Project Feasibility Study Checklist
Project Feasibility Study Checklist
Project Delivery
267518010
Maintainer: [email protected]
Version: 20120622
Page: 1 of 5
Existing Facilities
a. Inventory and Gross Floor Areas
b. Condition assessment/serviceability
Area Requirement
a. Net Floor Areas
b. Gross Floor Areas
c. Efficiency Factors
Special Requirements
a. Voice, Data and Video Communications
b. Energy Management Systems
c. Power Supply
d. Building Services
e. External Works
f. Impacts on other buildings
g. Loose Furniture
h. Major Laboratory Equipment
Performance Specifications
A basic summary of the project building structure, exterior and roofing, interior finishes, and major
mechanical and electrical systems, as well as any special systems such as telecommunications.
Scope of external works, paving and landscaping. Quality of internal furnishings, fittings and
equipment.
Future Requirements
267518010
Maintainer: [email protected]
Version: 20120622
Page: 2 of 5
Purpose A brief statement as to the specific problem or objective that creates the need for the
project:
Alternatives Considered Give a brief description of each alternative that was considered. Also
describe why the alternate is not proposed.
Project Management Detail the management method proposed to procure the design and
construction of the project. An organisational chart should identify in-house and consultant services
required to procure the project. Options such as project management, design & construct,
construction management, staged construction, fast tracking, negotiated tender, or cost-plus
construction should be considered.
Schedule The Feasibility Report should include a milestone schedule for the project, including
budget approval, design, bid, construction, equipment installation, testing, start-up, and full
operation milestone target dates. Possible staging of the project should be discussed. Long lead
time supply items should be identified. The schedule should reflect the recommended
management method as discussed above. Attention should also be paid to the funding schedule
when will funds be available for the project phases?
267518010
Maintainer: [email protected]
Version: 20120622
Page: 3 of 5
Physical Issues
a.
Topography
b.
Geotechnical/Soils
c.
Utilities and/or Services Infrastructure
d.
Environmentally Sensitive Conditions
e.
Hazardous Materials (asbestos, contaminated soil etc.)
a.
Planning Issues (zoning)
b.
Requirements of Local Authorities
c.
Building Codes and Requirements
f.
Disability Discrimination Act
g.
Permits
h.
Master Plan Implications
i.
Heritage Issues
j.
Adjoining Owners
k.
Parking
l.
Building Loading Bay, and Delivery Points
m.
Construction Issues (noise, access, site sheds, deliveries, craneage, scaffolding, site
deliveries and storage)
n.
Construction EH&S issues (noise, dust, stormwater discharge, excavation, protection of
public).
Preferred Sites
a.
Opportunities
b.
Limitations
Conclusions
c.
Cost Estimate Comparisons
d.
Conceptual Drawings
267518010
Maintainer: [email protected]
Version: 20120622
Page: 4 of 5
Cost/Benefit Analysis
Life Cycle Costing Assumptions and Conclusions on Critical &/or Major Expenditures
PROJECT DRAWINGS
Site Plan
Shading Diagrams
Staging Plan
267518010
Maintainer: [email protected]
Version: 20120622
Page: 5 of 5