Inspection & Test Plan for Khabat PP
132kV Switchyard Earthing
Installation Works
TOTAL 3 PAGES
(Including Cover)
PROJECT NAME
: Khabat Thermal Power Plant Units 1&2
Purpose
DOCUMENT NO.
: KP-00+++-CQ712-B7363
For Information
TITLE
: Inspection&Test Plan for Khabat PP
132kV Switchyard Earthing Installation Works
OWNER
: Ministry of Electricity (MOE) of
Kurdistan Regional Government
For Review
For Approval
For Construction
As-Built
24.04.2015
For Construction
DE
AY
08.04.2015
First Issue
DE
AY
PREPARED
CHECKED
REVIEWED
APPROVED
Rev.
No.
DATE
DESCRIPTION
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.
Owner
Ministry of Electricity (MOE)
of Kurdistan Regional Government
Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
GAMA POWER SYSTEMS
ENGINEERING & CONTRACTING,INC.
ITP No.
Inspection & Test Plan
for EARTHING INSTALLATION WORKS
Item Name
No.
Earthing
Inspection & Test
Activity
Inspection & Test
Description
Application
Document/Code/Spec.
Supplier/
No.
KP-00+++-CQ712-B7363
Rev. No.
Page
1/1
Document Submittal
Remarks
Inspection Status
Subcontractor
GAMA
3rd Party POSCO
/ AI
E&C
Owner
1.1
Receiving
Inspection
Visually checking of the
earthing materials for and
physical damage.
Drawings and Technical
Specifications
Check List for Earthing Erection Item 1
1.2
Package List
Checking of package list
Assembly Catalog
Check List for Earthing Erection Item 2
1.3
Survey works
Checking coordinates of wire
Drawings and Technical
trenchs and depth of
Specifications
excavations
Check List for Earthing Erection Item 3
1.4
Excavation
Checking excavations
Drawings and Technical
Specifications
Check List for Earthing Erection Item 3
1.5
Construction of
grid copper
structure
Checking of construction
Drawings and Technical
Specifications
Check List for Earthing Erection Item 4
1.6
Earthing System
Resistance Test
Check List for Earthing Erection Item 5
1.7
Site Construction
Dossier
Site Construction Dossier
Document preparation and
review
Drawings and Technical
Specifications
Notes) #1 CL (Check List) form of Earthing Erection is submitted as attachment of this ITP.
Legend
SIEMENS
P
H
W
S
V
R
Perform
Hold Point
Witness Point
Spot Witness
Surveillance
Report Review
CHECK LIST of Earthing
Num
.
Identification
Visual check of the equipment
Checking of Package List
Survey Works
a.
Coordinates of Wire Trench
b.
Depth of Excavations
Accept
Reject
KHABAT THERMAL POWER PLANT UNITS
1 & 2 PROJECT 132kV AIR INSULATED
SWITCHGEAR
Rev: 0
Page No:1 of 1
Job No:
N/A
Signature
Comments
Subcontractor
Construction of copper grid structure
a.
Wire Type
b.
Joints and Connections of Copper Wires
c.
Count of Copper Rods
d.
Connection to the Copper Rods
e.
Manholes of the Copper Rods
Earthing system resistance test
SIGN OFF AS ACCEPTED
SIEMENS
GAMA
POSCO
Employer
Name:
Date:
Sign:
Name:
Date:
Sign:
Name:
Date:
Sign:
Name:
Date:
Sign:
GAMA
Employer