100% found this document useful (2 votes)
134 views

Project Schedule Example

This project plan outlines the tasks and timeline for renovations over 65 days from April 2nd to July 4th. It involves demolitions, installing proprietary partitions and electrical/fire systems over 48 days, followed by plumbing, air conditioning, builder's work and finishing over the next 17 days. The final tasks are installing internal doors, painting, and handing over the completed renovations to the client.

Uploaded by

gman444
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
134 views

Project Schedule Example

This project plan outlines the tasks and timeline for renovations over 65 days from April 2nd to July 4th. It involves demolitions, installing proprietary partitions and electrical/fire systems over 48 days, followed by plumbing, air conditioning, builder's work and finishing over the next 17 days. The final tasks are installing internal doors, painting, and handing over the completed renovations to the client.

Uploaded by

gman444
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71

Task Name

Duration

Start

Finish

Predecessors Thu 4/17


13
2

Mon 4/21
Fri 4/25
15
4
17
6
19

Tue 4/29
8
21 10

Sat 5/3
23 12

Wed 5/7
14
3

Sun 5/11
16
5

18

Thu 5/15
7
20

Mon 5/19
Fri 5/23
9
22 11
0
13

Tue 5/27
15
4

Sat 5/31
17
6

19

Wed 6/4
8
21

Sun 6/8
10 23

12

Thu 6/12
1
14

CONTRACT PERIOD

65 days Mon 4/2... Fri 7/4/14


4 days Mon 4/21... Thu 4/24/...
DEMOLITIONS
2 days Fri 4/25/14 Sat 4/26/... 4
Pull down blockwork
2 days Fri 4/25/14 Sat 4/26/14
Pull down timber fins
1 day Fri 4/25/14 Fri 4/25/14 6SS
Dismantling of the existing timber doors
2 days Fri 4/25/14 Sat 4/26/14 7SS
Pull down aluminium partitons
2 days Fri 4/25/14 Sat 4/26/14 8SS
Dismantle any electrical cables
2 days Fri 4/25/14 Sat 4/26/14 9SS
PROPRIETARY PARTITONS
8 days Mon 4/2... Tue 5/6/14 5
Blockwork walls
6 days Mon 4/28... Sat 5/3/14 5
Maclok - steel
6 days Mon 4/28... Sat 5/3/14 12SS
Maclock - aluminium
5 days Mon 4/28... Fri 5/2/14 13SS
MDF boarding
2 days Fri 5/2/14 Sat 5/3/14
Glass fibre accoustic wall
2 days Mon 5/5/... Tue 5/6/14 15
ELECTRICAL & FIRE PROTECTION INSTALLATION
48 days Wed 5/7/... Tue 7/1/14
Conduiting - 1st fix
5 days Wed 5/7/... Mon 5/12... 11
Cable trays installation
3 days Wed 5/7/... Fri 5/9/14 18SS
Install junction boxes & switches
3 days Wed 5/7/... Fri 5/9/14 18SS
Pull cables into conduits
3 days Sat 5/10/14 Tue 5/13/... 20
Fix electrical fittings
1 day Mon 6/30... Mon 6/30... 66
Test & commission
1 day Tue 7/1/14 Tue 7/1/14 22
PLUMBING & FIRE FIGHTING SYSTEMS
8 days Wed 5/1... Thu 5/22... 21
Relocate existing sprinkler heads
4 days Wed 5/14... Sat 5/17/14 21
GS piping
1 day Mon 5/19... Mon 5/19... 25
Fix new sprinkler heads
1 day Mon 5/19... Mon 5/19... 26SS
Floor Drain
1 day Wed 5/21... Wed 5/21...
Sanitary appliances
2 days Wed 5/21... Thu 5/22/... 28SS
Supply fire extinguishers
1 day Wed 5/14... Wed 5/14...
Test & commission
1 day Wed 5/14... Wed 5/14...
AIR-CONDITIONING INSTALLATION
4 days Sat 5/17/... Wed 5/2...
Ducting works
1 day Sat 5/17/... Sat 5/17/...
Condensate drainage piping
1 day Sat 5/17/14 Sat 5/17/14 21
Copper piping
1 day Sat 5/17/14 Sat 5/17/14 34SS
AC units installation
3 days Mon 5/1... Wed 5/2...
Check electrical points
1 day Mon 5/19... Mon 5/19...
Fix AC units
1 day Tue 5/20/... Tue 5/20/...
Test & commission
1 day Wed 5/21... Wed 5/21... 38
Check & repair existing AC units
2 days Tue 5/20/... Wed 5/21... 38SS
BUILDER'S WORK
2 days Thu 5/22... Fri 5/23/14
Electrical installations
2 days Thu 5/22/... Fri 5/23/14
AC installations
2 days Thu 5/22/... Fri 5/23/14
Plumbing & fire fighting systems
2 days Thu 5/22/... Fri 5/23/14
FINISHINGS
17 days Mon 6/2/... Fri 6/20/14
Hack off existing unwanted floor & wall finishes 2 days Sat 5/24/14 Mon 5/26... 29
Plaster to walls
3 days Tue 5/27/... Thu 5/29/... 46
Grid ceiling systems - steel
3 days Fri 5/30/14 Mon 6/2/... 47
Skimming plastered surfaces
2 days Tue 6/3/14 Wed 6/4/...
Skirtings, architraves, fillets etc
3 days Thu 6/5/14 Sat 6/7/14 49
Carpet tiling
4 days Mon 6/9/... Thu 6/12/... 50
Maintenance of existing ceilings
2 days Fri 6/13/14 Sat 6/14/14 51
Timber brandering to ceiling
2 days Mon 6/16... Tue 6/17/... 52
Cover grid ceiling with Lafarge gypsum boards 2 days Wed 6/18... Thu 6/19/... 53
Cover timber brandering with Lafarge
3 days
Wed Fri 6/20/14 53
gypsum boards
6/18/14
INTERNAL DOORS
8 days Sat 6/21/... Mon 6/3...
Automatic sliding doors
1 day Sat 6/21/14 Sat 6/21/14 55
Frames
3 days Sat 6/21/14 Tue 6/24/... 57SS
High security doors
3 days Wed 6/25... Fri 6/27/14 58
Hardwood timber doors
3 days Wed 6/25... Fri 6/27/14 59SS
Other iron mongery
2 days Sat 6/28/14 Mon 6/30... 60
Flush doors
2 days Sat 6/28/14 Mon 6/30... 60
PAINTING & DECORATIONS
10 days Mon 6/2... Thu 7/3/14
Sand down existing surfaces
1 day Mon 6/23... Mon 6/23... 57SS+1 day
Primer coat
3 days Tue 6/24/... Thu 6/26/... 64
Undercoat to walls & ceilings
2 days Fri 6/27/14 Sat 6/28/14 65
Finishing coats
2 days Mon 6/30... Tue 7/1/14 66
Varnish to all wood surfaces & doors
2 days Wed 7/2/... Thu 7/3/14 67
HANDOVER
3 days Wed 7/2/... Fri 7/4/14
Snagling
2 days Wed 7/2/... Thu 7/3/14 68SS
Inspection and Handover to Client
1 day Fri 7/4/14 Fri 7/4/14 70
Mobilization

Project: Project1

Task

Summary

External Milestone

Inactive Summary

Manual Summary Rollup

Finish-only

Split

Project Summary

Inactive Task

Manual Task

Manual Summary

Deadline

Milestone

External Tasks

Inactive Milestone

Duration-only

Start-only

Progress

Page 1

Manual Progress

Mon 6/16
16
5

Fri 6/20
18
7

20

Tue 6/24
9
22

Sat 6/28
Wed 7/2
11
0
13
2
15

Sun 7/6
17

You might also like