(P-7) As A Hospital Administrator of A Large Hospital, You Are Concerned With The Absenteeism Among Nurses' Aides. The Issue Has
(P-7) As A Hospital Administrator of A Large Hospital, You Are Concerned With The Absenteeism Among Nurses' Aides. The Issue Has
( )
UCLp = + z
= 0,0875 + 3 (0,0353)
= 0,0875 + 0,1059
= 0,1935
LCLp = - z
= 0,0875 - 3 (0,0353)
= 0,0875 - 0,1059
= - 0,0184 0
z = 99 % + 0,5 %
= 99,5 %
= 0,995
= 2,57 zigma (based on table)
LCLp = - z
= 0,0875 2,57 (0,0353)
= 0,0875 0,090721
= - 0, 0033 0
UCLp = + z
= 0,0875 + 2,57 (0,0353)
= 0,0875 + 0,090721
= 0,1783
b. Based on your p-chart and the data from the last 3 weeks, what can you conclude about the absenteeism of nurse aides?
Berdasarkan hasil p-chart dari data 3 minggu terakhir mengenai absenteeism, maka dapat dikatakan bahwa proses tersebut masih
dalam batas in control, yang berarti data-data dari sample aides absent tersebut masih dalam batas yang sewajarnya dan tidak
berpengaruh besar terhadap kinerja para suster. Namun demikian, isu bahwa suster merasa akan lebih berkinerja baik dengan
bantuan aides juga harus tetap diperhatikan oleh pihak manajerial rumah sakit.
(P-12)Management at Webster, in Problem 16, is now concerned as to whether caulking tubes are being properly capped. If a
significant proportion of the tubes are not being sealed, Webster is placing its customers in a messy situation. Tubes are packaged in
large boxes of 144. Several boxes are inspected, and the following numbers of leaking tubes are found :
Sample Tubes Sample Tubes Sample Tubes
1 3 8 6 15 5
2 5 9 4 16 0
3 3 10 9 17 2
4 4 11 2 18 6
5 2 12 6 19 2
6 4 13 5 20 1
7 2 14 1 Total 72
Calculate p-chart three-sigma control limits to assess whether the capping process is in statistical control.
( )
UCLp = + z
= 0,025 + 3 (0,0130)
= 0,025 + 0,039
= 0,064
LCLp = - z
= 0,025 - 3 (0,0130)
= 0,025 - 0,039
= - 0,014 0
z = 95 % + 2,5 %
= 97,5 %
= 0,975
= 1,96 zigma (based on table)
LCLp = - z
= 0,025 1,96 (0,0130)
= 0,0875 0,069188
= - 0
UCLp = + z
= 0,025 + 1,96 (0,0130)
= 0,0875 + 0,069188
= 0,0505
Berdasarkan p-chart yang dihasilkan dari data sample, dapat dikatakan bahwa proses masih dalam in control. Masih dapat dikatan
bahwa proses packaged dalam pengawasan yang baik. Namun demikian, Manajemen Webster juga harus selalu berhati-hati pada
proses ini demi tetap menjaga kepuasan dari konsumen.