Construction Contract Administration

The document discusses key issues related to construction contract administration for the State Government of Victoria, Australia's Department of Health. It outlines responsibilities for project managers, requirements for construction insurance, how provisional sums and quantities can impact budgets, policies around nominating subcontractors, and procedures for inspections and site meetings during construction projects. Specifically, it notes that the contractor is responsible for oversight of construction work and safety, while the superintendent oversees conformance to contract requirements and communicates with the principal. Regular site meetings should be held and minutes distributed to track project progress.

Uploaded by

Kaleelur Rahman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
208 views10 pages

Construction Contract Administration

The document discusses key issues related to construction contract administration for the State Government of Victoria, Australia's Department of Health. It outlines responsibilities for project managers, requirements for construction insurance, how provisional sums and quantities can impact budgets, policies around nominating subcontractors, and procedures for inspections and site meetings during construction projects. Specifically, it notes that the contractor is responsible for oversight of construction work and safety, while the superintendent oversees conformance to contract requirements and communicates with the principal. Regular site meetings should be held and minutes distributed to track project progress.

Uploaded by

Kaleelur Rahman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

State Government of Victoria, Australia, Department of Health

Construction Contract Administration

1.ContractAdministrationIssues

Thefollowingkeyissuesaretobeaddressedduringtheconstructionphase.

HealthService/AgencyPM(LiaisonOfficer)
WhenaHealthserviceoragencyisthePrincipal,theyshouldappointanagencyprojectmanagerwhowillact
asaliaisonofficer.Thispersonwillbetheprincipalpointofcontactforthecontractor/builderand
Superintendentandassistinprogramming,scheduling,dealingwithissuesofmaintaininghealthservice
deliverywhereworksareoccurringincludingaccessissues,commissioning,decanting,visits,openingsand
furnitureandequipmentselection.
Forlargeand/orcomplexprojects,particularlywherefacilitieswillneedtoremainfunctioningandoccupiedby
thePrincipalduringtheconstructionperiod,theliaisonofficermayneedtobeafulltimeappointment.

ConstructionInsurance
Itisessentialthattherelevantpartiesarecoveredbyinsuranceforbuildingaspectsduringtheconstruction
process,includingexistingbuildings,theworksandpublicliability.
Normally,theDepartmentarrangesPrincipalControlledInsuranceforthebuildingworks.Thestandardformof
contractAS21241992providestheoptionforthePrincipaltotakeoutsuchinsurance.Theinsuranceis
takenoutwiththeVictorianManagedInsuranceAuthority.
NotethatDepartmentalapprovalisrequiredpriortoanycapitalprojectdeviatingfromthenormalpracticeof
usingPrincipalControlledInsurance.
ThisPrincipalControlledInsurancecoverscontractworks,andpublicliability,includingallequipmentincludedin
thecontract.Thisextendstocomponentspreparedorassembledoffsite.Howeverthecoveragedoesnot
includeareasnotdesignatedinthePrincipalControlledInsurancepolicydocument,suchasthecontractors'
plantandvehicles,asbestosremoval,majordemolition,thecontractor'sandsubcontractor'spersonnel,tools
etc.TheBuilder/ContractoristorefertothePrincipalControlledInsurancepolicyfordetails,including
excessesandclaimsetc.
ThePrincipalortheSuperintendentshouldclearlyadvisetheContractorthattheexcessunderthePrincipal
ControlledInsurancearrangementsistotheaccountoftheContractor.RefertotheConstructionInsurance
Guidelineforfurtherdetails.

ProvisionalSums&Quantities
Thefinalcostofaconstructioncontractmaybeinfluencedbyprovisionalsumsandquantities.Aprovisional
sumisanominatedamountofmoney,usuallyestimatedbyaQuantitySurveyor,wheretheexactscopeand
costofspecificworkcannotbedeterminedatthestartofthecontract,suchasforremovalofrock.
Itisincludedintheoriginalcontractsum,butismonitoredcarefullysothatthesumcanbeadjustedas
required.Theprovisionalsummaybeusedforworkcarriedoutbysubcontractorsorformaterialsand
componentstobeprovidedbysuppliers,orforscheduleofratesworks,whereanagreedpriceratehasbeen
reached(e.g.$30/sqmforplasteringexistingdamagedwalls).Theseitemsareincludedwherenofirmprice
canbeobtainedorthefullextentoftheworkcannotbedeterminedatthetimethebuildingcontractislet.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 1 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


Thefinaladjustedcontractsumwillvaryfromtheoriginalcontractsumwhentheexpenditureagainstthese
itemsdiffersfromthatnominatedinthecontractdocument.Provisionalsumsandquantitiesshouldbekeptto
aminimumtominimisebudgetvariations.

PreferredSubContractors/Suppliers
TheDepartmentPolicy
TominimiserisktothePrincipal,theDepartmentrecommendsthatallsubcontracts,includingmechanicaland
electricalthatcanoftenrepresentalmosthalfoftheprojectsbudget,betenderedasacomponentofthemain
contract.Nominatedsubcontractsarenotrecommendedastheyblurrisks,liabilitiesandresponsibilitiesand
shouldbeavoidedwhereverpossible.
ConsiderationwillnotnormallybegivenbytheDepartmentfortheinclusionofnominatedorrecommended
subcontractors/suppliers.
ArecommendationcanbemadetotheDepartmentutilisingthismethodofsubcontractinghoweveritmust
clearlydemonstratewithdocumentedreasonsshowingthattheprojectwillbenefitgreatlyandthatthe
proposalissupportedbythePrincipal/agencyandSuperintendent.Exceptionswillgenerallybeconsidered
onlyif:
l

Thereisaclearindicationthattheequipment/tradebeingspecifiedcanonlybesuppliedbythe
nominatedcompanies.
Sitespecificconsiderationssuchasintegrationofspecialistworkswithsafety/firesystems.

ContractPosition
IfapprovedbytheDepartment,theSuperintendentmayproposetonominateparticularsubcontractorsor
suppliers,wheresuchworkorproductsarerecommendedtobeincorporatedinthebuilding.However,the
Governmentsupplypolicyrequirementsmustalwaysbeconsidered.Thismeansthattheselectionand
approvalofsubcontractorsorsuppliersshouldbemadeonacontestablebasis,allpartiesaretreatedfairly
anddecisionsbebasedonusingassessmentcriteriasuchasfitforpurposeandbestvalueapplicabletoall
submissions.
TheContractormaycalltendersorobtainquotationsforsubcontractsandsupplies.Whereexistingservice
providershavesufficientexpertiseandcapacity,theyshouldbegiventheopportunitytotenderforsub
contractwork.
TheSuperintendentmakesrecommendationstotheSteeringCommittee/PCGforendorsementofthe
recommendedsubcontractor/supplier.TherecommendationisnormallybasedontheContractor's
recommendation.ThisisbecausetheContractorisultimatelyresponsibleforworkandmaterialsorproducts
ofallthesubcontractors&/orsuppliers.
Options
Thereareoptionsforengaging&appointingsubcontractors/suppliers.
l

AseparatetenderisinvitedandthesuccessfultendererisnominatedtotheBuilderforinclusioninthe
Contract.Inthisinstance,thefirmisaNominated'SubcontractortotheContractor.
Alistofapprovedsubcontractors/suppliersisincludedinthetenderdocumentsadvisingtheBuilderthat
theyareresponsibleforobtainingquotationsfromtheapprovedorequivalentfirms.Inthisinstancethe
firmisselectedbytheBuilder.

TheDepartmenthasnoobjectiontotheengagementofselectedsubcontractors/suppliers.Experiencehas
shownthattheuseofselectedsubcontractors/suppliersislesslikelytoleadtocontractualdisputes.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 2 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


Inspection/SiteMeetings
Inspection
ItistheContractor'sresponsibilityandobligationtoundertaketheconstructionofaprojectinaccordance
withcontractdocuments.Thecontractormustensurethattheconstructionmeetsalltime,cost,qualityand
statutoryrequirements.Thisincludestheinspectionandsupervisionofallsubcontractorsanddaylabour.
NOTE:ConsulttheseparateOccupationalHealth&SafetyCDGforspecificsafetyrequirements.
TheContractorisissuedwitha"PossessionofSite"noticebytheSuperintendent,onbehalfofthePrincipal,
andfromthedateofpossessionofsiteisresponsibleforallpersonswhovisitthesite,whethertoperform
workofservices,toundertakeinspections,toassistwithcoordinationorattendmeetings.Allpersonsvisiting
thesitemustreportinitiallytothesiteoffice,andareusuallyrequiredtoundertakeasiteinductionarranged
bytheContractor,andaretobeescortedbythecontractoratalltimes.
Forsmallerprojects,theContractor'sforemangenerallyexercisescoordinationandsupervisionduties.On
largerprojects,supervisionandcoordinationisexercisedthroughtheContractor'steamwhichmayincludea
separateProjectManager,WorksProgrammer,SafetySupervisor,GeneralForemanandTradesForemenetc.
TheSuperintendent,ortheSuperintendent'sRepresentative(SR),isresponsibleforoverseeingthatthe
constructionworksconformtotherequirementsofthecontractandforgivingtheContractoranynecessary
instructionsorclarifications/interpretationsofthecontractdocumentsbeingusedtoconstructthefacility.
TheSuperintendentortheSRisalsoresponsibleforcoordinatingcommunicationwiththePrincipaland
Consultantsoncontractorbuildingconstructionrelatedissues.
ItistheContractor'sresponsibilitytoarrangeforthenecessaryinspections(bythecontractor,relevant
authoritiesandsubconsultants)andtokeeprecordsofthoseinspections.
TheContractormustalsoensurethatallsafetyrequirementsaremaintainedonthesiteduringconstruction.
TheContractorperformstheOH&SroleofPrincipalContractor'.
SiteMeetings
RegularSiteMeetingsshouldbeheldattheconstructionsite(sitemeetings)e.g.fortnightly.Thesemeetings
shouldbeattendedbytheContractor,Superintendent,Superintendent'srepresentative,consultantsas
requiredandaPrincipal'srepresentative(theClient).Theyshouldideallybechairedandminutedbythe
Contractor.Minutesshouldbedistributedwithinfourworkingdaysofthemeeting.Theyshouldrecordpoints
discussed,outcomes,actionstobetaken,andbywhom,andasummaryofproposed/approvedvariations.
Theminutesareagoodwayofkeepingtrackoftheprogressoftheprojectanditisusualforthe
SuperintendenttoissuecopiestotheProjectControlGroup.
Itisgoodpracticetocheckminutesforcompleteness&accuracypriortoacceptanceandincludephotographic
recordsoftheprojectwiththeminutesforreportingtothePCG.

Payments
ContractSum
UndertheContractrequirementsofAS21241992,thePrincipalagreestopaytheContractorastated
amountorlumpsumforcompletionoftheworks,subjecttotheprovisionsofthecontract.Thislumpsumis
knownasthe'ContractSum'.
ChangestotheContractSummayoccurasaresultofvariations,arisingfromrequestsforamendments,

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 3 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


generallyfromthePrincipalorHealthService/Agency,leadingtoadditions,deletionsoralterationsduringthe
courseofconstructionorforrequiredadjustmentstothecontractdocuments.
ItiscriticalfortheHealthService/Agencyandconsultantstocontrolandrestrictthesechangestoanabsolute
minimuminordertoeffectivelymanagetheprojectwithintheapprovedbudgetandprogram.
Variationsareoftenacauseofcontractconflictsandmayleadtonegotiation,mediationorarbitration.The
Principal,ContractorandSuperintendentshouldcollectivelyseektoresolvesuchconflictsattheearliesttime
andintheleastexpensivewaywhereverpossible.
ProgressPayments
TheContractorispaidprogressivelyastheworkproceeds.TheSuperintendentissuesprogresscertificates
basedonanassessmentofthevalueofcompletedwork.TheProgresscertificatestatesthatacertainvalueof
workhasbeencompletedandthereforetheworkshouldbepaidfor.ForlargerorcomplexprojectsaQuantity
Surveyorisresponsibleforassessingthestatusofthecontract'sprogressandtheevaluationofthe
Contractor'sprogressclaim.
WhenaSecurityofPayment'claimisreceivedfromthecontractor,theSuperintendentistoensure
compliancewiththecurrentprovisionsoftheSecurityofPaymentAct.Contractconditionsstipulateaspecified
period(eg28days)forthepayment.Thisperiodshouldbestrictlyadheredto.
SecurityofPaymentlegislationhasbeenenactedtoensurethatcontractorsandsubcontractorsreceive
paymentsinatimelymanner.TheeasiestwaytoavoidactivatingtherequirementsoftheSOPActistoensure
thatpaymentschedulesareissuedwithinthedesignatedperiod,thatreasonsforreducingorwithholding
paymentareclearlyexplained,andthatpaymentsaremadeinatimelymanner.
ProgresspaymentsarebasedonaprogressclaimpreparedbytheContractoronamonthlybasis.Theclaim
outlinesthebreakdownofthetradeworkandthepercentageofworkcompletedagainsteachtrade.The
progressclaimalsousuallyshowsapprovedcontractvariationsandpercentagecompletionagainstthe
variations.
TheSuperintendentand/orQuantitySurveyorwillthenverifytheamountclaimedand,ifappropriate,
recommendthatthePrincipalmakeapayment(certifytheprogressclaim).Insomeinstancestheamount
claimedmaybemoreorlessthanthevalueofworksassessedascompleted.TheSuperintendentwilladjust
progresspaymentsaccordingly.Inmakinganyadjustment,theSuperintendentshouldbeawareofGST
requirementsandmustnotifythecontractorofthereasonsforvaryingtheclaimwithinthetimespecifiedin
thecontract.
ToobtainareimbursementfromtheGovernmentfortheprogresspayment,theHealthService/Agencymust
completetheapprovedDepartmentalclaimformandforwardthis,togetherwithacopyofcertifiedprogress
claim,totheDepartment.

Variations
AvariationcanbestbedefinedasThechangeormodificationofthedesign,qualityorquantityoftheworks
ortheadditionoromissionorsubstitutionofanywork,materialsorgoods'.
VariationscanonlybeimplementediftheSuperintendentissuesaninstructioninwriting.Variationsmayoccur
becauseof:
l
l
l

CorrectionoferrorsandomissionsintheContractdocuments
Site/buildingconditionsdifferingfromthosedescribedintheContractdocuments
ChangerequestedbythePrincipal(theseshouldbekepttoanabsoluteminimum).

Somevariationsentailcostand/ortimeadjustmentstothecontract.Suchvariationsshouldbepricedbythe

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 4 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


Contractor,valuedbytheQuantitySurveyorandacceptedifsatisfactorybytheSuperintendentpriortobeing
implemented.
TheextenttowhichavariationtotheworksisreflectedinanadjustmenttotheContractSumisdetermined
bythevaluation'ofthevariation.Afteravariationhasbeenvaluedandagreed,anadjustmentcanbemade
totheContractSum.
Thedepartmentrequiresthattheprocessforapprovingvariationsismanagedinamannerthatisrigorous
andconsistentandatemplatehasbeendevelopedformanagingthevariationofacontractseesampleform
attachedinAppendix7.
RefertoGovernanceguidelinesondelegationsregardingapprovalsofvariationsandfinancialpowers.

ContractSumAdjustments
AContractSumadjustmentisamonetaryadjustmenttotheinitialContractSum,duringthecourseofthe
contract.
ThefinalContractSum,afterContractSumadjustment,maybeforahigherorloweramountthantheoriginal
ContractSum',dependingonthenatureoftheadjustment.
SomeContractSumadjustmentsmayoccurasaresultof:
l
l
l
l
l
l

Approvedvariations
Superintendent'sinstructions,orlackofthem
DiscrepanciesarisingfromquantitiesspecifiedinthecontractortheBillofQuantities
ChangestoAuthoritylevies
Unexpectedsiteconditions(latentconditions)or
Provisionalsumsincludedinthecontractbeinginsufficientorexcessivefortheactualcostofthechosen
productorworkactivity

Variationsmaycauseareductionorincreasetotheoriginalscopeofthecontract.

ContingencySum
Acontingencyamountshouldnormallybeallowedinthebudgetfornewandrefurbishmentworks.The
SteeringCommittee/PCGcansetaseparateamountdependingonthespecificsoftheproject.Theamount
shouldneverbedisclosedorstatedinthetenderorcontractdocumentsnorshouldthisinformationbe
providedtopartieswhomaycommunicatewiththeContractor.ThissumisavailablesolelyforthePrincipalto
managerisksandisintendedtocoverthecostofunknownsorunforseenmattersthatmayariseand
adjustmentsfordiscrepanciesinthedocuments.Theamountisnotavailableforincreasesinthescopeofthe
project.
ContingencyisakeyelementtobeestablishedandmanagedbytheSteeringCommittee/PCGtoensurethe
projectisconstructedappropriatelyandwithintheallocationprovidedbytheDepartmentofTreasury&
Finance.
TheprojectbudgetincludescontingenciesthataretobeapprovedbytheDepartmentfollowingendorsement
bytheSteeringCommittee/PCGwhoshouldassesstheneedtousethecontingenciesbasedona
recommendationfromtheSuperintendent.

WorksProgramming
TheContractorisresponsiblefortheprogrammingoftheworkstoachievecompletionwithinthecontract
period.Theconstructionprogramsequencescontractactivitiesandtrades,showingdurationsand
dependenciesandtheexpecteddatesforachievementofmilestonessuchasstructurallockup',services

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 5 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


commissioningandhandoveretc.
Thesequencing,dependenciesanddurationscollectivelydefinethecriticalpath',whichistheshortestperiod
inwhichthecontractworkscanbecompleted.TheContractormustkeeptheprogramuptodateasdelaysto
oraccelerationofactivitiescanleadtochangesinthecriticalpath.
TheSuperintendentshouldregularlyreporttothePCGonthecriticalpath,achievementoforchangestothe
worksprogram,toenabletheagencytocoordinatetheirownactivitieswiththebuildingworks.

ExtensionsofTime
Foravarietyofreasons,acontractormaybeunabletocompletetheWorksbythedatestipulatedinthe
contract.ThedelaysmaybeoftheContractor'smakingorattributabletocircumstancesbeyondthe
Contractor'scontrol.Whenthelatteroccurs,theContractorisentitledtoanextensionoftimetothecontract
period,asjustifiedagainsttheconstructionprogram.
Therearetwotypesofextensionsoftime.Those:
l
l

Withoutcostimplication
WithcostimplicationsthesearecalledProlongation.

Generally,extensionsoftimewouldnotleadtoanincreasedcost.Wherethedelayisduetotheactionsofthe
Principal(client)whichthereforeaffectstheprogrammedcriticalactivities,thentheContractorhasan
entitlementtoreasonablecostsfordelay..
Causesofdelaymayincludethefollowing:
WithoutCostImplicationstotheContract
l
l
l

Industrialdisputese.g.StatewideorNational
Inclementweather
Delaysinreceivingpermitsandapprovalsfromauthoritiesorutilitycompanies.

PotentialforCostImplicationstotheContract
l
l
l

DelaysbytheSuperintendentingivinginstructionsorresponsestothecontractor
Majorvariationstoconstruction,planningordesignapprovedbythePrincipal
Instructionstodeferordelayaportionorthewholeoftheworkduetooperationrequirementsofthe
HealthService/Agency.

Notethat:
l

Unexpectedsiteconditions(incertaincircumstances,costsmaybeapplicable)mayfallintoeither
category

Itisnotalwayseasytodetermineifaparticulardelaywillwarrantanextensiontothetimeofthe
contract.TheSuperintendentmayrequestthattheContractorjustifyclaimsforextensionoftime
throughthepresentationofarecent(nomorethan14daysold)criticalpathprogram/diagramforthe
contractworks.

PracticalCompletion
Theterm'PracticalCompletion'describesthestagewhen
l
l

theworkhasbeencompleted,allequipmentinstalled,testedandfoundtobeinrunningorder,
theprojectisdeemedsafeandfitforoccupationtothesatisfactionoftheSuperintendent.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 6 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


l
l
l

thefacilityisfitforitspurpose,complieswithservicedeliveryperformancerequirements,and
thefacilitycommissioninghasbeenundertaken
operationandmaintenancemanuals,traininganddocumentationhavebeenprovided.

TheAustralianStandardcontractAS21241992providesthattheSuperintendentmayissueacertificate
statingadatethat,intheSuperintendent'sopinion,thebuildingworksarePracticallyComplete',meaning
thatallworksarecomplete,withtheexceptionofminoromissionsanddefectswhichwillnotaffecthandover
to,andoccupationby,thePrincipalandfacilityusers.Atthistimethefinalisedworksarehandedovertothe
HealthService/AgencywithnecessarydocumentationincludingaCertificateofOccupancy,operationmanuals,
warrantiesetc.
PracticalCompletiondoesnotrelievethecontractorfromtheneedtorectifyomissionsanddefectsinatimely
manner,anditisimportantthattheSuperintendentcloselymonitorsprogressonrectifyingomissionsand
defects.
ItisimportanttodetermineandadvisetheDateofPracticalCompletionforitscontractualimplications.
Othercontractualeffects,whichoccuratthetimePracticalCompletionisreached,arethe:
l
l

Beginningofthedefectsliabilityperiod
Contractualendtothecontractor'sliabilityforliquidateddamagesorthePrincipal'sliabilityfor
prolongationcosts
Partialreductionofsecurityorbankguarantee,requiredunderthecontract.

WhereaprojectcontainsSeparablePortions',applythePracticalCompletionindividuallytoeachofthe
separableportionsunderthecontract.
ThePrincipalhasnocontractualrighttooccupyanypartoftheworksarea(portionofthesiteforwhichthe
contractorisgivenpossessionforthepurposeofexecutingtheconstructionworks)beforePractical
CompletionwithouttheconsentoftheContractor.TheDepartmentrequiresthatoccupationoccuronly
followingtheissueofaCertificateofOccupancy.
AfullinspectionpriortoissueofaPracticalCompletioncertificateisnecessary.Ifthefacilityisnotsuitablefor
occupancy,afollowupinspectionwillberequiredfollowingremedialworksbythecontractor.
AnomissionsanddefectslististobepreparedbytheSuperintendentandprovidedtotheContractorat
PracticalCompletion.Itshouldonlycontainminoromissions&defectsthatdonotrestrictthefacilitybeing
usedforitsintendedpurposeorrequireclosureforrestorativeworks.

LiquidatedDamages

Underthecontract,iftheContractorfailstobringtheworkstoastageofPracticalCompletionbythedue
date,(i.e.thedatestatedinthecontract,adjustedforanyagreedextensionsoftime)thenthePrincipalis
entitledtoLiquidatedDamages(LDs).TheamountofLDsissetoutinthecontractatthestartoftheproject
andmustbejustifiable(seebelow).
Itisimportantthatalltimebasedcontractualissuesrelatedtovariationstotheoriginalscopeofworksand
otherdelayshavebeenresolvedpriortotheapplicationofLDs.
LossesandcostsduetodelaycanbeclaimedattheratestatedinthecontractbytheHealthServiceor
Agency,providingthecorrectstepshavebeenfollowed.Thenominatedamountsmusthavebeenagenuine
pretenderestimateofcostsandmustbeabletobesubstantiated.Forexample,thecostofengagingan
alternativefacilitytodeliverhealthservicesorcostsassociatedwithcontinuingtousetheexistingfacilities.
Asaminimum,LDsmaybebasedonthecapitalinvestmentatthelongtermbondrate,plusanallowancefor
additionalcostsofmaintainingtheSuperintendentandotherConsultantsforanextendedperiod.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 7 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


TheHealthService/AgencyisnotifiedoftheLDsthataretobedeductedfromthecontractsum,bythe
Superintendent.
LDsarenormallyassessedatthetimethatcontractualissuesarebeingcompletedandoutstandingvariations
areconsidered.

ProlongationCosts

Inthestandardcontractformthatgovernstheusuallumpsum'buildingcontract,thebuilder/contractoris
responsibleforthemajorityofrisks.However,delaysandcostsmayresultfromthePrincipal'sinstructions
causingadelay.SuchdelaysincludeadelayinmakingdecisionsorinprovidinginformationtotheContractor
ormayarisefromexcessiverequestsforvariationsandchangestobemade.
TheContractormaybeentitledtoclaimcompensationunderthecontractfordelayscausedbyothers,egthe
SuperintendentorPrincipal.Theclaimmaybeforidleequipment,staffandoverheadse.g.scaffoldingplant,
cranes,foreman'stime,officesandshedsdisruptionsoftheprogramstorageandothercosts.
TheSuperintendentistonotifythePrincipalandProjectControlGroupifsuchanissuearisesandthemajor
costimplicationsinvolved.ProlongationclaimsshouldbevaluedbytheQuantitySurveyoranddeterminedto
beclearlyjustifiablepriortoendorsementbytheSuperintendent.Departmentapprovalisrequiredofall
prolongationcostclaimspriortotheiracceptance.

SecurityandRetentionMoneys

ToensurethattheContractorperformsinaccordancewiththeContract,thePrincipalshouldrequestan
appropriateformofguaranteefromtheContractor.
Themostcommonformsofguaranteesare:
l

Security(PreferredOption)TheacceptancefromtheContractorofanunconditionalbankguarantee.
Similarformsofsecuritymaybeconsidered.Theamountisequivalenttotheamountstatedinthe
contractandisheldbythePrincipalshouldtheContractordefault.Theamountofsecurityisnormally
setbyassessingfinancialrisk.Anindustrystandardminimumis5%oftheContractSum

Thenormalpracticeisforsecurity,intheformofabankguarantee,tobeprovidedtothePrincipalfollowing
tenderacceptance,andpriortositepossessionbythecontractor.Itisheldintwoequalparts.Halfisnormally
releasedatPracticalCompletionandthebalancewhenFinalCertificateisissuedafterthedefectsliabilityperiod
hasfinished.
Thisformofguaranteeisrecommendedforallcontractsinexcessof$1Musingthestandardformavailable.
ThebalanceofsecuritymustbereleasedontheissueoftheFinalCertificate.
l

RetentionMoneys(NonPreferredOption,butmaybeapplicabletoverysmallcontracts,generally
below$50,000.)Apercentage(upto10%)oftheamountdueoneachprogresscertificate(payment)
isretaineduntilastatedsumisreached.ThissumisasafeguardforthePrincipalshouldtheContractor
default.Itisknownastheretentionamount.Normallythetotalretentiondoesnotexceed5%ofthe
ContractSum.HalfoftheretentionisnormallyreleasedtotheContractoronissuingthenoticeof
PracticalCompletionandthebalancewhentheFinalCertificateisissued(afterthedefectsliabilityperiod
hasfinished).

DefectsLiability

ThedefectsliabilityperiodistheperiodstatedintheContractthatprovidesfortherectificationofminor
defectsand/oromissionsoritemsthatfailtoperformsuitably,thatmaybeoutstandingoroccurafter
PracticalCompletion.ThePrincipal,SuperintendentandContractorstillhaveobligationsandrightsduringthis

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 8 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


period.Theremayalsobeparticularitemsofequipment,finishesandservicesunderparticular
warranties/guarantees(e.g.roofing),whichexceedtheDefectsLiabilityPeriod.Theseguaranteesrequire
Contractorsignoffandcontinualmonitoringuntiltheirexpirydate.
CareistobetakenbythePrincipal,nottovoidwarrantiesortheContractor'sresponsibility,e.g.byusing
anothercontractortoundertakerepaironworksorequipmentassociatedwiththecompletedmaincontract,
duringthedefectsorwarrantyperiod.
AminimumDefectsLiabilityperiodof12monthsisrecommended.ThePrincipalshouldcheckwiththe
Superintendenttodeterminethemostsuitableperiodoftime,andtoarrangeaprocessfortherecordingand
referralofissuesforactionbytheContractor.

FinalCertification

UponcompletionoftheDefectsLiabilityperiodtheSuperintendentissuesaFinalCertificateonthebasisthat
theContractorhasrectifiedalloutstandingomissions/defectsaccordingtothecontract.Thisusuallyinvolves
afinalinspectionbyallparties.

IssuesRequiringSpecialAttention

Consultantsaretoensurethatthecontractdocumentationisclear,anddrawsattentionofcontractorsto
theseimportantphasesofprocurement.Keyissuesofconcerninclude:
l

WorkinanOperatingFacility:

Awarenessoftheimpactonhealthandrelatedservicesbeingdeliveredbyconstructionactivitiesinvolving
essentialservices,access,infectionandnoisecontroletc.isvital.Measurestomitigaterisksorreduce
negativeeffectsneedtobesetoutbythePrincipalandSuperintendentforprojectswhereconstructionwork
isbeingundertakeninanoperatingfacility.
l

CommissioningPeriod:

TheContractadministratorshouldbeawareofthenecessityofallowingfortwocommissioningperiods.
l

Period1fortheContractoranditssubcontractorstoensureoperabilityofbuildingsandservices
tocomplywiththecontract'sTechnicalPerformanceRequirements'.
Period2forthecontractortorecommissionfollowinghandovertoandoccupationbyusersof
thefacilitytoensureproperperformanceinaccordancewiththeiruserrequirements,following
occupancy.

CertificateofOccupancy:

Toobtainthiscertificatethemaintenancemanualrequirementsmustbetakenintoaccount,whichincludesthe
maintenanceofessentialservices,plusreportingandrecordingrequirements.
UndernocircumstancesisafacilitytobehandedoverwithoutanoperationmanualbeingprovidedforHealth
Service/Agencyuseaswellasallemergencybackuparrangements.
l

EnvironmentalSustainability:

Variousenvironmentalissuesmustbecontrolledandmonitoredduringconstruction,suchasuse/wasteof
water,recyclingofmaterialspowerandotherservices,dustandnoisegenerationandstormwaterrunoff
fromthesite.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 9 of 10
Generated at 17-Nov-2014
22:32:43 PM

State Government of Victoria, Australia, Department of Health

Construction Contract Administration


Checklist
Thisisthechecklistthatrelatestothecontentofthisguideline.
TheContractAdministrationchecklististobecompletedandsignedwitheachprojectandsenttothe
appropriateDepartmentalProjectManager.

Checklists
ContractAdministrationChecklist(pdf,31.1KB)
TheContractAdministrationchecklististobecompletedandsignedwitheachprojectandsenttothe
appropriateDHSProjectManager.

Examples
Thesearetheexamplesthatrelatetothecontentofthisguideline.

ExampleFiles

LetterofNominationofSuperintendent(MSWord,27.0KB)
ThisletterisatemplatethatshouldbeusedtoassistinnominatingtheSuperintendent.
MonthlyReportsSiteMinutes(MSWord,92.5KB)
SiteMinutesaretobecompletedaspartofthemonthlyreport.
ContractAdministrationCostVariationsExample(MSWord,37.0KB)
TheCostVariationsformistobecompletedasrequiredforpaymentpurposes.
ContractAdministrationProgressFinancialStatus(MSWord,23.0KB)
TheProgressFinancialStatusFormistobecompletedbytheQuantitySurveyorandsubmittedwiththe
monthlyreport.
ContractAdministrationSampleProgressClaim(MSWord,42.5KB)
TheProgressClaimformistobecompletedtoreceivepayment.
ContractAdministrationSampleVariationForm(MSWord,61.0KB)
TheVariationsformistobecompletedasrequiredforvariationpurposes.
ContractAdministrationSampleProgressCertificateForm(MSWord,23.0KB)
TheProgressCertificateFormverifiesthatworkshavebeencompletedandpaymentcanbeprocessed.
ContractAdministrationCapitalPaymentClaimForm(MSWord,181.5KB)
TheAgencycompletesthisformaspartofthepaymentprocess.

For information relating to this content contact:


Capital Projects and Service Planning, Department of Health
Email: [email protected]

Page 10 of 10