United States Court of Appeals, Fourth Circuit
United States Court of Appeals, Fourth Circuit
2d 272
35 ERC 2074, 137 P.U.R.4th 444, 23
Envtl. L. Rep. 20,357
I.
2
As part of the 1990 amendments to the Clean Air Act, 42 U.S.C. 7401-7671,
Congress authorized the Administrator to establish a program to control the
effects of acid rain through limitations on emissions allowances. Under the
program established by the Administrator, an affected utility that has been
allocated allowances based on historical emissions has flexibility to comply
with the new emissions requirements by adding to its industrial equipment
sulfur dioxide control technology ("scrubbers"), switching to lower sulfur
content coal, or purchasing additional of the limited, fully marketable
allowances from other utilities to cover its own emissions. This latter allowance
trading system represents the centerpiece of the program.
To encourage the use of scrubbers, certain utilities that install them are allowed
to apply for a two-year extension of a compliance deadline. Id. 7651c(d)(1).
Utilities making such an application become eligible to receive, from a limited
reserve, the additional allowances needed to cover their emissions for the
extension period, as well as additional ("bonus") allowances for use after the
extension period. Id. 7651c(d). Anticipating that the demand for such
allowances would outstrip their supply, Congress directed the Administrator to
"review and take final action on each extension proposal in order of receipt." Id.
7651c(d)(3).
4
The Administrator argued below that the district court should dismiss the
complaint for lack of jurisdiction and that, in any event, a preliminary
injunction was inappropriate. The district court rejected both arguments,
holding that the Administrator had failed to perform a nondiscretionary duty.
The court entered a preliminary injunction requiring the EPA to rank
Monongahela's application in order of receipt and to determine its entitlement to
extension and bonus allowances. From this order, an appeal was taken.
The Administrator advances two arguments before this court. First, he contends
that the district court lacked jurisdiction over Monongahela's complaint.
Alternatively, he argues that the district court's preliminary injunction should
be vacated as an abuse of its discretion. Because we agree with his former
claim, we do not reach the latter.
II.
9
We must first determine whether jurisdiction was proper only in the Court of
Appeals for the District of Columbia Circuit pursuant to 42 U.S.C. 7607(b)
(1), which confers on that court exclusive jurisdiction over "petition[s] for
review of ... nationally applicable regulations promulgated, or final action
taken, by the Administrator." See Environmental Defense Fund v. Thomas, 870
F.2d 892, 896 (2d Cir.) ("Because [section 7607] embodies a grant of exclusive
jurisdiction, it appears that if the District of Columbia has jurisdiction over the
present action, the district court does not."), cert. denied, 493 U.S. 991, 110
S.Ct. 537, 107 L.Ed.2d 535 (1989). Such actions must be brought "within sixty
days from the date notice of such promulgation, approval, or action appears in
the Federal Register." 42 U.S.C. 7607(b)(1). The Administrator characterizes
Monongahela's claim as "in substance, an attack on a proposed nationally
applicable regulation" because it allegedly challenges the scheme developed in
the proposed regulations, Appellant's Br. at 28, and argues that it is therefore
both premature and filed in the wrong court.1 Contrary to the Administrator's
assertions, Monongahela's complaint cannot be characterized as a petition for
review of nationally applicable regulations, for at the time it was filed, the EPA
had yet to promulgate any such regulations. We conclude, therefore, that the
Court of Appeals for the District of Columbia Circuit did not have jurisdiction
over Monongahela's claim. This does not end our inquiry, however, for we must
yet determine whether the district court had jurisdiction over this claim under
42 U.S.C. 7604(a)(2). See Environmental Defense Fund, 870 F.2d at 896 ("If
the District of Columbia Circuit does not have jurisdiction ..., then either the
district court has jurisdiction or [plaintiffs] have no forum in which to assert
their claims."); cf. Sierra Club v. Thomas, 828 F.2d 783, 792 (D.C.Cir.1987)
("It does not follow automatically that, if the district court lacks jurisdiction,
then it must lie in [the District of Columbia Circuit], for both courts have just so
much jurisdiction as Congress has provided by statute.").2 III.
10
Jurisdiction of the district court over this suit turns upon the question of
whether the Administrator's challenged course of action violates a
nondiscretionary duty imposed upon him by the terms of the Act. The Act sets
forth its jurisdictional requirements:
11
******
12
13
******
14
15 district courts shall have jurisdiction, without regard to the amount in
The
controversy or the citizenship of the parties, ... to order the Administrator to perform
such act or duty, as the case may be....
16
42 U.S.C. 7604(a). We need decide today only whether the statute imposed
upon the Administrator a nondiscretionary duty to process extension
applications before he promulgated final regulations implementing the statutory
program. See Sierra Club v. Train, 557 F.2d 485, 488 (5th Cir.1977) ("The
substantive issue in this case is one of statutory construction, specifically
whether [the Act] imposes a discretionary or non-discretionary duty on the EPA
Administrator.").3 We conclude that the statute is silent on this question and
that we must therefore defer to the Administrator's reasonable interpretation of
the statute as not requiring the consideration of extension applications before
the agency's final regulations were in place.
A.
17
The district court concluded that the Administrator had a nondiscretionary duty
under section 7651c(d)(3) to accept and review extension proposals
immediately in the order of their receipt. J.A. at 357-58 ("[T]here is no
statutory authority which suggests that Congress authorized the EPA to defer
consideration of extension proposals until [promulgation of permit program
regulations]."). At the heart of the court's holding was its conclusion that the
Administrator's obligation to review proposals in the order of receipt is "distinct
from" his obligation under 42 U.S.C. 7651g(c)(3) to promulgate permit
regulations. Id. at 357. The Administrator contends that the language of the Act
not only does not impose upon him a nondiscretionary duty to review extension
proposals prior to the promulgation of regulations, see Appellant's Br. at 20, it
"directly contradicts" the conclusion that he had such a duty. Id. at 18. He
argues in the alternative that, even if not dictated by the statutory text, his
interpretation of section 7651c(d)(3) is a reasonable interpretation to which we
We disagree with the Administrator that the language of the Act "directly
contradicts" the conclusion of the district court. Title 42, section 7651c(d)(1)
provides for utilities to petition for extensions "in [their] permit application
under section 7651g."4 Permit applications and compliance plans must, under
the statute, be submitted "pursuant to regulations promulgated by the
Administrator." See 7651g(b), 7651g(c)(1). The Administrator argues that
because utilities "must" petition for extensions in the permit application itself,
and because the permit application must be filed in accordance with regulations
promulgated by the Administrator, it necessarily follows that an extension
proposal cannot be filed until regulations have been promulgated. From this
syllogism, he reasons that he need not accept or review extension proposals
prior to the promulgation of regulations.
19
Contrary to the Administrator's assertion, see Appellant's Br. at 22; see also
Appellant's Reply Br. at 1, 7, however, section 7651c(d)(1) does not provide
that a utility "must" petition for an extension in its permit application; that
section provides only that a utility "may" petition for an extension in its permit
application. While it may be reasonable to read section 7651c(d)(1) in the
manner proposed by the Administrator, see discussion infra, it is not correct to
say, as the Administrator does, that the language of section 7651c(d)(1) that a
utility may petition for extensions in its section 7651g permit application
"directly contradicts" the district court's conclusion.
20
The Administrator also contends that the "express reference" to section 7651g
in section 7651c(d)(3) "preclude[s] the interpretation of [section 7651c(d)(3) ]
adopted by the district court." Appellant's Br. at 21.5 In this regard, the
Administrator argues that the section's proviso that the Administrator's review
and final action on extension proposals shall be "consistent with section 7651g"
"plainly requires" that regulations be extant before proposals are accepted. Id.
Again, although this may be a plausible interpretation of congressional intent, it
is not manifest from the language of the statute that Congress so intended.
Congress provided in section 7651c(d)(3) only that review and final action on
extension proposals shall be "consistent with" section 7651g; it did not provide
that review and final action shall be undertaken subject to the same
requirements in section 7651g-- i.e., pursuant to regulations. It does not
necessarily follow from the facts that permit applications must be made
"pursuant to regulations promulgated by the Administrator," see 42 U.S.C.
7651g(b), and that a source must submit a permit application and compliance
plan by February 15, 1993, "in accordance with regulations issued by the
Administrator," see id. at 7651g(c)(1), that an extension proposal also must be
22
23
24
Although the Act does not unambiguously authorize the Administrator to await
his regulations before reviewing and acting upon extension proposals, section
7651c(d)(1) does provide, as noted, that utilities may petition for extensions in
their permit applications. A reasonable interpretation of this section is that
Congress intended, as the Administrator contends, that extension proposals
would be submitted only with permit applications. Assuming that this was
Congress' intent, it may reasonably be inferred from the clear requirement in
26
27
B.
28
determining order of receipt. See Appellees' Br. at 29-30. Neither argument has
merit. Even assuming that an agency's litigation position is entitled to less
deference than are other articulations of the agency's views, cf. Church of
Scientology v. IRS, 792 F.2d 153, 162 n. 4 (D.C.Cir.1986) (en banc ) ("There is
some question ... whether an interpretive theory put forth only by agency
counsel in litigation ... constitutes an 'agency position' for purposes of
Chevron."), aff'd, 484 U.S. 9, 108 S.Ct. 271, 98 L.Ed.2d 228 (1987), the
interpretation advanced by the Administrator in this case represents far more
than a mere "litigation position."7 The EPA consistently has maintained this
position, at the very least since the time it rejected Monongahela's application.
Now, of course, the agency has even embodied its interpretation in final
regulations implementing the Act.
29
Monongahela's second argument, even if we accept as true the premise that the
White House exerted influence over the EPA, is frivolous. The authority of the
President over executive agencies and departments is without exception, save as
may exist by law, because all executive power exercised by the federal agencies
derives from the Chief Executive. The various agencies and departments are
not autonomous of the President. See Sierra Club v. Costle, 657 F.2d 298, 405
(D.C.Cir.1981) ("recogniz[ing] the basic need of the President and his White
House staff to monitor the consistency of executive agency regulations with
Administration policy"). Thus, any policymaking influence exerted over the
EPA by the White House--provided such was consistent with law--was fully
permissible under our tripartite system of separated powers. Id. at 406 ("The
authority of the President to control and supervise executive policymaking is
derived from the Constitution; the desirability of such control is demonstrable
from the practical realities of administrative rulemaking." (footnote omitted)).
CONCLUSION
30
For the reasons set forth above, we conclude that the district court lacked
jurisdiction over this action under 42 U.S.C. 7604(a)(2). Therefore, we vacate
its order and remand with instructions to dismiss the complaint.
31
The Administrator does not contend that the district court lacked jurisdiction
because EPA's refusal to process Monongahela's application constituted final
agency action within the meaning 42 U.S.C. 7607(b)(1)--for which appeal
lies exclusively in the D.C. Circuit--and we do not address this issue
(1981)
Monongahela assails these decisions, asserting that "[i]t is doubtful whether the
more restrictive aspects of the decisions relied upon by [the Administrator]
remain good law following the extensive amendments to the Citizen Suit
provisions made in 1990." See Appellees' Br. at 25. The 1990 amendments,
however, did not change the language of section 7604(a)(2). Rather, they added
new language establishing jurisdiction over suits seeking to compel action
"unreasonably delayed," a basis of jurisdiction not relied upon by the district
court. See supra note 2.
4
The Administrator suggests that unless the plain terms of the statute impose a
nondiscretionary duty, then none exists. See, e.g., Appellant's Br. at 22-23;
Appellant's Reply Br. at 13. We are not persuaded that this is correct.
Presumably, the existence of a nondiscretionary duty could be recognized
through application of Chevron's rule of construction, even if it could not arise
by inference, see Appellant's Br. at 22-23. For example, the Administrator
could reasonably interpret an ambiguous statute so as to impose a
nondiscretionary duty. In such a circumstance, the duty would exist no less than
if it appeared on the face of the statute
without presentation of contrary views), cert. denied, 493 U.S. 1055, 110 S.Ct.
863, 107 L.Ed.2d 947 (1990)