  each  transformer  room  for  tripping  the 
breakers 
4.9.13.3  LT Bus duct 
Secondary side of transformers will be connected to the incomers of 
the  proposed  Power  Control  Centres  (PCCs)  by  non  phase 
segregated LT aluminum bus ducts of adequate rating. 
4.9.13.4  Power control Centres (PCCs) 
The 415 v switchboards will comprise of air circuit breakers, in draw 
out  design  and  multi  tier  formation.  The  switchboard  will  have  two 
incomers  and  one  bus  coupler  breaker  with  provision  for  auto 
changeover  in  the  event  of  loss  of  power  on  any  one  bus  section. 
The  circuit  breakers  will  be  electrically  operated  and  equipped  with 
microprocessor  /  static  type  direct  acting  releases  for  over  load  and 
short  circuit  as  well  as  earth  fault  protection,  indicating  lamps  and 
meters.  All  motor  control  centers  (MCCs),  large  drives  starter  panel 
(above  90Kw  and  up  to  200  Kw)  and  power  distribution  boards 
(PDBs) will be supplied power from the 415v switchboard. The 415v 
switchgear will confirm to IS-8623 and IS 13947. 
4.9.14   Power Distribution Board (PDB) 
4.9.14.1  LT PDBs are proposed to be set up for feeding power supply to various 
auxiliaries  like  EOT  cranes,  hoists,  exhaust  fans,  welding  network, 
machine  shop,  mechanical  and  electrical  workshops,  illumination 
system, ACVS system, etc. 
4.9.14.2  Roller  table  distribution  boards  are  also  considered  for  roller  table 
motors for different zones. 
4.9.15   Converter Transformers 
4.9.15.1  The following type of converter transformers have been considered:  
a.  33Kv / 3.6 kV converter transformers are considered to feed large 
rating stand motors through medium voltage VFD controller.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.55    
33  kV  grade  converter  duty  transformers  for  main  mill  motors  will 
preferably  be  imported  from  reputed  OEM  &  will  be  conform  to  IEC-
61378. 
b.  6.6Kv  /  690V  Converter  transformers  are  considered  to  feed 
motors of 690V through VFD controllers. 
c.  More  over  the  ratings  of  converter  transformers  (of  same  voltage 
ratio) will be of identical kVA rating to extent possible.  
4.9.15.2  Main Features: 
a.  Two winding / 3 winding  
b.  Isolation from power supply network. 
c.  Capable of handling RMS load current drawn by the motor 
d.  Class H Insulation 
e.  OCTC and voltage variation +/- 7.5 % in steps of 2.5% 
f.  Dry  type up  to  2000 KVA and ONAN cooled for more than 2000 
kVA. 
g.  Conforms to IEEE 444, 1973 and IS; 2026,1977 
4.9.16   Shop Electrics and Automation 
The electrical drives, controls and automation equipment, envisaged 
for  smooth  and  efficient  operation  of  new  units  will  be  of  modern 
design  and  with  latest  technology.  The  following  major  equipment 
has been envisaged: 
4.9.17  AC Motors for Mill Stand Application 
The  large  rating  AC  motors  employed  for  stand  application.  These 
motors are considered as Inverter duty AC motors. These motors are 
considered  to  be  fed  from  Converter  Transformers  (33kV  /  3.6kV) 
and MV VFD drives. VFD motors will be fitted with accessories such 
as base plate, pulse encoder, RTDs, space heater etc. These motors 
are  to  be  provided  with  proper  Air  to  water  heat  exchangers  will  be 
provided water cooling system.  
4.9.18   MILL Auxiliaries & Utilities  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.56  
4.9.18.1  The  Squirrel  cage  induction  motors  above  200kW  &  up to 2000  kW for 
auxiliaries system of fixed speed are considered to be fed directly from 
6.6kV level.  
Fixed  speed  motors  above  200  kW,  will  be  started  &  controlled  by 
symmetrically operated thyristor based electronic soft starter.  
However,  in  case  of  motors  above  200kW  like  CA  fan,  ID  fan,  vertical 
edger,  etc  which  may  need  speed  variation  are  proposed  to  be  fed 
through converter transformers (6.6kV / 690V) and 690V LV VFD drives. 
VFD  motors  will  be  fitted  with  accessories  such  as  base  plate,  pulse 
encoders,  RTDs,  space  heater,  etc.  These  motors  are  to  be  provided 
with proper Air or water cooling system. 
4.9.18.2  The squirrel cage induction motors equal or below 200kW is considered 
on  415V.  All the motors equal and above 110kW and up to 200kW are 
considered with 415V Variable Frequency Drives (VFDs).  
4.9.18.3  The  squirrel  cage  induction  motors  below  110kW  is  considered  with 
Direct  on  line.  However,  the  mechanism  needing  speed  regulation  like 
roller table motors, pinch rolls and also other auxiliaries are considered 
with VFD. Motors having VFD controller will be inverter grade. 
4.9.18.4  VFD  motors  will  be  fitted  with  accessories  such  as  base  plate,  pulse 
tacho,  PTCs  etc.  Space  heater  for  motors  above  75  KW  will  be 
provided. 
4.9.18.5  Intermittent  duty,  reversible,  heavy  duty  squirrel  cage  Induction  motors 
for crane duty application are proposed to be installed in all the drives of 
the  EOT  cranes  &  transfer  car.  These  motors  will  be  provided  with 
thermistors  &  will  have  min.  150  starts  per  hours.  All  motors  of  EOT 
cranes  are  considered  to  be  controlled  by  VFD  and  will  be  inverter 
grade. 
4.9.19   AC Drives 
4.9.19.1  For Larger rating drives 
Main AC drives will be IGBT/ IGCT based depending upon the rating 
of  the  drive.  These  main  AC  drives  will  be  digital  drives  with  active 
front  end.  These  high  efficiency  drives  with  DC  link,  will  result  in 
approx unity PF. These drives will have following features: 
  Fully regenerative topology for bi-directional power flow. 
  High output frequency, which may result in smaller motors. 
  Minimum torque ripple 
  Synchronous & induction motor drive capability    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.57    
  Low harmonics 
  Close to unity power factor 
  High efficiency 
  Speed precision  
  Soft water cooled heat exchangers 
4.9.19.2  AC Drives for Mill auxiliaries   
IGBT based VVVF drives with sine coded PWM & vector control are 
envisaged. These drives will be with: 
  High response & control precision 
  Adaptable to actual supply frequency 
  Quick Fault localization 
4.9.20   Intelligent Motor Control Centers (MCCs) 
The  intelligent  MCCs  are  considered  for  feeding  power  supply  for 
controlling  the  auxiliary  drives  of  fixed-speed  mechanisms,  drives  of 
utilities  &  services  equipment.  Each  MCC  will  have  one  single 
incomer  with  requisite  no.  of  out-going  feeders.  MCCBs,  power 
contactors,  thermal  overload  relays,  auxiliary  relays,  meters, 
indicating  lamps  are  considered  to  be  provided  in  MCC  Electronic 
Motor  protection  relay  will  be  considered  for  motor  ratings  greater 
than equal to 55KW. The MCC will be equipped with Signal modules, 
Microcontrollers and profibus interface cards. 
4.9.21   Electrics of Miscellaneous items 
It is proposed that Hydraulic power packs, lubrication system, pumps 
for  emulsion,  compressors,  air  conditioning  &  ventilation  system, 
equipment  for  mechanical  &  electrical  workshop,  water  facilities 
system  will  be  supplied  complete  with  soft  starters,  Vacuum 
contactors etc. 
4.9.22   Sensors/ Field Devices and measuring devices 
Field  devices  and  sensors  like  pulse  encoders,  proximity  switches, 
HMDs,  limit  switches,  level  switches,  load  cells,  etc.  as  required  for 
feedback, inter-locking and sequencing have been considered. 
4.9.23   Control Desk / Local control stations (LCS)  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.58  
A  number  of  desks,  LCB  and  pulpits  are  envisaged  for  control  of 
lines/  mills  and  utilities.  Pulpit  will  be  structural,  aesthetically 
designed  with  false  ceiling,  false  floors,  decorative  lighting  and  will 
have  toughened  glass  front.  All  the  pulpits  will  be  air-conditioned. 
Desks will be floor mounted and will house HMI PCs in additions to 
other controlling devices. LCSs will be wall-mounted type and will be 
used for local control of different mechanisms, pumps, fans, etc. 
4.9.24   Uninterrupted power supply (UPS) 
Uninterrupted power supply (UPS) of required rating will be provided 
in  different  unit  for  supplying  power  to  automation  system  (CPU), 
controllers and in some cases important instrumentation. UPS will be 
of  digital  type  with  PWM  technology  based  in  IGBT.  This  will  be  hot 
redundant  type  with  a  provision  to  power  change  over  through  a 
static  switch.  The  batteries  will  be  of  Ni-Cd  type  along  with  battery 
charger.  Distribution  board  for  distributing  uninterrupted  power 
supply is also considered. 
4.9.25   Automation System 
Two levels of automation are envisaged. Basic automation (Level-1) 
and Process automation (Level-2). 
4.9.25.1  Basic automation 
The  basic  automation  ie  level  -1  comprises  of  Technological  control 
system  (TCS),  PLC  &  drive  system  HMI  stations  &  measuring 
instruments  suitably  integrated  on  high  performance  local  area 
network,  which  controls  the  actuating  system  and  ensures  fast 
dynamic performance. This level will consist of all closed loop & open 
loop  controls,  regulatory  controls,  logic  &  sequential  controls, 
dialogue  &  display  for  operators,  process  interface,  alarm  &  extent 
registration etc. 
4.9.25.2  Technological Control system (TCS) 
Complete  technological  functions  of  the  mill  like  Mill  stand  motors, 
screw  down  motors,  mechanical  equipment  &  instruments  of  HAGC 
system  are  proposed  to  be  controlled  and  monitored  by  dedicated 
multitasking process controllers. These controllers will also cater the 
following functions: 
  Reference generation, Sequencing & interlocking 
  Interfacing with control console & drives 
  Fault annunciation 
  Real time calculations    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.59    
4.9.25.3  Programmable Logic Controllers (PLC) 
Apart  from  TCS,  Programmable  logic  controllers  (PLCs)  are  also 
envisaged  for  the  functional  control  of  various  auxiliaries  like 
Reheating  furnace  ,  water  management,  air  compressors,  oil 
lubrication,  roller  tables  etc.  Wherever  necessary  remote  I/Os  are 
envisaged to provided.  
4.9.25.4  Human Machine Interface (HMI) 
Visualization system will be through PC based HMI terminals. These 
have  been  envisaged  for  control  &  operation  of  plant.  Different 
screens  will  be  provided  in  these  PC  terminals  showing  different 
sections of the plant and their status graphically. The graphic display 
will be interactive type. These screens will be programmable through 
engineering stations. The HMIs will have process diagnostic system 
to  provide  status  &  fault  signals  of  the  process  along  with  process 
error display. 
4.9.26   Cables 
4.9.26.1  HT Power Cables 
  220  kV  single  core  XLPE  insulated  welded  corrugated 
aluminium-alloy  sheathed  with  copper  conductor  conforming 
to IEC 68040 cables from switchyard to 220 kV GIS, from GIS 
to 160 MVA, 220 kV/ 33 kV transformers. 
  220  kV  earthed  grade,  XLPE  insulated  armoured  aluminium 
conductor  cables  from  switchyard  to  the  primary  of  33kV/  3.6 
kV Converter Transformers. 
  33kV  earthed  grade,  XLPE  insulated  armoured  aluminium 
conductor  cables  from  33  kV  GIS  to  30  MVA,  33  kV/  6.6  kV 
transformers. 
  33kV  earthed  grade,  XLPE  insulated  armoured  aluminium 
conductor  cables  from  switchyard  to  the  primary  of  33kV/  3.6 
kV Converter Transformers. 
  6.6 kV unearthed grade, XLPE insulated armoured aluminium 
conductor  cables  are  considered  for  supplying  power  to  the 
primary  of  6.6kV  /  433V  transformers  at  different  LT  Sub-
stations,  to  converter  transformers  (6.6kV  /690V)  and  also  to 
6.6kV HT motors. 
  3.3kV  grade  unearthed  grade,  XLPE  insulated  armoured 
copper  conductor  cable  from  medium  voltage  (MV)  VFD 
controller to the large rating stand motors.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.60  
  HT power cables will conform to IS: 7098. 
  Minimum  size  for  6.6  kV  will  be  185  sq.mm.  Short  circuit 
duration of 0.25 S will be considered for cable sizing 
4.9.26.2  LT Power Cables & Control Cables 
LT power cables for 415 V system will be heavy duty, 1.1 kV grade, 
XLPE  insulated  PVC  sheathed  aluminum  conductor,  armoured.  The 
control cables will be multi strand copper conductor, XLPE insulated 
and  PVC  sheathed  with  minimum  cross  section  of  2.5  sq.  mm  for 
control  voltage  circuit  and  4.0  sq.  mm  for  power  circuit.  The  LT 
power and control cable will confirm to IS-1554-1988. 
4.9.26.3  Special cables 
Screened  cables,  signal  cables,  coaxial  cables,  etc  are  also 
considered for the project. 
4.9.26.4  Cabling 
Power  inside  the  plant  will  be  distributed  through  cables  to  various 
premises  through  RCC  cable  tunnels  (of  size  2.5mx  2.5m  with  600 
mm  cable  tray  on  both  sides  of  tunnel)  and  through  RCC  cable 
trenches.  GI  pipes/  hume  pipes  will  be  used  at  road/  rail  crossings. 
Inside  the  substations  and  covered  premises,  the  cables  will  be  laid 
in  basement  or  in  concrete  trenches  (over  cable  supporting 
structures/  cable  trays)  or  on  columns  and  other  structures.  Power 
cables will be laid on ladder type trays, whereas control cable will be 
laid on perforated cable trays. 
4.9.27   Illumination  
4.9.27.1  For  supply  of  various  illumination  loads  in  the  sub-station  building, 
provision  of  Main  lighting  distribution  boards  (MLDBs)  has  been 
considered.  These  MLDBs  will  be  installed  in  HT  /  LT  substation  room 
and will be fed from the 415 V switchboard. MLDBs will supply power to 
the  various  Lighting  Distribution  Boards  (LDBs)  installed  in  various 
buildings. Further the LDBs is considered to supply different Sub-lighting 
Distribution  Boards  (SLDBs).  Lighting  fixtures  is  considered  to  be  fed 
from SLDBs. 
4.9.27.2  The  internal  illumination  of  low  roof  buildings  will  be  with  fluorescent 
tube light fittings whereas for shops as well as high roof building will be 
illuminated  with  HPSV  lamp  fittings.  Wherever  high  colour  rendering  is 
required  (low  colour  distortion)  metal  halide  lamp  fittings  will  be  used. 
For  mill  bay  illumination  High  bay/  medium  bay  lighting  fixtures  are 
considered.  Average  illumination  inside  the  shop  building  will  be  100-
150  lux,  however  the  illumination  level  in  control  rooms  will  be  300  lux.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.61    
Illumination  in  open  yard  and  area  illumination  will  be  provided  with 
HPSV flood light fittings. The average illumination level will be 15 to 30 
lux for outdoor illumination. The use of energy saving, high power factor 
lamp  fittings  will  be  preferred.  The  code  of  practice  for  illumination 
system is considered as per IS: 3646. 
4.9.28   Welding System 
For ease of maintenance 3 ph welding sockets suitably located along 
length  of  the  bay  and  near  other  premises  are  envisaged.  Welding 
distribution  boards  (WDB)  are  considered  for  feeding  the  welding 
receptacles. 
4.9.29   Harmonic filtering system 
In the proposed plant harmonic filtering system is also considered for 
suppressing of harmonics. 
4.9.30   Air conditioning & ventilation system (ACVS) 
4.9.30.1  Air  conditioning  system  for  GIS,  6.6  kV  switchgear  rooms  including 
cable vaults suitable for upto 38
0
 C has been considered.  
4.9.30.2  Ventilation  of  MCC  rooms,  basement  floors,  LT  switch  gear  rooms  are 
envisaged.  Areas  of  ECR  housing  electronics/  automation  equipment, 
UPS,  telephone  exchanges,  weighing  panels  and  all  pulpits  will  be  air-
conditioned. Complete electrics of ACVS has been considered. 
4.9.31 Earthing 
4.9.31.1  An  outdoor  protective  earthing  network  made  of  number  of  electrode 
stations  interconnected  by  means  of  GI  strip  earth  continuity conductor 
are  envisaged  to  be  provided  around  the  main  shops  and  auxiliary 
buildings.  A  low  earth  resistance  is  envisaged  to  be  obtained  by  using 
sufficient number of earth electrode. Main earth rings effectively bonded 
to the outer ring will be provided inside the electrical control and building 
structures. Parts of electrical equipment and machinery, not intended to 
be alive, are envisaged to be connected to the main earth rings by two 
separate  and  distinct  earth  connections  in  accordance  with  Indian 
Electricity rules and as per IS-3043. 
4.9.31.2  A  separate  electronic  earthing  system  will  be  provided  for  the  earthing 
of  electronic  equipment  such  as  PLCs  &  drives.  Special  earthing, 
Foundation  earthing  if  any,  will  be  as  per  suppliers  practice  / 
recommendation  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.62  
4.9.32   Lightning Protection system 
Lightning  Protection  system  will  be  provided  for  protection  of  plant 
and equipment against lightning. The design of this system will be as 
per  IS:  2309-1969.  The  lightning  masts  /  rings  /  down  leads  will  be 
connected  to  earthing  pits  specifically  provided  for  lightning 
protection. 
4.9.33   Crane and Crane trolley lines/ electric hoists 
4.9.33.1  Electrics  of  all  EOT  Cranes  and  electric  hoists  are  considered.  All  the 
motors of the EOT cranes is considered with VFD controllers and radio 
remote controls. Electric hoists are considered with all electrics including 
festoon cable arrangement. 
4.9.33.2  Power to the electrical overhead travelling (EOT) cranes are envisaged 
to  be  fed  through  the  crane  trolley  line  system.  The  crane  trolley  lines 
are  envisaged  to  run  longitudinally  along  crane  girder,  suitably 
supported  on  intermediate  and  sectionalizing  brackets  and  are 
envisaged to be fed from nearby power distribution boards.  
4.10    CIVIL WORKS 
4.10.1  The  following  are  the  major  civil  engineering  jobs  envisaged  for  the 
project 
a.  Construction  of  RCC/Pile  foundations  and  all  civil  works  for  all 
machine  /  equipment,  reheating  furnace,  chimney,  mill 
equipments and its drive, transfer car track if any, auxiliaries and 
other technological structures to be installed in the proposed Hot 
Strip Mill. 
b.  Construction  of  RCC/Pile  foundations for all steel structural shed 
like  slab  yard  bay,  furnace  charging  bay,  furnace  bay,  mill  bay, 
motor  bays,  coil  storage  and  dispatch  bay  ,  roll  shop,  shearing 
line and dispatch bay etc. for the proposed Hot Strip Mill 
c.  Construction  of  RCC  framed  with  brick  cladding  HT/LT 
Substation,  PCC  Room,  MCC  rooms  Transformer  Room,  ECR 
buildings, Compressor buildings, PLC and Control rooms etc.  
d.  Construction  of  RCC  foundation  of  switch  yard  structures 
including  RCC  cable  trenches  with  RCC  Pre-Cast  cover 
slabs/chequered plates as per requirement 
e.  Civil works for soft water plant, chilled water plants etc. 
f.  RCC  framed  and  RCC  walled  underground  cellars  along  with 
RCC foundations for various equipment   etc.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.63    
g.  Construction of RCC framed with brick cladding hydraulic rooms, 
heat  exchanger  rooms,  filter  house,  rooms  for  AHU,  ventilation 
rooms,  booster  house,  blower  house,  different  rooms  for 
instrumentation and automation etc.  
h.  Construction  of  RCC  framed  with  brick  cladding  roll  shop, 
mechanical  and  electrical  shops,  Product  Testing  Laboratory, 
Pump  House,  DG  room,  stores,  security  posts,  watch  towers, 
Administrative  Building,  Shift  room,  rest  room,  utility  rooms  & 
canteen  building  with  toilet  and  drinking  water  facilities, buildings 
for Oil & lubrication systems, air condition and ventilation system 
etc. 
i.  Construction  of  RCC  foundation  for  Compressor,  booster, 
blowers,  pumps,  A/c  and  ventilation  equipment,  electrical 
equipments,  equipments  for  fire  fighting  and  water  circulating 
system etc. 
j.  RCC overhead soft and make up water tanks 
k.  RCC cooling towers 
l.  Construction  of  trestle  foundations  for  different  pipe  lines, 
foundations for vehicle parking shed etc. 
m.  Construction  of  RCC  floor  in  new  shed  and  hard  stand  as  per 
requirement 
n.  Construction  of  flue  duct/tunnels  as  per  requirement.  RCC 
Sumps, Settling tanks, channels, scale bins and pits, etc 
o.  Construction of RCC foundation for furnace oil day tank. 
p.  Construction  of  RCC  framed  with  brick  cladding  pump  house  at 
old HSM. 
q.  Construction of RCC foundations for furnace oil pipe line supports 
from old HSM to new HSM. 
r.  Construction  of  new  railway  track  and  connection  with  existing 
network. 
s.  Construction of approach roads to all new units for operation and 
maintenance purposes and connection to plant main road.  
t.  Suitable  Surface  drainage  around  the  new  buildings  /  facilities 
and  the  entire  area  and  connection  of  the  same  to  the  existing 
storm  water  drainage  system.  Plant  drainage  system  including 
culverts is also considered  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.64  
u.  Area survey and soil investigation has been envisaged and it will 
be carried out in separate package. 
v.  Bush  and  jungle  clearance,  site  leveling,  land  and  area 
development  for  the  areas  where  the  new  units  are  to  be 
installed. 
w.  Dismantling  of  existing  RCC,  PCC,  Brickwork,  railway  lines  etc. 
as per site requirement. 
x.  Existing  over  head/  under  ground  communication  lines  are 
envisaged to be  suitably protected/diverted 
y.  Dismantling of existing boundary wall and diversion of connecting 
road between Plant and NH 
z.  New  RCC  framed  boundary  walls  with  masonry  cladding  and 
barbed  wire  anti  climbing  arrangement  with  necessary  entry  and 
exit gates.  
aa. Water harvesting and green area as per requirement 
The sizes, finishes, doors, windows, rolling shutters, floors, ceilings 
etc of the buildings/rooms will be as per technological and process 
requirements  
4.10.2   Land & site development 
The  proposed  HSM  is  planned  on  east  side  of  the  present  BF  Slag 
Granulation  Plant  in  the  slag  dump  area  partly  and  by  the  side  of 
National  highway.  The  proposed  plant  area  is  surrounded  on  north 
side  by  existing  MSDS  2,  east  side  by  existing  boundary  wall  of 
plant, south side by hillocks and west by National Highway. The part 
of new mill is planned over the existing BF/SMS slag dump. The slag 
dump  is  still  operated  by  Rourkela  Steel  for  dumping  BF  slag  and 
rubbish  materials  etc.  The  area  for  the  proposed  plant  is  undulated 
and having the slope towards both north and south side.  
The proposed site has huge slag heap and there are low lying areas 
also.  The  facilities  envisaged  in  this  report  pertain  only  to  the  units 
inside the boundary of the hot strip mill. 
The  water  treatment  plant  has  been  envisaged  to  installed  on  the 
space available  in  between  the Lagoon and National Highway. Area 
requirement  will  be  to  the  tune  of  100mx200m,  which  will  be 
developed accordingly.  
Other  infrastructures  like  external  linkage  railway  lines,  etc 
need  to  be  studied  by  specialized  agencies.  External  railway 
connection  is  to  be  taken  up  with  railway  authority.  However,    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.65    
cost  towards  these  has  been  assumed  considering  certain  rail 
length. 
Topographical  survey  of  the  land,  soil  investigation,  boundary  wall, 
entry  gates,  drainage  of  the  land,  etc  are  all  included.  Leveling  & 
terracing  of  the  plant  area  will  be  done  taking  care  of  the  needs  of 
the  different  units,  drainage  requirement,  natural  drainage  system, 
etc.  The  leveling  will  be  done in  such  a  way that cutting &  filling  will 
be optimized. 
The  present  finished  ground  level  of  Plate  mill  has  been  kept  as 
+214.6 m AMSL. It is considered that the same FGL will be kept for 
new HSM 
As  per  eye  estimation,  it  is  estimated  that  about  2.0  million  cu.m  of 
Slag for site-filling will be required for the project. Further, the project 
also will  involve removal and disposal of 2.1 million cu.m of BF slag 
out of total 4.1 million cu.m of Slag. Since this is a massive volume, 
advance  action  will  have  to  be  taken  for  undertaking  the  site  filing  / 
grading work and other development work. 
4.10.3    General Layout 
The  layout  of  the  new  HSM  will  be  such  that  the  movement  of  raw 
materials,  semi  finished  goods,  and  finished  goods  will  follow  a 
logical  sequence.  The  incoming  raw  materials  will  be  received  from 
the  nearest  road/rail  head  and  will  be  dispatched  through  rail/road 
network.  There  will  be  provision  for  incoming  railway  rakes,  truck 
parking space, weigh bridges, etc. to cater to the needs of the logical 
movements. 
The layout indicated in drawing no. CET RN 3379 CE0 00 001 R=0 
and enclosed in this FR is preliminary and will be finalized during DE 
stage  considering  technological  requirement,  survey  drawing  and 
reports  by  specialized  agencies  for  external/internal  railway 
connection. 
4.10.4   Rail and Road network 
Movements  of  incoming  raw  materials  etc  and  dispatch  of  finished 
goods, etc will all be done by railway/road system. Movement of semi 
finished goods; inter plant transfers, and disposal of waste materials 
like scrap, scales etc. will be done by roadway/ railway system as per 
system requirement.  
In  laying  the  tracks,  norms  of  Indian  Railways,  as  formulated  by 
RDSO,  with  regard  to  radius  of  curve,  sizes  of  switches,  distance 
between  tracks,  gradients,  clearances  on  the  sides  and  above,  etc. 
will  be  followed.  Signaling  and  communication  facilities  with  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.66  
interlocking arrangement will be provided. Over head electric traction 
will  be  provided  to  enable  Indian  Railways  electric  locos  coming 
inside  the  plant  and  will  be  limited  to  the  yard  area  only.  Proper 
drainage  system  will  be  provided  along  the  tracks  and  yards.  Level 
crossings  with  drop  gate  arrangement  will  be  provided  at  rail-road 
crossings 
Generally  the  roads  will  be  5  m/7  m  wide.  Berm  of  proper  width  will 
be  provided  for  all  roads.  Road  drainage,  arboriculture  etc  will  be 
duly  taken  care  of.  Road  and  rail  crossings  will  be  protected  for 
safety  of  men,  road  vehicles  and  rail  traffic  with  proper  signaling, 
gates,  visual  and  sound  alarms.  Wherever  heavy  movement  of  rail 
traffic  is  envisaged,  road  and  rail  gate  separators  will  be  provided. 
Proper  road  approaches  to  all  units  will  be  provided.  In  addition 
peripheral road along the inside of the boundary wall be provided for 
patrolling by security personnel. Necessary service corridor on either 
side  of  main  roads  will  be  earmarked  for  laying  of  underground 
facilities like cable tunnel, drains, water pipe lines, gas lines, power & 
communication cables, etc 
Logistic for Rail Transportation  
The  finished  products  i.e.  sheets  and  coils  from  new  HSM  will  be 
dispatched to two destinations  
a.  Internal destination i.e. to Cold Rolling Mill, Pipe Plant Silicon 
Steel Mill and dividing Line of RSP. 
It is envisaged that about 1550 t of HR coils will be dispatched 
per  day  from  new  HSM  to  different  internal  destinations 
mentioned  above.  The  mode  of  transportation  will be  through 
internal railway wagons. 
b.  External destination i.e. outside RSP through railway 
exchange yard. 
It  is  envisaged  that  about  6700  t  of  finished  product  will  be 
dispatched  per  day  from  new  HSM  to  railway  exchange  yard  for 
different  external  destinations.  The  mode  of  transportation  will  be 
through Indian railway wagons. 
It is envisaged that there will be three bays in which finished products 
will  be  loaded  to  railway  wagons  for  different  destinations  as  stated 
above from new HSM. The loading bays are: 
Coil Yard -1, 
Coil Yard -2 and 
Sheet Shearing Line.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.67    
It  is  proposed  to  accommodate  half  rake  of  railway  wagons  in  each 
loading bay of new HSM.  
4.10.5   Buildings 
Main  administration  building,  other  departmental  offices,  spot/shop 
laboratory,  computer  building,  Security  building  etc,  canteen 
buildings,  etc  will  be  provided  as  per  requirement.  Each  office 
building will be provided with adequate parking facilities and required 
amenities. 
4.10.6   Statutory Requirement 
A  separate  Report  will  be  prepared  by  specialized  agencies  for 
Indian railways approval for the new railway system for HSM and its 
connectivity  from  Indian  railways.  Further,  Rail  Traffic  clearance 
(RTC) also will be obtained from railways for the proposed traffic 
Provision  for  green  belt  and  rainwater  harvesting  will  be  kept  in 
layout. 
4.10.7   Civil Works 
4.10.7.1  General 
The  civil  works  will  comprise  land  development,    site  preparation& 
leveling,  design  and  construction  of  building  structures,  shed 
structures,  underground  structures,  foundations  for  equipments,  its 
auxiliaries,  foundation/civil works for all technological units, electrical 
and  power  distribution  system,  utility  and  services  facilities,  
ventilation  and  de-dusting  system,  instrument  and  control  system, 
water  supply  facilities,  fire  fighting  and  detection  system,  floors, 
surface  channels,  tunnels,  drainage  and  sewerage  network,  cellar 
structures,  roads,  railways,  hard  stand,  modification  of  boundary 
walls    and  new  boundary  walls  etc.  and  all  other  infrastructural 
facilities for HSM. 
Dismantling  of  existing  civil  buildings  and  all  other  civil  foundation 
has also been considered 
Dismantling  of  existing  plant  boundary  has  been  considered. 
Diversion  of  connecting  road  between  NH  and  plant  has  also  been 
considered 
Soil characteristics and site data 
The site is filled up with heterogeneous slag fill of 1m to 13 m depth 
whose  N  values  are  not  representative  of  the  consistency  of 
material.  In  absence  of  soil  report  and  the  nature  and  magnitude  of 
proposed  construction,  bored  cast  in  situ  RCC  piles  has  been 
considered.  The  bottom  of  pile  will  be  embedded  in  weathered  rock  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.68  
and  it  is  assumed  that  the  same  will  be  available  at  8-10  m  depth 
below virgin soil. 
Further,  the  allowable  bearing  capacity  of  soil  is  assumed  to  be  10 
ton/sq.  meter  at  a  depth  of  3m  from  virgin  soil.  Moreover,  ground 
improvement by removing slag and fill up with granular material has 
been considered. 
Water Table has been considered to be at 1 meter below the finished 
terrace level 
Soil  characteristics  will  be  known  after  the  soil  investigation  is 
got done in the proposed area for HSM. This is required prior to 
detail  engineering.  Type  of  foundations  to  be  adopted  for  each 
equipment/building/structure  will  be  decided  based  on  the  soil 
characteristics  at  that  particular  location.  Independent  foundations, 
combined  footings,  raft  foundations  or  piling  will  be  adopted  to  suit 
the quantum of load and the Safe Bearing Capacity of soil. For piling, 
mostly bored cast in situ piles will be used. 
4.10.7.2  Site surveying and leveling 
Contour  survey  of  the  site  needs  to  be  carried  out  first.  This  is 
required  prior  to  finalization  of  detail  engineering.  The  extent  of 
site  leveling  will  be  decided  based  on  the  level  difference  between 
the  highest  and  lowest  places  and  also  keeping  in  view  the 
connection  to  the  nearest  railway  network.  Terracing  will  be  done  in 
such  a  way  that  cutting  and  filling  will  be  optimum.  Drainage  of  the 
plant area will also be suitably planned. 
4.10.7.3  Advance Action 
  Soil investigation and survey 
  Bush and shrub clearance, site preparation, site leveling and 
land development work 
4.10.8   Design Philosophy & Guideline 
i) Foundations 
In  general  pile  foundations  have  been  envisaged  based  on  the  soil 
report of nearby plate mill. However, on the basis of actual report of 
soil  investigation  for  HSM,  which  is  proposed  to  be  carried  out 
separately  before  detail  engineering,  the  final  selection  of  type  of 
foundation will be made.  
ii) Plain Cement Concrete & Reinforced Cement Concrete    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.69    
All  RCC  structures  will  be  designed  as  per  IS:  456-2000.In  general, 
cast-in-situ concrete will be used for all RCC works and the minimum 
grade  of  concrete  will  be  M-25C.  Jigs,  fixtures  will  be  used  to  fix  all 
anchor  bolts,  inserts  etc.,  wherever  required.  Grade  of  concrete  for 
mud mat has been envisaged as M-10B. 
iii) Building Materials 
Cement 
Ordinary  Portland  cement  conforming  to  IS  12269-1987  [53  grade 
cement], IS:8112-1989 [43 grade cement] and Portland slag cement 
conforming  to  IS:455-1989  will  be  used  in  all  constructions.  Special 
types  of  cements  will  be  used  wherever  required  for  specific 
applications. 
Reinforcing steel 
Reinforcing  steel  conforming  IS:  1786-2008  with  minimum  yield 
strength  of  500  N/mm
2
  will  be  used  and  as  far  as  possible  will  be 
from SAIL. 
Aggregates 
Locally  available  best  quality  Coarse  and  fine  aggregates  will 
conform to IS:383-1970 and  
Bricks 
Building bricks to be used in the works will be common building burnt 
clay bricks/ Fly ash bricks & locally available best quality conforming 
to  the  requirements  of  IS:1077-1992  [burnt  clay  bricks]  or  IS:13757-
1993 [Fly ash bricks] depending on the availability locally. 
iv)  Doors and Windows 
Steel/Aluminum  doors,  window  and  ventilators  with  glass  panes  will 
be as per IS: 1038: 1983/ INDAL specifications. 
v) Road  
Flexible pavement/ road have been envisaged. Thickness of different 
layer  of  road/  pavement  will  be  adequate  for  traffic  intensity  and 
imposed loading.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.70  
vi)  Railway Track 
Railway  track  materials  and  construction  will  be  as  per  specification 
of Indian Railway Standard (IRS). The rail for the railway track will be 
of section weighing 60-kg/ m length and conforming to IRS T-18. The 
sleeper density will generally be M+7 where m is the length of rail (13 
meters). In general pre-stressed concrete sleepers/Steel sleeper will 
be laid over crushed stone ballast.  
Abstract  of  specifications  of  major  civil  work  has  been  assumed  as 
follow:   
  R.C.C        :M20C  or  M-25C  or  M-30C  as  per 
requirement 
  P.C.C        :M-10B/M10C 
Anchor pocket grouting   :M-30D  with  anti-shrinkage 
compound/epoxy 
Flooring        :RCC/PCC (as per design) 
Floor finish      :Ironite topping or IPS as per requirement 
Brick masonry work in C.M  :1:6 
Cement plaster for walls/ceiling 
/drain        :1:6/1:4/ 
Inside finish for buildings    : White washing/ Distemper 
Outer finishing for buildings  : Cement paint   
Plinth protection     :PCC 100mm thick over brick on flat 
          around the buildings.(1m wide). 
Drainage        :Proper drainage will be provided 
around  the  work  area.(Peripheral  drain 
will be provided around buildings).  
  Sewer/faecal sewer line  :  To  be  laid  as  per  requirement  &  to  be 
connected septic tank and soak pit. 
  Drinking water line  :  To  be  laid  as  per  requirement  &  to  be 
connected with the existing system. 
  Roads  :  Flexible/Rigid  pavement  with  shoulder  on  either  side  as  per 
drawings  and  IRC/MORTH  specification.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.71    
It  will  be  connected  to  existing  road 
network with proper logistic.  
  Railway Track   Will be as per IRS specification. It will be connected to 
existing rail network with proper logistic. 
4.11    STRUCTURAL WORK 
4.11.1  The  scope  of  structural  steelwork  for  Installation  of  Hot  Strip  Mill  at 
Rourkela Steel Plant is as below:- 
Fabrication, erection, painting, testing and commissioning of all structural 
steelwork required.  
The structural steelworks envisaged broadly includes:  
i.  Multibay Structural Building for;  
Sl.no.  Description 
Approx. Dimension 
1  Slab Yard(2 Bays) 
220*30 m  
2  Furnace Charging  110*36 m 
3  Furnace 
110*30 m  
4  Mill 
660*30 m 
5  Roll shop 
336*36 m 
6  Motor Bay-1 
24*24 m 
7  Motor Bay-2 
24*24 m 
8  Motor Bay-3 
70*24 m 
9  Coil  Storage  &  Dispatch 
bay(2-Bays) 
400*36 m 
10  Shearing  Line  & 
Dispatch 
400*36 m  
ii.  Control-Room & Control-Pulpits as required.  
iii.  Platforms, Staircases & Handrails as required.  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.72  
iv.  Supporting structures for pipe lines for furnace oil, compressed air, 
and water. 
v.  Shed for Compressed air station 15X12m. 
4.11.2  Steel structural work will include columns, column bracings, beams, stairs, 
platforms, ladders, handrails, walkways, claddings, supports for piping & 
working platforms, storage water tanks and chimneys. 
4.11.3  Design Consideration 
4.11.3.1  All steel structures will be designed to meet the technological requirement 
with  due  consideration  to  the  existing  plant  and  facilities  apart  from 
technological loads indicated by the equipment manufacturer /supplier to be 
supported on steel structures. 
4.11.3.2.  Design of steel structures will be as per IS 800:1984.  
4.11.3.3  Self weight and superimposed loads for the design will be according to IS 
875:1987(relevent parts). 
4.11.3.4  Structures will be designed for wind or seismic forces as applicable. Seismic 
loads will be taken from IS 1893:2002. 
4.11.3.5  Material for structural steel will be as per IS 2062:2006 (Grade-A & B) as 
applicable. Chequered plate will conform to IS 3502:1994. Steel tubes for 
handrail will conform to IS 1161:1998. High strength micro alloyed steel 
SAIL-MA: 300/350/410/450 where the numbers indicate the yield strength 
in MPa will be used as per technological requirement. 
4.11.3.6  In  general,  steel  structures  will  be  of  welded  construction.  The  welding 
procedure  will  conform  to  IS  816:1969  and  IS  9595:1996.  Covered 
electrodes will conform to IS 814:2004. 
4.11.3.7  Fabrication and erection of steel structures will conform to IS 800:1984 and 
tolerances of fabrication will be as per IS 7215:1974.Tolerances for erection 
will be as per IS 12843:1989.  
4.11.3.8  All the structures will be duly inspected and made defect free.  
4.11.3.9  All structures will receive two coats of zinc phosphate in phenolic alkyd 
medium primer (DFT/coat 35 micron) of approved make and finishing paint 
on erected structures will be two coats of synthetic enamel paint(DFT/coat 
30 micron) conforming to IS 2932:2003. 
4.11.3.10  Galvanized corrugated sheets will be as per IS 277:2003. 
4.11.3.11  Plastic  translucent sheets made from thermo-setting polyester resin (glass 
fibre reinforced) will be as per IS 12866:1989.    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 4.73    
4.11.3.12  Pre-painted  galvanised  steel  sheet/Polyester-coated  galvanised  steel  sheet 
will  be  of  IS  14246:1995  made  from  cold  rolled  steel  conforming  to  IS 
513:2008, zinc galvanised (hot dipped) as per IS 277:2003. 
4.11.3.13  The steel chimney will be designed as per the provisions of IS 6533:1989. 
4.11.3.14  Structural  steelworks,  if  any,  to  be  dismantled/strengthened,  are  to  be 
properly  identified.  Adequate  protection  is  to  be  taken  during 
dismantling/strengthening in order to ensure safety/stability of the adjoining 
existing structures. 
4.12    MAN POWER & TRAINING 
A  total  of  around  690  manpower  including  90  executives  and  600 
non  executives  will  be  required  for  operation  &  maintenance  of  the 
proposed  Hot  Strip  Mill  along  with  associated  facilities.  Training  to 
the  man  power  will  be  provided  by  the  Suppliers  in  the  area  of 
operations,  maintenance,  automation,  process  simulations, 
hardwares,  softwares,  etc.  180  man  weeks  of  training  at  suppliers 
premises  and  similar  Hot  Strip  Mills  has  been  considered  besides 
training at RSPs site.     
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 5.1     
5  PROJECT IMPLEMENTATION 
5.1  COMPLETION SCHEDULE 
It  is  estimated  that  the  project  will  be  completed  in  42  months  from 
the  date  of  sanction  and  36  months  from  the  date  of  stage-II 
approval.  The  activity-wise  implementation  schedule  is  enclosed  at 
Annexure-5.1-1 and 5.1-2.  
5.2  IMPLEMENTATION STRATEGY 
5.2.1    The complete project is proposed to be implemented under following 
packages : 
 Pkg-1 :  Soil Investigation & Survey 
This package will be executed in advance. 
Pkg-2 :  Site development 
Pkg-3 :  Rail network 
This is to be done under a specialized agency 
Pkg-4:  HOT Strip Mill  
This  package  will  include  all  the  equipment  including 
auxiliaries,  electrics,  utilities,  material  handling,  etc. 
Civil  foundation  of  all  equipment  and  other  associated 
civil  work  will  be  under  this  package.  Construction  of 
bays,  rooms,  buildings,  etc.  will  also  be  under  this 
package.  Major  scope  under  this  package  is  indicated 
below :  
  Reheating Furnaces with auxiliaries 
  Mill proper with auxiliaries 
  Sheet Shearing Line 
  Roll Shop 
  Water supply & Utilities 
  Automation system 
  Power Supply Facilities & Electrics 
  Eqpt. Foundation & other civil work 
  Cranes & material handling 
  Construction of bays, rooms, buildings, etc.     
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 6.1    
6.0    FINANCIAL ANALYSIS 
6.1    Capital Cost Estimates: 
6.1.1      The  capital  cost  estimate  for  the  project  Installation  of  a  Hot  Strip 
Mill, RSP has been estimated to be Rs. 3879.42 crore, net of cenvat 
credit  of  Rs.  356.03  crore  and  inclusive  of  IDC  component  of  Rs 
192.06  crore.  The  capital  cost  estimate  envisages  expenditure  in 
foreign  currency  to  the  tune  of  
Rs. 1231.37 crore. The capital cost estimate (summary) is appended 
at  Annexure-6.1.1-1  and  the  Capital  cost  estimate  at  Annexure-
6.1.1-2.  Basis  of  estimate  and  volume  of  work  is  appended  at 
Annexure 6.1.1-3 and 6.1.14 respectively.  
6.1.2    The  cost  estimates  are  based  on  available  in-house  information, 
budgetary quotations and costs extracted from similar projects being 
executed  in  SAIL  plants,  suitably  adjusted  to  reflect  current  prices. 
The base date for the estimate is 1st Quarter of 2012. FE parity has 
been  taken  as  1Euro  =  Rs  65.82.  The  estimates  do  not  include  any 
provision for future escalation or foreign exchange fluctuations.  
6.1.3      Necessary  provisions  have  been  made  in  the  estimates  as  per  the 
details given below: 
i)  Taxes and duties: 
1.  Excise duty @ 12.36% on basic cost of indigenous 
equipment and structures. 
2.  Customs duty @ 5% on CIF cost of imported equipment 
and landing charges, CVD @ 12.36% on CIF & landing 
cost of imported equipment and CD and ADC @ 4% on 
CIF cost of imported equipment & landing charge , CD, 
CVD and educational cess on CD & CVD. 
3.  CST @ 2% on basic cost of indigenous equipment and 
structures and excise duty amount on the same. 
4.  WCT/VAT@ 13.5% on 67% of civil work & 30% of erection 
work. 
5.  IT (grossed-up) @ 11.80% on foreign services. 
6.  Service tax @ 12.36% on erection, 33% of civil work, 
foreign /indigenous design engineering and services, IT and 
freight & insurance. 
7.  Educational cess @3% on Customs duty, Counter veiling 
duty and Additional Duty on Customs. 
8.  Entry tax @ 2% on supplies 
ii)  Ocean Freight & Insurance Charges: 
@ 7% on FOB price of imported equipment. 
iii)   Freight & Insurance charges:  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 6.2  
 @ 2% of basic cost of indigenous equipment and @9% of the 
basic cost of indigenous structures & refractory 
 @  3%  of  CIF  cost  of  imported  equipment  towards  port 
handling,  customs  &  port  clearance  as  well  as  inland 
transport to site. 
iv)  Erection & commissioning charges: 
@  6%  for  imported  equipment,  @  12%  for  indigenous 
equipment and @20% of basic cost of structures.  
v)  Engineering & construction and foreign supervision: 
@  12%  of  basic  cost  of  both  imported  &  indigenous 
equipment, Structures, Refractories, Civil works and erection 
and  commissioning  charges.  Besides,  suitable  provision  on 
perdiem  basis  has  been  kept  towards  foreign  supervision 
during erection & commissioning.  
vi)  Contingencies: @ 5% on overall basis. 
6.2    Mode of Financing: 
6.2.1    The  total  capital  requirement  of  the  project  is  proposed  to  be 
provided  from  debt  equity  ratio  of  1:1.  An  interest  rate  @  10%  per 
annum is considered on commercial loan borrowings. 
6.3    Phasing of Capital Expenditure: 
6.3.1    With the project duration of 36 months from Final /Stage-II approval, 
the phasing of capital expenditure is proposed as indicated below: 
(Rs. Crore) 
Year    Plant 
Cost 
Equity  Market 
Loan 
IDC  Total 
1
st
 Year  202.17  101.08  101.08   5.05   207.22 
2
nd
 Year  1617.36  808.68  808.68   50.54   1667.90 
3
rd
 Year  1819.53  909.76  909.76   136.46   1955.99 
Post Comm.  404.34  202.17  202.17      404.34 
Total  4043.39  2021.69  2021.69   192.06   4235.45 
Cenvat Credit          356.03   
Total 
Investment 
net of Cenvat 
        3879.42   
6.4    Interest During Construction (IDC) 
6.4.1  Based on the mode of financing and phasing of capital expenditures 
indicated above, the total IDC has been calculated to be Rs. 192.06    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 6.3    
crore.  
6.5    Techno-Economics: 
6.5.1    It  has  been  envisaged  that  the  proposed  Hot  Strip  Mill  will  produce 
2,940,000 HR coils out of which 720,000 tpa would be processed in 
the  Sheet  shearing  line  to  produce  705,600  tpa  of  saleable  HR 
Sheets & Plates.  
6.5.2    Annual Manufacturing Expenses: 
6.5.2.1  Raw Materials & Consumables:  
    The  cost  raw  materials  (CC  slabs)  has  been  estimated  based  on 
specific  consumption  (for  the  slabs  to  be  sourced  from  within  RSP 
based on Std cost 2011-12)/ Market price (for slabs to be sourced from 
the market)  
6.5.1.2  Salary & Wages: 
Manpower  cost  of  existing  HSM  as  per  Standard  cost  2011-12  has 
been  considered.  For  the  operation  &  maintenance  of  new  shearing 
line,  manpower  cost  corresponding  to  10  executives  &  60  non 
executives  has  been  considered,  based  on  prevailing  pay  scales  in 
SAIL.  
6.5.1.3 Operating Consumables & Utilities: 
    The  costs  of  various  Operating  Consumables  has  been  estimated 
based on sp.cost per ton of HR coil and that of utilities & services such 
as power, water, & oxygen etc. has been considered based on specific 
consumption and unit costs as per Standard Cost 2011-12 of RSP. 
6.5.1.4  Repair & Maintenance: 
    Provision  for  repair  &  maintenance  of  plant  &  machinery,  building/ 
structures,  and  civil  engineering  works  etc.  has  been  considered 
while computing the total manufacturing expenses @ 2.5% of capital 
cost net of cenvat.  
6.5.1.5  Overheads 
    Provision  towards  works  overhead  has  been  kept  @  2%  of  the  total 
operating cost.  
 6.5.1.6    Based on the above, the manufacturing expenses for production  
RSP  
CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 6.4  
of  HR  coil/  HR  sheets  and  plates  have  been  worked  out  to  be  Rs. 
26289/t.  and  Rs.  26806/t.  respectively,  as  per  details  given  at 
Annexure -6.5.1.6-1. 
6.5.2    Income 
6.5.2.1 The total saleable HR coils which will be produced in the new Hot Strip Mill is 
estimated  to  be  2,220,000  tpa  whereas  the  saleable  HR  plates  & 
sheets from the new Sheet Shearing Line is estimated to be 705,600 
tpa.  Considering  avg.  NSR  of  Rs  33500/t  for  HR  coil  (commercial 
grade),  Rs  36133/t  for  special  grades of HR  coils  (API,  Boiler,  LPG, 
Automotive  etc)  and  Rs  39000/t  for  HR  Sheets/Plates,  the  annual 
income works out to be Rs. 10683.53 crore. The total works cost for 
HR Coil & Plates/sheets works out to be Rs. 7727.51 crore. Loss of 
contribution  from  the  slab  sourced  from  RSP  works  out  to  be  Rs. 
2024.84 crore. 
6.5.2.2  Based  on  the  above,  the  gross  margin  works  out  to  be  Rs.931.18 
crore. The details are given at Annexure  6.5.2.2-1. 
6.6    FINANCIAL ANALYSIS: 
6.6.1      Financial  analysis  has  been  carried  out  on  the  basis  of  cash  flow 
during  23  years.  Life  of  the  project  is  considered  20  years  after 
commissioning.  The  detailed  profit  loss  statement,  cash-flow 
statement,  NPV  and  IRR  calculations  are  appended  at  Annexure 
6.6.1-1. 
6.6.2      The financial indices have been worked out and given at Annexure-
6.6.2-1. Some of the important parameters are indicated below: 
S. No.  Description  Value 
1  IRR Pre Tax 
IRR- Post Tax 
21.36% 
18.08% 
2  NPV Pre Tax @ 10% discount 
NPV-Post Tax @ 10% discount 
Rs. 2875.83 crore 
Rs. 1782.92 crore  
6.6.3    Sensitivity Analysis 
  Sensitivity  analysis  has  been  worked  out  to  assess  the  impact  of 
variations  in  capital  cost  &  gross  margin  on  the  financial  indices  of    
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 6.5    
the project and the results are presented below:           
  IRR 
Sl.No  Variance  Pre Tax  Post Tax
1   Base Case 
21.36%  18.08%
2   Capital cost up by 10% 
19.34%  16.12%
3   Gross margin less by 10% 
19.30%  16.38%
4  
Combined effect of above two 
factors 
17.41%  14.53%
5 
Production with own slab (2.67 
Mtpa) only 
19.34%  16.41%   
RSP  CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  Page 7.1     
7  RECOMMENDATION 
7.1     A  new  Hot  Strip  Mill  with  modern  features  is  required  to  roll  the 
required volume of slabs available after the ongoing modernisation of 
RSP  and  to  avoid  sales  of  semis  as  slabs.  Market  requirements  of 
higher  coil  weight,  wider  strip,  higher  strength  grades,  excellent 
product qualities, etc. will be met through the new Hot Strip mill.  
7.2  The project is technically feasible and technoeconomically viable and 
hence recommended for implementation      
RSP  Annexure-2.6.2-1 CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  (Page 1 of 1)      
Annexure-2.6.2-1 
Copy of letter for assignment from RSP 
To 
GM & I/C, CET, 
Rourkela Sub center 
CET building, Rourkela 
Ref. No.: AMR-M&SC/Consultancy/15/433-37       Date: 17.03.2011 
Respected Sir, 
Sub: Assignment of consultancy services to M/S CET for Installation of 
a New HOT STRIP MILL in Rourkrla Steel Plant 
Please find enclosed herewith the copy of approved note sheet (approved by 
ED(W)  &  concurred  by  Finance  )  for  working  out  a  comprehensive  scheme  for 
Installation of New HOT STRIP MILL in Rourkela Steel Plant. 
We  are  pleased  to  appoint  M/S  CET  as  the  consultant  for  the  study  for 
Installation of New HOT STRIP MILL with the following scope of services : 
1.   To study and finalise the location 
2.  To prepare Feasibility report & TS 
3.  Budget cost estimation & Financial analysis 
4.  Preparation of Board Note for sanction & approval 
5.  Project finalization and monitoring 
With regards, 
Sd/- 
(D R Biswas) 
DGM (AMR-M&SC  
Copy: 
1. GM I/C (Services) 
2. GM (HSM) 
3. DGM (Finance) Project 
4. AGM (Tech) to ED (Works)    
RSP  Annexure-4.2-1 CET/05/RN/3379/FR/RF/01/R-0
NEW HOT STRIP MILL  (Page 1 of 1)   
Annexure-4.2-1 
Tentative Product Mix 
(,000 tpa) 
   Thickness (mm) 
Width (mm)  1.2-1.8  1.9-2.5  2.6-3.5  3.6-6.5  6.6-11.0  11.1-25  Total  % 
725-1000  15  30 30 15 15 15 120 4.00%
1001-1500  255  420 515 515 150 190 2045 68.17%
1501-1880  30  30 180 165 90 160 655 21.83%
1881-2100  0  15 15 15 120 15 180 6.00%
Total  300  495 740 710 375 380 3000   
   10.00%  16.50% 24.67% 23.67% 12.50% 12.67% 100.00% 100.00%     
RSP  Annexure 5.1-1  CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 1 of 1    
ANNEXURE-5.1-1 
PROJECT IMPLEMENTATION SCHEDULE 
(Pre-ordering Activities (Stage-I))  
Activities                            0 1 2  3 4 5 6
Stage-I approval of Project           *             
Issue of tender & receipt of offers               
Scrutiny of offers, TD, tender finalisation                 
Scrutiny  by  Corporate  Office,  reply  to  queries  and  stage-II 
approval                   
RSP  Annexure 5.1-2  CET/05/RN/3379/FR/RF/01/R-0 
NEW HOT STRIP MILL  Page 1 of 1    
ANNEXURE-5.1-2 
PROJECT IMPLEMENTATION SCHEDULE 
(After Stage-II Approval)  
Sl. 
Month
Activity 
2  4  6  8  10  12  14  16  18  20  22  24  26  28  30  32  34  36 
  Stage II approval   Zero date                                  
1  Placement of Order and Contract signing 
(effective date of Contract)                                  
2  Submission  &  approval  of 
drawings/documents.                                      
3  Civil work                                    
5  Supply of eqpt.                                    
6  Erection                                    
7  Testing & trial run                                      
8  Commissioning                                                     
56840
13770 4000
4
0
0
0
350 220 3500 1910 3480 3080 6130 4000 3000 5400 8000
735
700
2000
4000
2
1
3
13
11
10 9 8 
7
6
5
4
1.  UNCOILER & DUTBOARO BEARING 
2.  ANTI COIL-BREAK ROLL(OPTION)
3.  CENTERING DEVICE
4.  PEELER TABLE, PINCH ROLLS AND STRAIGHTENER
5.  CROP SHEAR & BLANK REMOVER
6.  VERTICAL GUIDES & PINCH ROLLS
7.  SCRAP GUIDING SYTEM & SCRAP CHOPPER
8.  .LEVELLER-1
10.  FEEDING ROLLS & FHYING SHEAR
11.  CONVEYOR 
12.  MARKING MACHINE
13. PILER
9.  LEVELLER-2
STEEL AUTHORITY OF INDIA LTD.
CENTRE FOR ENGINEERING & TECHNOLOGY, RANCHI
PLANT (    ) :
DRG. NO.
UNIT(    ):
REV
NO. DATE REMARKS BY APPD. DRG. NO. DETAILS
REF. DRAWINGS REVISIONS
C L E A R A N C E
SECTION BY DATE
A
D
B
4
,
D R G .   N O .  
SIZE : A3 01 01
CET RN 3379 RF1 00 004 SCALE
G KUMAR DRAWN
DESIGNED
CHECKED
APPROVED
ROURKELA STEEL PLANT
DATE:
SHEET OF
File Name: 3379RF004FR.Dwg
6 5 4 3
D
C
B
C E T   R N   3 3 7 9   R F 1   0 0   0 0 4   R = 0
C
E
N
T
R
E
 
F
O
R
 
E
N
G
I
N
E
E
R
I
N
G
 
&
 
T
E
C
H
N
O
L
O
G
Y
,
S
A
IL
.
 
IT
 
M
U
S
T
 
N
O
T
 
B
E
 
D
IS
C
L
O
S
E
D
.
 
C
O
P
IE
D
 
O
R
 
L
E
N
T
 
T
O
 
A
 
T
H
IR
D
 
P
A
R
T
Y
 
W
IT
H
O
U
T
 
W
R
IT
T
E
N
 
C
O
N
S
E
N
T
T
H
IS
 
D
R
A
W
IN
G
 
IS
 
C
O
N
F
ID
E
N
T
IA
L
 
A
N
D
 
IS
 
T
H
E
 
P
R
O
P
E
R
T
Y
 
O
F
 
C
E
N
T
R
E
 
F
O
R
 
E
N
G
IN
E
E
R
IN
G
 
&
 
T
E
C
H
N
O
L
O
G
Y
,
 
R
A
N
C
H
I.
NEW HOT STRIP MILL
LAYOUT OF SHEET SHEARING LINE 
G KUMAR
NTS R=0
FOR FR PURPOSE ONLY
S P RAI
S P RAI
08.08.2011
(SCHEMATIC)
12