Advanced Techniques in Project Management Overview
Advanced Techniques in Project Management Overview
3. Earned Value Management (EVM). Project managers can use EVM to become powerful at
predicting outcomes of projects. They can use EVM to integrate scope, schedule and
resources, objectively measure project performance, and forecast future outcomes1. EVM
only requires a few items, including a project plan that identifies the work to be
accomplished, valuation of planned work (PV) and actual costs (AC), and earning rules for
accruing earned value (EV) on the project. With these items in place, the following metrics
can be used to control cost and schedule:
Cost Variance (CV) and Schedule Variance (SV) track the difference between
planned and actual cost and time spent.
Cost Performance Index (CPI) and Schedule Performance Index (SPI) track the
performance of a dollar or day spent on the project, respectively.
The following metrics can be used to forecast future performance:
Estimate at Completion (EAC) projects the cost of the project work once its
complete.
Estimate to Completion (ETC) projects the cost to finish the remaining project work.
To-Complete Performance Index (TCPI) projects the efficiency required to finish the
remaining project work.
By setting up the project and combining these metrics, project managers can track
performance achieved to-date and provide forecasts of where the project is going. These
reports can be used to make important decisions about scope, schedule, and resources.
4. Advanced Risk Management. Project managers can use two advanced techniques to take
their risk management to the next level. First, they can calculate Expected Monetary Value
(EMV) for each risk by multiplying probability percentage of a risk occurring by the
anticipated impact in days or dollars. EMV is a powerful tool because it provides a strong
sense of a risks real impact. For example, a risk that carries 20 percent probability and
$20,000 expected monetary impact may not seem bad, but with an EMV of $4,000, the
team may want to revisit the risk and come up with a response.
Expected Monetary Value is also the backbone of the risk contingency reserve, a reserve or
days and dollars set aside to address known unknowns on a project. For example, if the total
EMV of all risks is $20,000 and 5 days, then those dollars and days are combined with the
project estimates to come up with the cost baseline for the project. The cost baseline is then
combined with management reserve to form the project budget.
1 Project Management Institute (2011). Practice Standard for Earned Value Management. Second Edition. Newtown Square, PA: Project
Management Institute.
By using risk contingency reserve, project managers can dramatically improve the
predictability of project outcomes. Project managers can achieve this improved
predictability through remaining risk contingency reserve as it is spent in terms of extra
money or time on a project. Figure 1 shows where the risk contingency reserve fits into the
overall cost of a project.
Leadership Skills
Where advanced technical project management skills rest on a foundation of seeing how knowledge
areas and processes can work with each other, advanced leadership skills rest on a foundation of
emotional intelligence. Emotional intelligence hinges on the ability to manage ones emotions and how
they are expressed, as well as master social awareness and social skills. The following leadership
techniques described in this section can all be enhanced by strong emotional intelligence.
1. Developing Clarity and Focus. A project managers first job as a leader is to help develop
clarity and focus on the team. To achieve this goal, the project manager must first seek and
achieve full understanding of the project, its relation to key business objectives, its
requirements, and its success criteria. From there, the challenge becomes relaying this
understanding to the project team so they can buy in to the project. Three types of clarity
are needed for teams to function effectively:
Clarity of plan: What is the plan?
Clarity of purpose: Why are we carrying out this plan?
Clarity of responsibility: What is each members role in the plan?
By helping team members gain clarity of plan, purpose, and responsibility, project managers
can effectively secure their focus on key milestones and deliverables. Once the team is
focused, the project managers primary activity is monitoring and controlling to ensure team
accountability for meeting the projects objectives.
2. Inspiring and Motivating. Motivational leadership is a leadership style based on vision,
integrity, courage, realism, and responsibility2. Motivational leaders use their personal style
to energize people into increasing their commitment to a project. Project managers who
want to inspire their team can do so by showing them what the end goal looks like. Specific
actions like displaying mockups or progress maps can help team members stay committed
to the end goals of the project. Once this clear picture of the end goal is in mind, celebrating
accomplishments in the form of milestones achieved helps keep the team energized.
3. Effective communication. The majority of a project managers job is communication, not
only with the team but also with stakeholders. Effective communication is more than verbal
and written communication; it also is comprised of body language and other non-verbal
cues. Effective communication helps build bridges between different departments, team
members, and stakeholders and unifies the team toward a common vision.
2 Zenger and Folkman (2011, 4 October). The 16 days of competencies: #10 inspires and motivates others to high performance. Accessed 10
February 2016 from http://zengerfolkman.com/the-16-days-of-competencies-10-inspires-and-motivates-others-to-high-performance/
They can then approach any negotiation with the end goal in mind, helping them craft
effective criteria for what constitutes a win for either side. This approach results in
successful negotiations because, while everyone may not leave fully happy, each side has
gotten something, and mutual trust has been maintained.
6. Managing Stress on Projects. Yet another inevitable fact about projects is that they are
stressful. When a project team is working on building something unique, they are stretching
their skills to the limit and operating under what is often a tight deadline. The pressure on
project teams to perform can lead to a lot of stress, and by diffusing this stress wherever
possible, project managers can build trust.
The first step in stress management is to identify the overall level of stress. Some stress is
good for a team because it keeps them motivated and engaged. However, too much for too
long will lead to burnout and additional conflict. If there is too much stress on a project,
then project managers need to find and address root causes and come up with a plan to first
prevent further stress and then reduce the stress level. Some factors that could be root
causes of stress include6:
Long work schedules to meet tight deadlines.
Team members participating in multiple projects.
Lots of changes adding time and cost onto the schedule.
Conflicts over resources and priorities.
Organizational factors such as workplace conditions and policies.
The second step is preventing further stress. Project managers can start by grounding
themselves in the current project situation. Are any tasks slipping? Are any risks becoming
issues? Are there any stakeholders who are not satisfied? Taking this step helps project
managers alleviate their own stress by establishing a big-picture view of the project and
determining what stress factors can be controlled. For example, can negotiations with a
stakeholder result in an extended timeline or more resources to free up pressure? Can
teams be co-located to reduce their time spent in meetings?
6 Verma, Vijay (1996). Human resource skills for the project manager. Newtown Square, PA: Project Management Institute
Finally, stress management techniques can reduce the teams overall stress level. One
method for reducing work environment stress is PERKS:
Participation: Team members feel less stressed when they feel like theyre
contributing.
Environment: The project environment needs to be respectful and inspire
motivation.
Recognition: Team members need to be praised for their achievements.
Knowledge: Team members need to be able to expand their professional
development.
Style: The work environment should be known for open communication and trust.
Conclusion
Mastering the key techniques of advanced stakeholder, scope, earned value, and risk management,
along with the leadership skills described in this article, puts any project manager in a strong position to
manage and lead any project, even a large or complex one. Along with mastering these skills, mastering
the mindsets behind them will also help project managers chart their career path upwards. An
important step for project managers is finding opportunities to use the processes together and seeing
them as integrated parts rather than separate techniques. For example, advanced stakeholder
management combines aspects of communications management, and advanced risk management and
EVM incorporate scope, schedule, and resource management. Likewise, key leadership skills depend on
mastering the foundational skills of emotional intelligence and effective communication. By building on
the foundations of technical and leadership skills, project managers can increase their project delivery
capability.
For more about the advanced techniques discussed in this article, visit RefineMs blog. We also offer
project management consulting and project management training.
References
1. Business Productivity (2013, 16 September). Communicate effectively leveraging DISC profiles.
Accessed 10 February 2016 from http://www.businessproductivity.com/communicateeffectively-leveraging-disc-profiles/
2. Goleman, Daniel (2000, March-April). "Leadership that gets results." Harvard Business Review.
3. Project Management Institute (2013). Guide to the Project Management Body of Knowledge
(PMBOK Guide). Fifth Edition. Newtown Square, PA: Project Management Institute.
4. Project Management Institute (2011). Practice Standard for Earned Value Management. Second
Edition. Newtown Square, PA: Project Management Institute.
5. Verma, Vijay (1996). Human resource skills for the project manager. Newtown Square, PA:
Project Management Institute.
6. Zenger and Folkman (2011, 4 October). The 16 days of competencies: #10 inspires and
motivates others to high performance. Accessed 10 February 2016 from
http://zengerfolkman.com/the-16-days-of-competencies-10-inspires-and-motivates-others-tohigh-performance/