United States v. Princeton Gamma-Tech, Inc., Defendant/third-Party Jeffrey Sands 206 Center, Inc. Hilton Realty Company of Princeton, Inc. (George Sands & Jeffrey Sands T/a Hilton Realty Company of Princeton, Inc.) George Sands Estelle Sands Fifth Dimensions, Inc. J & R Associates, Ltd. Princeton Chemical Research, Inc. Cornelius Van Cleef Frederick Decicco Joseph A. Baicker Alden Sayres Abc Co. (1-100), John Doe (1-100), Xyz Co. (1-100), Jane Doe (1-100), Third-Party Princeton Gamma-Tech, Inc., 31 F.3d 138, 3rd Cir. (1994)
United States v. Princeton Gamma-Tech, Inc., Defendant/third-Party Jeffrey Sands 206 Center, Inc. Hilton Realty Company of Princeton, Inc. (George Sands & Jeffrey Sands T/a Hilton Realty Company of Princeton, Inc.) George Sands Estelle Sands Fifth Dimensions, Inc. J & R Associates, Ltd. Princeton Chemical Research, Inc. Cornelius Van Cleef Frederick Decicco Joseph A. Baicker Alden Sayres Abc Co. (1-100), John Doe (1-100), Xyz Co. (1-100), Jane Doe (1-100), Third-Party Princeton Gamma-Tech, Inc., 31 F.3d 138, 3rd Cir. (1994)
3d 138
39 ERC 1001, 63 USLW 2084, 24 Envtl.
L. Rep. 21,243
At least some of the proposed wells have already been installed on the property,
but the pump treatment system has not yet been fully implemented. The final
design was expected to be completed in the fall of 1993 and the remedial
process begun in the spring of 1994. It is anticipated that the cleanup will be
completed in five to seven years.
5
The district court concluded that it lacked subject matter jurisdiction to grant
Gamma-Tech's request for injunctive relief. The court based its conclusion on
the general principle, garnered from statutory and decisional law, that district
courts have no jurisdiction over claims challenging the EPA's choice of
remedies until after completion of a distinct phase of the cleanup. 817 F.Supp.
488.
Appealing under 28 U.S.C. Sec. 1292(a)(1), Gamma-Tech asserts that once the
EPA brought its cost-recovery suit under CERCLA, the general jurisdictional
bar to the review of challenges was lifted pursuant to the cost-recovery action
exception under 42 U.S.C. Sec. 9613(h)(1). The district court thus had authority
to grant an injunction even though the remedial work has not yet been
completed. Gamma-Tech also contends that it was denied due process and that
the district court erred in denying leave to file a supplemental pleading adding
claims for damages.
I.
9
waste sites pose to public health or the environment. The EPA was granted
broad powers to eliminate or reduce toxic contamination in the environment by
either requiring responsible parties to clean up the sites, 42 U.S.C. Sec. 9606, or
by undertaking the task itself, 42 U.S.C. Sec. 9604.
10
Because of the menace to public health and the environment, Congress was
anxious to safeguard EPA remedial efforts from delay resulting from litigation
brought by potentially responsible parties. See Lone Pine Steering Comm. v.
EPA, 777 F.2d 882, 886-87 (3d Cir.1985); Wheaton Indus. v. EPA, 781 F.2d
354, 356 (3d Cir.1986). In the Superfund Amendments and Reauthorization Act
of 1986 (SARA), Congress adopted a "clean up first, litigate later" philosophy.
See 132 Cong.Rec. 28,409 (1986) (statement of Sen. Stafford) (Congress
wanted to avoid "specious suits [that] would slow cleanup and enable private
parties to avoid or at least delay paying their fair share of cleanup costs.").
11
12 Federal court shall have jurisdiction under Federal law ... to review any
No
challenges to removal or remedial action selected under section 9604 ... in any action
except one of the following:
13
"(1) An action under section 9607 of this title to recover response costs or
damages or for contribution.
******
14
15
(4) An action under section 9659 of this title (relating to citizens suits) alleging
that the removal or remedial action taken under section 9604 of this title or
secured under 9606 of this title was in violation of any requirement of this
chapter...."
16
The language in section 9613(h) demonstrates Congress' intent that the EPA be
free to conduct prompt and expeditious cleanups without obstructive legal
entanglements. By providing several exceptions to the timeliness bar, however,
Congress recognized that the limitation on court challenges should not be
absolute.
17
20
It is the cost-recovery suit that opens the door for alleged responsible parties to
contest their liability as well as to challenge the EPA's response action as being
unnecessarily expensive or otherwise not in accordance with applicable law.
See 42 U.S.C. Sec. 9607(a)(4)(A) (permits challenges against costs inconsistent
with National Contingency Plan); id. Sec. 9607(b) (sets out defenses to
liability); id. Sec. 9613(j)(2) (arbitrary and capricious standard of review
applies to response actions). The language in subsection 9613(h)(1), the
corresponding legislative history, and relevant caselaw establish that once the
EPA brings an enforcement action under section 9607, the agency is subject to
challenges to its response action.
21
Courts have held that liability and cost-effectiveness suits filed by potentially
responsible parties to challenge a selected response plan were premature when
the EPA had not yet sought enforcement through a cost-recovery action. Those
opinions describe the suit for reimbursement of response costs as the
opportunity for challenging the EPA's remedial or removal decisions. See
Reardon v. United States, 947 F.2d 1509, 1512 (1st Cir.1991) (en banc)
(section 9613(h) precludes "review of 'innocent landowner' and 'overbroad lien'
claims prior to the commencement of an enforcement or recovery action");
Voluntary Purchasing Groups, Inc. v. Reilly, 889 F.2d 1380, 1390 n. 21 (5th
Cir.1989) (" '[O]nce the cost-recovery action is brought, the alleged responsible
party can assert all its statutory and nonstatutory defenses and can obtain a
complete declaration of its rights and liabilities.' " (quoting B.R. MacKay &
Sons, Inc. v. United States, 633 F.Supp. 1290, 1297 (D.Utah 1986))); Barmet
Aluminum Corp. v. Reilly, 927 F.2d 289, 295 (6th Cir.1991) (CERCLA
scheme "merely serves to effectuate a delay in a plaintiff's ability to have a full
hearing on the issue of liability and does not substantively affect the adequacy
of such a hearing"); Dickerson v. EPA, 834 F.2d 974, 978 (11th Cir.1987)
(property owner may contest cost effectiveness of the EPA remedy as soon as
cost-recovery suit is brought).
22
23
"[w]hen
the essence of a lawsuit involves contesting the liability of the plaintiff for
cleanup costs, the courts should apply the other provisions of section [9613(h) ],
which require such plaintiff to wait until the Government has filed a suit under
[sections 9606 or 9607] to seek review of the liability issue."
24
25
26
The question thus becomes whether the exception under subsection 9613(h)(1)
would lift the bar to challenges against response actions even where the EPA
brings a cost-recovery suit before cleanup is complete, as is permitted under
subsection 9613(g)(2). Because an interim decision on costs may affect the
completion of the project, such suits introduce an additional factor into the
jurisdictional question.
27
28
Once it has been established that subsection 9613(h)(1) applies and that review
28
Once it has been established that subsection 9613(h)(1) applies and that review
under that exception is available, a court must then resolve the question of what
types of challenges may be considered and what remedies are available.
Although the statute makes no distinction between cost-recovery suits brought
after completion of a project and those brought while work is continuing, the
remedies may differ because of the possibility of affecting future work at a site.
29
42 U.S.C. Sec. 9607(b) sets out defenses to liability vel non as contrasted with
disputes over the amount of the claim due or the legality of the remedy
selected. In United States v. Hardage, 982 F.2d 1436, 1446 (10th Cir.1992), the
Court held that a responsible party may contest EPA expenditures as well as its
liability in a response action. In that case, the Court of Appeals, citing section
9607(a)(4)(A), concluded that a person found to be a responsible party may
nevertheless contest payment of expenses resulting from a remedial action that
is inconsistent with the National Contingency Plan. Id. at 1443, 1447.
30
31
32
33
"[T]he
court shall award (A) only the response costs or damages that are not
inconsistent with the national contingency plan, and (B) such other relief as is
consistent with the National Contingency Plan."
34
42 U.S.C. Sec. 9613(j)(3). The language of that section makes it clear that the
available remedies are not limited to a mere reduction of the amount
recoverable for expenditures, but may also include any relief consistent with
the National Contingency Plan.
B. Citizens' Suit Exception Under Subsection 9613(h)(4)
35
36
37
38
In Schalk v. Reilly, 900 F.2d 1091, 1095 (7th Cir.1990) and Alabama v. EPA,
871 F.2d 1548, 1557 (11th Cir.1989), the Courts of Appeals decided that even
if a remedy or a discrete phase of a remedy has been selected by the EPA, no
citizens' suit challenge may be recognized before the remedy has been
completed. The opinions in those two cases noted that the language of the
citizens' suit exception of section 9613(h)(4) applies only to those "removal or
remedial action[s] taken under section 9604 [response actions by EPA] ... or
secured under section 9606 [abatement order]...." Schalk, 900 F.2d at 1095
(emphasis in original); see Alabama v. EPA, 871 F.2d at 1557. Noting the
statute's use of the past tense, the Courts of Appeals stated that absent clear
legislative intent to the contrary, the statutory language establishes that the
remedial action must already have been implemented and completed before
challenges can be made against it. Id.
39
In the Schalk case, incineration had been selected as the form of remedy, but
had not yet been put into operation. In those circumstances, the Court
concluded that it lacked jurisdiction to consider a citizens' suit in which it was
alleged that the EPA had violated the National Contingency Plan by failing to
prepare an environmental impact statement. Schalk, 900 F.2d at 1095; see also
Alabama v. EPA, 871 F.2d at 1556 (citizens' suit alleged EPA failed to comply
with notice and comment provision); Arkansas Peace Ctr. v. Arkansas Dep't of
Pollution Control & Ecology, 999 F.2d 1212, 1216-19 (8th Cir.1993) (citizens'
suit alleged incineration remedy failed to meet EPA regulations), cert. denied, -- U.S. ----, 114 S.Ct. 1397, 128 L.Ed.2d 70 (1994).
40
41
Although these interpretations of the timing of the review of citizens' suits have
superficial pertinency, none of the Courts of Appeals were confronted with
bona fide assertions of irreparable environmental damage resulting from
violations of CERCLA's policies.2 In circumstances where irreparable
environmental damage will result from a planned response action, forcing
parties to wait until the project has been fully completed before hearing
objections to the action would violate the purposes of CERCLA. This concern
was articulated in congressional deliberations and elicited conflicting
statements by members of the conference committee that was convened to
resolve differences between the Senate and House versions of SARA.
Whether a challenge raised in a citizens' suit may be reviewed under subsection
9613(h)(4) depends upon whether the challenge is directed at remedial action
that is "taken" or "secured" in violation of the statute. 42 U.S.C. Sec. 9613(h)
(4). In discussing the proper timing of a citizens' suit, some courts have quoted
the comments of Senator Thurmond, who stated:
"42'Taken or secured,' [in section 9613(h)(4) ] means that all of the activities set forth
in the record of decision which includes the challenged action have been
completed.... The section is designed to preclude lawsuits by any person concerning
particular segments of the response action ... until those segments of the response
have been constructed and given the chance to operate and demonstrate their
effectiveness in meeting the requirements of the act. Completion of all of the work
set out in a particular record of decision marks the first opportunity at which review
of that portion of the response action can occur."
43
132 Cong.Rec. 28,441 (1986). For comments along similar lines in the House
debate, see 132 Cong.Rec. 29,736 (1986) (statements of Rep. Glickman).
44
46
47
Id. at 28,409. For similar statements made in the House debates, see id. at
29,754 (statement of Rep. Roe).
In his comments, Senator Mitchell noted the difference between responsible
parties whose interests are purely financial and citizens or responsible parties
whose concerns are with public health or environmental damage. The Senator
said:
48
"Clearly
the risk to the public health is more of an irreparable injury than the
momentary loss of money.... The public, however, has no recourse if their [sic]
health has been impaired. For this reason, courts should carefully weigh the equities
and give great weight to the public health risks involved."
49
Id. at 28,429.
50
51 final cleanup decision, or plan, constitutes the taking of action at a site, and the
"A
legislative language makes it clear that citizens' suits under [section 9659] will lie
alleging violations of law and irreparable injury to health as soon as--and these
words are a direct quote [from subsection 9613(h)(4) ]--'action is taken.' "
52
Id. at 29,741.
53
54
damages and legitimate citizens' suits complaining of irreparable injury that can be
only addressed only [sic] if a claim is heard during or prior to response action."
56
132 Cong.Rec. 28,409 (1986); see also Cabot Corp. v. EPA, 677 F.Supp. 823,
829 (E.D.Pa.1988) (recognizing differences between compensatory and
irreparable injury in selecting proper remedies under subsections 9613(h)(1),
(h)(4)).
57
The problem may be illustrated by an extreme scenario that has the EPA
deciding to take leaking drums containing a highly toxic substance from a
dump site and to empty them into a nearby lake, thus causing permanent
damage to public health and the environment. If citizens cannot prevent such
dumping from taking place, no effective remedy exists.
58
59
Several district courts have grappled with the timing of review under the
citizens' suit exception and have reached inconsistent results in cases where
irreparable harm to public health or the environment was alleged. Cabot Corp.,
677 F.Supp. at 829, for example, concluded that "[h]ealth and environmental
hazards must be addressed as promptly as possible rather than awaiting the
completion of an inadequately protective response action." In Neighborhood
Toxic, 716 F.Supp. at 834, the court commented that even where there are
allegations that a remedial plan is unsafe to public health, review of a citizens'
suit is only allowed after the first phase of the cleanup is complete. In that case,
however, plaintiffs did not assert that they could prove environmental harm, but
merely demanded that the EPA perform a public health study to support its
choice of remedy. Id. at 829.
60
In the Courts of Appeals cases previously cited, where the citizens' suits were
held to be premature, allegations of genuine irreparable damage were not
discussed and presumably were not present. The issue presented here appears to
be a case of first impression in the appellate courts. With this general
background on the law, we review the parties' contentions.
II.
61
Gamma-Tech asserts that when the EPA filed the suit for response costs, the
district court obtained jurisdiction, including its inherent injunctive powers,
over all challenges to the government's selection of a remedy for the polluted
site. Although it relies on subsection 9613(h)(1), Gamma-Tech asserts that the
citizens' suit exception in subsection 9613(h)(4) supports justiciability of
contentions that the EPA's action violates CERCLA by being inconsistent with
the National Contingency Plan.3 Gamma-Tech also maintains that the Due
Process Clause requires a party to be given an opportunity to prevent
irreparable harm before it occurs.
62
The EPA argues that its cost-recovery action seeks only reimbursement for the
actual expenditures incurred as of the time of the suit, and that subsection
9613(h)(1) does not permit challenges to portions of a response action not yet
completed and for which costs have not yet been incurred. Moreover, the EPA
contends that courts do not have the power to grant equitable relief in a section
9607 cost-recovery action.
63
The EPA does concede that Gamma-Tech may contest its liability for actual
costs claimed by the government that are inconsistent with the National
Contingency Plan. However, relying on this Court's opinion in Boarhead Corp.
v. Erickson, 923 F.2d 1011 (3d Cir.1991), the EPA maintains that because the
remedy has not yet been fully implemented, the citizens' suit provision does not
permit judicial review despite allegations of irreparable harm.
64
65
Boarhead is clearly distinguishable and does not control the matter before us for
two crucial reasons. First, Boarhead was brought by a property owner and was
not, as here, a suit brought by the government where the exception in
subsection 9613(h)(1) comes into play. Second, the case before us is based on
allegations that the EPA has violated and will continue to violate CERCLA
itself, not another unrelated statute--a point that the Court noted and did not
decide. See id. at 1019 n. 13. Consequently, Boarhead and the other previously
cited cases where the property owners brought suit prematurely do not govern a
court's power to grant injunctive relief in the circumstances where there are
allegations that the EPA's action will cause irreparable harm inconsistent with
the National Contingency Plan.
66
In assessing the scope of review and the availability of remedies in this costrecovery action, it is important to clarify just what it is that the EPA seeks in
this suit. The complaint alleges that, as of September 28, 1990 (approximately
five months before the complaint was filed), disbursements by the government
amounted to at least $1,816,151. The EPA seeks this sum and, in addition, all
response costs incurred "as of the date of judgment."
67
68
That being so, Gamma-Tech is free to challenge those phases that have been
completed and also that portion of the remedial plan that has not yet been fully
completed as of the date of judgment, but for which some expenses have been
incurred. The timeliness requirement of section 9613(h) has been met as to
everything claimed as of the date of judgment. We thus have no need to
consider here whether under different circumstances, the commencement of a
cost-recovery action under section 9607 would allow challenges to all aspects
of the remedial plan even if no expenses have been incurred for a specific phase
to come into effect in the future.
69
The next issue is the scope of the relief that Gamma-Tech may obtain.
Compliance with the National Contingency Plan criteria previously mentioned
(e.g., protection of public health and the environment, including the overall
feasibility of the plan) is a substantial factor in determining what costs the EPA
may recover from Gamma-Tech. As noted earlier, section 9613(j)(3) outlines
the scope of the remedy that the district court may grant. If the response the
EPA has selected is determined to be arbitrary and capricious, or "otherwise not
in accordance with law," the court is only permitted to award the response costs
that are consistent with the National Contingency Plan. The court may also
grant "such other relief as is consistent with the National Contingency Plan." 42
U.S.C. Sec. 9613(j)(3) (emphasis added).
70
Notably, section 9613(j)(3) does not exclude injunctive relief as a remedy. The
broad language "such other relief" implies the contrary. See Weinberger v.
Romero-Barcelo, 456 U.S. 305, 320, 102 S.Ct. 1798, 1807, 72 L.Ed.2d 91
(1982) ("[A] major departure from the long tradition of equity practice should
not be lightly implied."); Califano v. Yamasaki, 442 U.S. 682, 705, 99 S.Ct.
2545, 2559, 61 L.Ed.2d 176 (1979) ("Absent the clearest command to the
contrary from Congress, federal courts retain their equitable power to issue
injunctions in suits over which they have jurisdiction."); Mitchell v. Robert
DeMario Jewelry, Inc., 361 U.S. 288, 291-92, 80 S.Ct. 332, 335, 4 L.Ed.2d 323
(1960) ("When Congress entrusts to an equity court the enforcement of
prohibitions contained in a regulatory enactment, it must be taken to have acted
cognizant of the historic power of equity to provide complete relief in light of
the statutory purposes.").
71
Therefore, if the response selected by the EPA is inconsistent with the National
Contingency Plan--for example, the remedial plan is harmful to public health-nothing in the statute prohibits a court from utilizing its inherent power to direct
the agency to cease the harmful practice and, in addition, to deny claims for
expenses incurred to that point in carrying out that phase of the remedy.
72
Permitting the EPA to continue with actions that have been found to be
inconsistent with the National Contingency Plan would be contrary to the spirit
and intent of CERCLA. The Act is designed to facilitate the cleanup of
hazardous waste sites, but that process must be conducted by methods that meet
specified criteria. Thus, in some circumstances, granting injunctive relief would
be consistent with the National Contingency Plan pursuant to the provisions of
section 9613(j)(3) and, in fact, injunctions may be required to insure
compliance with the Plan. We therefore reject the EPA's contention that
injunctions, per se, are barred in a suit for response provisions costs.
73
Cadillac Fairview/California, Inc. v. Dow Chem. Co., 840 F.2d 691 (9th
Cir.1988), is not to the contrary. In that case, a private entity sought an
injunction directing other parties to commence cleanup operations. In
considering the interplay between section 9606 that allows only the government
to seek an order directing cleanup and section 9607 that arguably only calls for
reimbursement of costs, the Court held that section 9607 did not confer a
private right of action. Id. at 697. To the same effect, see New York v. Shore
Realty Corp., 759 F.2d 1032, 1049 (2d Cir.1985).
74
Those situations are quite different from the one presented here, and the Courts'
opinions in those cases did not discuss the remedies provision in section 9613(j)
(3). Moreover, the injunctive relief sought in Cadillac Fairview was not
directed against the federal government in its capacity as a regulator, but merely
as the owner of a hazardous waste site.
75
Both parties have cited to the citizens' suit provision in subsection 9613(h)(4)
as support for their respective positions. Even though it is a potentially
responsible party, Gamma-Tech could qualify as a plaintiff in a citizens' suit
alleging irreparable harm to the environment. Hence, Gamma-Tech argues that
as a defendant in the EPA's cost-recovery suit, it should be permitted to allege
matters that would normally be considered in a separate citizens' suit.
76
The EPA, on the other hand, takes the position that a citizens' suit will not lie in
the circumstances presented here because the remedial action at the pollution
site has not yet been completed. The EPA relies on such cases as Schalk,
Alabama v. EPA, and Arkansas Peace Ctr. As we noted earlier, however, we
find the holdings in those cases to be inapposite to the facts presented here,
where bona fide assertions of irreparable environmental damage were made.
77
78
79
It is clear that if a court finds that an aspect of the response action already
completed was contrary to the National Contingency Plan, the judgment could
not include the expenses attributable to that particular activity. It would be
highly unlikely that the EPA would continue to spend money on that same
remedial activity in the future if it knew that the recovery of costs for that work
from the responsible party would not be permitted in later suits. Nor is it likely
that the EPA would continue its course of action in the face of a court decree
that its remedial processes have failed to comply with the law. Thus, future
work is affected to the extent that a denial of reimbursement for a particular
item is, for all intents and purposes, a finding that a particular aspect of a
project violates applicable law.
80
Interim judicial review is often advantageous to the EPA. If a court upholds the
legality of a response action and the costs thus far incurred, the likelihood of a
settlement with a responsible party at the conclusion of the cleanup is
substantially increased. On the other hand, if a court finds defects in the EPA's
response action, they may be corrected before further unwarranted drains on
limited Superfund resources occur--a result the EPA would no doubt find
desirable. A knee-jerk opposition to a reasonable interpretation of the
jurisdictional limitations on judicial review in CERCLA is therefore not
consistent with the aims of the Act.
81
Based on our review of the statute, its legislative history, and the procedural
posture of this suit, we hold that where a bona fide allegation of irreparable
injury to public health or the environment is made, injunctive relief is available
in a cost-recovery action under subsection 9613(h)(1).
82
Our holding does not mean that frivolous litigation will be permitted to delay
critical cleanup efforts. Courts must be wary of dilatory tactics by potentially
responsible parties who might raise specious allegations of irreparable harm to
public health or the environment merely to obtain immediate review. The mere
possibility of such abuse, however, does not justify an abdication by the courts
of their responsibility to adjudicate legitimate claims of irreparable harm.
83
Our holding on jurisdiction does not imply that relief must be granted here. We
note first that the parties' versions of the facts are in dispute, and perhaps more
important, Congress' intention that cleanup not be delayed or diverted by
dilatory litigation must be honored. To overcome that admonition, GammaTech, as the alleged responsible party, has the burden to establish that the
EPA's choice of remedy was indeed arbitrary and capricious or otherwise
contrary to law.
84
In cases like the one at hand, a reviewing court should give deference to the
scientific expertise of the agency. This is not a circumstance where a court is
called upon to simply acquiesce in a determination of law; rather, this is a
situation where an administrative agency does possess expert knowledge in a
factual and scientific field. See Baltimore Gas & Elec. Co. v. Natural Resources
Defense Council, Inc., 462 U.S. 87, 103, 103 S.Ct. 2246, 2255, 76 L.Ed.2d 437
(1983) ("When examining this kind of scientific determination, as opposed to
simple findings of fact, a reviewing court must generally be at its most
deferential."); United States v. Akzo Coatings of Am., Inc., 949 F.2d 1409,
1424 (6th Cir.1991); Hi-Craft Clothing Co. v. NLRB, 660 F.2d 910, 915 (3d
Cir.1981).
85
86
III.
87
Gamma-Tech has also challenged the district court's order denying a motion to
file certain pleadings after the dates specified in the pre-trial order had passed.
As we said in Kershner v. Mazurkiewicz, 670 F.2d 440, 449 (3d Cir.1982), our
scope of review under 28 U.S.C. Sec. 1292(a)(1) is limited to issues that are
"inextricably bound" to the grant or denial of a preliminary injunction. A
court's order enforcing a pre-trial time table does not fall within that category.
Therefore, we will not review the court's order at this time.
88
Accordingly, the order of the district court will be reversed insofar as the court
held that it had no jurisdiction to review the contentions of irreparable harm
and the request for an injunction. The case will be remanded for further
proceedings consistent with this opinion.
NYGAARD, Circuit Judge, concurring:
89
I agree with the majority that the district court had and that we have jurisdiction
under 42 U.S.C. Sec. 9613(h)(1). I reach this conclusion because I think it
would be anomalous to say, for example, that because the remedy it chose was
arbitrary and capricious, the EPA could not recover in a cost recovery action
for wells already drilled, but the propriety of its decision regarding all the
future wells in the same response phase would not yet be ripe for review. It
seems to me that when the EPA opens the door by bringing a cost recovery suit
while a response action remains in progress, common sense and judicial
economy require us to review both the completed work and those similar
portions of the response phase that are either planned or partially completed.1
90
I part company with the majority, however, on the issue of whether the citizens'
suit provision codified at Sec. 9613(h)(4) provides an additional and
independent basis for federal jurisdiction. The majority suggests that whenever
irreparable harm to the environment is alleged, jurisdiction for judicial review
is established by that subsection. To the extent that Sec. 9613(h)(1)
independently provides a source of jurisdiction, the question of whether
jurisdiction is also present under Sec. 9613(h)(4) is unnecessary to the result
the majority reaches and its observations regarding that subsection are dicta.
91
I would not reach the issue of jurisdiction under Sec. 9613(h)(4) because I
believe Gamma-Tech clearly waived it at oral argument in the following
exchange:
98
In Hallstrom v. Tillamook County, 493 U.S. 20, 110 S.Ct. 304, 107 L.Ed.2d
237 (1989), certain property owners sued their county government, alleging that
the county's sanitary landfill violated the Resource Conservation and Recovery
Act (RCRA). They failed, however, to give the notice required by the statute.
The district court held that by notifying the state and federal agencies one day
after the defendant moved for summary judgment, the plaintiff cured any
defect in notice. The Supreme Court, however, after noting that a variety of
environmental statutes contain similar provisions, disagreed:
[T]he
99 notice and 60-day delay requirements are mandatory conditions precedent to
commencing suit under the RCRA citizen suit provision; a district court may not
disregard these requirements at its discretion.
100 Id. at 31, 110 S.Ct. at 311.
101 Likewise, in Greene v. Reilly, 956 F.2d 593 (6th Cir.1992), the plaintiff sued
under the Clean Water Act. Although he did notify the EPA that he considered
it in violation of the Act, the plaintiff did not formally threaten to sue. The
Court of Appeals for the Sixth Circuit, although acknowledging that the EPA
had some notice of the violation and was aware of the situation generally,
nevertheless held that noncompliance with the formal notice requirement
barred the suit. Id. at 594.
102 Accordingly, I am convinced that federal courts do not have jurisdiction to the
extent this case is argued as a citizens' suit.
103 Moreover, even if the citizens' suit were not barred by waiver and procedural
default, I do not believe that Sec. 9613(h)(4) provides jurisdiction until the
remedial work complained of is actually completed. Every United States Court
of Appeals that has construed this section has so held. These holdings are based
on a textual analysis of the statute, which refers in the past tense to removal or
remedial action taken or secured, and on CERCLA's legislative history. See
Arkansas Peace Ctr. v. Arkansas Dep't of Pollution Control & Ecology, 999
F.2d 1212, 1216-17 (8th Cir.1993) (discussing cases), cert. denied, --- U.S. ----,
114 S.Ct. 1397, 128 L.Ed.2d 70 (1994); North Shore Gas Co. v. Environmental
Protection Agency, 930 F.2d 1239, 1244-45 (7th Cir.1991); Schalk v. Reilly,
900 F.2d 1091, 1095 (7th Cir.), cert. denied, 498 U.S. 981, 111 S.Ct. 509, 112
L.Ed.2d 521 (1990); State of Alabama v. United States Envtl. Protection
Agency, 871 F.2d 1548, 1557-58 (11th Cir.), cert. denied, 493 U.S. 991, 110
S.Ct. 538, 107 L.Ed.2d 535 (1989).2
104 Beyond the plain language of the statute, a section such as 9613(h) that
104 Beyond the plain language of the statute, a section such as 9613(h) that
withdraws federal jurisdiction from suits brought against the United States is
essentially a reassertion of sovereign immunity, and it is a basic principle of law
that "[w]aivers of immunity must be construed strictly in favor of the sovereign,
and not enlarged beyond what the language requires." Ruckelshaus v. Sierra
Club, 463 U.S. 680, 685, 103 S.Ct. 3274, 3278, 77 L.Ed.2d 938 (1983)
(citations and internal quotation marks omitted); see Voluntary Purchasing
Groups, Inc. v. Reilly, 889 F.2d 1380, 1385 (5th Cir.1989) (applying Sierra
Club to section 9613). Thus, even if the plain language of the statute were
equivocal on the timing of review, it would still not support a waiver of
sovereign immunity, and we should not imply one unless the legislative history
in favor of such a construction is compelling. Cf. Smith v. Fidelity Consumer
Discount Co., 898 F.2d 907, 912 (3d Cir.1990).
105 The legislative history of CERCLA, however, hardly compels the conclusion
that Congress intended the broad judicial review that the majority holds is
available. Instead, as the majority purports to recognize, "Congress was anxious
to safeguard EPA removal efforts from delay resulting from litigation brought
by potentially responsible parties." Majority at 141. That desire was equally
present for the circumstances here.
106 In considering and reporting out H.R. 2817, which was later incorporated into
H.R. 2005 and passed, the Committee on Energy and Commerce said of what is
now Sec. 9613(h):
107 section is intended to codify the current position of the Administrator and the
The
Department of Justice with respect to preenforcement review: there is no right of
judicial review of the Administrator's selection and implementation of response
actions until after the response action [sic] have been completed to their completion.
108 H.R.Rep. No. 253(I), 99th Cong., 1st Sess. 81 (1985), reprinted in 1986
U.S.C.C.A.N. 2835, 2863. Indeed, a thorough review of the legislative history
reveals no evidence whatsoever that Congress intended anything other than a
judicial review of completed response actions under the citizens' suit provision.
See H.R.Rep. No. 253(III), 99th Cong., 1st Sess. 22-23 (1985), reprinted in
1986 U.S.C.C.A.N. 3038, 3045-46 (House Committee on the Judiciary,
emphasizing that judicial review must be postponed until after the response
action is taken and completed); H.R.Rep. No. 253(V), 99th Cong., 1st Sess. 2526 (1985), reprinted in 1986 U.S.C.C.A.N. 3124, 3148-49 (House Committee
on Public Works and Transportation, referring to actions taken in past tense).
109 In fact, the Conference Report accompanying the Superfund Amendments of
Boarhead Corp. v. Erickson, 923 F.2d 1011 (3d Cir.1991), discussed allegations
that the response action would cause irreparable harm to historic artifacts and
did not involve a situation where EPA action caused injury to the environment
in violation of CERCLA. See id. at 1023
Or sixty days later if compliance with the redundant sixty-day notice provision
of section 9659(d)-(e) would be required
See also City of Eureka v. United States, 770 F.Supp. 500, 502 (E.D.Mo.1991);
See, e.g., Resolution Trust Corp. v. Gallagher, 10 F.3d 416, 421 (7th Cir.1993);
RJR Nabisco, Inc. v. United States, 955 F.2d 1457, 1462 (11th Cir.1992);
Demby v. Schweiker, 671 F.2d 507, 510 (D.C.Cir.1981) (opinion announcing
judgment of court)
Moreover, as the Dowdle court pointed out, id., irreparable harm, whether
explicitly asserted or not, was present on the facts of Arkansas Peace Center,
Schalk and Alabama, cited by the majority as having only "superficial
pertinency." Majority at 144-45. Yet, each of these courts held that judicial
review was not available under section 9613(h)(4). Thus, for the majority's
view of section 9613(h)(4) to be correct, these decisions by three other courts of
appeals would have to be repudiated outright