ITB 2011-012 BOQ
Contractor Signature
United Nation Development Programme
Rehabilitation of Al Adham road, road No.1, and road No.2 in Bait Lahia And f Salah El Deen Road in
Rafah by Using Crushed Material.
PAL 10-71646: UXOs and Rubble Removal from Gaza Strip and Solid Waste Management
Bill of Quantity (BOQ)
ITB 2011-012
Contractors signature and stamp Page2
Bill of Quantity (BOQ)
PREAMBLE TO BILL OF QUANTITY (BOQ)
1. GENERAL
The nature of this contract is re-measured unit price contract and the Bill of Quantity
(BOQ) shall reflect this fact.
BOQ shall be read and construed in conjunction with other Contract Documents.
General directions and description of work and material given in the Technical
Specification are not necessarily repeated in the Bill of Quantity. The Technical
Specification forms an integral part of the Bill of Quantity.
The Tenderer is obliged to check the number of the pages of the Bill of Quantity and
should any be found missing or duplicated or the figures of writing indistinct, the Tenderer
must notify the Employer/Engineer at once and have the matter rectified before the Tender
is submitted. No liability whatsoever will be accepted in respect of any claim for errors in
the Tenderers offer resulting from failure to comply with the fore-going.
The Tenderer is deemed to have visited the site/s and fully acquainted himself as to the
location of each of the items and works to be carried out and to all conditions which may
affect the performance of the works, including but not limited to:
Access for the storing dump site and UNDP crushing site as well as access to
required services
Restrictions applicable to working in GAZA Strip area.
All safety regulations and employer site safety procedures.
All Palestinian regulations.
The Tenderer is also deemed to have surveyed the actual condition of the site and buildings
and made his own assessment of the type and extent of the works prior to submitting his
offer.
2. QUANTITIES
Although practical care was exercised in preparing the BOQ, all quantities given herein
shall be deemed to be estimated quantities of the work to be done. They are not to be taken
as actual and correct quantities of the work to be executed and they do not absolve the
contractor of his obligations under the Contract. At any time, the actual quantities increase
or decrease, hence, it is understood that the actual quantities increase or decrease is
expected risk and no claim whatsoever will be taken into consideration for extra cost in
that respect by employer. Any claim whatsoever submitted for cost or extra expenses
incurred from such increase or decrease will not be accepted by Employer/Engineer except
where else stipulated in the Contract.
ITB 2011-012
Contractors signature and stamp Page3
3. MATERIALS
All materials used are to be of the best new available, subject to the Employer/Engineer
approval, durable nature, guaranteed, not liable to any base exchange and manufactured
according to applicable BS, ASTM or DIN Standards. Execution also is subject to
approval of Employer/Engineer and shall be in conformance of the best available common
practice in engineering codes at the time of execution.
Items that contain materials or products of special make with names of manufacturers are
to be taken as samples of what will be required. Subject to the Employer/Engineer
approval, the Contractor may, at his discretion, offer similar products of other make if the
equivalent quality of the specified materials is obtained. In this case, the Contractor shall
submit a description and/or drawings showing all technical conditions, characteristics,
make, type and address of Manufacturer, etc., of the materials offered as alternatives.
4. PRICES
The Unit Prices entered against the various items in the following Bill of Quantities
include all operation costs for execution, completion and maintenance of the various items
of the works finished completely in every respect till the final acceptance as specified or
described in the Tender Documents, with or without modifications, either by way of
additions or deductions, or alterations as may be offered in writing during the progress of
the works, and include, without being limited to, all what is deemed necessary particularly
referred to in the Tender Documents.
The Unit Price shall cover all costs of every kind whatsoever including, without being
limited to, all charges for additional site installations, relocation, supervision, labor,
transportation and supply of materials; the provision, maintenance, use and efficient repair
of all plant, equipment and appliance of every kind, the construction and maintenance of
all temporary works, the performance of all services and the fulfillment of all obligations
and responsibilities herein defined.
The Tenderer shall be deemed to have fully considered all the conditions, obligations, and
requirements of the Tender Documents before entering the respective unit price against the
various items of the Bill of Quantities.
The Unit Prices given hereunder the BOQ shall also include erection, installation, fixing,
and re-fixing of all elements. These prices shall also include taxes, visa for labor, gate
passes, accommodations for the Contractors staff and labors, all required insurance and
work permits, guarantees, bonds, traffic plan requirements, safety procedures, etc. and all
requirements necessary to have the work maintained until its final handing over.
The Unit Prices given hereunder in the Bill of Quantity for this work shall also include
overheads, risks, profit etc. and all other financial matters to have all these civil works
completed.
ITB 2011-012
Contractors signature and stamp Page4
The works, materials or activities listed in the following shall always be considered as
supportive works to be included in the Unit Prices bid for any item in the Bill of
Quantities:
Any measurement for execution and payment of the works, including the provision of
measuring instruments, gauges, setting out marks, marking paint and relevant tools,
labor, etc., the maintenance and preservation of gauges and setting-out marks during
the execution of the works.
Provision of small tackle tools or any other equipment required for the execution of the
works.
Supply of consumable materials for the Contractors equipment.
Removal of all contamination (refuse, debris, building rubbish and the like) arising
from or in connection with the Contractors work to locations approved by the
engineers
Protection of the executed works and of the items made available for execution of the
works from damage, fire, inclement weather, vandalism and theft etc., until the time of
final acceptance.
Transportation of all materials and structural components from the storage places on
site to the points of use and return transportation, if required.
Submitting and transporting any samples required.
Carrying out tests on materials and works, etc., that is required by the Engineer.
Fuel and lubricants for operation of Contractors equipment.
All safety precautions and measures for safeguarding labor as well as securing
surrounding areas.
Lighting of the work site.
Maintenance , repair or reconstruct damaged infrastructure resulted by contractors
activities.
5. RIGHTS OF EMPLOYER
The following rights are reserved to the Employer:
To omit individual items mentioned in the Schedule of Prices if not required in the
opinion of the Employer and/or to replace them should it be more advantageous to
execute them in another way.
To order execution of alternative or provisional items as if they were main items.
To order execution of additional works as well as alternatives of works, always in
conformity with the conditions outlined in the Contract.
Any order and/or delivery of material or equipment by the Contractor for performance of
the works may only be based on instructions and/or approved execution drawings by the
Employer/Engineer.
All equipment and materials for installation and finishing works to be incorporated in this
contract shall prior to ordering and/or delivery by the Contractor, be approved by the
Employer/Engineer both in respect of quality and type as well as of quantity.
ITB 2011-012
Contractors signature and stamp Page5
6. SITE ACCESS AND STORAGE
The Tenderer shall visit all sites and ascertain the location of required access onto these
sites and the location of allowance for complying with the requirements and for the
reinstatement to original condition of all roads and areas used or disturbed by the
Contractor to the satisfaction of the Engineer.
7. SITE INSTALLATION
All costs of labor, works, provisions, materials and equipment for Site Installations
required by the Contractor and stipulated in the Tender Documents shall be included in the
various unit prices of the Bill of Quantities. No extra payment will be allowed by the
Employer for any of these activities.
8. DURATION
The total duration of the contract is Four (4) calendar months including weekends,
holidays and official holidays. Official weekends are Fridays and Saturdays.
9. OTHER CONTRACTORS OBLIGATIONS
The Contractor has to submit Detailed Shop Drawings to be approved by the Engineer
before commencement of the work, and all required materials should be supplied as
specified and subject to the Engineer approval.
The Contractor has to fix the underground services that may be damaged during his
work.
The Contractor has to maintain the Existing Open Channels flow during construction.
All works has to be done according to the Engineer's instructions, Drawings and
specification.
The Contractor has to repair any damages of any services at full satisfaction of
relevant Service Authority
The contractor has to test on his own expenses, the sub-grade CBR before
commencement of work, In case the CBR value less than 15%, then soil replacement
should be applied.
The contractor has to check the upper 30 cm below the top of the sub-grade to verify
that they are uniform, and any rubbish material or saturated /wet soil shall be removed
and replaced with suitable material approved by the Engineer ,
NO EXTRA COST SHALL BE PAID FOR SUCH REPLACEMENT
The contractor has to Execute any required side slope according to specifications,
drawings , and Engineers instructions
Price will include costs of removing and/or relocating of all obstacles such as debris,
garbage, trees and existing services in addition to the required materials necessary for
work completion according to engineer's instructions and specifications.
The contractor has to coordinate with Municipalities regarding garbage containers
location.
The contractor should include in his price the costs of cut and removal of trees roots,
backfilling, watering, and compaction in layers with clean sand as specified and
ITB 2011-012
Contractors signature and stamp Page6
according to the Engineer instructions, the price will also include relocation of Power,
Telephone poles and networks to sidewalk.
Price will include costs of adjusting the levels of existing manholes (in any diameter)
to suit the new situation. Replacing covers, frames, rings if defected and all materials
and work required to complete the task.
The contractor has to remove the existing base coarse during preparation works and
transport it wherever directed by the engineer to the related Municipality.
The price will include costs of cutting and removing of the existing asphalt pavement
layer and transporting the removed material to a site approved by the Engineer
Prices for excavation item shall include the removal of any buried structure not to be
part of the proposed roads, including transport of excavated, surplus material and
buried structure (not to be part of the proposed roads) to a location approved by the
engineer or his representative outside the site, workmanship and anywhere else,
needed, all according to drawings, specifications, conditions and directed instructions
by the Engineer or his representative.
The price will include costs of Warranty and maintenance of two weighting
balances located in UNDP crushing site from the date of signing contract to the
handing over the project .The maintenance includes preventive maintenance
each two weeks, instant maintenance as required ,balance calibration for perfect
accuracy when needed and UNDP will supply the contractor with load cells and
indicators if needed , any other maintenance requirements for proper operation
of two weighting balances and complete maintenance of hard and software for
two computers and two printers of two weighting balances for a period of
contract date starting from the date of signing contract.
The price will include costs of appointment guard in the UNDP crushing site for
24 hour daily from the date of signing contract to the handing over the project.
Quantities of excavation shall be measured according to the dimensions mentioned in
the drawings(engineering measurements in m
2
)
Back-filling item should be in layers (25cm max. each & compaction test 97%). Prices
shall includes material supply, watering, compacting, transporting, testing and
anywhere else, needed, all according to drawings, specifications, conditions and direct
instructions by the Engineer or his representative.
Suitable clean sand should be used for back-filling in layers (25cm max. each &
compaction test 97%), selected from the approval excavated soil or imported. Prices
shall includes supply, watering, compacting, transporting, testing and anywhere else,
needed, all according to drawings, specifications, conditions and directed instructions
by the Engineer or his representative.
The contractor shall check and ascertain that the Benchmark used by him and its
elevation is accurate and correct in all respects. The contractor shall check the
surveying work. If correction is needed, the contractor has to redo the surveying work
on his own.
ITB 2011-012
Contractors signature and stamp Page7
Rehabilitation of Al Adham Road, Road No.1, and Road No.2 in Bait
Lahia by Using Crushed Material
Item
No.
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
1
Clean, and leveling including excavate, cut and fill
the carriage way and sidewalks with supply and
leveling clean sand or Kurkar according to the
engineer inspections from natural ground level to
the design of the Bottom of the Crushed concrete
base coarse layer including watering, compaction
not less than 97% and CBR not less than 15%,
removal of existing asphalt and/ or relocated to the
new street edge of the existing retaining walls(steel
boxes filled with sand) or any other obstacles,
disposal off site of surplus excavated material, the
price includes disassembling of the existing curb
stone or any obstructions to be removed and
transport away from the site. The price includes
adjust levels of existing H.C manholes (diam. Of
60cm or less) or exchange when required, also
lowering the pipe and connect it to the main
manhole.
Also the price including fill with compaction all the
existing septic tanks and retaining walls steel boxes
All in accordance with the drawings, specifications
and Engineers directions.
m
2
30,000
2
Transport and lay approved crushed stone base
coarse 20 cm thick in one layer with CBR >80%
for the carriage way to the levels shown in the
drawings . Price includes transporting crushed
material, watering and compaction to reach 98 % of
maximum dry density. The work includes all tests
as per specifications and Engineers instructions.
Grader must be used in spreading and leveling of
final layer.
Note: Crushed materials to be transported from
UNDP crushing site west of Khanyounis (GAN-OR
ex-settlement).
m
2
15,000
3
Supply, spread and compact 5cm thick granular
sand Kurkar with CBR >30%. The price shall
include spreading , leveling, watering and
compaction.
m
2
15000
ITB 2011-012
Contractors signature and stamp Page8
Item
No.
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
4
Supply and cast reinforced concrete B250 for
(20*40cm) beam. The work includes shuttering,
steel reinforcement (2 10 top, 2 10 bottom &
8/20cm as stirrups), vibration & all the required
material. In accordance with the drawings
specifications and Engineers directions.
LM
215
5
Adjust levels of existing manholes (sewer, water,
telephone, storm water etc.) to the required level.
the work includes decreasing the height of
manholes by demolishing the extra parts or
increasing the height by supplying & installing
precast concrete rings (B300), in case the height is
more than 30cm. Otherwise casting of concrete
may be used, also includes (if needed) cast iron
cover 25 ton (with the word sewer in English &
Arabic) and all required material. The work
includes also cleaning of the existing manholes and
lines.
NO.
30
6
Supply and install razor wire fence. The item
includes supply and install oven-painted three-
pronged steel angles ( Type ST-37) each 4 m with
length 3 meter ,steel beams IBE 80 ( Type ST-
37) with dimension 8*4.6 cm , 3.8mm web
thickness, and 3 m long each 50m; and 8 rows of
razor wires to be fixed on the angles by using 1
mm galvanized tie wire in addition two diagonal
from the same wire in the panel . All works must be
implemented according to the specifications and
engineers instruction.
LM
2000
Total of Al Adham Road, Road No.1, and Road
No.2
ITB 2011-012
Contractors signature and stamp Page9
Rehabilitation of Salah El Deen road in Rafah road in Rafah by Using
Crushed Material
Item
No.
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
1.1
Clean, and leveling including excavate, cut and fill
the carriage way and sidewalks with supply and
leveling clean sand or Kurkar according to the
engineer inspections from natural ground level to
the design of the Bottom of the Crushed concrete
base coarse layer including watering, compaction
not less than 97% and CBR not less than 15%,
removal of existing asphalt and/ or relocated to the
new street edge of the existing retaining walls(steel
boxes filled with sand) or any other obstacles,
disposal off site of surplus excavated material, the
price includes disassembling of the existing curb
stone or any obstructions to be removed and
transport away from the site. The price includes
adjust levels of existing H.C manholes (diam. Of
60cm or less) or exchange when required, also
lowering the pipe and connect it to the main
manhole.
Also the price including fill with compaction all the
existing septic tanks and retaining walls steel boxes
All in accordance with the drawings, specifications
and Engineers directions.
m
2
15600
1.2
Transport and lay approved crushed stone base
coarse 20 cm thick in one layer with CBR >80%
for the carriage way to the levels shown in the
drawings. Price includes transporting crushed
material, watering and compaction to reach 98 % of
maximum dry density. The work includes all tests
as per specifications and Engineers instructions.
Grader must be used in spreading and leveling of
final layer.
Note: Crushed materials to be transported from
UNDP crushing site west of Khanyounis (GAN-OR
ex-settlement).
m
2
15600
1.3
Supply, spread and compact 5cm thick granular
sand Kurkar with CBR >30%. The price shall
include spreading, leveling, watering and
compaction.
m
2
15600
ITB 2011-012
Contractors signature and stamp Page10
Item
No.
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
1.4
Adjust levels of existing irrigation, municipals
networks and manholes (sewer, water, telephone,
storm water etc.) to the required level. the work
includes all needed fittings, parts, all materials
workmanship required for completing the works
properly and decreasing the height of manholes by
demolishing the extra parts or increasing the height
by supplying & installing precast concrete rings
(B300), in case the height is more than 30cm.
Otherwise casting of concrete may be used, also
includes (if needed) cast iron cover 25 ton (with the
word sewer in English & Arabic) and all required
material. The work includes also cleaning of the
existing manholes and lines.
Lump
Sum.
1
Total of Salah El Deen road
ITB 2011-012
Contractors signature and stamp Page11
Summary
Description Total (US$)
Total of Al Adham Road, road No.1, and
road No.2
Total of Salah El Deen road
Total (US$)
Vat (0%) 0.00
Grand Total (US$)
Grand Total (in letters):-------------------------------------------------------------
Contractors Name:------------------------------------------------------------------
Signature and Stamp:----------------------------------------------------------------
Date:-------------------------------------------------------------------------------------