United States of America, For The Use and Benefit of Roper, Ibg, A Division of Roper Corporation v. A.I. Reisz and National Surety Corporation, 718 F.2d 1004, 11th Cir. (1983)
United States of America, For The Use and Benefit of Roper, Ibg, A Division of Roper Corporation v. A.I. Reisz and National Surety Corporation, 718 F.2d 1004, 11th Cir. (1983)
2d 1004
I.
Reisz was prime contractor for the Tennessee Valley Authority (TVA) on an
experimental greenhouse project entailing the use of cooling waters from its
Browns Ferry nuclear plant near Athens, Alabama. Reisz hired I.B.G. as a
subcontractor to supply a substantial part of the materials and labor for the
project. Shortly after I.B.G. came on the job in December 1977, a dispute arose
between them as to whether I.B.G. was to do the plumbing work. When the
dispute was not resolved at the end of December, I.B.G. pulled its men off the
job. Negotiations for a resolution of the dispute ensued, culminating in an
agreement between the two parties dated April 4, 1978. I.B.G. returned to the
job in May, and the greenhouse was completed and accepted by TVA in
December 1978.
Reisz withheld the final payment due I.B.G.; therefore, in August 1979, I.B.G.
brought this suit against Reisz and its surety, National Surety Company,
seeking the withheld sum. As an affirmative defense Reisz admitted that it had
failed to make the final payment, as alleged, but claimed that it was not
indebted to I.B.G. because I.B.G. was liable to it for certain warranty items and
backcharges, and for damages Reisz allegedly suffered because of I.B.G.'s
delay in performing the subcontract.1 Reisz counterclaimed for these items of
damages. Because of the possibility that its claim for delay damages occurring
prior to April 4, 1978, had been foreclosed by the settlement agreement of that
date,2 Reisz alleged, in its counterclaim, that the settlement agreement was void
for lack of consideration. I.B.G., in reply, denied all the allegations of Reisz'
counterclaim.
At the pretrial conference, the parties stipulated that I.B.G. was due a final
payment of $91,499.03 and that Reisz was due $12,776.93 for warranty items
and back charges. The only matter remaining for trial was Reisz' counterclaim
for delay damages.
The counterclaim was tried to a jury. At the close of Reisz' case, I.B.G. moved
for a directed verdict under rule 50(a) of the Federal Rules of Civil Procedure
on the ground, inter alia, that the April 4 settlement agreement had foreclosed
all of Reisz' claims for delay, whether they had occurred before or after April 4,
1978. The court denied the motion. I.B.G. then put on its case. Reisz offered no
rebuttal. Neither side moved for a directed verdict at the close of all the
evidence. See Fed.R.Civ.P. 50(b). Following a charge conference and the final
summations of counsel, the court submitted Reisz' counterclaim to the jury.3
The jury returned a verdict awarding Reisz $87,223.07 in delay damages. After
taking into account the amounts the parties stipulated were due one another, the
court entered a final judgment for Reisz in the sum of $8,500.97, together with
prejudgment interest on this amount from January 1, 1979. I.B.G. then moved
the court for judgment n.o.v. or, alternatively, for a new trial. See Fed.R.Civ.P.
50(b). That motion was denied, and I.B.G. took this appeal.
II.
6
We first address I.B.G.'s motion for judgment n.o.v. Rule 50(b) of the Federal
Rules of Civil Procedure requires that a party move for a directed verdict at the
close of all the evidence as a prerequisite to its motion for judgment n.o.v.
Fed.R.Civ.P. 50(b) advisory committee note. A motion for a directed verdict at
the close of plaintiff's case will not suffice unless it is renewed at the close of
all the evidence. Special Promotions, Inc. v. Southwest Photos, Ltd., 559 F.2d
430, 432 (5th Cir.1977). 4 As this case went to trial on the counterclaim, Reisz
presented evidence first. I.B.G., though it moved for a directed verdict at the
close of Reisz' case, never renewed its motion after presenting its case.
Therefore, I.B.G. was not entitled to move for a judgment n.o.v., the district
court had no authority to entertain I.B.G.'s motion therefor, and we will not
determine whether the court should have directed a verdict for I.B.G. at the
close of all the evidence.
I.B.G.'s failure to move timely for a directed verdict does not, however,
preclude our review of the district court's denial of I.B.G.'s motion for a new
trial. Special Promotions, 559 F.2d at 432. I.B.G.'s claim that the district court
wrongfully allowed the jury to find that Reisz was damaged by I.B.G.'s delay
prior to April 4, 1978, could, if I.B.G. made proper and timely objection at
trial, warrant a new trial. The submission to the jury of an issue not proper for
its consideration may be a ground for a new trial. United N.Y. & N.J. Sandy
Hook Pilots Ass'n v. Halecki, 358 U.S. 613, 619, 79 S.Ct. 517, 520, 3 L.Ed.2d
541 (1959). Thus, if I.B.G. had requested the district court, in its instructions, to
take the issue of pre-April 4 delay from the jury, or had objected to the court's
instruction that the jury could find pre-April 4 delay, we could consider
whether a new trial is warranted. However, I.B.G. made no such objection.5
We therefore cannot award I.B.G. a new trial on the ground that the district
court erred in permitting the jury to consider pre-April 4 delay. Generally,
issues not raised and preserved in the trial court will not be considered on
appeal. Brookhaven Landscape v. Barton Contracting Co., 676 F.2d 516, 523
(11th Cir.1982).
I.B.G. raises no other claims for a new trial meriting discussion here.
Accordingly, the district court properly denied I.B.G.'s motion for a new trial.6
III.
10
(1) when the amount of damages are capable of being ascertained by mere
computation; and (2) when the damages are complete at a particular time and
can be determined as of such time in accordance with fixed rules of evidence
and known standards of value.
11
Belcher v. Birmingham Trust National Bank, 488 F.2d 474, 477 (5th cir.1973).
12
Neither of these exceptions is applicable here; the parties did not agree that
I.B.G. caused any specific number of delay days, and cost per day was not even
in evidence. Thus, the duration of the delay was not certain and the amount of
damages was not ascertainable simply by computation. The damages
responsibility and amount were jury questions; therefore, the claim was not
subject to a prejudgment interest calculation.
13
Whether the unliquidated portion should have been set off against the
liquidated amount stipulated to be owed to I.B.G. is a more difficult question.
The trial court, finding no Alabama law on point, applied the proposition
asserted in Macri v. United States, 353 F.2d 804, 808 (9th Cir.1965):
14
[S]ome
courts declare that in instances where the counterclaim is for defective
performance of the contract on which the liquidated claim is based, the damages
assessed under the counterclaim are regarded as payment pro tanto and interest
should be awarded only on the remainder.
15
This theory recognizes that when the contractor withholds payment at a time
when an unliquidated damages claim has accrued to him, where the two claims
are related, it would penalize the contractor to award interest on that part of the
liquidated claim which is offset by the unliquidated claim. This approach has
been called the "interest on the balance rule." While it is often discussed in the
context of a small unliquidated claim partially offsetting a larger liquidated
claim, such that prejudgment interest is only awarded on the balance, the same
principle applies, as here, when a large unliquidated claim more than offsets a
smaller liquidated claim. See Socony Mobile Oil Company v. Klapal, 205
F.Supp. 388, 390 (D.Neb.1962). The delay claim asserted here accrued before
the withholding of I.B.G.'s final payment, and, according to Reisz, justified the
The trial judge was correct in recognizing the appropriateness of applying the
"interest on the balance rule"; however, he failed to apply it correctly in this
case. The judge offset the jury award of $100,000 ($87,223.07 unliquidated and
$12,776.93 liquidated warranty and backcharge) against the stipulated
liquidated damages of $91,499.03 owing to I.B.G. for work performed. The
judge noted that the remaining $8,500.97, as it was less than the liquidated
$12,776.93, was a liquidated balance, on which prejudgment interest should be
awarded.7
17
18
This result fits the interest on the balance theory in that Reisz withheld the final
payment recognizing that I.B.G. owed it the warranty and backcharge and
delay damages effectively as of that date. While an unliquidated amount does
not accumulate prejudgment interest, it would penalize Reisz not to allow so
much of the unliquidated amount as it withheld because of I.B.G.'s inadequate
performance of the work to be set off against the amount due I.B.G. on a dollar
for dollar basis. Since Reisz knew when it withheld the sum from I.B.G. that
I.B.G. owed it the warranty and backcharge, Reisz can be said to have withheld
only $78,722.10 as contemplated delay damages. Since Reisz was awarded
$8,500.97 more than that amount on its unliquidated claim, that unliquidated
amount is what remains after the set-off.8 As the unliquidated amount does not
accumulate prejudgment interest, we reverse on the award of prejudgment
interest on the $8,500.97 owed to Reisz, and direct the district court, on
remand, to correct the final judgment accordingly.
19
The district court had subject matter jurisdiction of Reisz' counterclaim because
it was a compulsory counterclaim, arising out of the same contract for which
I.B.G. sought payment under the Miller Act bond Reisz had posted pursuant to
40 U.S.C. Sec. 270b(b) (1976). United States v. Thermo Contracting Corp.,
437 F.Supp. 195, 198 (D.N.J.1976). See Graybar Elec. Co. v. John A. Volpe
Const. Co., 387 F.2d 55, 57 n. 3 (5th Cir.1967)
Alabama law regarding the scope of a settlement agreement is set forth in Nero
v. Chastang, 358 So.2d 740 (Ala.Civ.App.1978), cert. denied, ex parte Nero,
358 So.2d 744 (Ala.1978). Generally, a compromise agreement covers only
matters that the parties "have fairly intended to include"; however, this notion
is read broadly to cover all claims arising from the dispute known at the time of
the settlement and not expressly preserved. Id. at 743. Since at the time of the
agreement I.B.G. and Reisz both had ripe delay claims for damages caused by
the dispute, the delay claims were arguably settled by the agreement, as they
were not expressly reserved
The court instructed the jury to return a verdict for Reisz in the amount of the
stipulated damages (for the warranty and back charge items) of $12,776.93,
plus whatever sums the jury might determine were due Reisz as a result of any
delay in the work caused by I.B.G
In Bonner v. City of Prichard, 661 F.2d 1206, 1209 (11th Cir.1981) (en banc),
this court adopted as binding precedent all decisions of the former Fifth Circuit
handed down prior to October 1, 1981
In fact, I.B.G. requested the court to allow the jury to determine whether or not
the April 4, 1978, agreement settled and therefore foreclosed Reisz' claim.
Such an instruction would have been proper only if the April 4 agreement were
ambiguous, so that the parties' intent became an issue. Since the April 4
agreement was not ambiguous, the scope of the agreement was a question of
law for the court, not for the jury
I.B.G. does not contend on appeal that the damages award was against the
manifest weight of the evidence, thus warranting a new trial; rather it only
contends that its directed verdict motion should have been granted on that issue.
I.B.G.'s other claims for a new trial are without merit
While Reisz never claimed interest on the warranty and backcharge, the judge
recognized that Reisz did not need to claim interest on these amounts in order to
be entitled to interest. Alabama Terminix Co. v. Howell, 276 Ala. 59, 158
So.2d 915, 918 (1963)
In other words, the liquidated $12,776.93 owing to Reisz should be set off
against the liquidated final payment of $91,449.03 owing to I.B.G. first. Then,
the unliquidated delay damage award owing to Reisz should be set off dollar
for dollar against the final payment until the entire final payment is offset. At
that point Reisz has justified its withholding, and I.B.G. has not been allowed
any interest advantage because its claim was liquidated. Thus, Reisz takes the
rest of its unliquidated damage claim according to the general rule, without
prejudgment interest