Revised Final Estimate of Earth Mat - 220kV Yard
Revised Final Estimate of Earth Mat - 220kV Yard
Quantity
Details of Work
Rate
Per
Unit
Amount
280.000 m3
m3
213360.00
285.000 m3
m3
178794.75
100.000 m3
m3
3995.00
m3
m3
31205.20
m3
m3
27002.60
m2
m2
6635.00
17.000
4.000
25.000
39.95
Sl.
No
.
Quantity
###
Details of Work
Rate
Per
Unit
Amount
R. m
431400.00
59.25
No.
56287.50
84.65
No.
110045.00
Qtl
191207.50
No.
14376.00
###
Sl.
No
.
Quantity
Details of Work
Rate
Per
Unit
Amount
60.000
No.
103170.00
###
No.
776837.50
No.
130442.00
12 200.000
13
14
29270.00
Sl.
No
.
Quantity
Details of Work
Rate
Per
Unit
No.
Amount
36534.00
197880.00
No.
157465.00
Nos.
17
###
20175.00
Sl.
No
.
Quantity
Details of Work
Rate
Per
Unit
Amount
No.
83210.00
m3
m3
54170.90
22 150.000 m2
m2
41535.00
No.
23787.00
No.
76398.00
21
7.000
90.95
Total
Service Tax @ 12.36%
Add for Unforeseen
Grand Total
###
###
###
###
Particulars
No.
Total
Unit
50.00
75.00
0.10
375.000
51.00
35.00
0.10
178.500
553.500
276.750
Add extra
3.250
Total
280.000
m3
50.00
75.00
0.05
51.00
35.00
0.05
187.500
89.250
276.750
Add extra
8.250
Total
Additional head load conveyance required for
items 1 & 2 above 100m for every additional
50m of 40mm broken stone, Mixture of broken
stones and dirty sand, River sand / quarry dust
etc as per the direction of departmental officers
at site.
285.000
m3
100.000
m3
3
3
4
1.00
1.00
0.25
1.00
1.00
0.25
2.00
2.00
1.00
6.000
6.000
0.250
12.250
Add extra
4.750
Total
2.00
2.00
1.00
17.000
m3
4.000
m3
5.00
5.00
1.00
25.000
m2
10
11
35.00
75.00
350.000
825.000
8
8
101.00
40.00
808.000
320.000
2303.000
Add Extra
97.000
Total
2400.000 R. m
37
90
37.000
90.000
25
90
406
234
25.000
90.000
406.000
234.000
882.000
Add Extra
68.000
Total
950.000
No.
500
466
256
500.000
466.000
256.000
1222.000
Add Extra
78.000
Total
1300.000 No.
2400
2400.000
15
135.000
125
120
466
400
256
1.8
3
1.5
0.15
1
225.000
360.000
699.000
60.000
256.000
m
m
m
m
m
4135.000
Weight = 6.3kg/m
###
kg
Add Extra
1449.500
kg
Total
275.000
Qtl
11
71
21
12
Add Extra
Total
71.000
21.000
12.000
104.000
16.000
120.000
No.
200
200.000
60
60.000
No.
400
400.000
18
18.000
466
466.000
512
512.000
1396.000
Add extra
54.000
Total
1450.000 No.
11
88.000
21
168.000
Auxiliary Mat
25
225.000
481.000
Add extra
39.000
Total
520.000
No.
71
71.000
21
21.000
Transformer
12
12.000
104.000
Add Extra
16.000
Total
120.000
No.
1526.000
174.000
1700.000
326
326.000
24.000
Total
350.000
No.
100.000
No.
100
140
140.000
60.000
200.000
48
2.00
0.10
0.60
No.
5.760
1.240
7.000
m3
48
2.4
0.6
69.120
Inner side
48
1.6
0.6
46.080
115.200
Add extra
34.800
Total
150.000
m2
12
15
180.000
No.
12
70
840.000
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
Amount
Day
1.00
329.00
329.00
cum
1.00
136.44
136.44
Beldar
Conveyance by head load(50M to
100M)
1
1.2.6
465.44
470.09
465.44
4.65
470.09
70.51
540.60
221.38
540.60
Cost of 1cum
Say Rs.
761.98
762.00
/ 1m3
Day
0.75
329.00
246.75
cum
1.00
136.44
136.44
Beldar
Conveyance by head load(50M to
100M)
2
1.2.6
383.19
387.02
445.07
383.19
3.83
387.02
58.05
445.07
182.26
Cost of 1cum
Say Rs.
627.33
627.35
/ 1m3
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
cum
1.00
24.4
Amount
1.2.6
24.40
24.64
28.34
24.40
0.24
24.64
3.70
28.34
11.61
Cost of 1cum
Say Rs.
39.95
39.95
/ 1m3
m3
0114
0115
day
day
2.650
0.720
329.00
329.00
9999
Sundries
L.S.
7.020
1.78
1121.23
1302.31
12.50
1121.23
11.21
533.30
1835.61
Cost of 1 cum
Say Rs.
871.85
236.88
1132.44
169.87
1302.31
1132.44
24.40
1835.60
/ 1m3
1000 Nos
494
4500.00
1000 Nos
494
283.96
Bricks
(non
modular
22.9x11.4x7cm)
2201
Carriage of bricks
Cement mortar 1 :6
of
size
2223.00
140.28
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
3.11
m3
0.25
5550.87
9999
Sundries
Amount
1387.72
LS
2.73
1.78
123
124
115
day
day
day
0.36
0.36
1.37
435.00
399.00
329.00
156.60
143.64
450.73
101
Bhisti
day
0.2
363.00
72.60
4579.43
31.92
3191.71
3223.63
for
1000 Nos
4.86
4611.35
483.54
5094.89
494
412.45
203.75
1549.04
1452.03
6750.67
Say Rs.
6750.65
/ 1m3
m3
0.144
8397.56
LABOUR:
Mason (average)
Coolie
day
day
0.67
0.75
417.00
329.00
279.39
246.75
Bhisti
Scaffolding and sundries.
day
LS
0.92
12.61
363.00
1.78
333.96
22.45
2091.80
882.55
891.38
3.3
3.3
155
115
101
9999
1209.25
8.83
2100.63
133.71
2234.34
1209.25
1025.09
419.77
Cost of 10M2
2654.11
Cost of 1M2
Say Rs.
265.41
265.40
/ 1m2
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
Amount
85.05
222.00
18881.10
2.8.1
cum
7
Sl.
No.
Item
No. in
Data
Book /
Code
2.25
34(a) as
per
Transmi
ssion
Data for
substati
on
works
0116
0100
8
Particulars
Unit
cum
Quantity
Rate
Amount
85.05
158.45
13476.17
TOTAL
Cost of 180 metre length of pipe
32357.27
32357.27
Cost of 1 metre
Say Rs.
179.76
179.75
/ 1 R. m
1 No.
day
0.40
435.00
174.00
Bandhani
Hire Charges of T & P
day
LS
0.40
363.00
145.20
60.00
379.20
379.20
382.99
3.79
382.99
57.45
440.44
35(a) as
per
Transmi
ssion
Data for
substati
on
works
69.00
371.44
Say Rs.
59.25
1 No.
152.10
592.54
59.25
/ 1cut
0102
day
0.20
435.00
87.00
0100
Bandhani
day
0.33
363.00
119.79
206.79
208.86
240.19
206.79
2.07
208.86
31.33
240.19
98.36
338.55
84.64
84.65
/ 1bend
Sl.
No.
10
Item
No. in
Data
Book /
Code
Particulars
Unit
36 as
per
Transmi
ssion
Data for
substati
on
works
1 Qtl
0102
0100
Blacksmith
Bandhani for assisting
0100
0114
37 as
per
Transmi
ssion
Data for
substati
on
works
Quantity
Rate
day
day
0.40
0.40
435.00
363.00
174.00
145.20
day
day
0.20
0.10
363.00
329.00
72.60
32.90
424.70
424.70
428.95
493.29
Say Rs.
695.30
Driving
down
the
MS
ground
electrode upto a depth of 3m from
the already taken earth pit
as
directed by departmental officers at
site. Charges include the lifting of
ground electrode from the stockyard
to the site, backfilling, placing and
leveling the electrode etc complete.
1 No.
Amount
4.25
428.95
64.34
493.29
202.00
695.29
/ 1Qtl
Bandhani
Beldar
Cost of making scaffolding etc
day
day
LS
803.60
811.64
0.80
0.80
121.75
933.39
287.50
645.89
264.49
1197.88
Cost of 1no
Say Rs.
290.40
263.20
250.00
803.60
8.04
811.64
363.00
329.00
119.79
119.80
/ 1no
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
38 as
per
Transmi
ssion
Data for
substati
on
works
1m
Quantity
Rate
Amount
Rate for 30 M
0134
0100
12
day
day
day
1.00
1.75
3.00
329.00
471.00
363.00
329.00
824.25
1089.00
Day
LS
1.00
500.00
500.00
125.00
LS
3192.25
3224.17
325.00
3192.25
31.92
3224.17
483.63
3707.80
2040.39
682.80
4390.60
Cost of 1m
Arrived
Data
based
on 39 of
Transmi
ssion
Data for
substati
on
works
146.35
Say Rs.
146.35
/ 1m
1 No.
3.00
320.00
Bentonite Clay
kg
80.00
6.69
13
1495.20
1719.50
535.20
1495.20
224.28
1719.48
Cost of 1no
Say Rs.
960.00
/ 1no
Sl.
No.
14
Item
No. in
Data
Book /
Code
Particulars
Unit
40 as
per
Transmi
ssion
Data for
substati
n works
1 No.
Quantity
Rate
Amount
1087
0102
0100
Welder
Blacksmith
Bandhani
day
day
day
0.10
0.10
0.12
399.00
435.00
363.00
39.90
43.50
43.56
0114
Beldar
day
0.10
329.00
32.90
LS
110.00
LS
110.00
LS
LS
10.00
5.00
394.86
394.86
398.81
3.95
398.81
59.82
458.63
41 as
per
Transmi
ssion
Data for
substati
n works
15
270.25
188.38
535.75
77.14
535.77
/ 1no
1 No.
1087
0102
0100
Welder
Blacksmith
Bandhani
day
day
day
0.07
0.05
0.05
399.00
435.00
363.00
27.93
21.75
18.15
0114
Beldar
day
0.03
329.00
9.87
LS
50.00
Sl.
No.
15
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
Amount
LS
50.00
LS
LS
4.00
2.00
183.70
183.70
185.54
1.84
185.54
27.83
213.37
42 as
per
Transmi
ssion
Data for
substati
on
works
16
121.90
91.47
250.85
37.46
250.83
/ 1no
1 No.
1087
0102
0100
Welder
Blacksmith
Bandhani
day
day
day
0.08
0.05
0.08
399.00
435.00
363.00
31.92
21.75
29.04
0114
Beldar
day
0.08
329.00
26.32
LS
50.00
LS
50.00
LS
LS
5.00
3.00
217.03
217.03
219.20
2.17
219.20
32.88
252.08
124.20
127.88
304.45
52.37
304.45
/ 1no
Sl.
No.
17
Item
No. in
Data
Book /
Code
Particulars
Unit
43 as
per
Transmi
ssion
Data for
substati
on
works
1m
0116
0114
Fitter
Beldar
0102
Blacksmith
Add Water Charges @ 1%
44 as
per
Transmi
ssion
Data for
substati
on
works
18
Quantity
Rate
day
day
0.40
1.50
435.00
329.00
174.00
493.50
day
0.10
435.00
43.50
711.00
7.11
711.00
718.11
825.83
Say Rs.
116.40
1 No.
Amount
718.11
107.72
825.83
338.18
1164.01
116.40
/ 1m
1087
0102
0100
Welder
Blacksmith
Bandhani
day
day
day
0.12
0.08
0.08
399.00
435.00
363.00
47.88
34.80
29.04
0114
Beldar
day
0.08
329.00
26.32
LS
100.00
LS
80.00
LS
8.00
Cost of Paint
LS
4.00
330.04
3.30
330.04
333.34
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
333.34
50.00
383.34
45 as
per
Transmi
ssion
Data for
substati
on
works
19
220.80
162.54
Say Rs.
449.90
Welding
overlapping
joints
of
50x6mm GI strip with 50mm long,
6mm thick welding on all three sides
after doing 2 Nos. bolted joints at the
centre as specified after cleaning the
surface. Charges include hire charges
of DC arc welding set, current
charges, cost of low hydrogen
content DC arc welding electrodes
(No.E7018), cost of anti corrosive
paint etc complete as per the
direction of departmental officers at
site.
1 No.
66.56
449.90
/ 1no
1087
Welder
day
0.08
399.00
31.92
0102
0100
0114
Blacksmith
Bandhani
Beldar
day
day
day
0.08
0.05
0.03
435.00
363.00
329.00
34.80
18.15
9.87
LS
134.74
136.09
40.00
134.74
1.35
136.09
20.41
156.50
46 as
per
Transmi
ssion
Data for
substati
on
works
20
Amount
46.00
110.50
Say Rs.
201.75
1 No.
45.25
201.75
/ 1no
1087
0102
Welder
Blacksmith
day
day
0.08
0.08
399.00
435.00
31.92
34.80
0100
0114
Bandhani
Beldar
day
day
0.12
0.08
363.00
329.00
43.56
26.32
Sl.
No.
20
Item
No. in
Data
Book /
Code
Particulars
Unit
LS
90.00
LS
75.00
301.60
304.62
Quantity
Rate
301.60
3.02
304.62
45.69
350.31
189.75
160.56
65.75
Cost of 1no
Say Rs.
Amount
416.06
416.05
/ 1no
21
0295
m3
0.67
1175.00
787.25
0297
m3
0.22
1175.00
258.50
2202
m3
0.89
106.49
m3
0.445
1750.00
2203
m3
0.445
106.49
0367
2209
tonne
tonne
0.32
0.32
6300.00
94.65
1.63
0.70
329.00
363.00
536.27
254.10
0114
0101
LABOUR :Beldar
94.78
778.75
47.39
2016.00
30.29
Bhisti
day
day
0155
Mason average
day
0.10
417.00
41.70
0002
day
0.07
800.00
56.00
0012
9999
day
LS
0.07
14.30
350.00
1.78
24.50
25.45
4950.98
49.51
5000.49
750.07
5000.49
5750.56
Cost of carriage, market rate and
their CPOH and water charges
895.56
7738.70
1988.12
7738.68
/ 1m3
Sl.
No.
Item
No. in
Data
Book /
Code
Particulars
Unit
Quantity
Rate
Amount
Data for 1
sqm
Cost of 1 sqm
Details of cost for footing size
2.7mx2.7mx 1.00m Contact area =
10.8 sqm.
MATERIAL : Assuming shuttering material will
become unserviceable after use of
40 times, Adding for maintenance @
10% of cost, Taking salvage value
after full use of material @ 25% of
cost Wall form panel 1250x500 mm
7319
each
0.34
1050.00
7326
each
0.085
300.00
7327
each
0.17
1160.00
7328
each
0.34
97.00
32.98
7329
each
0.17
77.00
13.09
7330
0.2295
280.00
64.26
9999
LS
22.1
1.78
39.34
LS
78
1.78
138.84
day
day
LS
0.75
1.5
52
435.00
329.00
1.78
326.25
493.50
92.56
LS
26
1.78
22
9999
116
0114
9999
9999
Carriage
LABOUR : Fitter (grade 1)
Beldar
Shuttering oil
Sundries
Add Water Charges @ 1%
1826.80
1845.07
276.90
25.50
197.20
46.28
1826.80
18.27
1845.07
276.76
2121.83
357.00
868.89
2990.72
276.92
/1m2
Sl.
No.
23
Item
No. in
Data
Book /
Code
0116
0100
Particulars
Unit
1 No.
day
day
645.69
652.15
Quantity
Rate
0.75
0.88
435.00
363.00
326.25
319.44
645.69
6.46
652.15
97.82
749.97
307.11
749.97
Cost of 8nos
Cost of 1cut
1087
Amount
1057.08
132.14
Say Rs.
132.15
1 No.
/ 1cut
No.
300.00
4.20
1260.00
Welder
Current charge and hire charges
day
LS
1.75
399.00
698.25
100.00
2058.25
24
Add Water Charges @ 1%
2058.25
2078.83
20.58
2078.83
311.82
2390.65
1564.00
826.65
Say Rs.
90.95
338.51
2729.16
90.97
/ 1no
Sl. No.
Code
Description
Unit
Qty.
Rate
1750.00
Amount
3.11 of
Cement mortar 1:6 (1 cement : 6
CPWD
coarse sand)
2014
Details of cost for 1 cum
MATERIAL:(0.375 cum. of cement = 0.51
tonne)
Cement
required
for
cement mortar is 35.70%
0982
m3
1.070
2203
Carriage of sand
1.070
106.49
0367
Cement
MT
0.25
6300.00
2209
Carriage of cement
MT
0.25
94.65
day
0.75
329.00
246.75
day
0.07
363.00
25.41
day
26.91
1.78
47.90
L.S.
13.52
1.78
24.07
3929.23
1872.50
113.94
1575.00
23.66
LABOUR:-
For
measuring,
depositing and mixing.
114
101
carrying,
Beldar
Bhisthi
9999
Hire
running
mechanical mixer.
9999
Sundries
charges
of
3929.23
39.29
3968.52
3968.52
595.28
4563.80
2153.38
2410.42
987.07
Cost of 1 cum
Say Rs.
5550.87
###
/ 1m3
Portland Cement
tonne
0.51
6300.00
Carriage of cement
tonne
0.51
94.65
m3
1.07
1850.00
m3
1.07
106.49
113.94
Beldar
Bhisti
day
day
0.75
0.07
329.00
363.00
246.75
25.41
L.S.
26.91
1.78
L.S.
13.52
1.78
3.3 of
Cement mortar 1:3 (1 cement : 3
CPWD
fine sand)
2014
Details of cost for 1 cum.
MATERIAL:(0.375 cum. of cement = 0.51
tonne)
Cement
required
for
cement mortar is 35.70%
367
2209
2261
3213.00
48.27
1979.50
LABOUR:For
measuring,
depositing and mixing.
2
114
101
9999
9999
Sundries
carrying,
47.90
24.07
5698.84
56.99
Sl. No.
Code
Description
Unit
Qty.
Rate
Amount
5755.83
Add CPOH @ 15%
5755.83
863.37
6619.20
2276.43
1778.36
Cost of 1 cum
Say Rs.
8397.56
###
/ 1m3
Sl. No.
Code
Description
Unit
Qty.
Rate
Amount
0020
day
###
8000.00
330.00
0018
day
###
5000.00
206.25
day
day
0.400
2.050
363.00
329.00
145.20
674.45
LABOUR:0128
0115
Mate
Beldar/Coolie
Add Water Charges @ 1%
1355.90
1369.46
1355.90
13.56
1369.46
205.42
1574.88
644.91
Cost of 10 cum
Cost of 1 cum
Say Rs.
2.25
2219.79
221.98
222.00
/ 1m3
0128
Mate
day
0.200
363.00
72.60
0115
0101
Coolie
day
2.500
329.00
822.50
Bhisti
day
0.200
363.00
72.60
967.70
967.70
9.68
977.38
977.38
146.61
1123.99
1123.99
460.27
Cost of 10 cum
Cost of 1 cum
Say Rs.
1584.26
158.43
158.45
/ 1m3
Description
Place
Road distance
Cement
Kottayam
5km
Kottayam
5km
Kottayam
5km
Bentonite clay
Kottayam
5km
Bricks
Kattachira
25 km
Certificate
The distance noted in the data for the conveyance from quarry or source have
been personally verified by me and found correct. These are the minimum leads required.
Particulars
Cutting of ms rod
Breadth
Height
cutting(x/12)
1
Total length of 32mm ms rod
3m
total number of earth electrode(main mat
electrodes periphery)
electrode for LA
electrode for NCT
200MVA Transformer
Total
total lenth of earth elctrode(90*3)
Auxiliary auxiliary mat size(1.5 x 1.5)
mat
1.5*5
1.5*5
total
we have 9no auxilary mat
Riser
2400
200.000
22.500
65
15
2
8
90
270
7.5
7.5
15
135
line isolator
bus isolator
ct
pt
tower footings
cb
LA
cc
NCT
Transformer
Fencing
total no
total length of riser
total cutting
Number of MS rod bend
Excavation
inside the feeder area
Behind area of transformer
No C bend in Excavted points
Number of C Bend in feeder area
Number of C Bend behind trasformer
3
6
15
9
19
15
15
2
2
6
144
32
88
20
17
total
Total number of bend
125
500
Laying of Earthmat
Excavation
Total length
length C bend
Number of C Bend in feeder area
2400
125
20
m
5
5
4
4
4
3
4
4
4
4
11.250
15
30
60
36
76
45
60
8
8
24
35.00
397.00
595.50
49.625
17
162
648
2400
250
100
135
2885
240.417
200.00
20.83
8.33
11.25
7
75
101
65
Calculation of Excavation
35
14
2623.00
0.3
0.6
8
8
Total length
excavation in m3
Add Extra
Total
3 Calculation of nodal points
total length of mat periphery
nodal points in the periphery(5m spacing)
LA
200mva Transformer(6x2+2x2+2x1)
total
add extra
352
71
21
18
110
10
120
14
7
16
8
1.5
1.5
5
5
7.5
7.5
15
3
6
15
15
19
15
21
2
6
6
4
4
3
4
3
4
18
36
60
60
57
60
63
8
7 Calculation of riser
equipment
line isolator
bus isolator
ct
pt
tower footings
cb
LA
CC
2
2
2
2
2
NCT
Transformer
Supporting Stucture
Fencing
Kiosk
Lamp post
Handle
8 Calculation of GI strip
isolator
cb
ct
pt
la
nct
transformer
Column
Platform
Fencing
Supporting structure (Bus Post Insulator)
Coupling Capacitor
Marshalling Kiosk
Lamp post
2
6
8
1
12
10
no
4
3
2
36
1
1
m
9
15
15
15
21
2
6
19
9
36
16
4
12
10
8
18
16
36
12
10
4
466
bolt
30
12
11
11
11
11
20
6
3
3
3
5
3
2
2
4
weld
3
2
2
2
1
2
4
0
0
1
3
2
2
2
2
2
0
3
2
2
1
Quantity
10
10
16
12
4
8
8
3
1
1
8
10
10
1
3
1
2
3
28
283.38
10
189
57
42
135
40
12
10
475
245.00
1050.00
808.00
520.00
2623.00
472.14
27.86
500.00
6
6
8
5
10
138
equipment structure
0
15
0
30
30
30
30
30
0
76
30
0
42
42
4
4
4
4
24
0
5
0
20
5
164
251
2
2
4
0
2
2
224
56
280
structure
22
20
total in m
270
180
165
165
231
22
120
114
27
108
48
20
36
20
1526
no of weld no of bolt
27
27
30
30
30
30
30
30
42
21
4
4
0
24
57
0
18
0
72
0
16
16
326
182
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
A1
A2
A3
A4
2
2
2
2
1
1
1
1
2
2
2
2
1
1
1
1
B1
B2
B3
B4
2
1
1
1
1
1
1
1
2
2
2
2
1
0
0
0
Total
B5
B6
B7
B8
B9
B10
B11
B12
B13
B14
B15
B16
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
1
1
B17
B18
B19
B20
B21
3
3
2
2
2
2
2
1
1
1
4
4
2
2
2
1
1
1
1
1
Total
41
23
46
18
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
C12
C13
C14
C15
C16
C17
C18
C19
C20
C21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
D1
D2
D3
D4
D5
D6
D7
D8
D9
D10
D11
D12
D13
D14
D15
D16
D17
D18
D19
D20
D21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Total
22
21
42
Total
22
21
42
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
E1
E2
E3
E4
E5
E6
E7
E8
E9
E10
E11
E12
E13
E14
E15
E16
E17
E18
E19
E20
E21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
F1
F2
F3
F4
F5
F6
F7
F8
F9
F10
F11
F12
F13
F14
F15
F16
F17
F18
F19
F20
F21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
Total
23
21
42
Total
23
21
42
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
G1
G2
G3
G4
G5
G6
G7
G8
G9
G10
G11
G12
G13
G14
G15
G16
G17
G18
G19
G20
G21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
H1
H2
H3
H4
H5
H6
H7
H8
H9
H10
H11
H12
H13
H14
H15
H16
H17
H18
H19
H20
H21
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Total
23
21
42
Total
22
21
42
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
I1
I2
I3
I4
I5
I6
I7
I8
I9
I10
I11
2
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
1
J1
J2
J3
J4
J5
J6
J7
J8
J9
J10
J11
2
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
1
I12
I13
I14
I15
I16
I17
I18
I19
I20
I21
2
2
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
Total
13
11
22
Total
33
21
42
12
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
K1
K2
K3
K4
K5
K6
K7
K8
K9
K10
K11
2
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
1
L1
L2
L3
L4
L5
L6
L7
L8
L9
L10
L11
2
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
0
1
Total
13
11
22
Total
13
11
22
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
M2
M3
M4
M5
M6
M7
M8
M9
M10
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
0
N3
N4
N5
N6
N7
N8
N9
N10
N11
2
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
1
0
0
0
0
0
0
0
1
M11
Total
11
18
Total
12
10
20
Node
Cut
Bend
Lap
Ground Electrode
Node
Cut
Bend
Lap
Ground Electrode
O
P0
P5
P6
P7
P8
P9
P10
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
1
1
0
0
0
0
0
0
Q
R0
R6
R7
R8
R9
R10
R11
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
P11
Total
16
16
Total
12
18
Node (520) Cut (950) Bend (1300) Lap (1450) Ground Electrode (120)
A1 - A4
B1 - B21
C1 - C21
D1 - D21
E1 - E21
F1 - F21
G1 - G21
H1 - H21
I1 - 121
J1 - J11
K1 - K11
L1 - L11
M2 - M11
N3 - N11
O - P0 - P11
Q - R0 - R11
4
21
21
21
21
21
21
21
21
11
11
11
10
9
9
8
8
41
22
22
23
23
23
22
33
13
13
13
12
11
12
16
4
23
21
21
21
21
21
21
21
11
11
11
10
9
9
8
8
46
42
42
42
42
42
42
42
22
22
22
20
18
18
16
4
18
1
1
2
2
2
1
12
2
2
2
2
2
3
8
Total
241
307
243
486
64
Particulars
10.00
8.00
2.00
160.00
Stack 2
8.00
6.00
2.00
96.00
Total
256.00
As per estimate
280.00
Stack 1
10.00
8.00
2.00
Stack 2
8.00
6.00
2.00
m3
160.00
96.00
256.00
285.00
m3
100.00
m3
17.00
m3
Total
As per estimate
Unit
Total
As per estimate
Total
Stack 1
Total
As per estimate
Total
As per estimate
No.
NIL
4.00
m3
Total
As per estimate
NIL
25.00
m2
17.00
1
1
99.00
3.30
17.00
17.00
99.00
3.30
99.00
2.10
102.30
99.00
2.10
Total
Along B-gridline
Add for diversion
Deduct for cable trench crossing
Total
Along C-gridline
Add for diversion
0.00
1
1
1
1
99.00
5.20
101.10
99.00
5.20
0.70
2.10
1.20
2.40
0.00
Total
Along E-gridline
Add for diversion
1
1
99.00
1.80
99.70
99.00
1.80
0.70
2.80
1.20
2.40
1.40
1.40
2.00
4.00
Total
Along F-gridline
Add for diversion
99.00
90.20
99.00
2.60
2.60
1.40
2.80
1
1
99.00
3.10
98.80
99.00
3.10
0.70
0.70
1.20
1.20
1.40
2.80
6.70
6.70
1
1
99.00
0.70
90.70
99.00
0.70
1.20
1.20
1.40
2.80
6.70
6.70
1
1
99.00
1.55
87.60
99.00
1.55
0.70
1.40
1.20
1.20
1.40
Total
2.80
95.15
Along J-gridline
Deduct for cable trench crossing
Total
Along K-gridline
Add for diversion
1
2
47.00
1.40
47.00
2.80
1
1
47.00
1.55
44.20
47.00
1.55
1.40
2.80
1
1
49.00
1.75
45.75
49.00
1.75
1.40
2.80
1
1
44.00
0.60
47.95
44.00
0.60
0.70
5.60
1.40
2.80
3.10
6.20
1
1
39.00
4.20
30.00
39.00
4.20
33.00
28.00
29.00
0.50
1.50
1
12
57.00
0.50
27.50
57.00
6.00
1
13
59.00
0.50
51.00
59.00
6.50
1
14
63.00
0.50
52.50
63.00
7.00
67.00
56.00
67.00
0.25
0.25
0.70
2.10
1.20
2.40
15
0.50
7.50
1
1
71.00
2.60
55.25
71.00
2.60
0.70
2.10
1.20
2.40
15
0.50
7.50
1
1
73.00
3.70
61.60
73.00
3.70
0.70
0.70
1.20
1.20
1.40
1.40
15
0.50
Total
Along N-gridline
Add for diversion
Total
Along P-gridline
Total
Along R-gridline
Total
Slanding trench b/w R & L gridlines along
periphery
Deduct for Earth mat node crossing
Total
Along 1-gridline
Deduct for Earth mat node crossing
Total
Along 2-gridline
Deduct for Earth mat node crossing
Total
Along 3-gridline
Deduct for Earth mat node crossing
Total
Along 4-gridline
Add for diversion
Deduct for cable trench crossing
Deduct for Earth mat node crossing
Total
Along 5-gridline
Add for diversion
Deduct for cable trench crossing
Deduct for Earth mat node crossing
Total
Along 6-gridline
Add for diversion
Deduct for cable trench crossing
43.20
33.00
33.00
28.00
28.00
29.00
7.50
65.90
Along 7-gridline
Add for diversion
1
1
73.00
0.50
73.00
0.50
0.70
0.70
1.20
1.20
1.40
1.40
15
0.50
7.50
1
1
73.00
1.00
62.70
73.00
1.00
0.70
1.40
1.20
1.20
1.40
1.40
2.00
2.00
15
0.50
7.50
1
4
73.00
0.70
60.50
73.00
2.80
1.20
1.20
1.40
1.40
15
0.50
7.50
1
1
73.00
0.35
60.10
73.00
0.35
0.70
1.40
1.20
2.40
1.40
1.40
2.00
2.00
15
0.50
7.50
1
1
73.00
5.50
58.65
73.00
5.50
1.20
1.20
1.40
1.40
3.10
3.10
15
0.50
7.50
33.00
65.30
33.00
1.40
1.40
0.50
4.00
1
1
33.00
1.40
27.60
33.00
1.40
0.50
4.00
1
1
33.00
0.50
27.60
33.00
0.50
1.40
1.40
0.50
4.00
1
1
33.00
1.40
28.10
33.00
1.40
0.50
4.00
27.60
Along 16-gridline
Deduct for cable trench crossing
1
1
33.00
1.40
33.00
1.40
4.50
4.50
0.50
4.00
1
1
33.00
1.40
23.10
33.00
1.40
4.50
4.50
0.50
4.00
33.00
23.10
33.00
1.40
1.40
0.50
4.00
1
1
33.00
1.40
27.60
33.00
1.40
0.50
4.00
33.00
27.60
33.00
1.40
1.40
0.50
4.00
1
1
33.00
1.60
27.60
33.00
1.60
1.40
1.40
0.50
4.00
29.20
2.60
2.60
1.20
1.20
1.80
1.80
1.20
1.20
1.25
1.25
1.25
1.25
1.50
1.50
1.70
1.70
1.80
1.80
1.70
1.70
1.00
1.00
2.00
2.00
2.00
2.00
2.00
2.00
1.00
1.00
2.00
2.00
R-phase C.T.
1.20
1.20
Y-phase C.T.
1.20
1.20
B-phase C.T.
0.80
0.80
1.30
1.30
1.30
1.30
1.70
1.70
2.30
2.30
1.60
1.60
1.40
1.40
2.30
2.30
1.00
1.00
2.00
2.00
Bus Isolator
1.80
1.80
1.80
1.80
0.80
0.80
Y-phase L.A.
B-phase L.A.
Line Isolator
R-phase P.T.
Y-phase P.T.
B-phase P.T.
R-phase P.T.
Y-phase P.T.
B-phase P.T.
R-phase C.T.
Y-phase C.T.
B-phase C.T.
R-phase breaker pole
1.50
1.50
1.50
1.50
1.30
1.30
1.20
1.20
1.20
1.20
1.80
1.80
2.20
2.20
2.00
2.00
1.00
1.00
1.20
1.20
1.40
1.40
1.40
1.40
1.00
1.00
1.40
1.40
1.70
1.70
1.20
1.20
1.40
1.40
2.30
2.30
2.30
2.30
2.30
2.30
2.30
2.30
1.60
1.60
1.00
1.00
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.50
1.50
1.00
1.00
1.20
1.20
Bus Isolator
2.00
2.00
1.50
1.50
2.50
2.50
1.00
1.00
1.80
1.80
1.00
1.00
1.40
1.40
1.80
1.80
1.80
1.80
1.00
1.00
Y-phase P.T.
1.20
1.20
B-phase P.T.
1.00
1.00
R-phase C.T.
1.60
1.60
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.00
1.00
0.70
0.70
Bus Isolator
0.80
0.80
0.70
0.70
1.60
1.60
1.00
1.00
1.50
1.50
Bus Isolator
1.50
1.50
Neutral C.T.
1.50
1.50
1.50
1.50
1.50
1.50
R-phase L.A.
6.00
6.00
2.40
2.40
R-phase L.A.
1.00
1.00
Y-phase L.A.
2.00
2.00
1.80
1.80
B-phase L.A.
2.30
2.30
R-phase C.T.
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.50
1.50
1.30
1.30
Neutral C.T.
1.50
1.50
1.00
1.00
1.00
1.00
1.50
1.50
6.00
6.00
6.00
6.00
5.00
5.00
6.00
6.00
1.00
1.00
1.00
1.00
1.75
1.75
2.20
2.20
1.20
1.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
2.00
2.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Y-phase C.T.
Bus Isolator
1.00
2215.00
2400.00 R. m
Total
Along B-gridline
Along Main grid
Total
1
Total
1.00
12.00
13.00
1.00
17
17.00
18.00
1.00
14
14.00
15.00
1.00
16
16.00
Total
Along H-gridline
Along Main grid
Along Bending points
17.00
1
1.00
13
13.00
Total
Along I-gridline
Along Main grid
Along Bending points
14.00
1
1.00
16
16.00
Total
17.00
Along J-gridline
Along Main grid
Total
Along K-gridline
Along Main grid
Along Bending points
1.00
10.00
11.00
1.00
13
13.00
14.00
Total
Along R-gridline
9.00
Total
1.00
8.00
9.00
Total
1.00
10
Along N-gridline
Along Main grid
Along P-gridline
Along Main grid
9.00
10.00
Total
Along M-gridline
Along Main grid
1.00
10.00
Total
Along L-gridline
Along Main grid
4.00
Total
Along G-gridline
Along Main grid
1.00
12
Total
Along F-gridline
Along Main grid
4.00
5.00
Total
Along E-gridline
Along Main grid
1.00
5.00
Along C-gridline
Along Main grid
Along D-gridline
Along Main grid
1.00
1.00
1.00
1.00
1.00
Total
Along R & L-gridlines in the periphery
Cut for Ground Electrodes
6.00
8.00
Total
1.00
1.00
15.00
Along 1-gridline
Cut for Ground Electrodes
Cut for L-Connectors
Along Main grid
8.00
11
11.00
Total
Along 2-gridline
Cut for Ground Electrodes
Cut for L-Connectors
Along Main grid
1.00
12
12.00
Total
Along 3-gridline
Cut for Ground Electrodes
Cut for L-Connectors
Along Main grid
1.00
14.00
1.00
13
13.00
Total
Along 4-gridline
Cut for Ground Electrodes
1.00
20.00
1.00
15.00
1.00
14
14.00
1.00
14
14.00
30.00
1.00
15
15.00
1.00
14
14.00
31.00
2.00
15
15.00
1.00
11
11.00
29.00
2.00
15
15.00
1.00
11
11.00
29.00
2.00
15
15.00
1.00
13
13.00
31.00
2.00
15
15.00
1.00
13
13.00
31.00
2.00
15
15.00
1.00
17
17.00
35.00
7.00
15
15.00
1.00
15
15.00
38.00
Along 12-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
3.00
14.00
Along 13-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
3.00
14.00
Along 14-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
3.00
14.00
Along 15-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
3.00
14.00
Along 16-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
7.00
18.00
Along 17-gridline
Cut for Ground Electrodes
2.00
9.00
1.00
Total
3.00
15.00
Along 18-gridline
Cut for Ground Electrodes
2.00
9.00
1.00
Total
3.00
15.00
Along 19-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
3.00
14.00
Along 20-gridline
Cut for Ground Electrodes
2.00
8.00
1.00
Total
Along 21-gridline
Cut for Ground Electrodes
4.00
15.00
6.00
10
10.00
1.00
6.00
Total
23.00
635.00
4.00
2.00
Total
2.00
8.00
Y-phase L.A.
Cut for Riser
4.00
2.00
Total
B-phase L.A.
Cut for Riser
2.00
8.00
4.00
Total
2.00
2.00
8.00
3.00
3.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
6.00
2.00
83.00
R-phase L.A.
Cut for Riser
4.00
2.00
Total
2.00
8.00
Y-phase L.A.
Cut for Riser
4.00
2.00
Total
2.00
8.00
B-phase L.A.
Cut for Riser
4.00
2.00
Total
Line Isolator
Cut for Riser
R-phase P.T.
Cut for Riser
Y-phase P.T.
Cut for Riser
B-phase P.T.
Cut for Riser
R-phase C.T.
Cut for Riser
Y-phase C.T.
Cut for Riser
B-phase C.T.
Cut for Riser
SF6 Breaker (R-phase unit)
Cut for Riser
2.00
8.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
6.00
2.00
77.00
4.00
2.00
Total
2.00
8.00
Y-phase L.A.
Cut for Riser
4.00
2.00
Total
2.00
8.00
B-phase L.A.
Cut for Riser
4.00
2.00
Total
Y-phase Coupling Capacitor
Cut for Riser
B-phase Coupling Capacitor
Cut for Riser
Line Isolator
Cut for Riser
R-phase P.T.
Cut for Riser
Y-phase P.T.
Cut for Riser
B-phase P.T.
Cut for Riser
R-phase C.T.
Cut for Riser
Y-phase C.T.
Cut for Riser
B-phase C.T.
Cut for Riser
SF6 Breaker (R-phase unit)
Cut for Riser
SF6 Breaker (Y-phase unit)
Cut for Riser
SF6 Breaker (B-phase unit)
Cut for Riser
Breaker Cubicle
Cut for Riser
Bus Isolator
Cut for Riser
Old Cubicles
Cut for Riser
3.00
3.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
6.00
2.00
8.00
1.00
82.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
Transformer Body (R-phase unit)
Cut for Riser
Transformer Body (Y-phase unit)
Cut for Riser
Transformer Body (B-phase unit)
Cut for Riser
Fan Control Cubicle (R-phase)
Cut for Riser
Fan Control Cubicle (Y-phase)
Cut for Riser
Fan Control Cubicle (B-phase)
Cut for Riser
Old Cubicles
Cut for Riser
Neutral C.T.
Cut for Riser
2.00
8.00
2.00
2.00
2.00
1.00
1.00
1.00
2.00
4.00
2.00
Total
2.00
8.00
Tertiary Connection
Cut for Riser
2.00
2.00
Total
1.00
5.00
105.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
2.00
8.00
4.00
2.00
Total
Transformer Body (R-phase unit)
Cut for Riser
Transformer Body (Y-phase unit)
Cut for Riser
Transformer Body (B-phase unit)
Cut for Riser
Fan Control Cubicle (R-phase)
Cut for Riser
Fan Control Cubicle (Y-phase)
Cut for Riser
Fan Control Cubicle (B-phase)
Cut for Riser
Old Cubicles
Cut for Riser
Neutral C.T.
Cut for Riser
2.00
8.00
2.00
2.00
2.00
1.00
1.00
1.00
1.00
4.00
2.00
Total
2.00
8.00
Tertiary Connection
Cut for Riser
2.00
2.00
Total
1.00
5.00
104.00
6
6.00
4.00
15
30.00
18.00
48.00
1.00
18
18.00
5.00
1.00
1.00
36
36.00
30
30.00
5.00
Spare transformer
Cut for Riser
574
155.00
1241.00
As per estimate
950.00
No.
Total
Along C-gridline
Bend for diversion
Total
Along D-gridline
Bend for diversion
10
14
14
12
10
12
12.00
12.00
Total
Along N-gridline
Bend for diversion
10.00
10.00
Total
Along M-gridline
Bend for diversion
8.00
8.00
Total
Along L-gridline
Bend for diversion
12.00
12.00
Total
Along K-gridline
Bend for diversion
8.00
8.00
Total
Along J-gridline
Bend for diversion
14.00
14.00
Total
Along I-gridline
Bend for diversion
14.00
14.00
Total
Along H-gridline
Bend for diversion
10.00
10.00
Total
Along G-gridline
Bend for diversion
8.00
8.00
Total
Along F-gridline
Bend for diversion
4.00
4.00
Total
Along E-gridline
Bend for diversion
6.00
6.00
8.00
8.00
Total
8.00
8.00
Along P-gridline
NIL
Along R-gridline
NIL
Along R & L-gridlines in the periphery
Bend for L-Connectors
Total
Along 1-gridline
Bend for L-Connectors
11
11.00
11.00
12
Total
1.00
9.00
Total
Along 2-gridline
Bend for L-Connectors
8.00
12.00
12.00
Along 3-gridline
Bend for L-Connectors
13
Total
Along 4-gridline
Bend for L-Connectors
Bend for diversion
14
Total
Along 5-gridline
Bend for L-Connectors
Bend for diversion
Total
13.00
13.00
14.00
6.00
20.00
15
15.00
6.00
21.00
Along 6-gridline
Bend for L-Connectors
15
14
Total
15
12
Total
15
10
Total
15
15
12
Total
15
16
Total
8
8.00
15.00
12.00
15.00
16.00
8.00
4.00
12.00
Along 13-gridline
Bend for L-Connectors
Total
8.00
4.00
12.00
Along 14-gridline
Bend for L-Connectors
Total
8.00
4.00
12.00
Along 15-gridline
Bend for L-Connectors
Total
8.00
4.00
12.00
Along 16-gridline
Bend for L-Connectors
Total
8.00
8.00
16.00
Along 17-gridline
Bend for L-Connectors
Total
9.00
4.00
13.00
Along 18-gridline
Bend for L-Connectors
Total
9.00
4.00
13.00
Along 19-gridline
Bend for L-Connectors
Total
8.00
4.00
12.00
Along 20-gridline
Bend for L-Connectors
Total
Total
15.00
31.00
Total
10.00
27.00
Along 11-gridline
Bend for L-Connectors
Along 21-gridline
Bend for L-Connectors
15.00
23.00
Along 10-gridline
Bend for L-Connectors
12.00
25.00
Total
Along 12-gridline
Bend for L-Connectors
15.00
27.00
Along 8-gridline
Bend for L-Connectors
14.00
29.00
Along 7-gridline
Bend for L-Connectors
Along 9-gridline
Bend for L-Connectors
15.00
8.00
4.00
12.00
10
10.00
6.00
16.00
500.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
6.00
6.00
12.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
6.00
12.00
4.00
148.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
12.00
8.00
3
1
2
1
6.00
1.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
Breaker Cubicle
Bend for Riser
Bus Isolator
Bend for Riser
Old Cubicle
Bend for Riser
6.00
12.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
6.00
6.00
12.00
8.00
3
1
2
1
6.00
1.00
1.5
6.00
8.00
3
1
2
1
6.00
1.00
3
1
2
1
6.00
1.00
8.00
8.00
8.00
6.00
5
1
2
3
10.00
3.00
4.00
135.00
1.00
141.00
12.00
8.00
8.00
8.00
8.00
8.00
8.00
6.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
1
1
2
1
2.00
1.00
2.00
2.00
1.00
1.00
1.00
2.00
4
2
2
1
8.00
2.00
10.00
1
1
1
2
1
1
2.00
1.00
1.00
4.00
152.00
12.00
8.00
8.00
8.00
8.00
8.00
8.00
6.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
4
2
2
1
8.00
2.00
10.00
1
1
2
1
2.00
1.00
2.00
2.00
1.00
1.00
1.00
1.00
4
2
2
1
8.00
2.00
10.00
1
1
1
2
1
1
2.00
1.00
1.00
4.00
151.00
12.00
8.00
15
6
4
6
60.00
36.00
96.00
18
36.00
10.00
2.00
1.00
36
36.00
30
30.00
4
1
2
1
8.00
1.00
Spare transformer
Bend for Riser
1.00
241.00
1468.00
As per estimate
1300.00 No.
17
Lap joint
0.18
Total
17.00
0.18
17.18
Along B-gridline
Main mat
99
99.00
Diversion
3.3
3.30
Lap joint
11
0.18
1.98
Total
104.28
Along C-gridline
Main mat
99
99.00
Diversion
2.1
2.10
Lap joint
10
0.18
Total
Along D-gridline
Main mat
99
99.00
Diversion
5.2
5.20
Lap joint
17
0.18
99
99.00
Diversion
1.8
1.80
2.00
21
0.18
Total
1
99
99.00
Diversion
2.6
2.60
2.00
17
0.18
Total
1
99
99.00
Diversion
3.1
3.10
2.00
0.3
0.60
20
0.18
Total
1
99
99.00
0.3
0.60
0.7
1.40
0.25
0.50
1.3
2.60
17
0.18
Total
1
99
99.00
Diversion
1.55
1.55
0.25
0.50
0.7
1.40
0.3
0.60
20
0.18
Total
Along J-gridline
3.06
107.16
Along I-gridline
Main mat
Lap joint
3.60
108.30
Along H-gridline
Main mat
Lap joint
3.06
106.66
Along G-gridline
Main mat
Lap joint
3.78
106.58
Along F-gridline
Main mat
Lap joint
3.06
107.26
Along E-gridline
Main mat
Lap joint
1.80
102.90
Total
3.60
106.65
Main mat
47
47.00
0.5
1.00
0.3
0.60
10
0.18
Lap joint
Total
1.80
50.40
Along K-gridline
Main mat
47
47.00
Diversion
1.55
1.55
0.5
1.00
0.3
0.60
10
0.18
Lap joint
Total
1.80
51.95
Along L-gridline
Main mat
49
49.00
Diversion
1.75
1.75
0.5
1.00
0.3
0.60
11
0.18
Lap joint
Total
44
44.00
Diversion
0.6
0.60
0.5
1.00
0.3
0.60
13
0.18
Total
Along N-gridline
Main mat
39
39.00
Diversion
4.2
4.20
Lap joint
0.18
33
Lap joint
0.18
Total
1
28
Lap joint
0.18
0.36
0.36
29
29.00
Ground electrode
21.00
L-connectors
0.6
4.80
Lap joint
0.18
28.36
57
57.00
Ground electrode
11
33.00
L-connectors
11
0.6
6.60
0.18
Total
1
59
59.00
Ground electrode
3.00
12
0.6
7.20
0.18
Lap joint
Total
63
63.00
Ground electrode
3.00
13
0.6
7.80
0.18
0.90
Lap joint
0.72
69.92
Along 3-gridline
Main mat
L-connectors
0.72
97.32
Along 2-gridline
Main mat
L-connectors
0.54
55.34
Along 1-gridline
Main mat
Lap joint
28.00
Total
Along L & R-gridlines in the periphery
Main mat
Total
33.00
33.36
Along R-gridline
Main mat
1.44
44.64
Along P-gridline
Main mat
2.34
48.54
Total
1.98
54.33
Along M-gridline
Main mat
Lap joint
Total
74.70
Along 4-gridline
Main mat
67
67.00
Diversion
0.25
0.25
0.5
1.00
Ground electrode
3.00
L-connectors
14
0.6
8.40
Lap joint
15
0.18
Total
2.70
82.35
Along 5-gridline
Main mat
71
71.00
Diversion
2.6
2.60
0.5
1.00
Ground electrode
3.00
L-connectors
15
0.6
9.00
Lap joint
16
0.18
2.88
Total
89.48
Along 6-gridline
Main mat
73
73.00
Diversion
3.7
3.70
0.5
1.00
0.25
0.50
6.00
L-connectors
15
0.6
9.00
Lap joint
14
0.18
Ground electrode
Total
1
73
73.00
Diversion
0.5
0.50
0.3
1.20
0.5
1.00
6.00
L-connectors
15
0.6
9.00
Lap joint
14
0.18
Total
1
73
73.00
Diversion
1.00
0.3
0.60
0.5
1.00
6.00
L-connectors
15
0.6
9.00
Lap joint
16
0.18
2.88
Total
93.48
Along 9-gridline
Main mat
73
73.00
0.3
1.20
0.5
1.00
6.00
L-connectors
15
0.6
9.00
Lap joint
15
0.18
Ground electrode
Total
1
73
73.00
Diversion
0.35
0.35
0.3
0.60
0.7
1.40
2.00
6.00
L-connectors
15
0.6
9.00
Lap joint
19
0.18
Total
2.70
92.90
Along 10-gridline
Main mat
Ground electrode
2.52
93.22
Along 8-gridline
Main mat
Ground electrode
2.52
95.72
Along 7-gridline
Main mat
Ground electrode
3.42
95.77
Along 11-gridline
Main mat
73
73.00
Diversion
5.5
5.50
0.3
0.60
0.7
1.40
2.00
27.00
9.00
Ground electrode
L-connectors
15
0.6
Lap joint
17
0.18
Total
3.06
121.56
Along 12-gridline
Main mat
33
33.00
0.8
1.60
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
0.90
Total
46.30
Along 13-gridline
Main mat
33
33.00
0.8
1.60
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
Total
Along 14-gridline
Main mat
33
33.00
Diversion
0.5
0.50
2.00
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
Along 15-gridline
Main mat
33
33.00
0.8
1.60
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
Along 16-gridline
Main mat
33
33.00
0.8
1.60
1.3
2.60
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
1.44
49.44
Along 17-gridline
Main mat
33
33.00
0.9
1.80
Ground electrode
6.00
L-connectors
0.6
5.40
Lap joint
0.18
Total
1
33
33.00
0.9
1.80
Ground electrode
6.00
L-connectors
0.6
5.40
Lap joint
0.18
Along 19-gridline
0.90
47.10
Along 18-gridline
Main mat
Total
0.90
46.30
Total
0.90
47.20
Total
0.90
46.30
Total
0.90
47.10
Main mat
33
33.00
0.8
1.60
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
Total
0.90
46.30
Along 20-gridline
Main mat
33
33.00
2.00
Ground electrode
6.00
L-connectors
0.6
4.80
Lap joint
0.18
Total
0.90
46.70
Along 21-gridline
Main mat
33
33.00
Diversion
1.6
1.60
2.00
Ground electrode
24.00
10
0.6
6.00
0.18
L-connectors
Lap joint
67.68
2730.73
3.5
3.50
2.25
2.25
1.7
3.40
Ground electrode
6.00
L-connectors
0.6
Total
Y-phase L.A.
Riser
1.20
16.35
2.7
5.40
1.75
3.50
Ground electrode
6.00
L-connectors
0.6
Total
B-phase L.A.
Riser
1.20
16.10
4.00
2.5
2.50
1.7
1.70
Ground electrode
6.00
L-connectors
0.6
1.20
Total
Y-phase Coupling Capacitor
Riser
B-phase Coupling Capacitor
Riser
Line Isolator
Riser
R-phase P.T.
Riser
Y-phase P.T.
Riser
B-phase P.T.
Riser
1.08
Total
R-phase L.A.
Riser
15.40
3
1.2
3.60
1.9
3.80
1.3
1.30
4.00
2.7
5.40
6.00
2.7
5.40
1.9
3.80
6.00
2.3
2.30
2.9
2.90
2.9
5.80
m
m
17231
R-phase C.T.
Riser
Y-phase C.T.
Riser
B-phase C.T.
Riser
SF6 Breaker (R-phase pole)
Riser
SF6 Breaker (Y-phase pole)
Riser
Old Cubicles
Riser
1.7
3.40
1.4
2.80
1.6
3.20
2.3
4.60
1.7
3.40
1.8
3.60
1.7
3.40
2.2
4.40
2.5
5.00
2.5
5.00
3.2
3.20
3.7
3.70
2.2
4.40
2.5
5.00
2.00
3.00
6.00
1.3
2.60
1.2
1.20
1.9
1.90
1.4
2.6
7.80
1.6
1.60
Ground electrode
6.00
L-connectors
0.6
Total
Y-phase L.A.
Riser
1.20
16.60
2.4
7.20
1.6
1.60
Ground electrode
6.00
L-connectors
0.6
Total
B-phase L.A.
Riser
10
2.80
172.75
1.20
16.00
1.8
3.60
1.3
2.60
Ground electrode
6.00
L-connectors
0.6
Total
Line Isolator
Riser
R-phase P.T.
Riser
Y-phase P.T.
Riser
B-phase P.T.
Riser
1.20
13.40
3.2
6.40
2.2
4.40
1.5
3.00
1.1
2.20
2.5
5.00
1.4
4.20
1.8
1.80
1.7
3.40
m 1090.05
R-phase C.T.
Riser
Y-phase C.T.
Riser
B-phase C.T.
Riser
SF6 Breaker (R-phase pole)
Riser
SF6 Breaker (Y-phase pole)
Riser
SF6 Breaker (B-phase pole)
Riser
Breaker Cubicle
Riser
Bus Isolator
Riser
Old Cubicle
Riser
2.1
2.10
2.5
2.50
3.3
6.60
2.2
4.40
3.4
6.80
1.5
3.00
1.5
4.50
2.5
2.50
2.5
5.00
4.00
2.5
7.50
2.2
2.20
1.5
3.00
2.3
2.30
2.7
2.70
2.2
6.60
1.3
2.60
1.4
2.80
2.2
2.20
3.2
3.20
1.2
2.40
155.30
1.4
2.80
2.3
2.30
3.2
3.20
Ground electrode
6.00
L-connectors
0.6
Total
Y-phase L.A.
Riser
1.20
15.50
3.2
6.40
1.5
3.00
Ground electrode
6.00
L-connectors
0.6
Total
B-phase L.A.
Riser
1.20
16.60
1.2
2.40
2.4
4.80
Ground electrode
6.00
L-connectors
0.6
Total
Y-phase Coupling Capacitor
Riser
B-phase Coupling Capacitor
Riser
Line Isolator
Riser
R-phase P.T.
1.20
14.40
2.6
5.20
2.00
2.6
5.20
1.3
1.30
1.8
3.60
1.5
3.00
1.3
2.60
979.943
Riser
Y-phase P.T.
Riser
B-phase P.T.
Riser
R-phase C.T.
Riser
Y-phase C.T.
Riser
B-phase C.T.
Riser
SF6 Breaker (R-phase pole)
Riser
SF6 Breaker (Y-phase pole)
Riser
Old Cubicle
Riser
4.00
2.8
5.60
2.00
1.5
1.50
2.4
2.40
2.00
2.00
4.00
2.7
5.40
1.7
3.40
2.00
1.6
3.20
2.00
1.7
3.40
1.2
2.40
1.3
2.60
1.3
2.60
1.6
1.60
2.3
2.30
1.3
2.60
1.2
2.40
1.2
2.40
1.8
1.80
2.7
2.70
1.5
3.00
1.7
5.10
1.6
1.60
R-phase C.T.
Riser
Y-phase C.T.
Riser
B-phase C.T.
Riser
SF6 Breaker (R-phase pole)
Riser
SF6 Breaker (Y-phase pole)
Riser
SF6 Breaker (B-phase pole)
Riser
145.40
1.9
3.80
2.5
5.00
4.00
1.7
3.40
1.5
1.50
2.00
4.00
1.7
3.40
1.6
3.20
1.4
2.80
1.7
3.40
1.5
3.00
1.8
3.60
1.4
2.80
1.4
2.80
m 917.474
1.7
1.70
1.00
1.2
2.40
1.9
1.90
2.2
4.40
1.5
3.00
Ground electrode
6.00
L-connectors
0.6
Breaker Cubicle
Riser
R-phase 220kV L.A.
Riser
Total
Y-phase 220kV L.A.
Riser
1.20
14.60
1.9
3.80
2.3
4.60
Ground electrode
6.00
L-connectors
0.6
Total
B-phase 220kV L.A.
Riser
1.20
15.60
2.5
5.00
1.3
2.60
Ground electrode
6.00
L-connectors
0.6
Total
R-phase 110kV L.A.
MS rod used for connecting the Risers
6.00
Riser
1.3
2.60
2.00
2.5
2.50
Ground electrode
6.00
L-connectors
0.6
4.00
Ground electrode
6.00
L-connectors
0.6
0.9
1.80
1.2
2.40
Ground electrode
6.00
L-connectors
0.6
2.3
4.60
4.00
2.5
5.00
0.8
0.80
0.9
0.90
1.00
2.4
4.80
1.7
1.70
1.2
1.20
Ground electrode
6.00
L-connectors
0.6
Tertiary Connection
1.20
11.40
Total
1.20
11.20
Total
Transformer Body (R-phase unit)
Riser
Transformer Body (Y-phase unit)
Riser
Transformer Body (B-phase unit)
Riser
Fan Control Cubicle (R-phase unit)
Riser
Fan Control Cubicle (Y-phase unit)
Riser
Fan Control Cubicle (B-phase unit)
Riser
Neutral C.T.
Riser
1.20
20.30
Total
1.20
14.80
Total
1.20
14.90
Riser
1.7
1.70
1.00
Ground electrode
6.00
L-connectors
0.6
Total
Old Cubicles
Riser
1.6
R-phase C.T.
Riser
Y-phase C.T.
Riser
B-phase C.T.
Riser
SF6 Breaker (R-phase pole)
Riser
SF6 Breaker (Y-phase pole)
Riser
Ground electrode
L-connectors
1.8
3.60
1.6
3.20
2.4
4.80
1.7
3.40
1.5
1.50
2.6
2.60
1.5
3.00
1.3
2.60
1.2
3.60
1.6
1.60
1.2
3.60
1.6
1.60
1.3
2.60
1.2
1.20
1.7
1.70
2.00
1.4
2.80
1.1
2.20
1.5
1.50
1.2
2.40
2.00
3.4
3.40
6.00
0.6
1.7
3.40
1.3
1.30
2.6
2.60
Ground electrode
6.00
L-connectors
0.6
1.2
2.40
1.9
1.90
2.6
2.60
Ground electrode
6.00
L-connectors
0.6
1.20
14.10
6.00
Riser
2.2
4.40
1.3
2.60
6.00
Ground electrode
1.20
14.50
Total
m 1181.86
1.20
15.00
Total
3.20
187.30
Total
Y-phase 220kV L.A.
Riser
0.60
9.30
L-connectors
0.6
Total
1.20
20.20
6.00
Riser
0.9
1.80
1.2
2.40
Ground electrode
6.00
L-connectors
0.6
Total
1.20
17.40
5.00
Riser
0.9
1.80
1.2
2.40
Ground electrode
6.00
L-connectors
0.6
Total
Transformer Body (R-phase unit)
Riser
Transformer Body (Y-phase unit)
Riser
Transformer Body (B-phase unit)
Riser
Fan Control Cubicle (R-phase unit)
Riser
Fan Control Cubicle (Y-phase unit)
Riser
Fan Control Cubicle (B-phase unit)
Riser
Neutral C.T.
Riser
2.5
5.00
2.7
5.40
2.4
4.80
1.00
1.00
2.00
1.5
4.50
2.5
2.50
Ground electrode
6.00
L-connectors
0.6
Tertiary Connection
MS rod used for connecting the Tertiary
6.00
Riser
1.4
1.40
1.2
1.20
Ground electrode
6.00
L-connectors
0.6
Old Cubicles
Riser
1.5
Riser
0.60
15.20
1.20
14.20
Total
1.20
16.40
Total
1.50
196.80
m 1241.81
1.3
3.90
4.00
3.3
3.30
1.5
3.00
2.5
5.00
Total
1.2
6.00
10
1.4
14.00
1.6
8.00
10.00
2.2
11.00
2.4
19.20
2.6
10.40
12.00
3.2
6.40
97.00
1.2
4.80
1.5
9.00
1.8
7.20
Total
8.00
29.00
2.3
2.30
1.5
4.50
Total
1.00
7.80
Spare transformer
Riser
1.8
1.80
1.5
1.50
1.8
1.80
17
0.8
13.60
15
15.00
1.2
Total
4.80
33.40
26
0.9
23.40
8.00
1.5
4.50
1.2
2.40
229.80
3818.08
###
240.92
As per estimate
275.00
11
11.00
Along 2-gridline
1.00
Along 3-gridline
1.00
Along 4-gridline
1.00
Along 5-gridline
1.00
Along 6-gridline
2.00
Along 7-gridline
2.00
Along 8-gridline
2.00
Along 9-gridline
2.00
Along 10-gridline
2.00
Along 11-gridline
9.00
Along 12-gridline
2.00
Along 13-gridline
2.00
Along 14-gridline
2.00
Along 15-gridline
2.00
11 Along 16-gridline
Along 17-gridline
2.00
2.00
Along 18-gridline
2.00
Along 19-gridline
2.00
Along 20-gridline
2.00
Qtl
1450
Along 21-gridline
8.00
6.00
6.00
6.00
6.00
6.00
2.00
2.00
6.00
6.00
2.00
2.00
7.00
117.00
As per estimate
120.00
No.
0.7
1.2
1.20
0.7
3.30
2.80
1.2
2.40
1.4
1.40
Total
Along E-gridline
Total
2.10
4.00
10.60
Along F-gridline
1.4
Along G-gridline
0.7
2.80
0.70
1.2
1.20
1.4
2.80
0.7
4.70
0.70
1.2
1.20
1.4
2.80
0.7
4.70
1.40
1.2
1.20
1.4
Total
Along H-gridline
Total
Along I-gridline
Total
2.80
5.40
Along J-gridline
1.4
2.80
Along K-gridline
1.4
2.80
Along L-gridline
1.4
Along M-gridline
0.7
2.80
5.60
1.4
2.80
3.1
6.20
0.7
14.60
2.10
1.2
2.40
0.7
4.50
2.10
1.2
2.40
0.7
4.50
0.70
1.2
1.20
1.4
1.40
0.7
3.30
0.70
Total
Along 4-gridline
Total
Along 5-gridline
12 Along 6-gridline
Total
Total
Along 7-gridline
1.2
1.4
1.40
0.7
3.30
1.40
1.2
1.20
1.4
1.40
2.00
0.7
6.00
2.80
1.2
1.20
1.4
1.40
0.7
5.40
1.40
1.2
2.40
1.4
1.40
2.00
1.2
7.20
1.20
1.4
1.40
3.1
Total
Along 8-gridline
Total
Along 9-gridline
Total
Along 10-gridline
Total
Along 11-gridline
Total
1.20
3.10
5.70
Along 12-gridline
1.4
1.40
Along 13-gridline
1.4
1.40
Along 14-gridline
1.4
1.40
Along 15-gridline
1.4
1.40
Along 16-gridline
1.4
1.40
Along 17-gridline
1.4
1.40
Along 18-gridline
1.4
1.40
Along 19-gridline
1.4
1.40
Along 20-gridline
1.4
1.40
Along 21-gridline
1.4
1.40
1.2
4.80
113.20
As per estimate
200.00
Total
NIL
As per estimate
60.00
1.00
1.00
7.00
5.00
12
12.00
4.00
17
17.00
3.00
14
14.00
2.00
18
18.00
3.00
14
14.00
4.00
16
16.00
4.00
11.00
6.00
4.00
10.00
17.00
21.00
17.00
20.00
17.00
20.00
Along J-gridline
Lap joint along main gridline
0.00
10
10.00
0.00
11
11.00
2.00
11
11.00
1.00
16.00
2.00
8.00
10.00
10.00
11.00
13.00
0.00
8.00
8.00
2.00
0.00
2.00
2.00
0.00
2.00
2.00
19.00
4.00
11
22.00
0.00
26.00
4.00
12
24.00
0.00
28.00
5.00
13
26.00
0.00
31.00
2.00
14
28.00
13
13.00
43.00
Along 5-gridline
Lap joint along main gridline
1.00
15
30.00
15
0.00
15
30.00
14
0.00
15
30.00
14
1.00
15
30.00
15
1.00
15
30.00
14
3.00
15
30.00
16
1.00
15
30.00
16
15.00
46.00
14.00
44.00
14.00
44.00
15.00
46.00
14.00
45.00
16.00
49.00
16.00
47.00
1.00
16.00
1.00
16.00
1.00
16.00
1.00
16.00
1.00
16.00
4.00
21.00
4.00
21.00
4.00
21.00
4.00
21.00
7.00
24.00
Along 17-gridline
Lap joint along main gridline
1.00
18.00
1.00
18.00
1.00
16.00
1.00
16.00
4.00
23.00
4.00
23.00
4.00
21.00
4.00
21.00
0.00
10
20.00
6.00
26.00
880.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
3.00
3.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
14
4.00
4.00
3.00
6.00
2.00
83.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
6.00
4.00
2.00
77.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
3.00
3.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
4.00
Breaker Cubicle
Lap joint for Riser
Bus Isolator
Lap joint for Riser
Old cubicle
Lap joint for Riser
3.00
6.00
1.00
82.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
2.00
2.00
2.00
1.00
1.00
1.00
4.00
4.00
Total
Tertiary Connection
Lap joint for Riser
Lap joint for Ground Electrode L-Connector
Total
Old cubicles
Lap joint for Riser
8.00
2
2.00
2.00
4.00
2.00
104.00
6.00
4.00
4.00
4.00
4.00
4.00
4.00
3.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
4.00
4.00
8.00
2.00
2.00
2.00
1.00
1.00
1.00
4.00
4.00
8.00
2.00
2.00
4.00
1.00
103.00
6.00
4.00
15
30.00
18.00
18
18.00
5.00
1.00
1.00
36
36.00
30
30.00
5.00
Spare Transformer
Lap joint for Riser
1.00
155.00
1484.00
As per estimate
1450.00 No.
11
11.00
Along 2-gridline
12
12.00
Along 3-gridline
13
13.00
Along 4-gridline
14
14.00
Along 5-gridline
14
14.00
Along 6-gridline
15
15.00
Along 7-gridline
15
15.00
Along 8-gridline
15
15.00
Along 9-gridline
15
15.00
15
15.00
15
15.00
Along 12-gridline
8.00
Along 13-gridline
8.00
Along 14-gridline
8.00
Along 15-gridline
8.00
Along 16-gridline
8.00
Along 17-gridline
8.00
Along 18-gridline
8.00
Along 19-gridline
8.00
Along 20-gridline
8.00
Along 21-gridline
8.00
15 Along 10-gridline
Along 11-gridline
7.00
241.00
5
25.00
12
25
300.00
541.00
As per estimate
520.00
No.
16
17
Along 1-gridline
11
11.00
Along 2-gridline
1.00
Along 3-gridline
1.00
Along 4-gridline
1.00
Along 5-gridline
1.00
Along 6-gridline
2.00
Along 7-gridline
2.00
Along 8-gridline
2.00
Along 9-gridline
2.00
Along 10-gridline
2.00
Along 11-gridline
9.00
Along 12-gridline
2.00
Along 13-gridline
2.00
Along 14-gridline
2.00
Along 15-gridline
2.00
Along 16-gridline
2.00
Along 17-gridline
2.00
Along 18-gridline
2.00
Along 19-gridline
2.00
Along 20-gridline
2.00
Along 21-gridline
8.00
6.00
6.00
6.00
6.00
6.00
2.00
2.00
6.00
6.00
2.00
2.00
7.00
117.00
As per estimate
120.00
No.
0.00
220kV LA
0.00
110kV LA
0.00
Neutral of Transformers
0.00
Tertiary of Transformers
0.00
0.00
As per estimate
1700.00
1.00
Y-phase L.A.
1.00
B-phase L.A.
1.00
1.00
1.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
4.00
4.00
4.00
Breaker Cubicle
2.00
Bus Isolator
3.00
Old Cubicle
2.00
39.00
R-phase L.A.
2.00
Y-phase L.A.
2.00
B-phase L.A.
2.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
2.00
Bus Isolator
3.00
Old Cubicle
2.00
34.00
R-phase L.A.
2.00
Y-phase L.A.
2.00
B-phase L.A.
2.00
1.00
1.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
18
Y-phase C.T.
2.00
B-phase C.T.
2.00
4.00
4.00
4.00
Breaker Cubicle
2.00
Bus Isolator
3.00
Old Cubicle
1.00
41.00
Bus Isolator
3.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
1.00
1.00
1.00
Neutral C.T.
3.00
Tertiary Connection
2.00
Old Cubicle
2.00
45.00
Bus Isolator
3.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
1.00
1.00
1.00
Neutral C.T.
3.00
Tertiary Connection
2.00
Old Cubicle
1.00
44.00
3.00
Bus P.T.
2.00
0.00
H-Structure
0.00
0.00
0.00
Spare Transformer
1.00
1.00
Fencing
0.00
30
30.00
5.00
Old earthing
Cable trench earth strip
42.00
245.00
As per estimate
350.00
No.
3.00
Line Isolator
3.00
3.00
Bus Isolator
3.00
Line Isolator
3.00
1.00
1.00
Bus Isolator
3.00
Neutral C.T.
1.00
1.00
7.00
7.00
Bus Isolator
3.00
Neutral C.T.
1.00
1.00
1.00
3.00
45.00
As per estimate
100.00
3.00
Y-phase L.A.
3.00
B-phase L.A.
3.00
2.00
No.
2.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
0.00
0.00
0.00
Breaker Cubicle
1.00
Bus Isolator
3.00
Old Cubicle
0.00
32.00
R-phase L.A.
2.00
Y-phase L.A.
2.00
B-phase L.A.
2.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
1.00
Bus Isolator
3.00
Old Cubicle
0.00
31.00
R-phase L.A.
2.00
Y-phase L.A.
2.00
B-phase L.A.
2.00
2.00
2.00
Line Isolator
3.00
R-phase P.T.
2.00
Y-phase P.T.
2.00
B-phase P.T.
2.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
0.00
0.00
0.00
Breaker Cubicle
1.00
Bus Isolator
3.00
Old Cubicle
0.00
29.00
Bus Isolator
3.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
1.00
2.00
2.00
2.00
2.00
2.00
2.00
Transformer Body
0.00
0.00
Neutral C.T.
1.00
Tertiary Connection
0.00
Old Cubicle
0.00
29.00
Bus Isolator
3.00
R-phase C.T.
2.00
Y-phase C.T.
2.00
B-phase C.T.
2.00
2.00
2.00
2.00
Breaker Cubicle
1.00
2.00
2.00
2.00
2.00
2.00
2.00
Transformer Body
0.00
0.00
Neutral C.T.
1.00
Tertiary Connection
0.00
Old Cubicle
0.00
29.00
Bus P.T.
2.00
15
30.00
3.00
18.00
H-Structure
1.00
9.00
5.00
Spare Transformer
0.00
0.00
36
36.00
Old earthing
0.00
Fencing
0.00
104.00
254.00
As per estimate
200.00
No.