P07-F06 Method Statement For Excavation
P07-F06 Method Statement For Excavation
Project Logo
Client
Consultant
Contractor
Subcontractor
Title :
DISCIPLINE: CIVIL
REV
DATE
STATUS
28-Dec-14
FA
REVISION DETAILS
Status Code:
D : Draft
P : Preliminary
FI : For Information
FA : For Approval
REVIEWER / APPROVER
Sub
Con
Main
Con
EXTERNAL
NW
FC : For Construction
* External Authorization (Client),
where required
Distribution :
Page 1 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
Table of Contents
1.
Scope /Objectives
2.
Reference
3.
Access/Egress
4.
Logistics
5.
6.
Definitions
7.
Responsibilities / Supervision
8.
9.
Training
10.
Working hours
11.
House keeping
12.
13.
Material Requirement
14.
15.
16.
Supporting documentation
17.
Distribution
18.
Other information
19.
20.
Attachments (Compulsary)
Risk Assessment
Inspection and Test Plan
Quality Control Check Lists
Page 2 of 9
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Project Logo
Client
Consultant
Contractor
Subcontractor
3. ACCESS/ EGRESS
Access will be through designated entrance and exit pathways.
4. LOGISTICS
Contractor will deploy a dedicated team for the earthwork, excavation, backfilling and shoring works.
5. HEALTH & SAFETY HAZARDS
Contractor will comply with all safety measures as applicable to project safety requirements.
5.1 Excavations shall be inspected daily by Section Engineer / Supervisor / Safety Officer.
5.2 Excavation shall be re-inspected after rainstorms, earthquakes or any other hazard increasing occurrences.
5.3 A convenient and safe means of access such as stairway, ladder or ramp shall be provided for employees to enter
and leave the excavated area.
5.4 Safe crossings shall be provided over trench excavations.
5.5 Before opening any excavation, all underground services shall be identified and the Supervisor shall explain to the
employees all the necessary precautions that need to be taken in the work preparation.
5.6 In no case the excavated material shall be placed closer than 600mm from the edge of the excavation.
5.7 Excavations shall be provided with warning barricades. Deep excavation to be barricaded with flashing lights
during night.
5.8 The sides of excavations shall be sloped in order to avoid sliding of sand / earth.
5.9 Personnel Protection Equipments shall be used at all the times.
Page 3 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
6. DEFINITIONS
AEB Arab Engineering Bureau (Consultant/Engineer)
AMTC Abdullah Al Muftah Trading and Contracting Co., w.l.l (Main Contractor)
MS Method Statement
QCP Quality Control Procedures
ITP Inspection and Test Plan
ITA Independent Testing Agency
7. RESPONSIBILITIES / SUPERVISION
The works will be undertaken by a competent workforce to do the works conforming to the project specifications through
the following responsibilities.
7.1 Project Engineer shall be responsible for the execution of this procedure and to ensure that works are undertaken in a
safe manner to the requisite quality and to the time agreed timescale. He shall advise and coordinate with other
contractors pertaining to access and interface requirements related to the excavation works to be undertaken.
7.2 Site Engineer shall be responsible for the site implementation of this procedure including control and the safety of the
workers.
7.3 QA/QC Inspector shall be responsible for the supervision of tests and inspection, control approvals for testing and
inspection plan and to arrange documentation required.
7.4 The Surveyor in coordination with site engineer has the responsibility to perform all survey works according to the IFC
drawings.
7.5 Safety Officer shall be responsible for the strict implementation of safety procedure during work commencements.
8. PROCEDURE / METHOD TO BE EMPLOYED:
8.1Preliminaries
a. Excavations shall be inspected daily by the Site Engineer / Supervisor / Safety Officer.
b. Excavation shall be re-inspected after rainstorms, earthquakes or any other hazard increasing occurrences if any.
c. A convenient and safe means of access such as stairway, ladder or ramp shall be provided for employees to enter
and leave the excavated area.
d. Safe crossings shall be provided over trench excavations.
e. Before opening any excavation, all underground services shall be identified and the Supervisor shall explain to the
employees all the necessary precautions that need to be taken in the work preparation.
f. In no case the excavated material shall be placed closer than 600mm from the edge of the excavation.Excavations
shall be provided with warning barricades. Deep excavation to be barricaded with flashing lights during
night.
g. The sides of excavations shall be sloped in order to avoid sliding of sand / earth.
Page 4 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
Page 5 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
Where necessary, all trenches and excavations will be adequately shored or supported to prevent a fall or
dislodgement of earth, rock or other material forming the side of or adjacent property to, any excavation work
from burying, trapping or striking a person that is in the excavation. Where such a risk also exists for those
installing supports, other appropriate control measures will be in place to ensure the safety of persons entering
the excavation. A shoring system will not be required if, having regard to the nature and slope of the side of the
excavation and other relevant circumstances there is no reasonable likelihood that earth, rocks other material
will fall or dislodge from a height of more than1.5m and bury, trap or strike a person that is in the excavation.
The risk assessment process will be used to identify unstable conditions and the risks involved. Shoring the
face of an excavation will proceed as the work of excavation progresses. Where a mechanical digger is used,
the risk assessment will be used to determine whether any part of the trench may be left unsupported. Shoring
may include any suitable system of temporary supports and sheeting material used to maintain the stability of
the sides of an excavation.
8.6.1 Benching and Battering Excavation Walls
Both benching and battering of excavation walls are methods of work which may be used to minimize the risk of
the soil or rock slipping onto the excavation.
If battering is implemented, it will commence from the bottom of the excavation. When benching or battering the
walls of an excavation, an angle of repose of 45 degrees will not be exceeded.
9. TRAINING
Relevant trainings and orientations have been provided to person who will perform their specified task.
10. WORKING HOURS
The working hours will be from 6:00AM to 6:00PM as agreed, with break time in between.
11. HOUSE KEEPING
Working Areas will be kept clean by disposing the waste materials at the designated areas. At the end of days work,
installation supervisor will ensure that the debris are disposed off.
12. MAN POWER REQUIREMENT
Foreman
Laborers
Operators
13. PLANT & EQUIPMENT REQUIREMENT
Excavator/Backhoe
Dump truck
14. QC APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS:
Page 6 of 9
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Project Logo
Client
Consultant
Contractor
Subcontractor
Follow approved Method Statement, ITP, QCP, HSE Plan, Material Approval & Checklist.
15. SUPPORTING DOCUMENTATION:
This MS to be read in conjunction with the below referenced documents
16. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
Project Manager
Site Engineer
QA/QC Engineer
HSE Engineer
17. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved
With Site in charge
SIGNATURE
Approved
Approved subject to compliance with
the following notes
Not Approved with reason
19. ATTACHMENTS (Compulsory)
Risk Assessment
Inspection & Test Plan
Quality Control Check Lists
Page 7 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
Page 8 of 9
Project Logo
Project Name : PRIVATE VILLA (B+G+2F) IN PLOT BVS-43@ THE PEARL QATAR
Project No. : 243
Location: PEARL QATAR
Client
Consultant
Contractor
Subcontractor
Page 9 of 9