Lessons Learned from the Texas City
Refinery Explosion
Mike Broadribb
Mary Kay OConnor Process Safety Center Symposium,
College Station, Texas
October 24, 2006
Texas City Refinery
Texas City refinery is located 40 miles from
Houston in Texas, USA
1600 people work at the refinery plus
contractors
It is one of the largest refineries in the USA,
processing 460,000 barrels of crude oil/day,
around 3% of gasoline US supplies
The accident
An explosion and fire occurred at the
refinerys isomerization unit
The explosion happened at 13:20
(Houston time) on March 23, 2005
15 people died and many more were
injured
Note: The isomerization unit boosts the
octane of gasoline blendstocks.
Simplified block diagram of Raffinate Splitter
Vent Relief system
Feed Heat
Exchanger
Condensate
Bottom
Product
Blowdown
stack
Feed
Furnace
Raffinate
Splitter
Raffinate Splitter and Blowdown Drum Stack
Raffinate Splitter Tower
Blowdown Drum Stack
Aerial Photograph of Isomerization Unit
What happened ?
Prior to Feb.
15
Temporary trailers placed 150 feet from the Isomerization unit. They were
being used by personnel preparing for a turnaround at another part of the
refinery
Feb. 21
Shut down part of the Isomerization unit to refresh the catalyst in the feed
unit
March 22
March 23
On the night shift, the raffinate splitter was being restarted after the
shutdown. The raffinate splitter is part of the Isomerization unit that distils
chemicals for the Isomerization process
Splitter was over-filled and over-heated
When liquid subsequently filled the overhead line the relief valves opened
This caused excessive liquid and vapour to flow to blowdown drum and vent
at top of the stack
An explosion occurred which killed 15 people and injured many others
Texas
TexasCity
CityRefinery
RefineryMarch
March23,
23,2005
2005
15
15People
PeopleKilled
Killed
Many
Manymore
moreinjured
injured
AAcommunity
communitydevastated
devastated
Incident
Isomerization Unit
Satellite Control Room
Inside Satellite Control Room
Cooling Tower
Trailer
Catalyst Warehouse
Storage Tank
Isomerization Unit
Double-Wide Trailer
10
Double-Wide Trailer
Key Issues
Operator Inattention
Following Procedures
Supervisor Absence
Communication shift handover
Trailers Too Close to Hazards
Some Instrumentation Did Not Work
Tower Level Transmitter Worked as Designed
Abnormal Start-ups
Investigation of Previous Incidents
Blowdown Drum Vented Hydrocarbons to Atmosphere
Opportunities to Replace Blowdown Drum
Evaluation of Connection to Flare
Key events timeline - 2005
Texas City
Incident
CSB safety
recommendation:
form an
Independent
Panel
23rd March
17th May
BP Incident
Investigation Team
established
BP Incident
Investigation Teams
Interim Report
published
17th August
CRITICAL FACTORS
OSHA and BP
Products
N America BP Announces
settlement
Formation of
agreed
Independent
Panel
22nd September 24thOct 27thOct
CSB
Preliminary
Findings
9th December
BP Incident
Investigation Teams
Final Report published
UNDERLYING
CAUSES &
CULTURAL ISSUES
BP incident investigation team reports
The Interim Report identified 4 critical factors; the Final Report
confirmed the critical factors and identified underlying cultural
issues:
CRITICAL FACTORS:
UNDERLYING CULTURE:
Insufficient business context
Safety as a priority
Organizational complexity
Inability to see risk
Lack of early warning indicators
Start-up procedures and
management oversight
Loss of containment
Design and engineering of
blowdown unit
Control of work and trailer siting
Underlying Cultural Issues
Business Context
Inability to See Risk
Motivation
Hazard Identification Skills
Morale
Understanding of Process Safety
PAS Score
Facility Siting
Vehicles
(Process) Safety as a Priority
Emphasis on Environment and
Occupational Safety
Lack of Early Warning
Depth of Audit
KPIs for Process Safety
Organizational Complexity &
Capability
Sharing of Learning / Ideas
Investment in People
Layers and Span of Control
Communication
Technical Lessons Learned
Many Lessons from Texas City
Level Indication
Blowdown Systems
Relief Systems
Facility Siting
Level Transmitter
Design typical of many in the industry
Displacer type instrument
Not faulty worked as designed before, during and after the incident
Trending downwards (but other data available)
Lessons Learned
Functionality changed when top tap flooded
Raffinate Splitter Bottoms Level
Level instrument submerged early with cold raffinate
Instrument output changed from reading liquid level to indication of buoyancy
As raffinate temperature went up (green), density decreased (purple)
Level output on the DCS screen decreased (blue)
Bottoms Level Indicator Performance
100
600
Bottoms Level Indication (%)
Estimated Density (lb/ft3)
Relative Density
Bottoms Temperature (F)
500
80
400
70
300
60
200
50
Bottoms Temperature (F)
Bottoms level Indication and Bottoms Density
90
100
40
30
3/23/05 10:00 AM
0
3/23/05 11:00 AM
3/23/05 12:00 PM
3/23/05 1:00 PM
Level Transmitter
Displacer type instrument
Not faulty worked as designed before, during and after the incident
Trending downwards (but other data available)
Design typical of many in the industry
Lessons Learned
Functionality changed when top tap flooded
Critical high level alarms/trips ? LOPA
Robust testing procedures and documentation of instrument testing
Blowdown Systems
Commitment to replacing blowdown drums on light
hydrocarbon duty
Survey all sites
Lessons Learned
Design basis sometimes unclear mods. over time
Some have flammable liquids (flash < 100F)
Limited understanding of vapor dispersion
Drums may be too small
- inadequate liquid holdup
- vapor/liquid disengagement
Discharge to sewers sometimes not well
understood
Quench designs may be ineffective
- Lack of contacting internals
- Inadequate or non-existent controls
- Potential for steam explosions
Potential for stack fire/explosion due to inadequate
purge
10
Blowdown Systems
Wider Issues
Atmospheric Relief
Variable practice
More common in USA
Vent Pipe Design
Dispersion adequacy ?
Possibility of liquid under upset
conditions ?
11
Relief System Studies
Design
Sites generally have some design basis documentation
Some very good practices in place
Completeness and format vary widely, no common framework
Some not updated for current operation
ACTION: Implement common practice for relief system documentation
ACTION: Improve MOC process to capture relief system changes
Accountability
Some sites have no accountable person for relief systems process design
Expertise and technical knowledge of pressure relief systems is limited
ACTION: Appoint SPAs
Competency
Operator training is critical to understanding relief system operation and for emergency
response
ACTION: Enhance program of training and drills
12
Facility Siting
Trailers used as temporary buildings
Local practice based on API RP 752 used for siting
Adopted own occupant vulnerability correlation as
allowed by API RP 752
Predicts lower vulnerability than CCPS
Predicted Side-On Pressure Contours (in psi)
Facility Siting
Trailers used as temporary buildings
Local practice based on API RP 752 used for siting
Adopted own occupant vulnerability correlation as
allowed by API RP 752
Predicts lower vulnerability than CCPS
Overpressure at trailers: 2.5psi peak side-on
430 psi.ms impulse
At 2.5 psi (side) CCPS/API predicts 50% vul.
Lessons Learned
CCPS vulnerability correlation may not be
conservative
Long impulse duration ?
API RP 752 may not be as conservative as thought
and is currently under review
BP commitment no trailers in h-c areas
3
Reminder of the Swiss Cheese Model
Hazard
Hazards are contained by multiple
protective barriers
Protective
Barriers
Weaknesses
Or Holes
Barriers may have weaknesses or
holes
When holes align hazard energy is
released, resulting in the potential for
harm
Barriers may be physical engineered
containment or behavioral controls
dependent on people
Accident
Holes can be latent/incipient, or
actively opened by people
Texas City Explosion
Hazard Management Diagram
Hierarchy of control Bias towards hardware/inherent safety & reducing the scope for human error multi barrier defence
Relief and
Blowdown
System
Control, Alarm &
Shutdown system
Inherent Design
Plant Layout
Effective
Supervision
/ Leadership
Operations
Procedures
Learning from
the Past
Maintenance
& Inspection
Work Control
Audit & Self
Regulation
Training &
Competency
Active & Passive
Fire Protection
Communication
Rescue &
Recovery
Escape /
Access
Management
of Change
Investigation &
Lessons Learned
Support to Next
of Kin & Injured
HAZARD
REALIZATION
HAZARD
Normal
Hydrocarbon
Inventory in
Raffinate
Splitter
Loss of
containment
Ignition
Explosion
Inventory
increased
Proximity
of nonessential
personnel
to hazard
Flare not
used
Multiple fatalities
and injuries
No up to
date relief
study design
basis
unclear
Capacity
of
blowdown
drum
exceeded
Operate
outside
envelop
No failsafe
shutdown
No mass
balance or
attention
to other
data
Lost
process
control
Faulty
high level
alarm not
reported
Previous
incidents &
upsets not
reported
Admin.
rather than
ISD
solutions
Hierarchy
of control
not applied
Procedures
not followed
Steps not
signed off
Use of
local
practices
Failure to
recognize
hazard to trailers
from start-up
People not
notified of startup
Multiple sources
of ignition in
adjacent areas
Inadequate
HAZID skills
Lack of
underpinning
knowledge
Failure to
follow
procedures
Confusion
over who was
in charge
No verification
on procedures
in use
Absent from
unit at critical
times
Pre-start-up
review not
performed
Procedural
compliance not
checked
Supervisor offsite
No interventions
Inadequate KPIs
for process safety
No effective
handover
between
shifts
Unit alarm
not sounded
No / incomplete
MOCs for trailer
siting
Blowdown drum
modified without
rigorous MOC
Active &
passive fire
protection
Emergency
response by site and
external authorities
Hospitalization
Access & escape route
diversity
Access to scene
Strategic concepts
In order to reduce the potential for future major incidents and losses, three layers of protection are to
be considered:
plant engineering hardware, control systems, and layouts to eliminate, control and mitigate
potential hazards to people, and improve productivity
processes management systems to identify, control and mitigate risks, and drive continuous
operational improvement
people capability of our people in terms of leadership skills, relevant knowledge and
experience, and the organizational culture they create
In layers of protection, hard barriers are more reliable than soft barriers, but all rely on people
hazard
reduction
hard barriers
soft barriers
accident
or loss
hazard
physical
controls
procedures
generic
systems
peoples
behaviors
Principal actions
Plant
No trailers or temporary accommodation to be placed inside areas (of
refineries) containing hydrocarbons, even if the assessment of risk is
negligible
Blowdown stacks used for light hydrocarbon to be phased out as quickly as
possible
Process
Operating procedures to be clear, appropriate for their purpose, and always
followed
People
Build capability for operational leadership, supervisors, and technicians
Other Actions
Texas City
Organization, accountabilities, communication,
$1 billion investment program, off-site offices, facility siting study, trailers removed,
reduced vehicles, blowdown stacks in light h-c duty being removed, engineering
studies (relief systems and SCE),
Supervisory oversight, operator training.
BP Group
Safety & Operations organization,
Assessment of temporary buildings, removal of blowdown drums, engineering
studies of atmospheric vents
Review of operating procedures,
Development of OMS, implementation of CoW and IM standards,
External
Assisting API, sharing lessons learned
Other BP Activities Associated with the
Response
Government Agencies
Continue to cooperate with government agencies and proactively share
reports and findings
US Chemical Safety Board
Continue discussions with CSB incident investigators in an effort to achieve a
common understanding of the facts
Independent Panel
Voluntarily appointed an independent panel, comprised of world renowned
experts, chaired by Former US Secretary of State James Baker
What can we learn from this incident ?
Many lessons that can be learnt from Texas City, including:
Temporary building siting is a critical step in managing flammable / toxic
risks
Atmospheric venting needs careful design and operation
Procedures are ineffective if they are not up-to-date and routinely followed
Competency and behaviors of Operations leadership, supervision and
workforce are fundamental to safe operations
Other lessons involve management visibility and accountability, hazard
identification, hazards of startup operations, performance measures for
process safety, emergency drills, etc.
Incident investigation report available at: www.bpresponse.org
10