MotoALT/CALT 2005 Test Procedure
MotoALT/CALT 2005 Test Procedure
motoalt 2005
REVISION DATE:
ISSUE: MEMO:
O
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
1 of 40
ORIGINATOR:
DATE:
Kenneth McKillip
Dec 04
_________________________________________________________________________________________________________________________________________________________
CONTENTS
1. Scope
2. Product Submission
3. Responsibility
3.1 ALT Reliability Manager
3.2 ALT Engineer/Technician
3.3 Responsible Motorola Engineer/OEM Engineer
4. Reference Documents
5. Definitions and Acronyms
6. Marking the Product
7. Testing
7.1 Allocation of Units to Modules
7.2 Overview of Testing
7.2.1 Parametric, Cameras, SPL, Blue Tooth and Desense Test
7.2.2 Power On Test
7.2.3 Module Description
7.2.4 Tests Between Stresses to Capture Failures
7.3 Functional Test
7.4 Signaling Test
7.5 Parametric, SPL, Blue Tooth and Desense Test Specifications
7.6 Camera Testing
8. Environmental and Mechanical Stresses and Finish Testing
8.1 Module I (Electrical/Physical Reliability Test) -- Thermal Environmental Sequence
8.1.1 Thermal Shock
8.1.2 First Drop Sequence
8.1.3 First Parallel Shaker Table Vibration and ESD Sequence
8.1.3.1 First Electrostatic Discharge (ESD)
8.1.3.2 First Shaker Table Vibration
8.1.4 Dust
8.1.5 Temperature Cycling
8.1.6 Temperature Humidity (+65OC/90%RH, 88 88hrs)
8.1.7 Second Drop Sequence
8.1.8 Second Parallel Shaker Table Vibration and ESD Sequence
8.1.8.1 Second Electrostatic Discharge (ESD)
8.1.8.2 Second Shaker Table Vibration
8.1.9 Final Parametric & Signaling
8.1.10 Initial & Final Desense Test Procedure
8.1.11 Initial & Final SPL Test Procedure
8.1.12 Initial & Final Blue Tooth Test Procedure
8.1.13 Initial & Final Embedded Camera Test Procedure
8.1.14 Initial & Final Embedded GPS Test Procedure
8.2 Module II (Mechanical Durability/Life Cycle Module) Mechanical Sequence
8.2.1 Thermal Shock
8.2.2 Temperature Humidity +65C/90% RH
8.2.3 Keypad Actuation
8.2.4 Chemical Exposure and Dry
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
2 of 40
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
3 of 40
1. Scope
1.1 This specification provides the proper procedures for successfully conducting both the MotoALT Motorola
Accelerated Life Test and MotoCALT "Motorola Continuous Accelerated Life Test" process audit on OEM
portable wireless products. Refer to Appendix A, B, C, and D for MotoALT flows and Appendix E, F, G, and
H for MotoCALT flows. Reference will be made to other supporting 12M specifications to further define
specific steps in this process.
1.2 The purpose of the MotoALT is to provide an assessment of product quality, reliability, and design
robustness prior to product shipment to customers. The purpose of the MotoCALT is to demonstrate that
the current product being shipped has maintained the product quality and reliability demonstrated by the
MotoALT goal for ship authorization. Both are accomplished by exposing the product to various
environmental and mechanical stresses and measuring the effect on product functionality and finish. These
environments have been designed to age and fatigue the product within acceptable limits based on material
specifications, historical performance, and known customer expectations. The results are then used to
estimate product failure rates.
1.3 It is not the purpose of the MotoALT/CALT to certify that the product meets all required specifications or to
verify software feature performance. MotoALT/CALT testing is conducted to detect customer perceivable
failures as the result of exposure to accelerated field stresses. Full compliance testing is the responsibility of
Development Engineering.
1.4 Engineering judgment has been used to align the process with what the customer would most likely
consider a product failure or flaw. Either soft and hard malfunction or degradation of the product may be
considered failures. The focus of the test structure is failure precipitation; not on definitively isolating what
stresses caused what failures.
2
Product Submission
Products may be submitted by Motorola Development Engineering, OEM Engineering, or at the request of
Reliability Engineering. Typical submission quantities are shown in the table below. The sample should be
homogeneous in nature and be fully flexed as a customer would receive the product. Products must include
ancillary components such as antennas, batteries, back covers, and SIM cards. The latest operating software and
RSS is to be supplied by appropriate Development Engineering. For Pilot and Production Vintage MotoALTs, the
product should be delivered in the condition a customer would receive it in. Hence, product labels should be
included and installed, even though these additions are normally made in distribution, and the product might
never have been there. Omissions to the above submission items may be waived by approval from the Reliability
Engineering Manager. Each submission will be assigned a tracking number by the ALT Reliability Manager.
Tracking numbers are generated sequentially as ALT submissions are made.
TEST
SUBMISSION QUANTITY
MotoALT
56
MotoCALT
22
Responsibility
3.1 ALT Reliability Manager
3.1.1
3.1.2
The manager shall assign each MotoALT/CALT to a specific Engineer and or Technician to perform
the necessary testing listed in this document in the order as specified.
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
3.1.3
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
4 of 40
The manager shall review the final results and either approve or disapprove the results of the
MotoALT/CALT. When approval is merited, conditionally or unconditionally, the ALT Reliability
Manager will issue an Approval Notice or demonstrate approval by other equivalent means as
required. To disapprove the results the ALT Reliability Manager will communicate directly with the
responsible Engineer in a manner that is mutually satisfactory
The Engineer/Technician shall perform the required testing as given in this document.
3.2.2
The Engineer/Technician shall fill in the electronic ALT Engineering Report form as given in the
Global Database at the Reliability website. Information and results shall be kept up to date as the
data is taken.
3.2.3
The Engineer/Technician shall keep the ALT Manager informed of any issues as they arise.
3.3.1
The engineer responsible for the MotoALT submission shall insure that all deliverables are met as
given in this document.
3.3.2
The Responsible Engineer shall review, perform failure analysis, determine corrective action, and act
upon all reported failures and defects. This shall be documented by the engineer filling in the failure
analysis and corrective action fields in the ALT Engineering Report form.
3.3.3
The Responsible Engineer shall be responsible for the implementation of all corrective actions and
close out of the MotoALT.
Reference Documents
ED00102
12M09158A58
12M09170A79
12M09174A85
12M09175A65
12M09175A68
12M09175A70
12M09176A22
12M09176A66
12M09176A72
12M09181A10
12M09182A40
12M09193A75
12M09193A59
ED00230
ED00144
12M09193A72
00R09188T25
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
MEMO:
ISSUE:
PAGE:
5 of 40
30-DEC-04
PRELIMINARY
Testing
7.1 Allocation of Units to Modules
The units are divided up between the modules as shown in the table below.
Module
I. Electrical & Physical Module
II. Mechanical Durability
III. Finish Module
IV. DTF
MotoALT
Units #1 - #24
Units #33 - #48
Units #49 - #56
Units #25 - #32
MotoCALT
Units #1 - #10
Units #11 - #16
Units #17 and #18
Units #19 - #22
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
6 of 40
"Power On" test is done on all units to be put through Module I before being placed into the
Temperature Shock.
7.2.2
Power On Test
The Power On Test consists of applying power to each unit by the easiest method possible and
verifying some level of functionality of the unit. In the case of a cellular phone, application of external
power should cause the phone to turn on, the vibrator or speaker to activate, the display and keypad
backlighting to light up, and all pixels of the display to turn on.
7.2.3
Module Description
All three modules go through the thermal shock environment. After thermal shock, the three modules
separate. Module I (Electrical/Physical Reliability Test) is the thermal environmental sequence and
subjects units to approximately seven (7) days of temperature, humidity, vibration, and drop
environments. Module II (Mechanical Durability/Life Cycle Module) is the mechanical sequence and
subjects units to temperature, humidity, chemical, fatigue, and mechanical stress environments. The
mechanical stresses used are intended to simulate actual customer usage. Module III (Finish Module)
is used to evaluate finish/paint performance. Module IV (DTF) is used as a check to ensure that the
prototype certification results are still valid and also to help judge what is observed during the Module
I drop tests (especially Drop1).
7.2.4
Actuating buttons and switches to provide the correct visual and audible feedback with consistent
motion and tactile feel
Displays and back-lighting are functional and uniform
Mechanical features such as flips and antennas maintain electromechanical function and freedom
of movement
Transducers should be checked for adequate levels and distortion
Interface connections for charging, headsets, boom mics should be verified to be functioning
properly, if supplied.
Internal circuits such as internal chargers perform properly and provide proper visual and audible
responses
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
7 of 40
Proper operation of visual indicators, audio quality, and accurate data transmission are to be verified.
Testing should be performed under radiated conditions if possible. A complete description of the attributes
to be tested on cellular phones is given in 12M09193A72.
7.5 Parametric, SPL, Blue Tooth and Desense Test Specifications
Parametric, SPL, Blue Tooth and desense (GSM) testing is conducted to insure that the product has
maintained specified performance with respect to major electrical parameters. Parametric, SPL, Blue Tooth
and desense (GSM) testing at the end of each MotoALT is to be performed at the specification limits set out
in the controlling specifications for the product or technology. Appendix R lists the minimal parametric test
set for AMPs, GSM, CDMA, TDMA and Appendix S lists desense levels that are to be measured as a
minimum for cell phones over the indicated ranges of variables. These parameters , SPL desense (GSM)
and their ranges are minimal and are not intended to limit parametric, SPL, Blue Tooth and desense (GSM)
testing but to insure that all PCS sites perform a set of tests that can be used to correlate data between the
sites. Additional testing may be performed by each test site.
7.6 Camera Testing
Camera Testing shall be performed in accordance with 12M09193A59. This testing is conducted to insure
that product has maintained specified performance with respect to major camera performance parameters.
Specific parametric requirements shall be provided by Development Engineering for the product to be
tested.
Thermal Shock
Procedure:
T/S: Thermal Shock should be completed in a chamber consisting of two compartments, one set to 40 C. and the other set to +75 C. Product is un-powered and started in either the Cold or Hot side of
the chamber for 45 minutes. Cycling is from one temperature extreme to the other, and the transition
time between extremes shall be 8 seconds or less. This complete cycle is repeated 27 times and
should end in the hot side of the chamber. Product is to be placed in the chamber in multiple
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
8 of 40
configurations such as antenna up, antenna down, flip open, flip closed, etc. All units are to be placed
face up in the chamber. Do not allow product to lie on top of a unit with its flip open.
Requirement:
Functional testing as defined in paragraph 7.3 is to be conducted after this test. No malfunction or
physical deformation should be evident.
8.1.2
8.1.3
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
9 of 40
Certification Testing. The discharge locations are to be illustrated per product to insure test to test
consistency. The locations are subject to change if new data presents itself. If applicable, add
information to the products address book, store messages in memory and set the time/date prior to
testing. Log the sequence of testing using the table in Appendix P. Record which units were used and
what results were obtained. If it is apparent that the unit for test has lost mechanical housing, then
consult Appendix I for alternate radios to use for this test. Refer to 12M09158A58 (class 1C and class
3) for more specific detail on conducting the testing. The discharge to the unit should be in both
standby (turned on only) and transmit mode (unit placed into a call, if possible). If the phone
possesses multiple mode and band capability, then tests should be conducted with calls placed in
each mode and in each band applicable to that mode. The units for this test are chosen as described
in the table below.
Unit number
ESD unit #1
ESD unit #2
ESD unit #3
MotoALT Unit #s
9
11
15
MotoCALT Unit #s
3
n/a
n/a
Requirement:
Generally speaking, no soft failures are allowed at +/-5kV and no hard failures are allowed at 15kV.
All functional and signaling tests per sections 7.3 and 7.4 are to occur periodically during the test to
determine whether a hard or soft failure has happened and to provide the failure location,
configuration and discharge polarity. Re-power up's are allowed at 15kV but are counted as failures at
+/-5kV. LOSS of address book, messages and/or time/date information is counted as a failure at both
+/-5 or and +/-15kV. If the product(s) exhibit loss of address book, messaging or time/date information
then the product(s) shall be reconfigured and testing continued. This is to allow full testing of the
defined test locations. Conversely, if a lock up condition occurs, the product must NOT be altered or
reconfigured. Rather, it should be submitted for analysis unchanged. Finally, one should be sure to
check for full functional operation of the RF front-end circuitry by measuring the units sensitivity.
8.1.3.2 First Shaker Table Vibration
Procedure:
The shaker table (Lab model BRVD-48 or equivalent) is to be preset to 30Hz with a displacement of
0.06. The test duration is 60 minutes. All units to be subjected to this environment are placed in a
box that is rigidly attached to the shaker. Separator inserts are to be used to maintain the units
orientation during the test. Units are to be powered by fresh fully charged batteries. If more than one
battery size is to be used, mix the sizes randomly among the phones. Units are to be marked by a
strip on the intended housings plane facing down using a paint pen. That will be designated the
defined plane. Units should be vibrated for 5 minutes, then checked to see if they are still on, address
book/messages and time/date still in memory, then vibrated for the remaining 55 minutes.
Continuous monitoring for the first 5 minutes is recommended but not required. Refer to
12M09174A85 for further information. The distribution of the units by orientation is given in the table
below. There will be 9 units vibrated in the X plane and 10 apiece vibrated in the Y and Z planes (3 in
each plane for MotoCALT).
X plane
Y plane
Z plane
MotoALT Unit #s
1, 6, 12, 13, 14, 19, 20
2, 3, 7, 8, 10, 21, 22
4, 5, 16, 17, 18, 23, 24
MotoCALT Unit #s
5, 8, 9
1, 4, 7
2, 6, 10
Requirement:
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
10 of 40
Units should remain on and address book/messages still in memory, during the first 5 minutes under
test, but may turn off during the next 55 minutes. Units should be free of functional and signaling
failures per testing specified in sections 7.3 and 7.4 after the stress. Cosmetic degradation to lenses
and keypads protected by flips should be counted as failures if they occur with the flip closed. Paint
wear through should be noted as an observation.
8.1.4
Dust
The dust test is to be completed on 16 units (8 units for MotoCALT). This test is done in parallel with
the functional and signaling testing on the 2nd 16 units (other 2 for MotoCALT) in Module I. This
parallel path increases the speed with which the overall sequence of environments can be
accomplished. None of the ESD units from 8.1.3.1 should be included in this test.
Procedure:
Place the units specified below in the dust chamber for 1 hour. Randomly have half with flip open, half
with antenna extended and units evenly dispersed in orientation between, face up, face down and a
mixture of four 90-degree rotations on supporting surface. If it is apparent that the unit for test has lost
mechanical housing integrity do not select it for this test. For further information refer to Dust
12M05019A87 procedure.
MotoALT Unit #s
1, 2, 3, 4, 5, 6, 10, 13, 14, 16,
17, 18, 19, 21, 22, 24
MotoCALT Unit #s
1, 2, 4, 5, 6, 7, 9, 10
Requirement:
All moving parts should retain freedom of movement and the display shall remain unobstructed.
Functional and Signaling performance per sections 7.3 and 7.4 is completed.
8.1.5
Meaning
Indicators Active
Rx time
Standby time
Suggestions for power cycling routine are defined more formally in Appendix J. Also, the T/C profile is
attached in Appendix K. A minimum temperature ramp rate of 17 degrees C. per minute is required.
Requirement:
All functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test to insure
electrical and mechanical integrity remains.
8.1.6
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
11 of 40
Procedure:
Units #17 through #32 (#6 through #10 for MotoCALT) are to be placed on a shelf inside the chamber
without piling them up on each other. Product should be fixtured in such a way as to prevent water
accumulation on its surfaces during the test. The units are to have the proper nominal product voltage
applied and the internal auto power-cycling software active throughout the exposure. The auto powercycling sequence will be the same here as above in the Temperature Cycling environment.
Requirement:
All functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test to insure
electrical and mechanical integrity remains.
8.1.7
8.1.8
Unit number
ESD unit #1
ESD unit #2
ESD unit #3
MotoALT Unit #s
12
20
23
MotoCALT Unit #s
9
n/a
n/a
Requirement:
The requirements are the same as those previously stated for the first ESD sequence.
8.1.8.2 Shaker Table Vibration
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
12 of 40
Procedure:
The shaker table test conducted here is the same as that conducted in 8.1.3.2. The distribution of
units within the test is as specified in the Table below. The table below describes the distribution of
units between vibration axes.
X plane
Y plane
Z plane
MotoALT Unit #s
1, 6, 10, 11, 13, 14, 19
2, 3, 7, 8, 15, 21, 22
4, 5, 9, 16, 17, 18, 24
MotoCALT Unit #s
5, 8, 4
1, 3, 7
2, 6, 10
Requirement:
The requirements are the same as those previously stated for the first shaker table vibration
sequence.
8.1.9
Final Parametrics
ALT2000 units
Final Parametrics
CALT2000 units
even numbered
units
Requirement: All parametric, functional and signaling tests are to be conducted during this test and all
product specifications are to be met.
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
13 of 40
The minimal requirements for SPL testing will utilize the standard ring tone against a requirement of
95dB SPL at 5 cm utilizing A weighting. The UUT ringer port shall be aligned with the SPL meter
mic.
*if defined unit not available then use the next sequential unit as a replacement.
8.1.12 Initial & Final Blue Tooth Test Procedure:
Blue Tooth Minimum Parametric Test Requirements:
a)Tx Power Out
b) Tx Freq
c) Sensitivity
d) Audio Loop back
e) BT Link Indicator verification (fun lighting or other indicator)
f) Blue Wake and Host Wake verification
8.1.13 Initial and Final Embedded Camera Test Procedure:
All tests shall be conducted per 12M09193A59. Test limits shall be specified by Development
Engineering. Minimum parametric test requirements will require color and focus testing.
8.1.14 Initial and Final Embedded GPS Test Procedure:
Testing shall be conducted per section 7.5 with parametric requirements per Appendix R.
8.2 Module II (Mechanical Durability/Life Cycle Module) Mechanical Sequence
The purpose of this portion of the test is to demonstrate the product maintains minimum performance levels.
It does not replace product certification requirements. The following stresses are performed on the units #33
through #48 (#11 through #16 for MotoCALT).
8.2.1
Thermal Shock
Procedure:
T/S: Thermal Shock should be completed as referenced in para. 8.1.1.
Requirement:
Functional testing as defined in paragraph 7.3 is to be conducted after this test. No malfunction or
physical deformation should be evident.
8.2.2
8.2.3
Keypad Actuation
Procedure:
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
14 of 40
Units #45 through #48 (#11 through #14 for MotoCALT) are to be placed on a fixture capable of
applying a 3lb force to each key in sequence, 30,000 cycles/key over the total entire test. The units
will be powered externally during the test, but depending on the product, batteries may be required for
support. Refer to 12M09175A68 for proper set-up and procedure.
Requirement:
Full functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test. Unit
status will be monitored manually or by automated test equipment so that added information about
product information may be obtained. A unit that powers down or has significant unexpected current
variation over time will be regarded as a failure, and logged as such. There should be no outwardly
visible signs of electrical or mechanical failure.
8.2.4
8.2.5
Squeeze Test
Procedure:
Units (33-36), which have been subjected to chemical stress (para. 8.2.4), are to be subjected to
2,000 cycles. The units need not be powered during test but batteries should be in place along with a
battery door if applicable. The thinnest and lightest battery should generally be used. Refer to
12M09175A65 for proper set-up and procedure. Units should be divided by orientation as follows: unit
33, 34-flip/face up, length parallel to tampo head length (perpendicular to hammock length), unit 35,
36-flip/face down, length parallel to tampo head length (perpendicular to hammock length). For
MotoCALT units #11 through #14 should be cycled like MotoALT units #33 through #36 respectively.
Flip Hyper-extension testing should commence within 2 hours of Squeeze test completion.
Requirement:
Full functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test. There
should be no outwardly visible signs of electrical or mechanical failure. Refer to 12M09175A65 for
information about a simple 1 cycle squeeze test that can be used to determine if units have failed in
the squeeze test.
8.2.6
Flip Cycling
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
15 of 40
it would be when the phone is pressed against the users head to form an acoustic seal. The units are
to be subjected to a total of 2500 cycles per 12M09182A40.
Requirement:
Full functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test. All
mechanics are expected to maintain functionality, with no loss of detent, cracked or broken plastic.
8.2.6.2 Flip Cycling
NOTE: THESE UNITS ARE NOT SUBJECTED TO ANY ENVIRONMENTAL STRESSING
PRIOR TO STARTING THIS TEST.
Procedure:
Units #41 through #44 (#15 and #16 for MotoCALT) are to be placed on a fixture capable of
simulating normal flip cycles. These cycles simulate typical usage of a phone with a clam form factor
by opening and closing the flip as it would be in normal use. The units are to be subjected to a total of
100,000 cycles per 12M09182A40.
Requirement:
Full functional and signaling tests per sections 7.3 and 7.4 are to be conducted after this test. All
mechanics are expected to maintain functionality, with no loss of detent, cracked or broken plastic.
8.2.7
Thermal Shock
Procedure:
T/S: Thermal Shock should be completed as referenced in para. 8.1.1.
Requirement:
Functional testing as defined in paragraph 7.3 is to be conducted after this test. No malfunction or
physical deformation should be evident.
8.3.2
8.3.3
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
16 of 40
Procedure:
Units #49 through #52 (#17 for MotoCALT) are wiped with oleic acid, soaked in temperature/humidity
for 2 hours, then vibrated with an abrasive material. Detailed procedures can be found in ED00144
Requirement:
Painted surfaces should not show excessive wear, or chipping.
8.3.4
Dry Tests
The following tests are accomplished in order on units that are dry or have not been exposed to
chemicals, oils, etc.
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
17 of 40
Requirement:
Pieces should pass up to at least a hardness level of 5H.
8.3.4.5 Edge Test
Procedure:
Units #53 through #56 (#18 for MotoCALT) are used for this test. The various painted/finished
pieces are exposed to a physical bend of 90 degrees. The edge along the bend is then examined
for the paint/finish reactions to the sharp bend.
Requirement:
Pieces should not have the paint/finish peeling off.
8.4 Module IV (DTF) Proto Cert. Verification / Module 1 Drop Test Judgment
The main purpose of this portion of the test is to demonstrate that the results from the products DTF
Prototype certification testing are valid. A secondary purpose is that the results from this module can assist
in the judgment of failures from the Module I drop test. MODULE IV SHOULD NOT BE STARTED UNTIL
COMPLETION OF MODULE I DROP 1.
8.4.1
8.4.2
DTF
Procedure:
The units #25 through #39 (#19 through #22 for MotoCALT) are to be dropped by hand at room
temperature. Log the sequence of drops using the table in Appendix Q. Drop testing is to be
conducted with a battery attached and the unit turned on. The units will be dropped by hand, in
alternating planes as determined in para. 8.4.1 (for example: drop1 -> bottom drop, drop2 -> top drop,
drop3 -> bottom drop, ). One cycle is equal to dropping twice (6 times for MotoCALT), once in each
of the alternating planes. The drop by hand will attempt to cause the unit to impact on the side held
downward and parallel to the floor at the time of release. For the purposes of record keeping the side
held parallel to the floor is the plane of drop. It should be noted that the release by hand will often
impart some rotation to the product. This rotation causes the drop to be somewhat random and
incidental impact of corners and edges to occur. Drop height is to be 4ft. The drop surface will be a
tiled concrete.
A functional check (per para. 7.3) should be accomplished after each drop cycle.
A complete call processing (per para. 7.4) should be accomplished after every 5 cycles (after every 2
cycles for MotoCALT).
Requirement:
The average drop to failure should be calculated by using a Weibull distribution. The minimum
specification is 46 drops to pass (MotoALT) and 45 drops to pass (MotoCALT). The results from
Module IV should also be compared to the results from Module I drop 1 to see if similar failures were
seen.
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
18 of 40
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
19 of 40
Functional Test
(Para 7.3)
Units #1 thru #24
Random Drop
(Para. 8.1.2)
Room Temp, 5ft, 6x,
1x/plane, to vinyl tile,
Units #1 thru #12
Functional Test
(Para 7.3)
Units #1 thru #24
Dust
(Para. 8.1.4)
2sec agitation, 15min dwell, 30
min test time, 30 min settling
time
16 units per above Para.
ESD
(Para 8.1.3.1)
+/-5,15kV
3 units-9,11,15
Temperature Cycling
(Para 8.1.5)
40/75C, 88hrs
Units #1 thru #12
Temperature Humidity
(para 8.1.6)
65C/90%RH, 88hrs
Units #13 thru #24
Functional Test
(Para 7.3 & 7.4)
Units #1 thru #24
Random Drop
(Para. 8.1.7)
Room Temp, 5ft, 6x, 1x/plane,
to vinyl tile,
Units #13 thru #24
Functional Test
(Para 7.3)
Units #1 thru #24
ESD
(Para 8.1.8.1)
+/-5,15kV
3 units--12,20,23
Parametrics
advertised cold or -10C
(Para. 8.1.9)
Odd numbered units
Parametrics
advertised hot or 55C
(Para. 8.1.9)
Even numbered units
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
TITLE:
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
20 of 40
Thermal Shock
(para 8.2.1)
75C/-40, 27 cycles, 40HR
Units #33 thru #48
Temperature Humidity
(para 8.2.2)
65C/90%RH, 48hrs
Units #33 thru #48
Squeeze Test
(Para. 8.2.5)
2K cycles
Units #33 thru #36
Keypad Actuation,
(Para. 8.2.3)
30K cycles,
Units #45 thru #48
Hyperextension flip
(Para. 8.2.6.1)
2.5K cycles,
Units #37 thru #40
Flip cycling
(Para. 8.2.6.2)
100Kcycles,
Units #41 thru #44
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
21 of 40
Thermal Shock
(para 8.3.1)
75C/-40, 27 cycles, 40HR
Units #49 thru #56
Temperature Humidity
(para 8.3.2)
65C/90%RH, 88hrs
Units #49 thru #56
Box of Rocks
(para 8.3.3)
Units #49 thru #52
Flip cycling
(Para. 8.3.4.1)
5Kcycles,
Units #53 thru #56
Cross Cut
(Para. 8.3.4.2)
Units #53 thru #56
Abrasion
(Para. 8.3.4.3)
Units #53 thru #56
Pencil Hardness
(Para. 8.3.4.4)
Units #53 thru #56
Edge Test
(Para. 8.3.4.5)
Units #53 thru #56
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
22 of 40
Sample : 8ea
working units
2 drops = 1 cycle
DTF
(Para. 8.4.2)
Room Temp, 4ft, 1x, on each
assigned plane (worst case
sides) , to vinyl tile,
Units #25 thru #32
Functional Test
(Para 7.3)
after each cycle
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
23 of 40
Thermal Shock
(Para 8.1.1)
Units #1 thru #10
Functional Test
(Para 7.3)
Units #1 thru #10
Random Drop
(Para. 8.1.2)
Room Temp, 5ft, 6x,
1x/plane, to vinyl tile,
Units #1 thru #5
Functional Test
(Para 7.3)
Units #1 thru #10
Dust
(Para. 8.1.4)
2sec agitation, 15min dwell, 30
min test time, 30 min settling
time
8 units per above Para.
ESD
(Para 8.1.3.1)
+/-5,15kV
Unit #3
Temperature Cycling
(Para 8.1.5)
40/75C, 88hrs
Units #1 thru #5
Temperature Humidity
(para 8.1.6)
65C/90%RH, 88hrs
Units #6 thru #10
Functional Test
(Para 7.3 & 7.4)
Units #1 thru #10
Random Drop
(Para. 8.1.7)
Room Temp, 5ft, 6x, 1x/plane,
to vinyl tile,
Units #6 thru #10
Functional Test
(Para 7.3)
Units #1 thru #10
ESD
(Para 8.1.8.1)
+/-5,15kV
1 units-9
Parametrics
advertised cold or -10C
(Para. 8.1.9)
Odd numbered units
Parametrics
advertised hot or 55C
(Para. 8.1.9)
Even numbered units
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
24 of 40
Thermal Shock
(para 8.2.1)
75C/-40, 27 cycles, 40HR
Units #11 thru #16
Temperature Humidity
(para 8.2.2)
65C/90%RH, 48hrs
Units #11 thru #16
Keypad Actuation,
(Para. 8.2.3)
30K cycles,
Units #11 thru #14
Squeeze Test
(Para. 8.2.5)
2K cycles
Units #11 thru #14
Flip cycling
(Para. 8.2.6.2)
100Kcycles,
Units #15 and #16
Hyperextension flip
(Para. 8.2.6.1)
2.5K cycles,
Units #11 thru #14
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
25 of 40
Thermal Shock
(para 8.3.1)
75C/-40, 27 cycles, 40HR
Units #17, #18
Temperature Humidity
(para 8.3.2)
65C/90%RH, 88hrs
Units #17, #18
Box of Rocks
(para 8.3.3)
Unit #17
Flip cycling
(Para. 8.2.6.2)
40Kcycles,
Unit #18
Cross Cut
(Para. 8.3.4.2)
Unit #18
Abrasion
(Para. 8.3.4.3)
Unit #18
Pencil Hardness
(Para. 8.3.4.4)
Unit #18
Edge Test
(Para. 8.3.4.5)
Unit #18
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
26 of 40
Sample : 4ea
working units
6 drops = 1 cycle
DTF
(Para. 8.4.2)
Room Temp, 4ft, 1x, on each
side (6 total) , to vinyl tile,
Units #19 thru #22
Functional Test
(Para 7.3)
after each cycle
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
27 of 40
INITIAL DATA
TEMP. SHOCK
DROP 1
SHAKER ESD
1
Open
Yes
+X
Closed
Yes
+Y
Open
Yes
+Y
Closed
Yes
+Z
Open
Yes
+Z
6
7
8
9
R
R
R
R
Closed
Open
Closed
Open
Yes
Yes
Yes
Yes
+X
+Y
+Y
ESD
10
Closed
Yes
+Y
11
12
R
R
Open
Closed
Yes
Yes
ESD
+X
13
Open
No
+X
14
Closed
No
+X
15
Open
No
ESD
16
Closed
No
+Z
17
Open
No
+Z
18
Closed
No
+Z
19
20
R
R
Open
Closed
No
No
+X
+X
21
Open
No
+Y
22
Closed
No
+Y
23
Open
No
+Z
24
Closed
No
+Z
INITIAL DATA
TEMP. SHOCK
DROP 1
Closed
Yes
SHAKER ESD
1
+Y
Open
Yes
+Z
Closed
Yes
ESD
Open
Yes
+Y
Closed
Yes
+X
Open
No
+Z
7
8
R
R
Closed
Open
No
No
+Y
+X
Closed
No
+X
10
Open
No
+Z
MotoCALT
RADIO
1
DUST
Closed Face
Down
Open Face
Down
Open Face Up
Closed Face
Up
Closed Face
Up
Open Face Up
Closed Face
Down
Open Face
Down
Closed Face
Up
Closed Face
Down
Open Face Up
Closed Face
Up
Open Face Up
Open Face
Down
Closed Face
Down
88 HOUR
DROP 2
SHAKER ESD
2
P-mets
Cycle
No
-X
Cold
Cycle
No
-Y
Hot
Cycle
No
-Y
Cold
Cycle
No
-Z
Hot
Cycle
No
-Z
Cold
Cycle
Cycle
Cycle
Cycle
No
No
No
No
-X
-Y
-Y
-Z
Hot
Cold
Hot
Cold
Cycle
No
-X
Hot
Cycle
Cycle
No
No
-X
ESD
Cold
Hot
65 / 90
Yes
-X
Cold
65 / 90
Yes
-X
Hot
65 / 90
Yes
-Y
Cold
65 / 90
Yes
-Z
Hot
65 / 90
Yes
-Z
Cold
65 / 90
Yes
-Z
Hot
65 / 90
65 / 90
Yes
Yes
-X
ESD
Cold
Hot
Cold
65 / 90
Yes
-Y
65 / 90
Yes
-Y
Hot
65 / 90
Yes
ESD
Cold
Open Face
Down
65 / 90
Yes
-Z
Hot
DUST
88 HOUR
DROP 2
Open Face Up
Closed Face
Up
Cycle
No
SHAKER ESD
2
-Y
Cycle
No
-Z
Hot
Cycle
No
-Y
Cold
Closed Face
Down
Open Face
Down
Closed Face
Up
Open face Up
Open Face
Down
Closed Face
Down
P-mets
Cold
Cycle
No
-X
Hot
Cycle
No
-X
Cold
65 / 90
Yes
-Z
Hot
65 / 90
65 / 90
Yes
Yes
-Y
-X
Cold
Hot
65 / 90
Yes
ESD
Cold
65 / 90
Yes
-Z
Hot
2nd ESD
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
28 of 40
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
MEMO:
30-DEC-04
PRELIMINARY
ISSUE:
PAGE:
29 of 40
RH
95
+75
70
50
30
10
Temp (deg C)
-10
-30
-40
-50
+75OC/85
1
+75OC
+75OC
17 C/min
O
-40OC
+75OC
+50OC/90%
+17OC/mi
n ramp
-10OC
-30OC
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
30 of 40
Intvl #
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Initia l
Initia l
Fina l
Fina l
Interva l Tem p era ture Hum id ity Tem p era ture Hum id ity Next
# of
Tim e
(Chn. 1)
(Chn. 2)
(Chn. 1)
(Chn. 2) Interva l Loop s
0:00:01
1:00:00
0:00:01
0:40:00
0:00:01
0:40:00
0:00:01
1:00:00
0:00:01
0:40:00
0:00:01
0:40:00
0:00:01
1:00:00
0:00:01
0:20:00
0:00:01
0:10:00
0:00:01
0:10:00
0:00:01
0:20:00
0:00:01
0:10:00
0:00:01
1:49:15
0:00:01
0:40:00
0:00:01
0:40:00
0:00:01
0:40:00
0:00:01
40
40
40
75
75
-40
-40
40
40
75
75
-40
-40
40
40
75
75
75
75
-30
-30
-10
-10
50
50
75
75
-40
-40
75
75
-40
-40
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
75
75
0
0
0
0
90
90
0
0
0
0
0
0
0
0
40
40
75
75
-40
-40
40
40
75
75
-40
-40
40
40
75
75
75
75
-30
-30
-10
-10
50
50
75
75
-40
-40
75
75
-40
-40
40
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
85
85
0
0
0
0
90
90
0
0
0
0
0
0
0
0
0
2
3
4
5
6
7
3
9
10
11
12
13
9
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
27
32
33
1
0
0
0
0
0
0
5
0
0
0
0
0
5
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
0
0
255
Ac c ess Point
Tem p era ture
Cyc le/ Shoc k
Ac c ess Point
Tem p era ture
Cyc le/ Shoc k
Ac c ess Point
Hea t Wa ter
Cond ensa tion
Cyc le
Dry-Out
Tem p era ture
Cyc le/ Shoc k
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
31 of 40
Y
-Z
-X
-Y
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
32 of 40
BATTERY
SMALL LARGE
ANTENNA
IN
OUT
FLIP
OPEN CLOSED
FRONT
BACK
RIGHT
LEFT
TOP
BOTTOM
COMMENTS
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
33 of 40
1 OR 2
RIGHT (+X)
LEFT (-X)
TOP (+Y)
BOTTOM (-Y)
COMMENTS
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
PRELIMINARY
MEMO:
ISSUE:
PAGE:
34 of 40
PRODUCT
DATE
UNITS
VOLTAGE APPLICATION
LEVEL
POINT
NOTE: 1st ESD units should be 9, 11, 27; 2nd ESD units should be 12, 26, 28
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
35 of 40
11
6 Cycle
12
2 Cycle
3
7 Cycle
13
14
3 Cycle
5
8 Cycle
15
16
4 Cycle
7
9 Cycle
17
18
5 Cycle
9
10
Signaling
Test
Failure Description
Signaling
Test
Failure Description
10 Cycle
19
20
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
36 of 40
Cellular
Channel
Cellular
Power
Steps
PCS
Channels
PCS
Power
Steps
799, 991
799, 991
2, 5, 8
2
2, 1989
2, 1989
2, 5, 8
2
n/a
n/a
799
n/a
799, 991
799, 991
799, 991
799, 991
2
2
2
2
2, 1989
2, 1989
2, 1989
2, 1989
799, 991
n/a
799, 991
DCS
Power
Steps
EGSM
Channels
EGSM
Power
Steps
Batt.
Lvl.s
n/a
n/a
n/a
n/a
n/a
n/a
Nom
Nom
n/a
n/a
n/a
n/a
Nom
2
2
2
2
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
Nom
Nom
Nom
2, 1989
n/a
n/a
n/a
n/a
n/a
Nom
n/a
2, 1989
n/a
n/a
n/a
n/a
n/a
Nom
1013, 777
n/a
25, 1175
n/a
n/a
n/a
n/a
n/a
Nom
1013, 777
1013, 777
1013, 777
1013, 777
n/a
n/a
n/a
n/a
25, 1175
25, 1175
25, 1175
25, 1175
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
Nom
Nom
Nom
1013, 777
n/a
25, 1175
n/a
n/a
n/a
n/a
n/a
Nom
1013, 777
n/a
25, 1175
n/a
n/a
n/a
n/a
n/a
Nom
DCS
Channels
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
799, 991
799, 991
799
799, 991
799, 991
2, 4, 7
2
2
2
2
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
Nom
Nom
Nom
Nom
799, 991
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
799
799
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
Nom
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Nom
62
n/a
660
n/a
700
n/a
38
n/a
Nom
1, 124
5, 10, 15
0, 8, 15
512, 700,885
0, 8,
15
5, 10,
19
Nom
1, 62, 124
512, 700,885
Nom
1, 62, 124
512, 700,885
Nom
1, 62, 124
512, 700,885
Nom
1, 62, 124
n/a
n/a
512, 700,885
n/a
n/a
Nom
1, 62, 124
n/a
n/a
512, 700,885
n/a
n/a
Nom
512, 660,
810
512, 660,
810
512, 660,
810
512, 660,
810
512, 660,
810
512, 660,
810
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
PRELIMINARY
MEMO:
30-DEC-04
ISSUE:
PAGE:
37 of 40
E-GSM
975
5
37
70
124
DCS
512
521
586
651
716
781
846
885
PCS
512
546
611
676
741
806
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
MEMO:
30-DEC-04
PRELIMINARY
ISSUE:
PAGE:
38 of 40
PFFR (%/month)
EXAMPLE:
# OF FAILURES = 1
# OF RADIOS = 24 (10 FOR MotoCALT)
TEST DAYS = 7
ACCELERATION FACTOR = 645
DAYS LOST = 0
1 x 30.3
FAILURE RATE = -------------------------------- = .00017 or (0.017% PER MONTH)
((40 * 7) 0) x 645
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
39 of 40
Percent complete
0%
5%
25%
45%
75%
94%
99%
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.
NO.
motoalt 2005
REVISION DATE:
30-DEC-04
MEMO:
PRELIMINARY
ISSUE:
PAGE:
40 of 40
_______________________________________________________________________________________________________________________________________________________
The information contained in this in document is PROPRIETARY to Motorola Inc. and shall not be reproduced
or used in part or whole without Motorolas written consent.