ITS DUCT Specification
ITS DUCT Specification
J.
Once construction has begun, automated or manual recording of all operational variables,
progress, drive behavior, etc., shall be carried out to ensure compliance with the intended
set of operational variables. The record produced shall form a continuous log of all
operational variables against the completed driving distance in a properly recorded time
frame. This record may be used as a tool and reference for inspection and control, and is a
pennanent record for troubleshooting and interpretation of a drive's behavior.
Throughout NDRC construction, existing works (roads, nearby structures, and utilities)
shall be frequently monitored by Contractor personnel under the supervision of qualified
staff to detect any ground surface movement.
k.
CONSTRUCTION,OPERATIONS & MAINTENANCE SERVICES FOR ITS INFRASTRUCTURE IN ABU DHABI- PHAS E I
SECTION XVII-llIP,goJ70J
Augu" 2012
b.
Measurement and Payment. Measurement for the item, PVC Conduit, 4-Way, not
encased in concrete, shall be by tbe linear meter as included in the Bill of Quantities, wbich
amount shall include all materials, labor, tools, cabling, equipment, and other
miscellaneous and subsidiary costs required for the provision of 4-way duct not encased in
concrete, as mentioned in this Particular Specifications.
17.11.06 Install DoT Type 1 Pullbox Over Du Duct
a
General. If requested by the Department the Contractor sball install a Type I pullbox
over the Du ducts in accordance with the requirements of Du as directed by the Engineer.
The installation shall include a 2-way, IOOmm, PVC duct bank from the field equipment
cabinet to the Type I pullbox. The installation shall not cause any disruption to the Du
telecommunications network.
b.
Measurement and Payment. Measurement for the item, Install DoT Type I pullbox
Over Du Duct, shall be as the unit item as included in the Bill of Quantities, which amount
shall include all materials, labor, tools, cabling, equipment, and other miscellaneous and
subsidiary costs required for the provision of the Type I pullbox over Du Duct. The
measurement and payment for supply of Type I pullbox and 2-way duct bank shall be as
indicated elsewhere in the Bill of Quantities.
17.11.07 DoT 2-Way Duct Link into Du Pullbox
a
General. If requested by the Department the Contractor shall install a 2-way duct link
into the Du pullbox in accordance with the requirements of Du, as directed by the
Engineer. The installation shall include the installation of a 2-way, IOOmm, PVC duct from
the field equipment cabinet pullbox into the Du pullbox. The installation shall not cause
any disruption to the Du telecommunications network.
b.
Measurement and Payment. Measurement for the item, Install DoT Type I pullbox
Over Du Duct, shall be as the unit item as included in the Bill of Quantities, which amount
shall include all materials, labor, tools, cabling, equipment, and other miscellaneous and
subsidiary costs required for the provision of the 2-way duct connection into the Du
pullbox. The 2-way duct bank shall be as indicated elsewhere in the Bill of Quantities.
17.11.08 Opening Block Conduits and Cleaning Existing Manholes.
a.
General. The Contractor is responsible for clearing any blocked ducts, and if
required, cleaning the existing manholes/pullboxes from sand, silt, dirt and water on the
proposed cable routes. The Contractor shall arrange all required tools and equipments to
open any blocked conduits that obstruct the laying of the cables. The Contractor shall
utilize a water jet or metal rod or any alternate method to open the blocked conduits, as
approved by the engineer. The Contractor shall be held responsible for damages to any
existing cable runs in the blocked duct, or to any part of the duct or pullbox that is caused
by the Contractor's duct-clearing operations.
b.
Measurement and Payment. No separate measurement or payment shall be made this
item, unless specifically indicated in the Bill of Quantities. All such works shall be
considered as a subsidiary obligation to the items in the Bill of Quantities.
CONSTRUCfION, OPERATIONS & MAINTENANCE SERVICES FOR ITS INFRASTRUCTURE IN ABU DHABI - PHASE 1