VT Technical
VT Technical
Preface
HRD Centre is pleased to present the technical manual of ISP, Burnpur. The aim of the
manual is provide an introduction to all the new units and facilities of the 2.5 MTPA steel
plant. The manual gives detail information about the working of various departments of the
plant. The purpose of technical manual is learning and development of the new entrants
andvarious stake holders of ISP, Burnpur.
HRD Centre would like to thank all the departments of ISP for their valuable contribution in
developing
the
manual.
HRD
Centre
is
grateful
to
Executive
Director
I/C,
Executive Directors, General Managers for their valuable suggestions and support in
developing this manual. We welcome feedback and suggestions for further improvements of
the manual.
Content
Sno
Department
Page. No
1.
ACVS
---------------------------
1-4
2.
BF
---------------------------
5-44
3.
BOF CCP
---------------------------
45-78
4.
C&A
---------------------------
79-83
5.
C&IT
---------------------------
84-92
6.
Capital Repair
---------------------------
93-93
7.
CCAS
---------------------------
94-105
8.
CCMD
---------------------------
106-107
9.
Coke Ovens
---------------------------
108-159
10.
Energy Management
---------------------------
160-163
11.
ERS
---------------------------
164-172
12.
ETL
---------------------------
173-178
13.
Instrumentation
---------------------------
179-187
14.
Marketing
---------------------------
188-194
15.
Medical
---------------------------
195-199
16.
MM
---------------------------
200-202
17.
Operation Garage
---------------------------
203-210
18.
Oxygen Plant
---------------------------
211-222
19.
P&A
---------------------------
223-228
20.
P&BS- 2
---------------------------
229-290
21.
Power Dist.
---------------------------
291-299
22.
PPC
---------------------------
300-302
23.
Projects
---------------------------
303-307
24.
RMHP
---------------------------
308-338
25.
Rolling Mills
---------------------------
339-367
26.
Safety Engineering
---------------------------
368-376
27.
---------------------------
377-383
28.
Sinter Plant
---------------------------
384-393
29.
Sports
---------------------------
394-398
30.
Telecom
---------------------------
399-408
31.
---------------------------
409-424
32.
Water Management
---------------------------
425-442
ACVS
AIR CONDITIONING & VENTILATION SYSTEM
A) Introduction
Air Conditioning and Ventilation system or ACVS department of IISCO Steel Plant, Burnpur is
entrusted with the job of round the clock operation and maintenance of various types of Air
conditioning systems- Windows ACs, Packaged ACs, Central ACs, Chiller water units installed
within the plant premises and also outside for their uninterrupted operation and their pro-active,
preventive, corrective and breakdown maintenance.
The ACVS department of ISP maintains 47 Central Air conditioning Plants, 111 Packaged Air
Conditioners, over 900 Room Air Conditioners (Window/Split), 20 Water coolers and 15
Refrigerators.
Central air conditioning plants of capacity 15 to 420 TR are installed in Burnpur Hospital , power
engineering plant control rooms, PEDD, Drawing office, confluence, Deepani.These plants
maintain desired temperature to safe guard control panels in control rooms and provide
comfortable working conditions.
Packed Air Conditioners of capacities 5.5 TR to 30 TR are installed in control rooms of CO &
BPP, Power plants, C&IT, PLC Boiler Control room, MRM etc. Also high ambient temp air
conditioners of Linter make , USA are installed at COB # 10 in pusher cars, charging cars, guide
cars & coke cars.
Room air conditioners of window and split type are installed at various offices and control rooms
inside and outside works area to control temperature for electronic cards & comfortable human
working conditions.
ACVS
C) Principles of Refrigeration
a. Liquids absorb heat when changed from liquid to gas ( Freon 22, R-124, R134a)
b. Gases give off heat when changed from gas to liquid.
All air conditioners use the same cycle of compression, condensation, expansion, and
evaporation in a closed circuit. The same refrigerant is used to move the heat from one area, to
cool this area, and to expel this heat in another area.
a. The refrigerant comes into the compressor as a low- pressure gas , it is compressed and
then moves out of the compressor as a high-pressure gas.
b. The gas then flows to the condenser. Here the gas condenses to a liquid , and gives off its
heat to the outside air.
c. The liquid then moves to the expansion value under high pressure. This valve restricts
the flow of the fluid, and lowers its pressure as it leaves the expansion valve.
d. The low-pressure liquid then moves to the evaporator, where heat from the inside air is
absorbed and changes it from a liquid to a gas.
e. As a hot low- pressure gas, the refrigerant moves to the compressor where the entire
cycle is repeated.
The four-part cycle is divided at the centre into a high side and a low side. This refers to the
pressure of the refrigerant in each side of the system.
a. Chiller Units
Sno
Area/Customer
Type
Quantity
Capacity/Unit(TR) Total
Tonnage
(TR)
SINTER PLANT
Chiller
5 Nos.
( 3x 155), (2x105)
675
CDCP-COB #11
Chiller
2 Nos.
110
220
PBS#2
Chiller
2 Nos.
220
440
MRS
Chiller
2 Nos.
60
120
WRM
Chiller
6 Nos.
270
1620
BOF
Chiller
6 Nos.
300
1800
CCP
Chiller
4 Nos.
150
600
ACVS
b. Packaged A.C. Units
Sno
Department
No
of
units Capacity
installed
of Total Capacity
WMD
11.0
88
BPP (COB#11)
11.0
22
16.5
99
5.5
11
12
11.0
132
16.5
33
8.5
51
10
11.0
110
16.5
66
5.5
16.5
11.0
22
16.5
33
RMHS (OHP)
CHP (COB#11)
WRM
PBS
16.5
33
OXYGEN
11
55
PLANT
Total = 66
Total 771.5
Department
A.C Type
Capacity/Unit
Total Nos.
COB#10
Split
1.5TR
22
d. Existing Plant
Sno.
Area/Customer
Type
Quantity
PEDD
Chiller
4 Nos.
Drawing Office
Chiller
1 Nos.
Control Gallery
Chiller
2 Nos.
SMS
PAU
2 Nos.
PAU
4 Nos.
PAU
2 Nos.
BF #2
PAU
2 Nos.
ACVS
7
PAU
2 Nos.
THF
PAU
2 Nos.
PAU
2 Nos.
10
Thyristor
PAU
3 Nos.
11
Telephone Ex.
PAU
2 Nos.
12
C&IT
PAU
2 Nos.
13
Control/ Galari
PAU
2 Nos.
14
Motor House
PAU
2 Nos.
15
ED (W) Office
PAU
1 Nos.
16
BF Distribution
PAU
2 Nos.
17
PAU
1 Nos.
18
34 Cabin
PAU
2 Nos.
Type
Quantity
Sno
Area/Customer
7 Nos.
Complex)
Deepani
Chiller
2 Nos.
Confluence
Chiller
3 Nos.
Bharati Bhavan
Chiller
1 Nos.
MD Office
PAU
3 Nos.
Hospital ( X Ray)
PAU
4 Nos.
Old OT Hospital
PAU
1 Nos.
Burnpur Club
PAU
4 Nos.
Blast Furnace
BLAST FURNACE
A) Introduction
The purpose of a blast furnace is to chemically reduce and physically convert iron oxides
into liquid iron called "hot metal". The blast furnace is a huge, steel stack lined with
refractory brick, where iron ore, coke and limestone are dumped into the top, and
preheated air is blown into the bottom. The raw materials require 6 to 8 hours to descend
to the bottom of the furnace where they become the final product of liquid slag and liquid
iron. These liquid products are drained from the furnace at regular intervals. The hot air
that was blown into the bottom of the furnace ascends to the top in 6 to 8 seconds after
going through numerous chemical reactions.
The aim of Blast Furnace is to produce pig iron from ore and sinter, i.e. iron bearing
materials. Theiron oxide ore and sinter is reduced to iron with the help of CO and this CO
is produced inside theblast furnace by the action of air with coke. Coke serves another
purpose of supplying heat for thereactions and melting iron inside the furnace. Part of the
heat load of the furnace is also provided bythe heat of the blast which is heated up to a
temperature of 1,000C or so before it is introduced intothe furnace. The gangue material
(i.e. unwanted materials like SiO2, AI2O3 etc.) of the ore, sinterand coke are removed as
slag with the help of flux. Other additives like quartzite and Mn are also charged in the
furnace in smallquantities (corrective materials for the proper furnace working and
control of analysis). Except blast and CDI which is fed from the lower part of the furnace
thorough tuyeres, all other materials are chargedfrom the top. The product of the furnace
is pig iron (hot metal), slag and BlastFurnace gas.
Out of 4 Blast Furnaces commissioned way back in 1922, 1924, 1958 & 1958, operation
of 3 furnaces, no.1, no. 4 & no. 3 has been stopped since 2008, 2008 & 2012 respectively.
Presently only one rebuilt furnace no. 2(in Nov. 2007) is in operation having useful
volume 530 m3 & average daily production of 610 MT. The upcoming blast furnace
number 5 is having a useful volume of 4161 m3 and it will produce 7900tpd of hot metal.
Blast Furnace
The entire Blast Furnace complex may be divided in the following sections:
1. Furnace Proper
2. Raw Material Charging
3. Stoves
4. Auxiliaries
i.
ii.
iii.
iv.
v.
Cooling System
vi.
B) Furnace Proper
Diameter by mm
1. Throat diameter 9800
2. Hearth diameter 13600
3. Belly diameter
15600
The furnace inner profile is designed based on the experience and know-how of POSCO
E&C with the reference profile of the similar scale furnaces designed by POSCO E&C,
which was shown the high productivity and stable operation.
The optimized carbon and ceramic material is arranged around the hearth area. The
furnace cooling system and refractory arrangement will ensure the campaign life of more
than 20 years without the intermediate capital repair.
The most advanced copper staves in the high heat load zone such as bosh, belly and
lower shaft zone (B1,B2.S1,S2), and cast iron staves at the zone of hearth, tuyere, middle
6
Blast Furnace
and upper shaft (H1~H4,T1,S3,S4, S5,R1,R2) with integral refractory are arranged. The
furnace under hearth is cooled by water through embedded pipes.
1. Structure and Measuring equipment
Independent furnace tower structure with platforms will be designed for supporting the
equipment of the charging system and the probes for furnace, and providing adequate
space for maintenance and operation of the equipment.
The fixed above burden temperature probe, under burden probe, and profile meter are
fitted in the furnace with the related power supply unit for measuring operation
situation inside the furnace.Reduced gas made from BF bottom will be reacted with
the materials falling down while the gas goes up, and this will make the ores to be
preheated up or deoxidized.
Reduced gas made from BF bottom will be reacted with the materials falling down
while the gas goes up, and this will make the ores to be preheated up or deoxidized.
IISCO Steel Plant
Blast Furnace
a. Type:
b. Useful volume:
c. Hearth diameter :
13.6 m
d. Number of Tuyere :
38 EA
4 EA, 10
f.
4.6/3.0 kg/
Blast Furnace
Design description of shell: The furnace shell is designed so as to endure the load of
some parts of the furnace top charging equipment, the raw materials, molten iron and
slag in the furnace, refractory and other auxiliary equipment, and the design blast
pressure of 4.6 kg/ and the design top pressure of 3.0 kg/. The blast furnace shell
was designed for the maximum operating pressure plus 10%.Considering the molten
iron & slag volume, the hearth diameter is set to be 13.6m. And, pool depth, defined
as the depth from the bottom of hearth to center of T/H, is 3.0m to obtain optimal
accumulated volume of iron and longer campaign life of the hearth. The slope of iron
notch (Tap hole) will be 10 to the horizontal, but the angle between two iron notches
will be 80.
The height of Bosh and Belly are decided to be 3.7m, and 2.5m respectively in order
to have enough melting and reduction function in cohesive zone, to absorb bosh gas
volume expansion and to smooth descending of burden materials.
The outsidetemperatures of shell depend on a number of factors and different
conditions, the design values to be assumed in calculation are 180 on the whole
shell with 300 to be considered on tap hole, tuyere zone, tuyere stock and top cone.
Blast Furnace
1,570
* Stock Line
B: 2248m3
17,450
80.564
D
E
G: 436m3
4,200
E: 87m3
4,200
3,000
CL OF TUYERE
13,600
7,800
74.876
3,700
D: 620m3
F: 610m3
2,500
15,600
C: 478m3
CL OF TAP HOLE
: 4597 (A+B+C+D+E+F+G)
IISCO Steel Plant
Blast Furnace
3. Furnace Cooling
Tuyere nozzle/cooler
Design pressure will be approximately1.2times of working pressure.
Working conditions approximately
Tuyere coolers
8 Kg/m2
Tuyere bodies
8 Kg/Cm2
Tuyere noses
10 Kg/cm2 (min)
99.9 % copper
ii.
Electrical conductivity:
60% IACS
iii.
Tuyere cooler:
99.5 % copper
iv.
Electrical conductivity:
50 % IACS
v.
Tuyere nose:
coating.
Copper staves will be manufactured by rolled slab. Refractory anchoring grooves are
machined into the hot face surface of copper stave. For fixing and lifting elements,
threaded holes are drilled into the stave.In the meanwhile, pipe inlets and outlets for
copper stave are sealed gastight by means of sealing boxes with integrated
expansion bellows, which are welded on the shell and on the cooling pipe of the
stave. And the cooling pipes inlets and outlets are fitted with a seal to prevent
castablefrom flowing into the shell openings.
Cast iron staves: The thinned cast iron stave in hearth, tuyere, middle & upper shaft
area (H1~H4, T1, S3~S5, R1, R2) which contains cast in pipes with integral brick
will be installed. In terms of stave material, high heat conductivity copper for the
IISCO Steel Plant
11
Blast Furnace
copper staves and a material with an excellent thermal shock resistance (Spheroidal
graphite) for cast iron staves(S3~R2) will be used practically. In the structural
aspect, to eliminate the less-cooled zone at the stave, the arrangement of the cast-in
pipes enables to cool uniformly the entire stave.
R2 have two serpentine cast-in pipes in one stave due to the thermal load lower than
that of other zones.
For cast iron stave, gas sealing is obtained at the fixed points by the use of
compensators that are welded both on the shell and on the protecting sheath pipes.
At the movable points of upper sealing of the stave, the seal boxes are fixed both on
the shell and welded on the protecting sheath pipes. At the rigid points of lower
sealing of the stave, the seal washers are welded both on the shell and on the
protecting sheath pipes.
12
Blast Furnace
Table: Specifications of Stave
Pipe number for
Row
Q'ty
Stave material
Thickness
Each stave
Vetical/
Serpentine
Horizontal
Hearth - H1
38
140
6/0
Hearth H2
38
140
6/0
Hearth H3
38
140
6/0
Hearth H4
38
140
6/0
Tuyere - T1
38
240
6/0
Bosh - B1
44
120
5/0
Belly - B2
44
120
5/0
Lower Shaft S1
44
120
5/0
Lower Shaft S2
44
120
5/0
Middle Shaft
- S3
36
330
6/2
Middle Shaft
- S4
36
330
6/2
Middle Shaft
S5
36
330
6/2
Upper Shaft R1
26
330
Upper Shaft R2
26
330
Copper
Spheroidal
Graphite
13
Blast Furnace
4. Furnace Top Water Spray Equipment
Furnace top water spray system is installed on the top cone for emergency cooling of
furnace inside and adequate steam and nitrogen purging system is fitted on the top
cone area.
Setting temperature
300
Number
8 EA
of
spraying
nozzle
Water Quantity
2 /min/pump 2
Operation
To prevent the spray nozzles from being clogged by dust, Nitrogen Gas is used at
time of no water spraying.
5. Furnace Auxiliaries
a. Fixed Above Burden Temperature Probe: 2 set
This device is installed above the stock in order to detect temperature
distribution and analysis of gas.
i.
ii.
iii.
iv.
v.
Cooling method : by N2
14
i.
ii.
Blast Furnace
iii.
iv.
v.
vi.
ii.
iii.
iv.
ii.
Control and Driving Method : Local Control, Electric motor & chain
drive mounted on frame
iii.
15
Blast Furnace
by conveyor system and transportation of screened fines for sinter, ore and coke to a
separate fines storage bunkers with discharge arrangement.
This equipment will be provided for discharging and weighing ferrous and coke from the
ferrous and coke bins and for charging to the furnace top with a charging conveyor.The
ore mentioned herein will be a general terms for sinter, sized ore and additive materials.
Sinter and ore will be screened and separated into lump [sinter (+15mm), ore(+8mm)]
and fines [sinter(-15mm), ore(-8mm)] by screen located under bins. Lump sinter and ore
will be weighed by the weighing hopper under the bins. On the other hand fines sinter
and fines ore will be transported to the fines bins through fines conveyors.
The fine ore that is transported through the fine conveyor will be charged to ore fine
bunker. The fine sinter will be sized by the screen which is installed under sinter fine bin,
and then oversized sinter (5~15mm) will be charged to the blast furnace through charging
belt conveyor after returning to small sinter bin of stock house through small sinter belt
conveyor. Also, undersized sinter (~5mm) will be transported to sinter plant or yard.
At coke plant, in a case of the coke that has two (2) kind of grain size is transported to
upper stock house bin, the coke that is separated as 60~80mm through the screen which is
installed at the lower coke bin will be charged to the blast furnace as a hard coke for
charging to center. On the other hand, the coke that is separated as 34 ~ 60 mm will be
charged to the blast furnace as a surface coke.
The undersized coke (-34mm) will be transported to the coke fines bin through fines
conveyor. The transported small-sized coke will be separated as the oversized coke
(8~34mm) and fine coke (-8mm) through the screen which is installed under coke fine
bin.
16
Blast Furnace
The oversized coke (8~34mm) will be charged to the blast furnace through the charging
belt conveyor after returning to the nut coke bin of stock house through the nut coke belt
conveyor. The fine coke (-8mm) will be transported to the sinter plant or yard.
Bins have the capacity for 8 ~ 24 hours operation continuously. Fines material will have
arrangement for discharge fines belt conveyor. The electrostatic precipitator isconstructed
to prevent dispersion of dust generated from the stock house.
1. Process Description
17
Blast Furnace
Blast Furnace
2. Coke System
a. Coke Bin
Six (6) coke bins are designed and the effective volume of each bin is 840 m3. This is
based on the storage capacity of 12hours for daily maximum production of 8,000ton
pig iron.
Coke to be transported by CRSC1,2 belt conveyor for the coke of 60~80mm and
CRSC3,4 belt conveyor for the coke of 34~60mm is fed in one of the coke bins to be
selected automatically by the level sensors at the bins.
The surface of the sloping walls at the lower part of bins is lined with basalt material
of 40mm thick. The sloping angle at the lower part of bins is limited to minimum
55degrees (Valley angle) with regard to angle of repose of coke.
A level detector is installed above the each bin for monitoring the level of stored coke
in the bins and control of the shuttle conveyor.
The slide manual gate is located below the bins. A vibrating feeder of the capacity of
200 ton per hour is fitted below the gate for higher screening efficiency.
A coke screen of the capacity of 200 ton per hour is located below the vibrating
feeder. The screen remove coke fine of 0 to 34mm size.
19
Blast Furnace
3. Coke Weighing Hoppers
All of weighing hoppers are respectively mounted on load cells for weighing purposes
and has a hydraulic operated gate for material discharge and a manual gate for controlling
of flow rate of discharge
The signal form the load cell will be displayed by weight value at HMI and used to
control of the screens and vibrating feeders. The stop signal will be calculated by PLC
with result from the last weighing.
During screening coke, the oversize fraction fall into the weighing hoppers and the
undersize fraction below 34mm fall onto the sinter fine conveyor (FCC-1). The
maximum of four (4) screens can be operated simultaneously.
This belt conveyor run continuously and has the dual drive unit system for stable
operation of blast furnace by connecting the coupling of a standby drive unit when the
duty drive unit are in trouble.
Metal detector is located on the BFC-1 belt conveyor and when the metal is detected the
BFC-1 belt conveyor will be stopped and alarm will give to HMI. And this will also
prohibit the gate of coke weighing hopper from open.
The undersize size fraction during screening sinter is sent via coke fine conveyor (FCC-1,
2) to two coke fine. The small screened by a coke fine screen is transported to the nut
coke bin and coke fines are then removed by FCC-3 belt conveyor.
20
Blast Furnace
All of coke belt conveyors run without stop during Automatic mode operation.
The coke sampler is located around the head pulley of BFC-1 belt conveyor, and the
sampling will be done by manual operation at local only when the sampling is required.
Each surge hopper is mounted on load cells for weighing purposes and has a hydraulic
operated gate for coke discharge and a manual gate for controlling of flow rate of coke
discharge. The signal from the load cells will be displayed at the HMI and used to control
of the screens. The stop signal will be calculated by PLC with result from the last
weighing.
Each coke surge hoppers has a moisture measurement that is used to measure the
moisture content in the coke.
A level sensor is installed at the sidewall of each hopper to detect the high level of the
filling materials and it gives alarm at HMI and stops the vibrating feeders, screens and
belts.
21
Blast Furnace
The coke fines below 34mm size are transported by FCC-1,2 and CRC-3 belt conveyor to
the coke fine bin for screening nut coke and holding purpose prier to removal by belt
conveyor(FCC-3). The coke fine bin of useful volume of 350 m3 is based on the storage
capacity of 8 hours for daily maximum production of 8000ton pig iron.
The surface of the sloping walls at the lower part of bins is lined with basalt material of
40mm thick. The sloping angle at the lower part of bins is limited to minimum 55degrees
(Valley angle) with regard to angle of repose of coke.
The vibrating feeder and manual gate are installed for discharging fine coke in the bin.
One coke fine screen is below the vibrating feeder for screening nut coke of coke fine.
And the level sensor is installed for measurement of the level of deposit coke in the bin.
The level signal is used to stop the FCC-1, FCC-2 and CRC-3 belt conveyor when the
level is high.
8. Ferrous System
The surface of the sloping walls at the lower part of bins is lined with basalt material
of 40mm thick. The sloping angle at the lower part of bins is limited to minimum 55
degrees of valley angle with regard to angle of repose of ore/ additive materials.
22
Blast Furnace
A level transmitter and a level switch are installed above all of the bins for
monitoring the level of stored materials in the bins. And the de-dusting duct with a
damper automatically actuated by pneumatics is installed at each bin for extracting
the dust generated when ore/additive materials are discharged from shuttle conveyors
to bins.
The slide gate of manual type is located below the bins. A vibrating feeder of the
capacity of 250 ton per hour is fitted below the gate of the ore bins for higher
screening efficiency.
An ore screen of the capacity of 250 ton per hour is located below the vibrating
feeder. The screen remove ore fine of 0 to 8mm size.
A vibrating feeder of the capacity of 50 ton per hour is located below the slide gate of
the additive bins for discharging of additive materials into the weighing hopper.]
The weighing hoppers are located below the ore screens and additive vibrating
feeders for weighing purpose.
b. Sinter Bin
There are six (6) sinter bins. The effective volume of a sinter bin is 800 m3. This is
the based on the storage capacity of 16 hours for daily maximum production of 8000
ton pig iron.
The surface of the sloping walls at the lower part of bins is lined with basalt material
of 40mm thick. The sloping angle at the lower part of bins is limited to minimum 55
degrees of valley angle with regard to angle of repose of ore/ additive materials.
IISCO Steel Plant
23
Blast Furnace
A level transmitter and a level switch are installed above all of the bins for
monitoring the level of stored materials in the bins. And the de-dusting duct with a
damper automatically actuated by pneumatics is installed at each bin for extracting
the dust generated when sinter materials are discharged from shuttle conveyors to
bins.
The slide gate of manual type is located below the bins. A vibrating feeder of the
capacity of 450 ton per hour is fitted below the gate of the sinter bins for higher
screening efficiency.
The weighing hoppers are located below the screens for weighing purpose and these
hoppers are used to weigh the sinter.
Nut coke to be transported by NCC-1 belt conveyor is fed in nut coke bin.
The surface of the sloping walls at the lower part of bins is lined with basalt material of
40mm thick. The sloping angle at the lower part of bins is limited to minimum 55
degrees of valley angle with regard to angle of repose of coke materials.
A level transmitter and a level switch are installed above the entire bin for monitoring
the level of stored materials in the bins. And the de-dusting duct with a damper
automatically actuated by pneumatics is installed at each bin for extracting the dust
generated when sinter materials are discharged from shuttle conveyors to bins.
24
Blast Furnace
The slide gate of manual type is located below the bins. A vibrating feeder of the
capacity of 50 ton per hour is fitted below the gate of the nut coke bin discharging nut
coke into the nut coke weighing hopper.
The weighing hopper is located below the vibrating feeder for weighing purpose and
this hopper is used to weigh nut coke.
Small sinter to be transported by SSC-1, 2 belt conveyor and SRSC-1 shuttle conveyor
is fed in one of the small sinter bins to be selected automatically by the level sensors at
the bins.
The surface of the sloping walls at the lower part of bins is lined with basalt material of
40mm thick. The sloping angle at the lower part of bins is limited to minimum
55degrees (Valley angle) with regard to angle of repose of small sinter.
A level detector is installed above the each bin for monitoring the level of stored small
sinter in the bins and control of the shuttle conveyor.
The slide gate of manual type is located below the bins. A vibrating feeder of the
capacity of 100 ton per hour is fitted below the gate for discharging small sinter on the
BFC-3 belt conveyor.
25
Blast Furnace
9. Ore/ Additive and Sinter Weighing Hoppers
Each one weighing hopper is located per two screens and an additive weighing hopper is
located below four additive vibrating feeders for weighing purpose.
All of weighing hoppers are respectively mounted on load cells for weighing purposes
and has a hydraulic operated gate for material discharge and a manual gate for controlling
of flow rate of discharge.
The signal form the load cell will be displayed by weight value at HMI and used to
control of the screens and belt feeders. The stop signal will be calculated by PLC with
result from the last weighing.
During screening sinter, the oversize fraction fall into the weighing hoppers and the
undersize fraction below 34mm fall onto the sinter fine conveyor (FSC-1). The maximum
of four (4) screens can be operated simultaneously.
During screening ore, the oversize fraction fall into the weighing hoppers and the
undersize fraction below 8mm fall onto the ore fine conveyor (FOC-1). The maximum of
two (2) of 2 screens and 2 vibrating feeders can be operated simultaneously.
The additive materials and nut coke fall into each weighing hopper by vibrating feeders
without screening.
Each hopper has a hydraulic operated gate for material discharge and a manual gate for
controlling of flow rate of discharge. The weighing hopper gate is open in order for
preventing the overfilling on the belt.
10. Ferrous BC
a. BFC-2 Belt Conveyor
26
Blast Furnace
The ore conveyor (BFC-2) feeds the materials into one of two surge hoppers via a
hydraulic-actuated change over chute located under the head of BFC-2 belt conveyor.
These belt conveyors run continuously and have the dual drive unit system for stable
operation of blast furnace by connecting the coupling of a standby drive unit when the
duty drive unit is in trouble.
Metal detector is located on the BFC-2 belt conveyor and when the metal is detected
the BFC-2 belt conveyor will be stopped and alarm will give to HMI. And this will
also prohibit the gate of ore weighing hopper from open.
The undersize size fraction during screening sinter is sent via sinter fine conveyor
(FSC-1, 2) to two sinter fine. The small screened by a sinter fine screen is transported
to the small sinter bin and sinter fines are then removed by FSC-3 belt conveyor. And
the undersize size fraction during screening ore is sent via ore fine conveyor (FOC1,
2) to an ore fine bin.
All of ferrous belt conveyors run without stop during Automatic mode operation.
b. BFC-3 Belt Conveyor
The small sinter falls on to the small sinter gathering conveyor (BFC-3B.C) of the
capacity of 100 ton per hour by the vibrating feeder. The small sinter on the gathering
conveyor (BFC-3 B.C) feeds into the weighing hopper (Transfer house).
The belt conveyors have the dual drive unit system for stable operation of blast
furnace by connecting the coupling of a standby drive unit when the duty drive unit is
in trouble. Metal detector is located on the BFC-3 belt conveyor and when the metal
is detected the BFC-3 belt conveyor and related Feeder will be stopped and alarm will
give to HMI.
27
Blast Furnace
isdischarge on the charging conveyor in turn from the ore surge hoppers by batch call
from the furnace top PLC.
Each ore surge hopper and small sinter weighing hopper are mounted on load cells for
weighing purposes and has an hydraulic operated gate for ferrous discharge and a manual
gate for controlling of flow rate of ferrous discharge. The signal form the load cell will be
displayed at the main control room.
A level sensor is installed at each hopper to detect the high level of the filling materials.
When the detector is activated, it gives alarm at HMI, stops conveyor (BFC-2, BFC-3)
and closes all weighing hopper gate and small sinter vibrating feeder.
The surface of the sloping walls at the lower part of bins is lined with basalt material of
40mm thick. The sloping angle at the lower part of bins is limited to minimum 55degrees
(Valley angle) with regard to angle of repose of small sinter.
The vibrating feeder and manual gate are installed for discharging fine materials in the
bins. One sinter fine screen is below the vibrating feeder for screening small sinter of
sinter fines. And the level sensor at each bin is installed for measurement of the level of
deposit materials in the bins. The level signal is used to stop the FSC1, 2, SRC-2 belt
conveyor or FOC-1, 2 when the level is high.
28
Blast Furnace
840 6 Bins
26 6Hoppers
800 6 Bins
Ore Bin
450 2 Bins
Additive Bin
100 4 Bins
640 1 Bin
18 6 Hoppers
10 2 Hoppers
29
Blast Furnace
Nut Coke Weigh Hopper
6 1 Hopper
3 2 Hopper
100 1 Bin
d. Transfer Hopper
Coke Surge Hopper
45 2 Hoppers
50 2 Hoppers
15 1 Hopper
30
3,600 t/hr
2,200 t/hr
600 t/hr
600 t/hr
400 t/hr
200 t/hr
Blast Furnace
Small sinter Conveyor
600 t/hr
100 t/hr
1,000 t/hr
1,000 t/hr
450 t/hr
1200/hr
Electrostatic precipitator
Capacity
13,000 Am3/min
Screen Efficiency
90%
Operating condition
a. Operating time
24 hours/continuous
D) STOVES
The Hot Blast System is one of main facility to operate the Blast Furnace. The Hot Blast
System is consisting of the Hot Stove Shell, Process Mains, Heat Recovery System, Fan
& Blower, HS Refractory, Chimney stack and various equipments.
The hot air, which is made inside Hot Stove Shell as mixing the Combustion Air and
Mixed Gas (Blast Furnace Gas + Coke Oven Gas), is blown to the Blast Furnace through
the Hot Blast Main & Bustle Main.
31
Blast Furnace
The On Gas and On Blast Cycle is continuously repeated in order to blow the
constant hot air. The Waste Gas, which is occurred during the On Gas phase, is used
for heat recovery system and the used waste gas is discharged.
Used Abbreviations
32
PCS
PLC
VDU
RTD
LCS
LCP
SP
Set Point
MV
Manipulated Value
PV
Process Value
HB
Hot Blast
CB
Cold Blast
MA
Mixing Air
CA
Combustion Air
MG
Mixed Gas
BG
CG
WG
Waste Gas
Blast Furnace
SV
Shutoff Valve
GV
Goggle Valve
IV
Isolation Valve
SN
Snort Valve
CV
Control Valve
BV
Bypass Valve
VV
Vent Valve
1. Safety Precautions
Basic Safety: Observance of safety regulations and good training of the personal are
essential to prevent accidents and to achieve an optimum life time of the equipment.
33
Blast Furnace
2. Process Description
3. Ceramic Burner
The burners are designed for the following flow rates:
Maximum
gas
flow
(2
gas
flow
(3
operation)
Maximum
operation)
Minimum gas flow (at start of ramp- 14,000 Nm3/hr
up)
34
54,000 Nm3/hr
130,000 Nm3/hr
Blast Furnace
Maximum air flow (3 stove operation)
116,000 Nm3/hr
64,000 Nm3/hr
10%
The ceramic burner is designed to perform complete burning under minimum excess
air conditions. Normally the excess air percentage at the start of the gas period will be
approx 10%, at the end of the gas period the excess air percentage will be around 20
to 30%. The ceramic burner, which has been incorporated, consists of rectangular gas
slots surrounded by air slots on each side.
The hot blast main form an integral unit with no external thrust forces or
expansion forces transferred to the stoves or to the tuyere stocks.
ii.
The thrust forces over the entire length of the hot blast main are taken up by
external tie rods attached to the hot blast main through thrust collars.
iii.
The hot blast main refractory lining will comprise alumina bricks on the hot
face, with a back-up of three (3) insulation fire brick layers. This design will
accommodate high temperature fluctuations with cold blast mixing. The "flat
arch" design will be applied at all "T" junctions of the hot blast main. In this
design, dense refractory bricks are suspended from the steelwork by stainless
steel anchors.
5. Valves
Each stove is provided with hydraulic actuated shut-off valves for the various media
during the stoves alternating gas and blast cycles. The valve types are:
IISCO Steel Plant
35
Blast Furnace
i.
Water cooled refractory gate valve for isolation of the hot blast outlets and
back draft line (HBSV & BDSV)
ii.
Eccentric disc valve for isolation for pressurization and blow-off (SPSV &
SDSV)
iii.
Eccentric disc valves, for isolating the cold blast line from the hot blast main
(hot blast mixer) (MASV)
iv.
Butterfly valves for flow control (MGCV, CACV, MACV, SPCV & CBCV)
v.
Two/three lever valve for all other valves. (CBSV, MGSV, MGIV, CASV,
WGSV 1 to 6, BGSV)
Other valves included in the hot blast system, but not used in the stoves sequencing
operation, will be sized and specified as follows:
i.
Blow-off type butterfly valve with silencer, for venting the cold blast (snort
valve : CBSN)
ii.
Butterfly valves for isolation of the waste gas heat exchangers. (WGSV 9 to
11 & CASV, BGSV)
iii.
Pressure control vanes with electric motors and two/three lever valves for
isolation of the combustion air fans (Pressure control vanes: CFCV, Two/three
lever valves: CFSV)
iv.
Butterfly and two/three lever valves for isolation of the COG mixing
lines.(Butterfly: CGCV, Two/three lever valves: CGSV, CGIV)
v.
Butterfly and two/three lever valves for pressure control and isolation of the
BFG main (Butterfly: BPCV, Two/three lever valves: BGSV)
vi.
36
Blast Furnace
The stove is built from a construction of various refractory materials to allow it to
withstand the extremes and fluctuations of temperature. During the gas phase,
preheated mixed gas, together with a large quantity of preheated combustion air, is
burned.
The hot gases go along the dome and then through the small channels of the checker
work. The heat is transferred to the checker work and thus the stove is heated. The
waste gases are discharged via the heat exchangers and the stack. When a stove is
sufficiently heated, the gas phase is ended by shutting a number of valves. The stove
is then ready to supply hot air to the blast furnace, in other words, ready for the "On
Blast" cycle. During the blast phase, cold air is blown through the checker work in the
reverse direction. The bricks of the checker work give up their heat to the air passing
through; the air becomes hot and leaves the stove as hot blast. The hot blast enters the
hot blast main and goes to the blast furnace via a bustle main. A central air mixer is
tied in the hot blast main to obtain control over the hot blast temperature. Thus, the
stove functions as a discontinuous heat exchanger. Since the blast furnace needs a
continuous supply of hot blast, three stoves are available. An important task of the
control system is to take care of the control of the hot blast system.
Stove combustion is only one aspect in the control and automation of a hot blast
system. The functions for a complete control system can be divided into the following
four (4) areas:
i.
Stove combustion
ii.
Stove sequencing
iii.
iv.
37
Blast Furnace
product with low moisture content. The plant is designed to handle slag produced by the
furnace, considering the variation in quantity of slag flow and sequence of tapings.
The slag discharged from the blast furnace is separated from the iron at the skimmer and
flows through the slag runners towards the SGP. The two Independent slag granulation
systems granulate molten slag discharged from the blast furnace, each being sized for
maximum slag flow conditions. The molten slag discharged from the blast furnace is
rapidly quenched by water jets at the Spray Box and granulated. The slag sand with water
flows into the granulated slag basin via the Granulated Slag Trough. From there the
granulated slag is dewatered and removed by means of a Screw Conveyor discharging
onto a belt conveyor and conveyed to product silo or yard.
The quality of the produced granulated slag depends on the volume, pressure and
temperature of the water, as well as on the design of the blowing box and the chemistry
and temperature of the slag. Efficient de-watering system has been considered that
normal moisture content in granulated slag shall not exceed 12% after three hours storage
in silo. Granulated slag after dewatering was conveyed up to junction houses including
interconnecting conveyors between junction houses.
Blast Furnace
of a screw conveyor, discharged onto a belt conveyor and transported to yard or one
of two product silos subsequently discharged into road vehicles.Hot water overflows
from the granulated slag basin to the Rasman Filter (Mesh Roll Type) where fine slag
(wool) is removed.The fine slag deposits on the Rasman Filter are continuously blowdown into the granulated belt conveyor and transported to the product silo or
yard.Cleaned water from the Rasman Filter is directed, via a trough, to the Hot Water
reservoir. The water pumped to the cooling Tower and collected in the Cold Water
Reservoir is pumped to the spray box.
39
Blast Furnace
silos, discharged onto a reversible belt conveyor and discharged into the silos or the
belt conveyor interconnected to yard.The slag sand is further dewatered in the silos
and the drained water from the silos is pumped back to the granulated slag
basin.Discharging of the silos is done manually. The slag sand can be discharged onto
trucks or other devices by opening the pneumatic actuated gate after three hours of
dewatering.
5. Cooling tower
The cooling tower was designed to cool down the quantity of heat up to a slag flow.
Underneath the cooling tower, there is a cold water reservoir, collecting the cold
water from the cooling tower cells.
The two water supply pumps are continuously running. After the water supply pumps
are started, the cooling circuit pumps are switched on. After passing the Rasman
filter, the granulation water flows into the hot water reservoir. From the hot water
reservoir, the water is pumped by the cooling pumps to the cooling tower.
The cooled water is collected and stored in the cold water reservoir below the cooling
tower. The water level in the cold water reservoir is monitored by a level switch.The
water losses, due to the remaining moisture in the granulated slag and the evaporation
at the cooling tower, are compensated by make-up water, which is fed into the cold
water reservoir below the cooling tower. A level transmitter, located in the cold water
reservoir initiates the opening of the make-up water valve.
Blast Furnace
i.
ii.
Rasman Filter
iii.
Drum Dia.
Drum Width
Screen
Speed
Gear Box
Air Spry
Water Spry
Water Seal
Stir Water
SGP Cooling Tower
Granulated Slag
550T-slag/hr
13800mm
5556mm
2540mm
180kw x 4P x 415V x 50Hz
20Deg
2330mm
2540mm
20mesh
0.4~4rpm
Cyclo Drive(11kW)
10m3/min x 1.0kg/cm2
270L/min x 2.0kg/cm2
20L/min x 2.0/0.5kg/cm2
200L/min x 2.0kg/cm2
Capacity
Hot/Cold Water Temp.
3000m3/hr x 2sets
85/40 oC(at Wet Bulb 29 oC)
iv.
v.
vi.
700Ton x 2sets
Dry Pit: This is to be used only when SGP is not under normal operation or
during metal slag separation during the initial days of furnace commissioning.
Size
Number
13m(w)x35m(L)/1set
4sets(2sets/each cast house)
41
Blast Furnace
F) CDI
In the era of growing demand for adoption of energy savings measures for Blast Furnace
Iron Making Technology and decreasing oven availability at Coke Ovens throughout the
world and increasing coke price the PCI or CDI process came into picture. Moreover it is
an environment friendly system and it will be clear from the following data:
For production of 1T of BF coke, 450kg of CO2 is released in atmosphere
For 1T of hot metal production through BF route we emit 1500kg of CO2 in atm.
And to produce 1T of crude steel through CO-> Sinter Plant-> BF->SMS route 2T of
CO2 is emitted in atmosphere.
42
Blast Furnace
Substituting a considerable amount of coke by CDI, CO2 emission to the atmosphere can
be reduced.
43
Blast Furnace
Improved BF Cooling
i.
As coal injection results in higher heat load on furnace wall, the following
counter-measures are incorporated:
ii.
iii.
iv.
v.
vi.
7 nos. of N2 guns in each silo have been provided to tackle the jamming problem
of raw coal silo.
vii.
44
Top covers of bag filters will be rubber sealed to check air infiltration.
IISCO Steel Plant
BOF-CCP (SMS)
BOF-CCP (STEEL MELTING SHOP)
A) Introduction
The SMS is equipped with 2 Hot metal desulfurization stations, 3 BOF converters
each of capacity 150 T nominal capacity with bottom stirring facility along with Gas
cleaning plants, 3 on-line Argon rinsing stations, 2 Ladle heating furnaces, 1 RH
Degasser, Slag disposal area, Scrap storage and handling, liquid steel treatment and
casting ladle preparation facilities and other auxiliaries.
The BOF SHOP consists of the following bays:
i.
Torpedo-Cum-Desulphurization Bay
ii.
iii.
HM Receipt-Cum-Charging Bay
iv.
Converter Bay
v.
Slag Bay
vi.
vii.
viii.
A brief description of each station of Steel Melting shop of ISP Burnpur is provided
in the following paragraphs:
45
BOF-CCP (SMS)
Technical Data for Hot Metal Desulfurization Units
(1)
(2)
Number
of
ladles
2,500,000 tonne
for 30 (nominal)
treatment/station/day
(3)
Capacity of ladle
(4)
(5)
Free board
0.35 m (min.)
(6)
(7)
Operating features
(8)
Reagents
(i)
CAD 9 F3
(a)
Tech. CaC2
50-55%
(b)
Coal powder
4%
(c)
Fluorspar
3.5 %
(ii)
Mg 97
(a)
Mg
97%
(b)
Coating
3%
(9)
Injection rates
(12) Conveying
medium
of Dry nitrogen
reagents
(i)
Pressure
10 bar (min.)
(ii)
Purity
99.9 %
BOF-CCP (SMS)
(two scrap boxes in the scrap yard, one in the charging bay and one spare scrap box).
Each scrap box has a capacity of 25 m3.
The return scrap, process scrap and cold pig iron are handled in the scrap yard where
two magnet EOT cranes of capacity 20+ 20 T are available for loading scrap from the
storage pit into one of the scrap boxes. The scrap boxes are placed on mobile scrap
box transfers car (carrying capacity = 75T). After transfer to the charging bay, the
scrap will be charged into the converter by one semi portal crane of capacity 60+60T.
Charging can also be done by two overhead cranes via traverse (capacity = 280+80/20
T).
Charging of Scrap
3 min
b)
4 min
c)
16 min
d)
2 min
e)
5 min
f)
2 min
h)
Tapping
7 min
i)
4 min
j)
Deslagging
3 min
k)
Lining Inspection
4 min
Tap-to-Tap time
50 min
There are two hot metal charging EOT cranes of 280+80/20 T capacity and two repair
trolleys of capacity 15 T for maintenance of 280 + 80/20T capacity at the charging
bay. Further, there is one semi portal crane of 60 + 60 T capacity at the charging bay.
There are two cranes at lance repair bay, each of capacity 10 T.
IISCO Steel Plant
47
BOF-CCP (SMS)
Before charging, the converter is inspected for lining condition, after which scrap and
hot metal are charged. Cooling is provided mainly by scrap and cold pig iron and/or
Iron ore. The required fluxes for slag formation will mainly consist of burnt lime and
burnt dolomite. The specific material consumption (kg/T of crude steel produced) and
their composition in BOF converters as per detailed project report are as follows:
S.No. Material
Composition
Requirement
(1)
%C-3.8-4.3, %Si-1.2-1.4,
1080 kg/T
Hot Metal
%Mn-0.3-0.4, %P-0.2,-0.25,
%S -0.04-0.05. Temperature:
1250 - 1280C
(2)
Scrap
80 kg/T
(3)
Calcined
%CaO-84-87, %MgO-3.3,
80 kg/T
lime
(4)
Calcined
% CaO-53, %MgO-35, %
Dolomite
SiO2-3.5, % Al2O3-1.0, %
25 kg/T
The specific oxygen blowing rate will be in the range of 3.3 - 4 Nm/T min, which is
about
500 - 600 Nm/min. For top blowing the converters will be equipped with an
independent oxygen lance system consisting of two oxygen lances. One will be in
blowing position and the other one as standby. The bottom is equipped with an inert
gas (Ar/N2) stirring through bottom porous plugs which along with top lance blowing
help in achieving the close approach to the equilibrium of oxidation reactions. The
bottom blowing rate may vary from 1.8-9 Nm3/min (maximum 600 lpm). Closed
circuit cooling water system has been provided for lance cooling. After the blow,
sample of steel is taken and temperature is measured.
The analysis of steel sample is done in the site container laboratory. Tapping is done
after getting the final desired chemistry and temperature. Tapping temperature is
48
BOF-CCP (SMS)
about
1660- 1680C.
The liquid steel is then tapped into a 150 T capacity steel ladle, placed on steel
transfer car moving below the converter. Ferro alloy additions are made as per
requirement of the grade of steel. The required amounts of ferroalloys are added to the
ladle during tapping as per grade of steel. The ladle is stirred during and after tapping
for the homogenisation of temperature and composition of liquid steel. For this 3 nos.
on-line Argon Rinsing Stations (ARS) are installed. Following this, steel is analyzed
for composition and its chemistry and temperature are adjusted. If the temperature is
high, it is brought down by further rinsing.
The important operational activities at BOF converter shop have been as described
below:
1. Charging System for Fluxes and Coolants
Flux material for converters will be taken over at the top of flux bunkers within
the steel making plant for further distribution into the different bins. From the high
level bin system including vibrating feeders, weighing hoppers, chutes etc. the
material is charged into the converters continuously during the blow. Mainly,
fluxes such as burnt lime, burnt dolomite as well as coolants like raw dolomite
and iron ore are charged. The required burnt lime and burnt dolomite mixture will
be about 70-80 kg/T of crude steel produced. There are a total of 11 overhead bins
per converter for charging fluxes and coolants, with volume varying from
30-150 m3.
49
BOF-CCP (SMS)
converter platform. From here the high level Ferro alloy bins will be filled by
means of vertical and horizontal belt conveyors for further charging into the ladles
below converters. There are 8 bins in total for ladle addition each of capacity 10
m3 .
BOF-CCP (SMS)
flaring. The gas temperature at the ID fan outlet is about 80-85C. The average
composition of the recovered LD gas is as follows:
S.No. Gas
% composition
(1)
CO
65-70%
(2)
CO2
15-20%
(3)
N2
15-20%
(4)
O2
0.1%
Ar plug
Fig: Working of Basic Oxygen Furnace (Schematic)
The Standard Operating Practices for BOF operation are as follows:
i.
ii.
iii.
Order hot metal & scrap as per process aim calculation and ordering
calculation or as per turn down condition, of the previous heat
iv.
Lift the Hot metal ladle with Hot Metal Charging Crane
v.
If there is excess slag carry over, pour out the slag by slightly tilting
the ladle.
vi.
51
BOF-CCP (SMS)
vii.
Bring Hot Metal ladle near converter and engage 80 T hook for
charging.
viii.
ix.
Get the information about exact amount of Hot Metal & Scrap
x.
xi.
xii.
xiii.
Tilt the converter on charging side. Charge hot metal into converter.
xiv.
xv.
Inform to place empty slag pot and record slag pot no.
xvi.
xvii.
Start the main blow after main blow calculation or as per level I auto
mode blowing scheme by pressing START OF BLOWING push
button. Within 20 sec. of bath ignition press Ignition push button.
xviii.
xix.
xx.
xxi.
Check whether steel ladle has been placed or not. If YES gives
nozzle filling compound & if NO again inform to place ladle
immediately.
xxii.
xxiii.
52
i.
ii.
iii.
BOF-CCP (SMS)
iv.
xxiv.
xxv.
ii.
xxvi.
xxvii.
Ladle addition
ii.
iii.
See the slag & inform slag condition to blower. It will help to
decide addition at the time of splashing.
iv.
xxviii.
xxix.
53
BOF-CCP (SMS)
PROCESS FLOW DIAGRAM OF STEEL MELTING SHOP AT ISP
HOT METAL
FROM BF
OXYGEN
HOT METAL
DESULFURIZATION
IRON ORE,
LIME STONE,
DOLOMITE,
DOLOMITE
CONVERTER VESSEL
CALCINED LIME/
DOLOMITE
150 T
STEELLADLE
SCRAP
FERRO ALLOYS,
CARBURIZERS, LIME
ARGON RINSING
STATION
ARGON
LADLE FURNACE
RH DEGASSER
ELECTRICAL POWER
ALUMINIUM &
ALLOYING ELEMENTS
TURRET
(BILLET/BLOOM CASTER)
TUNDISH
WATER (CLOSED M/C
COOLING)
WATER (SPRAY
MOULD
/STRAND GUIDE
COOLING)
CAST STRAND
WITHDRAWL &
STRAIGHTENER UNIT
CAST BILLET/ BLOOM /BEAM BLANKS
WIRE ROD
MILL & BAR
MILL
BILLETS
BEAM
BLANKS
FOR SALE
BOF-CCP (SMS)
E) Slag Bay
The slag from the converter is transported in slag pots placed on slag transfer cars to
the slag handling area. The slag pot transfer cars have a capacity of 90 T. The slag
pots will be handled by overhead cranes for dumping into the slag pits. After that the
slag pots will be coated with a mixture of 1 part lime fines to 3 parts of water for reuse and transferred back. Slag pot size is 18 m3. There are three 120+50 T EOT cranes
and three 5 T capacity repair trolleys for repair and maintenance of 120+50 T EOT
cranes at the slag bay.
ii.
iii.
iv.
For preheating purpose, Coke Oven gas is used as a fuel. There is one EOT crane of
capacity 280 + 80/20 T and two 15 T capacity repair trolley for repair of 280 + 80/20
T cranes at Ladle preparation bay.
55
BOF-CCP (SMS)
sampling etc. The roof construction ensures extraction of fumes and dust generated
during arcing.
During emergency condition (power failure) the roof is cooled by the water from the
emergency overhead tank. The Ladle transfer car with the liquid metal can be
removed from below the ladle roof during emergency cooling.
The electrodes move up and down by means of hydraulically actuated mechanism.
The electrodes are clamped by clamping devices provided in the electrode arms,
which are in turn supported by electrode columns. The electrode columns are guided
by means of electrode guiding system consisting of a set of guide rollers.
This guiding system ensures proper vertical movement of the electrodes through the
openings in the roof. A central control panel is provided in the control room of the
furnace. All necessary controls (Level 1) are provided in the main control room.
BOF-CCP (SMS)
ii.
Signal the crane to lift the ladle and place on ladle transfer car.
iii.
Release the crane and signal the LHF control room operator to take
LTC along with ladle to treatment position of LHF.
iv.
Connect Argon hose along with a quick coupling valve to the ladle and
signal the control room operator to open the Argon purging with the
help of push button provided at the control desk.
v.
vi.
If purging is not observed, open the by- pass valve by pressing push
button provided at local control desk.
vii.
viii.
ix.
After sending the sample and getting the analysis, process the heat as
per process chart of the particular grade of steel & continue the purging
as per requirement.
x.
xi.
Talk to the caster main control room when the heat is required.
xii.
xiii.
Send the heat to caster by the crane after stopping the argon flow by
pushing the push button provided at the control desk.
57
BOF-CCP (SMS)
1386000 T (approx)
(2)
Heat size
(3)
28
(4)
32
(5)
(6)
Hydraulic fluid
(7)
40 mm/s (hydraulic)
(8)
180 bar
(9)
80 mm/s (max)
2.5 m (approx.)
450 mm
250 T
30 m/min
60 Nm3/h
Flow rate
(ii)
8 bar
0.5 Nm3/t
Pressure
6 bar
(ii)
Purging requirements
30,000 KVA, 33 KV
47 KA
9-13 mm
150 m/min
5 C / min
58
BOF-CCP (SMS)
(i)
350 m/h.
(ii)
(iv)
15 C
(v)
(vi)
4.5 bar
59
BOF-CCP (SMS)
The ferro-alloy system of both the Ladle Furnaces and the RH Degasser is fed by one
20 / 10 T overhead crane through bottom self discharge buckets.
24
(2)
1,000,000 T
(3)
24 m/min approx.
(4)
Vacuum Vessels
(i)
Diameter
3.1 m approx.
(ii)
Quantity
3 nos.
(5)
500 mm
(6)
Nozzle life
(7)
Alloy System
(i)
8, 10 m3
(ii)
(iii)
2, 500 kg
(iv)
Speed of conveyors
1m/sec
(v)
4, 5m3
(8)
Width of conveyors
650 mm
(9)
(i)
Burner rating
2.6 MW approx.
(ii)
Type
(iii)
15.5 bar
(iv)
(v)
CBM pressure
2.5 bar
(vi)
(vii)
(10)
Vessel Preheater
(i)
Burner rating
2.6 MW approx.
(ii)
Type
(iii)
15.5 bar
(iv)
60
BOF-CCP (SMS)
(v)
CBM pressure
2.5 bar
(vi)
(vii)
Vessel Cooling
(i)
Water quality
Soft water
(ii)
Water pressure
(iii)
Total flow
(12)
Argon pressure
16 bar
(i)
(ii)
10
(13)
(i)
Nitrogen pressure
16 bar
(ii)
N2 requirement (purging)
ii.
Casting bay
61
BOF-CCP (SMS)
iii.
Discharge bay
iv.
Storage bay 1
v.
Storage bay 2
K) Casting Bay
The bay accommodates casting machine up to the automatic torch cutting machine,
part of discharge roller table and dummy bar storage. The bay also houses tundish
preparation, mould preparation and segment maintenance areas, internal mould
cooling pump house, water distribution room, main electrical building, control rooms,
hydraulic room, etc.
Continuous Casting Machines (Billet Casters and Bloom Caster): The ladle is
transported to the ladle turret on the caster platform after the required metallurgical
adjustments are done LF/RH Degasser. The casting ladle is deposited by the crane on
the ladle turret. After moving to casting position, the ladle outlet is opened and liquid
steel flows into the tundish, which serves as an intermediate container/distributor
between the ladle and the mould.
Two tundish cars are provided and each car is equipped with a drive and positioning
device for tundish change and centering of the tundish outlet nozzles in to the mould.
The moulds are mounted on oscillating tables and the mould copper tubes are cooled
by closed primary cooling water system. Due to mould cooling, a solidified strand
shell is formed and is supported by mould foot rollers and strand guide. In the strand
guides, the hot strands are cooled by water spray cooling. At the end of the strand
guides, pinch roll straightening units are arranged to straighten and withdraw the hot
strand. These units also serve for the insertion and withdrawal of the dummy bar.
The dummy bar is used to seal the mould at the start of casting and to withdraw the
hotstrand to the withdrawal and straightening unit. After the separation of the dummy
62
BOF-CCP (SMS)
barfrom the hot strand, the dummy bar goes into its storage position in stand by for
the next start of cast.
The continuous caster consists of 6 and 4, respectively, independently controlled
strands for the production of billets / blooms / beam blanks. The strands are cut by
high duty torch cutting machine into the required lengths. The billets / blooms / beam
blanks are transported on the run out roller tables to the final stop. From there they are
either carried over to the cooling bed or are delivered to the hot charging system.
The cast billets, blooms or beam blanks will be charged to the proposed mills in either
hot or cold condition for which hot charging roller tables or cold transfer roller tables
shall be provided. All continuous casting machines are located in the casting bay.
There are two billet casters and one bloom caster. The bay dimensions are: 33 x 483
m. The casting platform of the bay is at 9.8 m elevation.
The standard operating practise for continuous casting machine is as follows
1. Preparatory jobs for start-up of Casting
a. Preparation of Dummy bar head for casting
i.
Adjust the Dummy bar head as per plan at intermediate platform (5.6m).
ii.
iii.
iv.
Installation of inset device for the dummy bar with the hook and pin for
protecting mould from scratches during dummy bar insertion.
v.
ii.
iii.
Lift Support roller for the Dummy bar on cutting approach roller table.
iv.
Fulfill all pre conditions and then automatic feeding can be started.
v.
Stop feeding of Dummy bar when Dummy bar is about 500 mm below the
mould.
vi.
vii.
viii.
Clean the Dummy bar head with compressed air for removing moisture
ix.
x.
63
BOF-CCP (SMS)
xi.
xii.
xiii.
ii.
iii.
iv.
v.
vi.
Oscillating Device
vii.
viii.
ix.
Check water tight connection between water box of the mould and lifting
table of the oscillation unit.
x.
Check water hoses for inlet and outlet for tightness and damages.
xi.
xii.
xiii.
xiv.
Tundish Preparation and Tundish preheating (for open stream casting and
stopper casting)
xv.
xvi.
In case of open stream casting fix the nozzle changing device with correct
calibrated nozzles.
xvii.
xviii.
xix.
xx.
Tundish Preparation and Tundish Preheating (for open stream casting and
stopper casting)
64
xxi.
xxii.
BOF-CCP (SMS)
xxiii.
xxiv.
xxv.
ii.
iii.
iv.
v.
Ensure that nozzle changer should be opened (for open stream casting).
ii.
iii.
iv.
v.
vi.
f. Secondary Cooling
i.
ii.
iii.
iv.
ii.
iii.
iv.
v.
65
BOF-CCP (SMS)
e. Check mould oil lubrication system readiness only for open stream casting.
f. Select correct casting mode for both open stream and stopper casting.
g. Ensure all systems to be in automatic mode.
h. Following sub-points should be ready:
i.Cans with mould lubrication oil for first adding of oil into the mould or
for
emergency cases (only for open stream casting).
ii.
Casting powder and shovel for adding casting powder into the
mould (only for stopper casting).
iii.
Oxygen lances for tundish nozzle lancing (only for open stream
casting).
iv.
v.
vi.
vii.
Sampling devices.
viii.
Temperature tips.
ix.
x.
Ladle shroud.
i. Slag pots, emergency launders and emergency ladle must be capable to receive a
sufficient quantity of liquid steel in emergency situation.
j. Ensure swiveling launders on tundish car must be empty (only for open stream
casting).
k. Check torch cutting machines to be ready.
l. Ensure lamp test on all operating panels should be done.
m. Ensure closing of the cooling chamber doors.
3. Casting Operation
1. Check all preconditions on OS2.
2. Select CAST mode on OS1.
3. Arrival of heats with correct temperature and sample analysis on ladle turret
4. Place the ladle cover on ladle.
5. Connect hydraulic cylinder with ladle slide gate.
6. Switched off the tundish preheater and then tilted upwards.
7. Close the tundish outlet with blind plate of nozzle changer.
66
BOF-CCP (SMS)
8. Remove cover sheets above the mould opening.
9. Ensure availability all necessary tools (Slag fishing rods, oil cans etc.)
10. Ensure tundish car in upper position.
11. Place tundish car in cast position.
12. Center the tundish above mould openings.
13. Lower the tundish to the casting start level.
14. Place swiveling launders below the nozzles.
15. Rotate ladle turret in cast position.
16. Fix the ladle shroud by means of hydraulic cylinder
17. Open radioactive source for mould level measurement.
18. Ensure tundish weight should be zero in cast position.
19. Ensure READY FOR CAST is glowing permanently on OS1.
20. Open the ladle slide gate, in case not open then ladle shroud should be
removed and by lancing ladle should be opened.
21. Close the ladle slide gate when steel weight in tundish is 15 T (approximately)
and fix the ladle shroud in case ladle is opened by lancing
22. Ensure tundish covering powder to be thrown in to the tundish during the
filling of tundish.
23. Start outer strands 1 and 6 in the beginning followed by 2 and 5 and then
finally 3 and 4.
24. Remove the launder after 5 secs.
25. Fill the mould for 5 secs and then swiveling launder placed for 5 secs and then
again remove the swiveling launder.
26. Fill the mould to its 25 % capacity.
27. Select start cast by pressing button on OS1.
28. Ensure start of withdrawal drives in cast direction.
29. Ensure start of mould oscillation
30. Ensure start of strand tracking.
31. Ensure secondary cooling zones as per tracking system.
32. Ensure switch over from DUMMY BAR PRESSURE to HOT STRAND
PRESSURE to be carried out as per tracking system.
33. Check dummy bar disconnection which will initiate:i.
ii.
67
BOF-CCP (SMS)
iii.
34. Ensure length measuring system of the torch cutting is initiated as per tracking
value.
35. Select ladle slide gate operation from manual to AUTO on LC116 when filling
of tundish reaches its set value.
36. Select manual operation by pressing OPEN or CLOSE as per requirement.
37. Select AUTO mould control by pressing AUTO switch on HMI as per
requirement.
38. Take sample from tundish after 10 minutes of start cast.
39. Take first temperature immediately after the start of cast.
40. Take second temperature after 15 minutes and third one as per need.
41. Check mould, if found abnormal take corrective actions.
42. Ensure regularly amount of lubrication oil.
43. Fixed ladle slide gate in AUTO mode by pressing AUTO switch
4.
End of Cast
1. Empty of ladle
i.
Watch the slag when Ladle weight is 20T; if slag appears close the
ladle slide gate.
ii.
iii.
2. Empty of tundish
i.
ii.
iii.
ii.
iii.
iv.
Emptying of tundish
68
BOF-CCP (SMS)
a. Stop the withdrawal drives by pushing STOP on OS1 for 1 minute at the end
of cast.
b. Ensure the change of machine status to CLEAR mode by pushing the button
CLEAR.
c. Withdraw the strand after waiting for 1 minute by pressing START from
torch cutting control room.
d. Activate automatic CLEAR machine mode.
e. Press CLEAR on OS1.
6. Break-Out
a. In case of breakout during cast-start, close the tundish and stop withdrawal
units of affected strand.
b. In case breakout during casting:i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
Ensure cooling down to be carried out with maximum spray cooling water.
xii.
xiii.
69
BOF-CCP (SMS)
d. Availability of experienced crew to handle
derailment/disengagement of moving component
e. Provision for pouring of residual slag metal in emergency
containers
f. Contingency evacuation arrangement for solidified slag, metal
skull of steel ladle if generated during the process
g. Availability of new set of relined hot ladle for continuation of the
process
h. Availability of experienced personnel/representatives from
(2)
Machine radius
9000 mm
(3)
1200 mm
(4)
(5)
40 m/min
(6)
Max. 27 m
(7)
(8)
(9)
Casting mode
Cutting device
i.
ii.
6, 9, 12 m
approx. +800 mm
6 m/min
40-300 cycles/min
70
BOF-CCP (SMS)
(18) Length of Copper mould
900 mm (approx.)
(i)
100x100 mm2
(ii)
120x120 mm2
(iii)
150x150mm2
(2)
(i)
120x120 mm2
(ii)
150x150mm2
(3)
(i)
Open stream
42-72 min
(ii)
Closed stream
55-79 min
(4)
(i)
Mould cooling
(ii)
(iii)
(2)
Bow radius
12000 mm
(3)
2000 mm
(4)
Max. 37.1 m
(5)
Cutting device
(6)
(i)
Bloom thickness
(j)
71
BOF-CCP (SMS)
(7)
(i)
Blooms
(ii)
Beam blanks
(8)
6 to 12 m
(9)
832,000 T
(10)
0-300 strokes/min
(11)
0 - 12 mm ( 6 mm)
(12)
800 mm (approx.)
(i)
Bloom 235x235 mm
1.3-2 m/min
(ii)
Bloom 280x200 mm
1.3-2 m/min
(2)
(i)
292x205x85 mm
2.2 m/min
(ii)
430x350x90 mm
1.4 m/min
(iii)
686x350x90 mm
1.2 m/min
(3)
(i)
Bloom (200x280)
42.7-65.6 min
(ii)
Bloom (235x235)
43.3-66.5 min
(iii)
38-54.1 min
(4)
(i)
Mould cooling
(ii)
(iii)
72
BOF-CCP (SMS)
One cantilever crane of capacity 7.5 T is dedicated for mould preparation activities, adjacent
to tundish preparation area.
L) Discharge Bay
The bay accommodates remaining part of discharge roller table, cross
transfermechanism, cooling bed, end stops, marking machine, etc. This bay also
accommodates special roller tables for transfer of hot and cold billets from cooling
bedto billet storage bay I & II and up to Mill bay. The billets are also stored in this
bayand dispatched through a rail track and special roller table to mill. This bay shall
beequipped with two EOT cranes of capacity 25/5 T with rotating tongues and
magnets.A control room for transfer and storage of billets has been provided in this
bay.
73
BOF-CCP (SMS)
h. Fire extinguishers/fire buckets and drums must be kept ready at work site.
2.
Gas safety
a. Storage of gas cylinders is forbidden near the furnaces
b. Empty gas cylinders must be taken out of the shop after usage
c. Take care when working with oxygen. Oil and oxygen form a very dangerous
combination which can lead to serious accidents.
d. Clothing saturated with oxygen should be taken of immediately
e. Working with leaking oxygen hoses or couplings is prohibited
f. Usage of inert gases during operation must be done carefully
g. During Coke Oven gas pipeline maintenance, water seal of Coke Oven gas
must be ensured
3.
Fire safety
a. The prohibition of smoking established in the identified operational areas must
be observed conscientiously
b. Fire protection equipment such as fire extinguishers, hydrants, fire-escape
ladders etc must not be used for purposes other than originally intended.
c. Used fire extinguishers must be returned to the competent department under
indication of the reason for the use.
d. Oxygen must not be used for blowing down or blowing out clothing or for
ventilation.
4.
74
BOF-CCP (SMS)
g. Ensure that all persons on the charging side of converter are warned by horn
signal before charging of hot metal
h. Person giving signal to move to an area where he cannot be hit by splashes
during pouring
i. Charging ladles to be checked regularly for sticking slag and hot metal skulls
j. During blowing process dog house doors have to be closed
k. No one should be near vicinity of converter during blowing period
l. Slag pot must be dry. Keep a safe distance from the converter when slag is
being tapped into slag pot.
ii.
iii.
iv.
b. Turret
i.
ii.
iii.
75
BOF-CCP (SMS)
iv.
c. Tundish
i.
ii.
Safety appliances like fire retardant aprons, full leather gloves, blue
glass fitted helmets, LFC, safety shoes while on job to be used.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
xiii.
xiv.
xv.
xvi.
Ensure during travelling motion of the tundish car acoustic of siren and
flashing light should be activated.
xvii.
xviii.
76
BOF-CCP (SMS)
xix.
Ensure moulds and all materials used for packing as well as casting are
free from grease and humidity during packing of the Dummy bar
heads.
xx.
xxi.
xxii.
xxiii.
xxiv.
xxv.
xxvi.
7.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
xiii.
xiv.
xv.
xvi.
77
BOF-CCP (SMS)
xvii.
xviii.
xix.
xx.
xxi.
xxii.
xxiii.
xxiv.
Circuit modification to be done only with utmost care and after due
approval
78
xxv.
xxvi.
xxvii.
C&A
COMPUTER & AUTOMATION DEPARTMENT
A. Introduction
Expansion work of IISCO steel plant had been taken up in the year 2008 to make it a 2.5
MTA steel plant. With expansion,came the state of art technology. With the state of art
technology, came the process control computers. Computer & Automation (C&A)
department was formed in late 2011 to manage the process control system &
automation.The department C&IT (Computer and Information Technology) existed in
IISCO to carry the office and business computerization in the areas of personnel, finance
and materials.
B. Structure
C&A Department functions under GM (Electrical) under ED (Works). It is headed by
DGM(C&A).For ease of functioning the areas of automation under C&A has been
divided into six basic zones Raw materials, Iron, Steel, Rolling, Services and Office.
79
C&A
.
C. Areas of automation in ISP is as follow
AREA PKG
NO
OHP 01A
CHP 01B
PKG NAME
PARTY M/S
MCNALLY BHARAT
L&T
NA
COB # 10
TATA STEEL
O2
COB # 11
GIPROKOK/BEC/SOY
03
GIPROKOK/BEC
CHCS (LEVEL 2)
TATA
AUTOMATION
CPMS (LEVEL 2)
SIEMENS
SIEMENS
BMP
SP
01C
O6
Base Mix
Sinter Plant
L&T
L &T/OUTOTEC
ABB
ABB
BF
O7
Blast Furnace
POSCO/NAGARJUNA
O8
11A
CISRI/BEIJING
ELECT CO
SOMANI/KUTTLER
LEVEL#2
SIEMENS
SIEMENS
11B
SMS SIEMAG
11C
SMS INDIA
CO
SMS
AUTOMATION
SYSTEM
ROCKWELL
ABB
FL SMIDTH
LEVEL#2
SIEMENS
LEVEL#2
SIEMENS
LEVEL#2
SIEMENS
ABB
SMS MEER
SIEMENS
BRICKMONT
ROCKWELL
16
DANELLI
SIEMENS
MRS
21
AREVA
E-TERRA
EMC
69
Energy management
MASIBUS
CITECT
12A
13
Mills
14
15
80
SEIMENSVAI
C&A
It is apparent in the above table that there is a wide variety of system implemented and
technology suppliers have customized products. Keeping this in view dedicated
manpower of C&A departmenthas been put in the various automation areas.
D. Scope of Work
For the efficient running of the Plant, smooth working of the automation systems is
essential. Considering this the roles and responsibilities of C&A Deptt has been framed
as mentioned below.
1. Hardware & Software maintenance of Level 2 system.
a. Hardware
i.
Periodic Preventive Maintenance of Systems
ii.
Attending to Hardware problems in System and Network
b. Software
i.
Periodic back up of System Software, Application Software, Database
ii.
Trouble shooting in System Software, Application Software
iii. Maintenance of Database (Maintaining optimal size)
iv.
Achieving of Program and Data
v.
Modification of Application Software as per requirement
vi.
Generation / Modification of Reports for MIS as per requirement
vii.
Maintenance of Automation Interfacing between Departments
2. Maintenance of HMI servers,OPC servers & Operator work stations installed in
all automation system.
i.
Trouble shoot of HMI problem
ii.
Periodic Preventive Maintenance of HMIs
iii. Ensure availability of ready spares
iv.
Ensure communication of OPC Server
v.
Regular backups of Application Software
vi.
Periodic backup and maintenance of Database
vii.
Updating of Anti-Virus Software
3. Maintenance of SCADA system of Energy Management & Power Distribution.
i.
Install/uninstall of Software
ii.
Backupof Application
iii. Maintenance Software and application
iv.
Database Management
v.
Maintenance of Web Server and Client Server
vi.
Trouble shooting of System S/W and Application S/W
vii.
Maintenance of OFC & UTP network
IISCO Steel Plant
81
C&A
Description
sensors/measuring devices in field e.g. thermocouples, pyrometer
Controllers, PLC/DCS units
Mathematical and logical models to refine and generate set point for level 1
Supervisory control and data acquisition system
Programmable logic controller
Distributed Control System
Human Machine Interface
OLE for Process Control
Light/Line Interfacing Unit
IISCO Steel Plant
C&A
FO
OLM
Fiber Optic
Optical Link Module
83
C&IT
COMPUTER &INFORMATION TECHNOLOGY DEPARTMENT
A) Introduction
C & IT department formerly known as Data Processing Centre came into existence in
1943.
departments like Finance, Personnel and Training. With the advent of computers in
India this department has been entrusted with the work of computerization of various
departments of the work. This department was renamed C&IT in 2006. Earlier this
department used to operate from Evelyns lodge but later it was relocated to Burnpur
works in 1999. Presently this department is located at the ground floor of the general
office building of Burnpur works. This department deals with the information
processing need of the entire Burnpur works. Earlier it used to serve the various data
processing needs of the collieries at Chasnalla, Jitpur & Ramnagore as well as branch
offices of ISP at Kolkata&New Delhi.
Year
Major Events
The data processing started using UNIT Recorder M/c and accounted for
1943
1966
84
C&IT
This department was transferred to Evelyn lodge and it started functioning
1973
1981
1986
1992
under severe financial crisis for which this department faced a severe fund
crunch. This forced this department to upgrade its infrastructure on rental
basis and this practice was discontinued in November 2013
SUNE450 server with Solaris operating system ORACLE RDBMS server
1999
2006
2010
2011
2012
2013
85
C&IT
Cenvat & Input Tax credit module
CMMS
Materials Management & Price Stores Ledger Interface with Finance
Hospital Management Information System
Payroll and Allied systems like PF, SESBF, Final settlement, Income Tax, ETDS etc.
Employee Family benefit Scheme
Town Department Modules: i. Quarter Management System
ii.Estate Outsider Billing system
Training Department Modules
Human Resources Information System
Stores Accounting
Procurement & maintenance of H/W & S/W throughout the plant.
Administration of Database, Systems, Network, Intranet Site (Portal), Mail-Server etc.
Extension of network, Enhancement of application modules and maintenance of
existing Software
Visitor gate pass module.
Video Conferencing
Antivirus Server
Internet access to entire plant via proxy server
A number of projects are currently taken up by C&IT for implementation. They are in
various stages of planning and implementation. These projects once implemented will
change the very way day to day business is carried out in SAIL-ISP.
i.
Implementation of ERP
ii.
iii.
iv.
86
v.
vi.
C&IT
D) Infrastructure
Major architectural components in IT infrastructure in SAIL-ISP can be summed up
as follows:
a. Two NETRA T4-1are deployed to host Oracle 11g Database in RAC
environment.
b. Two no of SUNX3-2 Servers deployed with OVM as application server
host and willhave multiple virtual application servers on top of these two
servers to facilitate loadbalancing and high availability of Application
server.
c. EMC VNX 5100 storage is a datacenter class storage being used as a
shared storage.This storage has RAID -1 group dedicated to production
database and application
d. SL150 tape library is used as central tape backup.
e. EMC concertrix DS300B series SAN switch is used as a central SAN
switch for RACimplementation.
f. ORACLE VM3.2 is used to create virtual servers for Application layer
infrastructure.
g. Microsoft TFS is used for version management of Application.
h. EMC networker software is used for backup management of database.
i. CA infrastructure manager is used
j. Oracle Ops center is used for system management of Oracle H/W system.
E) Technical specifications
Technical specifications of the server hardwares installed at Dept. of C&IT is
detailed
In the following section.
1. Hardware
a. Application Server
87
C&IT
MB L3-cache with QPI technology
Memory Slots
16 DIMM Slots
Memory required
16 GB DDR3 RAM
Memory expandability
Storage
Expansion slots
4 PCI-E slots
Form Factor
Rack
Load balancer
b. Database Server
SUN/Oracle Netra SPARC T4-1 server
Processor
Memory required
32 GB DDR3 RAM
Memory expandability
Storage
Expansion slots
3 PCI-E Slots
Form Factor
Rack
OS Support
Solaris 11
Operating System
Solaris 11
Clustering Software
c. Proxy Server
SUN SERVER X3-2
Processor
88
C&IT
Memory Slots required
16 DIMM slots
Memory required
16 GB DDR3 RAM
Memory expandability
Storage
Expansion slots
4 PCI- E Slots
Form Factor
Rack
16 DIMM slots
Memory required
16 GB DDR3 RAM
Memory expandability
Storage
Expansion slots
4 PCI-E Slots
Form Factor
Rack
Backup Software
NetWorker
Disks
Scalability
Cache
IISCO Steel Plant
Memory 8 GB
89
C&IT
Availability
This
is
feature
of
the
native
Virtualisation support
Software
2. Software
Most of the web based applications that have been implemented and those under
development are developed using ASP.NET. The two tiers applications have been
developed using VB.NET.The backend data source in both cases is Oracle
11g.This run in RAC environment enabling high availability in case of failures.
3. NETWORK
To support the various web based application and other communication related
needa robust fiber optic network has been implemented and maintained by C&IT.
At present the network covers the entire old plant, hospital, Town Administration
office and CEOs office.There are plans to extend this network to various sites in
the new plant. The diagram of the existing network is provided in the following
page.
90
C&IT
F) Diagram of Existing Network
91
C&IT
G) Conclusion
C&IT department has evolved over the years from Data Processing Centre to one point
solution to various technical needs of the plant. With time this department has provided
various IT solutions to slow and manual works. This enabled faster and accurate
completion of the job without much manual intervention.
Internal Mailing and portal system has enabled ISP to reduce paperwork and introduced
a new medium of official communication between employees.
Payroll,
management etc. are online modules developed and maintained by C&IT have made lot
of business process in respective areas easier than before. The application has improved
the way the data is stored and preserved in a standard format in a centralized database.
With the implementation of ERP the business scenarios are going to change further in
the days to come and the role of C&IT will be more prominent in such a changed
scenario.
92
A) Introduction
Capital Repair was formed in the year 1979 primarily to carry out capital repair of Blast
Furnace. Later on it got involved in weekend and major repair of Rolling Mills, Coal
Handling Plant, Power Blowing Station, Coke Ovens, overhauling of Saturators,
Detarrers at Coke Ovens by product plant, Structural Repairs and emergency requirement
of the plant.
B) Manpower
At present the Department is having only one section consisting of
Executives - 4 Nos.
ISP Employees & Ex ropeway workers. 18 heads
Annexure Workers - 36 heads.
93
CCAS
CENTRELIZED COMPRESSED AIR STATION
A) Introduction
CCAS supplies Plant Grade Compressed Air (PGCA) as well as Instrument Grade
Compressed Air(IGCA) to all units in the new plant viz BOF,CCP, Coke Oven, Power
& Blowing Station (PBS), Blast Furnace, Mills, By-Product Plant, Sinter Plant, etc. (at
a set point pressure of 7.73 kg/cm2 .) through a dedicated network of Interplant Pipe
Lines.
IGCA is that part of air which is passed through air dryer so that it is devoid of
moisture & distributed to all units through a dedicated of Interplant Pipe Lines. IGCA
is used mainly for pneumatic valve operations and cooling purposes where as PGCA is
used for blowing and cleaning purposes.
a. Centrifugal Air Compressors
b. Air Dryers
c. Pump House
d. Cooling Tower
e. Water Treatment Plant
B) Centrifugal Air Compressor:
There are five nos. Centrifugal type three staged compressors of M/S Ingersoll Rand
make in CCAS.
Main Specification of these Compressors are given below:
Model
C3000-C150MX3
Speed
32000rpm
Flow rate
18000Nm3/hr
Power Rating
2.5MW
ii.
Work performed on the air by rotating impeller increase the pressure and
velocity with a subsequent drop in velocity through the diffuser resulting in a
further increase in pressure.
94
CCAS
iii.
Typically the 2/3 of the pressure developed occurs in the impeller area and 1/3
in the diffuser area.
Flows through the first stage Rotor Assembly ------------------ gains velocity
A
Intercooler
---------------------------------------------removes
heat
to
improve
efficiency
95
CCAS
Excess Air passes through the Bypass Control Valve to Silencer to atmosphere.
96
CCAS
C) Air Dryers: Compressed Air Dryers are designed to be non-cyclic, direct expansion type and to
provide high quality compressed air, free of moisture and offer minimum
maintenance. There are 10 nos. air dryers of M/S Sanpar make installed in CCAS
(Model : SXD 1500W, Capacity : 9000 Nm3/hr,
Type: Refrigerant type
Specification of these Air Dryers are given below:Type of Dryer
Non-cyclic,direct
expansion
Refrigeration type
Model No.
SXD 1500W
Capacity
Nm3/hr
Operating Pressure
8 bar (g)
46 C
+3 C
Refrigerant
R407c
Power Supply
Type of Condenser
Water Cooled
32 C
water connection
DN 40
DN 250
Dryer Design
97
CCAS
98
CCAS
Process Description
Refer Schematic diagram enclosed.
The entire Refrigerated Compressed Air Dryer consists of two cycles:
i.
ii.
ii.
The high pressure and high temperature refrigeration passes through Water-cooled
condenser.
iii.
iv.
The high -pressure low temperature refrigerant passes through the filter dryer.
v.
vi.
vii.
After expansion, the refrigerant becomes low pressure, low temperature liquid.
viii.
ix.
The liquid refrigerant boils and get itself converted to refrigerant vapor, thanks to the
hot compressed air passing through the evaporator.
x.
After the heat exchanged and having converted into vapour, refrigerant vapours returns
back to the compressor and the cycle repeats in the closed manner.
xi.
A Hot Gas Bypass valve is incorporated to ensure that during partial thermal load on
the dryer, liquid refrigerant do not enter the compressor.
The wet, hot, filtered compressed air enters the Air-to-Air heat Exchanger.
ii.
In the air-to-air heat exchanger the incoming wet air is pre-cooled using the outgoing
cold air. The air-to-air heat exchanger, which acts as a pre cooler, reduces the
temperature of the incoming compressed air by exchanging heat to the outgoing cool
air. Condensation taken place during this pre-cooling of compressed air is discharged
through an automatic drain valve.
iii.
The pre-cooled compressed air enters evaporator and gets further cooled to its Pressure
Dew Point by the refrigerant passing through the evaporator.
99
CCAS
iv.
The condensed moisture is separated through demister pad, discharged through the
condensate Automatic Drain Valve.
v.
The cold compressed air passes through the Air-to-Air heat exchanger and gets
reheated. Here the air-to-air heat exchanger acts as a re-heater.
vi.
The cold air having got heated up gets the relative humidity lower and dry.
Condensate discharge:
The condensate that gets collected in the demister is discharged through the condensate drain
tap.
Dew point indicator:
A dew point sensor, which is located at the moisture separator, gives signals to the dew point
indicator of the panel. Thus, ensuring continuous visual indication of the dryness of the
outgoing air.
Start up & Operation:
Before starting the dryer check:
i.
ii.
The air inlet valves are closed and that there is no airflow across the dryer.
iii.
iv.
Note: Ensure that crankcase heater is on for a minimum period of 4 hour before switching ON
the dryer for the first time or when the Dryer is being switched OFF for more than 6 days.
Starting the dryer:
i.
To start the dryer turn the rotary switch to ON position. Alarm & OFF indication
Allow
approximately
five
minutes
for
the
dryer
to
achieve
operating
temperature/pressures.
100
CCAS
v.
Open the air inlet valve slowly at first to pressurize the dryer. Now open the outlet
Before stopping the dryer ensure that air supply to the dryer is stopped.
ii.
iii.
Compressed air should never be passed through the dryer when dryer is in OFF
condition.
Maintenance:
To ensure that dryer operates efficiently, periodic maintenance described below should be
carried out.
Weekly:
i.
Monthly:
Electrical
a. Check for any loose connections in the electrical panel box.
Compressor
a. Check the oil level in the compressor sight glass, check for loose connection
and running
b. Amperage of the compressor.
Condenser
IISCO Steel Plant
101
CCAS
Check for leakages in the water connection and setting of water pressure valve.
Annually:
a. Dismantle the drain completely and clean all the components.
b. Check the power consumption of the refrigerant compressor.
D) Pump House
There are 6 pumps installed in CCAS for following purposes.
Function of Pumps House:
i.
For cooling of compressors & its accessories : 4nos. cooling pump (2W+2S)
ii.
For Make Up water in the water circuit system: 2 nos. pump (1W+1S)
UP80/30
Head
30 meter
Size
80125mm
Discharge
60m3/hr.
Speed
1460rpm
Pump input
MFG
Coupling Detail
Type Love-joy type flexible coupling (SW=150)
Size
102
2542, No.-50/89533
CCAS
04
Pump type
UP250/38
Head
15 Meter
Size
250250mm
Discharge
900m3/hr.
Speed
1485rpm
Pump input
MFG
COUPLING DETAIL
Type Love-joy type flexible coupling (SW=150)
Size
2542, No.-50/89533
D. Cooling Tower
Cooling tower is used to reduce the temperature of hot water that comes out of the
equipments like compressors, dryers, oil heat exchanger etc.
The cooling tower used in CCAS is of M/S Southern Cooling Tower(P) Ltd. make,
Crossed Flow Forced Draft type & there are 3 cells in unit.
E. Water Treatment Plant
Water Treatment Plant comprises of Chemical dosing, RO plant & Duplex Filter.
a) Chemical Dosing:Chemical treatment on the water is done in two phases in the water
treatment plant viz. online chemical dosing & Biocide Dosing into the sump. The details of
the chemicals used are given below:-
103
CCAS
Polymeric Dispersant
(Zeo-291)
regular dose-2.33Kg/Day
Scale cum Corrosion Inhibitor
(Zeo-293)
regular dose-1.43Kg/Day
Salt (Zeo-105)
regular dose-20.00Kg/Month
b) RO Plant:
RO System
70Kg./Month
166.6Ltr./Month
c) Duplex Filter:
The Duplex filter used for the filtration of the water that is entering the compressors. The
Duplex Filter used in CCAS is of M/S Filtration Enggs Pvt. Ltd. It comprises of two
vertical Simplex Filter vessels in which SS elements are properly fitted. The filter has
side entry with outlet at the opposite direction. The two nos. of Simplex Filters are
connected by means of four nos. of butterfly valves. The filters are switched from
standby mode to operation mode using these butterfly valves. When one filter is in
104
CCAS
operation, the other is closed and the element can be taken out for cleaning or backwash
purposes. There is thus zero down time in this design.
105
CCMD
CENTRAL CRANE MAINTENANCE DEPARTMENT (CCMD)
A) Introduction
Central Crane Maintenance Department (CCMD), recognized as a critical equipment area
is functional under M.E. (Steel) section of Old Plant.
ii.
iii.
iv.
Keep a watch on proper operation of EOT Cranes and highlight any case
of misuse.
v.
vi.
In addition to the above, CCMD has extended its presence to New Plant and is currently
involved in the following activities:
106
CCMD
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
107
Coke Ovens
COKE OVENS
1.1597Mt/yr
0.8814 Mt/yr
0.7757Mt/yr
0.1057Mt/yr
42365Nm3/hr
The above figures have been worked out based on the following data/norms
Useful oven chamber volume
Gross coking time
Dry equivalent bulk density
Generation of coke oven gas
Yield of dry run of oven coke from dry blend
Yield of dry blast furnace coke(25-80mm)from run-of- oven
coke
Yield of dry coke breeze(-25mm) from run-of-oven coke
41.6m3
17hrs
0.74t/m3
320Nm3/t of dry coal blend
76%
88%
12%
Description
Size
Ash
VM
Moisture
Coking Index
Unit
mm
%
%
%
Range
0-50
11.0 max
25
6-8
Above 20
IISCO Steel Plant
Coke Ovens
6
7
8
9
10
No.
%
G5
6.5
1.14-1.25
ddpm
C
C
%
600-2000
60
410 15
0.6 max
The coal blend is crushed to 80% (-3mm) in the Coal Handling Plant before being fed to
coal tower of Coke Oven Battery no.11
3. Coke Quality
The coke produced from the coke ovens is of good quality and strong enough to be
suitable for the use in the large blast furnace and have the following characteristics
Coke Ash
V.M.
M40
M10
CSR
CRI
14.5%max
0.8% max
82
7 max
60-62
24 max
4. Basic Design
i.
Top charged, Compound, twin flue, under jet, regenerative heating with partial
recirculation of waste gases.
ii.
iii.
Double gas collecting main (one in pusher side and one in coke side)
iv.
Two waste heat tunnel on pusher side and coke side and
v.
vi.
5. Basics of Battery
i.
Battery refractory
ii.
Civil work viz. nozzle deck and buttress walls, service platforms and benches
chimney and waste gas tunnel
109
Coke Ovens
iii.
Battery anchorage system consisting of flash plates, buck stays tie rods and
springs
iv.
v.
Under jet heating system for both coke oven gas and mixed gas with
computerized combustion control system.
vi.
vii.
viii.
ix.
Oven machines power trolley rails/ collector other than coke car power trolley
x.
Oven top raw gas off-take system and charging hole lids and frames.
xi.
Charging emission control system with high pressure liquor aspiration system,
water sealed AP caps etc.
xii.
xiii.
Spillage conveyor on pusher side and coke side service platform for mechanized
cleaning of service plat form with disposal system.
xiv.
End bench repair facilities for doors and machines including stationary high
pressure hydro jet cleaner.
xv.
xvi.
xvii.
xviii.
Coal tower of capacity 4000t with SS lining coal tower gates, skip hoist, and
other associated facilities.
xix.
Indoor pipelines consists of CO gas line for under firing, mixed gas line for
under firing, supply and return ammonia liquor line, compressed air line,
waterline steam line and gas condensate service
110
xx.
xxi.
xxii.
Coke Ovens
6. Pollution Control
The new battery meets the norms published in official gazette by MOEF (Ministry of
Environment and Forest). Government of India dated 3rd February2006 for by-product
recovery type coke ovens.
The following pollution control facilities are incorporated:
a. Zero-leak doors with matching door frames along with cleaning and maintenance
facilities.
b. Zero leak charging hole lids and frames along with cleaning and luting facilities.
c. Water seal AP lids and frames on pusher side and coke side has been provided.
d. High pressure ammoniacal liquor aspiration systems to achieve emission free
charging of ovens.
e. Leak proof stand pipe/goose neck/valve box assembly.
A dust free coke pushing system is provided for the localization of dust emissions during
coke pushing. The system comprises the following facilities:
i.
ii.
iii.
A stand-alone unit for the treatment of dust laden air. The dust treatment
unit consists of dry cyclones for the first stage of treatment, bag filters
(the second stage) and draft blow machines. The unit is automatically
operated.
The dry method used for the treatment of the dust laden air in high performance units of
modern design makes it possible to guarantee the reduction of the amount of emissions
discharged into the atmosphere down to 20-40mg/m3.
The filter regeneration system is automatically switched on as soon as dust accumulates
on the bag surface.
111
Coke Ovens
The bag filters regeneration is performed automatically as a result of reverse impact
blowing with compressed air from outdoor networks.Due to cyclic nature of coke
pushing from carbonization chambers, the draft blow machines provided with frequency
controlled electric drives permitting to considerably reduce the consumption of electric
power.
7. Specifications of COB#11
Under the 2.5MT modernization programme, one battery of capacity 8,81400t/yr
(approx.) of gross coke production (dry) and high capacity oven is to be installed. The
analogous technical data (based on batteries operating in India) for the design of the
battery is indicated below:
Total length(between buck stays)
15860mm
15020mm
Total height
7000mm
Useful height
6700mm
385mm
435mm
Average width
410mm
Taper
Useful volume of the oven
Axial distance between ovens
50mm
41.6m3
1400mm
32
480mm
Coking time
17hrs
Top charged, twin flue, under jet, compound, regenerative heating type with partial
recirculation of waste gases heating system.
112
Coke Ovens
ii.
iii.
iv.
Required sets of matching oven machine of latest proven design with hydraulic drive
for door extraction and latch lifting in pusher and platform type guide car and
provision of manual operation of crucial functions.
v.
Adequate and reliable facilities in the oven machines for mechanical cleaning and
maintenance of oven doors, door frames and gas removal system at the oven top.
vi.
Air cooled oven doors with diaphragm type design has been provided. The door is
spring loaded with self-adjusting sealing arrangement unlike conventional doors.
vii.
Battery heating system is designed for under firing with clean coke oven gas with
average heating value of 4250kcal/Nm3 and /or mixed gas with average heating
value of 1000kcal/Nm3.
viii.
U type gas collecting mains with built in valve box and design of ascension pipes
with improved system of adjustment between the gas collecting main and ascension
pipe.
ix.
A gas collecting main with effective sealing between gooseneck and isolation valve
box on both pusher side and coke side isbe provided with automatic functioning
bleeders.
x.
Oven anchorage system comprises of fabricated buck stays with single piece flash
plates, top crosstie rods (with suitable protection for entire length) and bottom cross
tie rods, longitudinal tie rods and necessary regenerator bracings in fireclay zone.
xi.
Sturdy and rugged anchorage and bracing system in which the door frames is held
through cast iron flash plates and not directly placed on the brickwork and held
through buck stays.
xii.
xiii.
One set of hydro jet door cleaner consisting of cleaning station (one for pusher side
and one for coke side) of high pressure not less than 600bar
xiv.
One set of door lowering for repair of pusher side and coke side doors.
xv.
Four sets of fixed door racks (2 on pusher side and 2 on coke side)
113
Coke Ovens
xvi.
Computerized Heating Control system is provided for ensuring proper coking. The
Model also takes care of oven identification, oven machine interlocking, and oven
scheduling.
9. Service Bunker
There is a coal tower of 4000T useful capacity for storing coal of dry equivalent bulk
density of 740kg/m3. The bunker is located at the east end to allow enough clearance for
the oven machines. At the bottom of coal tower, number of rows(8) of outlet has been
provided. Each row has number of outlets matching the number of charging holes along
the transverse axis. At each outlet, necessary mouth piece and sector gates are provided.
A parking and maintenance platform for charging car at the oven top level has been
provided. The bunker is of RCC construction and lined with stainless steel liners at the
sloping outlets. Level indicators for coal level with transmission devices to the control
room and alarm for alarm for low levels of coal charge are provided. Discharge from
each bunker compartment is through roller supported, horizontal cut off gates which are
operated by charging car operator. The mechanism for opening of the coal tower gates is
on the charging cars.The coal tower has been provided with pneumatic blow down
device to enable free flow coal.
10. Oven Anchorage
The battery anchorage consisting primarily of buck stays, flash plates, cross and
longitudinal tie rods, springs etc. is complete with all accessories. The anchorage system
maintains a positive pressure on the refractory to avoid opening of joints or cracks due
to temperature changes. They are rugged in design to with stand the stresses and loads.
Suitable protection for full length of upper cross tie rods is provided. Material of
construction (MOC) of cross tie rods is Chrome Molybdenum Steel. A set of regenerator
bracings has been provided for loading on the main walls and dividing walls of the
regenerators. Buttress wall are connected together at the top by longitudinal tie rods. To
ensure proper loading, six numbers longitudinal tie rods has been provided with helical
springs,
114
Coke Ovens
Buck stays are provided to transmit load on the heating walls through the flash plates.
They are of rugged design to with stand the stresses and loads during heating up and
battery operation. The buck stays are of welded box type design without any splicing
joint in critical zone and well ventilated. Buck stays on the pusher side and coke side are
held at the battery top level and nozzle decking level by suitable crosstie rods at each
level loaded with helical springs. There are no joints in the cross tie rods. Buck stays are
resting at the bottom on the nozzle decking. The transfer of load from buck stay to the
flash plates and to main wall are through helical spring located inside the buck stay.A set
of regenerator bracings are provided for loading on the main and dividing regenerator
walls, to take care of the differential expansion characteristics of refractories of this
region.
11. Door Body, Door Frame, And Flash Plates
Gas tight doors are provided. Doors have a flexible diaphragm sealing with a spring
loaded sealing strip made of suitable special alloy steel. Doorsare air cooled by keeping
the main door body separated from the diaphragm and the brick holders by an air gap of
approximately 30mm, which keeps the door body cool and prevent door warping. The
flexible diaphragm is able take the shape of the warped door frame. The diaphragm is
held against the door frame by spring loaded plungers mounted on the door body to
allow sealing of oven doors with distorted frames. The doors have provision for manual
adjustment of knife edge pressure. Between flash plates and end bricks and flash plates
and door frames sealing is done with ceramic ropes set in machined grooves.
Matching door frames are adopted Door frame on pusher side and coke side are of
identical design.
Flash plates are of single piece and are loaded at three different levels (top, middle, and
bottom) from buck stays. The design of flash plates ensures that load is transferred
through liner bricks and notthrough central axis of heating wall. Door frame on pusher
and coke side is provided with replaceable sole plate at the bottom.
Chemical composition of HRC is as follows:
C=3.2-3.6%,
P=0.3%Max.,
Mn=UPTO1%,
Cr=0.16-0.4%,
Si=1.4-2.0%
and
S=0.1%Max., Ni=0.07-0.6%
IISCO Steel Plant
115
Coke Ovens
116
Coke Ovens
temperature as per its application. Heat resistant castings physical properties conforms to
IS 210 93FG 200/ equivalent. Indicative composition of HRC is as given belowC- 3.23.4%, P-0.3% max., Mn-0.7-1%, Cr-0.4-0.8%, Si-1.6-2.0% and S-0.1%max.
14. Gas Collecting Main
U type Gas collecting mains on both pusher side and coke side is provided. Gas
collecting main is of welded construction with plate thickness suitable to with stand
corrosion due to gas and liquid. However, GCM is fabricated with plates less than 10mm
in thickness. Gas collecting main on both sides is supported from buck stays.
Gas collecting mains is provided with tar chasing system with high pressure ammonia
liquor. Openings with plugs are also provided on the collecting main for manual tar
chasing. Collecting mains has a suitable slope for smooth flow of liquor and tar. Liquor
from coke side and pusher side collecting mains is routed through pipe line stockades.
Walkway with hand rails is provided on the collecting mains. The height of walkway
above the Gas collecting main is such that plugs on gas collecting main is easily
approachable.
Automatic hydraulic seal bleeders are provided (2 numbers) on each collecting mains
which bleed gas when the pressure in the hydraulic main exceeds the designed pressure
limit. (25mm)
15. Cross Over Main And Suction Main
The collecting main on pusher side and coke side is interconnected with cross over main with
hydraulically controlled butterfly valve on pusher side. Hydraulic controller is of split type for
both side and coke side butterfly. Controllers are located in GCM booth on pusher side from
where impulse line is drawn up to actuator of butterfly valves. Cross over main is provided with
compensators to take care of stresses. Cross over main is provided with spray liquors at suitable
points. Cross over main is of welded steel construction with plate thickness not less than 10mm.
117
Coke Ovens
pressure ammoniacal liquor, is drawn from the liquor mains, pressurized to about 3035kg/cm2 and injected into goose neck while charging. The charging gases evolved is
sucked into the gas collecting mains, preventing emission of dust and smoke into the
atmosphere. During idle running of HPLA pumps, suitable pressure relieving system
along with necessary instrumentation is provided.
The spillage conveyors is provided for removing the hot coke spillage likely to fall
during opening of the coke oven doors and pushing of ovens on pusher side and coke
side service platforms. The total system consists of a special chain conveyor fitted with
drag plates running inside a lined trough on the service platform. Spillage chain
conveyor on the return side runs underneath the service platform.
The chain conveyor discharges the material on a belt conveyor which carries the same to
the structural storage hopper (capacity-20 M3) for disposal by trucks.Proper water
spraying arrangement system is provided before belt conveyor to take care of
temperature of coke to be transported on to belt conveyor.
18. Skip Hoist
Leveler bar present in pusher car, levels coal heaps formed inside oven during charging
and distributes it evenly inside oven. Any excess coal is dragged out by the leveler and
is collected inside the hopper of pusher car. This spillage coal is emptied in skip bunker
from time to time and is recirculated back to charging car.
A skip hoist system on pusher side is provided for charging back the spillage coal during
leveling. The skip carries the coal into an overhead steel bunker of 10M3 capacity. The
118
Coke Ovens
collected coal is then discharged into end bunker of the charging car. The skip hoist is
supplied complete with winch structures and electrics.
19. Service Platforms
Service platforms on pusher side and coke side consistof RCC slab supported over
columns. RCC have cast iron paving on pusher side. Coke side platform have CI lining.
Columns and beams on coke side are suitably designed to take load of coke guide car.
Pusher side and coke side service platform have provision for spillage conveyor.
Rail
Pusher Car
Charging Car
CR-100
60 kg/m
Center distance
between Rails
(mm)
12000
6820
Platform type
Guide Car
CR-100
7000
Wheel load
(max.)
Maximum
length (mm)
45 t
25 t
(without
coal)
25 t
15600
12900
17500
119
Coke Ovens
List of Coke oven Machines
Machines
Unit Qty.
Coke Pusher
Nos. 2
Nos. 2
Coke Pusher machine, Coal Charging Car, and Guide Car are designed with hydraulic
drives. All machines have centralized lubrication system, desert duty a/c operators
cabins.
22. Coke Pusher
The Coke Pusher Machine is of single spot type.
The machine has hydraulic drives for all mechanisms, except for long travel, pusher
ram, leveler, VVVF drives for speed control is provided for long travel, pusher ram and
leveler drives.Leveler muff Mechanical frame cleaning mechanism.Decarbonising
equipment, Leveler coal spillage system, Centralized lubrication system, PLC
Operations.
23. Coal Charging Car
The coal charging car is designed for single spot operation of lid opening /closing and
screw feed charging of ovens.
The charging cars have the following features:
i.
ii.
iii.
The speed control of charging car travel and screw feeder of coal charging
mechanism is VVVF type.
iv.
The machine is also be equipped with goose neck and stand pipe cleaning
mechanism.
120
Coke Ovens
v.
Lid luting mixer (consisting of tank with stirrer driven by geared motor) is
installed on the charging car machine.
vi.
vii.
viii.
PLC operation.
ii.
Mechanical frame cleaner Dust extraction system. Desert a/c operators cabin.
PLC operation
System
Medium of heating
No. of Ovens
74(37x2 blocks)
76(38x2 blocks)
No. of Pre-heaters
Pumped to GC Main
10
Reversing Machines
i. Hydraulically operated
ii. One for each block
iii. Five cylinders for operation, in each block, for:
a) one for CO Gas
121
Coke Ovens
b) one for Mixed Gas
c) one for WHB disk operation
d)two for Air Flap Operation
11
Interlockings
12
CO detectors in cellar
13
CO gas circuit
As per sketch 1
14
15
50 oC
16
Coke is obtained through destructive distillation of Coal. The heat required is supplied
by burning of Rich Coke Oven(Gas) or Mixed Gas in the heating chambers as per
availability. Rich Co gas is the supply gas from By Product Plant after extracting
valuable by-product chemicals (tar, naphthalene, ammonium sulphate , sulphur) from
Raw CO gas. Mixed gas is a mixture of cleaned blast Furnace and Rich Coke Oven gas
done in mixing Station to achieve the desired calorific value.
2. Gas Mains
There are two Rich Gas mains and two Mixed Gas mains in cellar to cater all the flues of
each Heating Wall. Each Gas Main has automatic pressure control by hydraulically operated
Butterfly Valves.Rich Gas Distribution to flues is done through rich gas distribution headers
and riser pipes. Connection is given to the distribution headers from Rich Gas main through
122
Coke Ovens
pipeline through Isolation and Reversing Cocks.Mixed gas connection to the Waste Heat
Box is through the riser pipe from the Gas main and is provided with isolation and reversing
cocks.
123
Coke Ovens
124
Coke Ovens
4. Reversing Machine
Hydraulic Reversing system is provided for the reversals. The system consists of Reversing
Machine (operated by hydraulic cylinder), Power Pack and accumulator Units. Power pack
consists of pumps, storage, filtering and distribution of hydraulic oil. Accumulators are
provided to take care of Emergency operations. Sensors for identification of failure of the
reversing machine are provided.
Chimney provides natural draught for the waste gas generated. It I a 120 m tall concrete
structure lined with fire clay and insulation bricks. The chimney is 8.56 m wide at the
bottom, while it is 4.86 m at the top.
Chimney draught for the battery is automatically controlled from the control room by
hydraulic regulator and butterfly valves. Waste gas analyzer installed inside the chimney
provides data on continuous basis. Proper functioning of Waste Heat boxes and heating
parameters ensures that the waste gas at chimney is within statutory norms.
125
Coke Ovens
126
Coke Ovens
C) Coal Route
Coking Coal received in COB#11 by railway wagons is unloaded in wagon tippler no. 3. In
case of emergency Wagon tippler no. 2 under RMHS can be used to unload these coal
wagons.
Coking coal is mainly received from Australia for Hard and soft variety, USA for Hard
variety and indigenous coal from Chasnala. The designed blend for COB#11 is as follows:-
Type
%age
Ash
VM
Australia (Hard)
55%
8-10%
23-24%
USA (hard)
15%
8-10%
27-28%
Australia (Soft)
10%
8-10%
27-28%
Chasnala
20%
18-20%
22-23%
127
Coke Ovens
the belt. Weigh Feeders feeds the coal to C1C1 or its alternate belt C1C2 using Diverter
Gate. C1C1 and C1C2 are parallel belts which run from Wagon tippler to C1 Junction
House (C1JH). Both the belts have Electro Magnetic Separator (EMS) to remove any
metallic component coming with the coal. In C1JH, C1C1 belt has Auto Sampling Unit
(ASU) which automatically collects sample from the belt and stores it in its bin for
collection. C1C2 on the other hand has Sample Cutter (SC) which cuts the sample on the
belt and gives the chance to collect the sample if the feeding is still in progress. C1C1 and
C1C2 belt feeds the coal to C1RSCA and C1RSCB respectively. C1RSCA and C1RSCB are
reversible shuttle conveyor i.e. it can run in both the direction. These belts can feed four
belts C2C1, C2C2, C7C1 and C7C2. C2C1/C2C2 takes coal to the beds and C7C1/C7C2
takes coal into the blending bunkers (will be discussed later). C2C1 and C2C2 are both
parallel belts and run from C1JH to C2JH. Here C2C1 can feed coal to CST-1 or C3C1
using diverter gate and C2C2 can feed coal to CST-1 or C3C2 using diverter gate. CST-1
belt takes coal to Stacker no. 410 which can stack coal to bed no.1 or bed no.2. C3C1 and
C3C2 are parallel belts running from C2JH to C3JH which feed coal to same belt CST-2.
CST-2 belt takes coal to stacker no. 409 which can stack coal to bed no.3 or bed no. 4.
While if C1RSCA/C1RSCB feeds coal to belt C7C1/C7C2, these belts take coal to C7JH.
C7C1 and C7C2 belts run parallel from C1JH to C7JH and can feed material to C8C1 which
is the belt for coal dust injection (CDI) (will be discussed later in CDI route) or to belt
YJH1C1 which runs from C7JH to YJH1JH. YJH1C1 belt can feed material to Y1 belt or
Y2 belt. Y1 belt is a small belt to change the direction of belt from Y2 which feed material
to Y2A belt. Y2 belt and Y2A belt run parallel to each other and finally stores coal in
Blending Bunkers using Travelling Trippers. Y2 belt has TT1 (Travelling Tripper 1) which
can store coal in silo no. 1, 2, 3, 4, 5, 11, and Y2A belt has TT2 which can store coal in silo
no. 6, 7, 8, 9, 10, and 12. There are a total of 12 silos or blending bunkers with each of
storage capacity of 1250T.
Coal stacked on beds can be reclaimed selectively by reclaimers. 3 Reclaimers are provided
with Reclaimer No. 416 for Bed No. 4, Reclaimer No. 417 for Bed No. 3 & 2 and Reclaimer
No. 418 for Bed No. 1. Reclaimer No. 416 feeds coal to C6C1 belt which run s to C6JH and
feeds coal to C7C1/C7C2 using diverter gate and the same process for Reclaimer No. 417
128
Coke Ovens
and C5C1 belt and Reclaimer No. 418 and C4C1 belt. C7C1/C7C2 belt takes coal to
Blending Bunkers as discussed earlier.
There is also a provision of coal dust injection (CDI) in Blast furnace, thus to supply Coal to
BF from Bed No. 1 using Reclaimer No. 418. However as discussed earlier C8C1 belt
starting from C7JH runs to C8JH and used for carrying CDI Coal only. At C8JH, C8C1
feeds material to CDIC1 belt which takes CDI Coal to CDI Bunkers of Blast Furnace.
3. CHP Blend Preparation
All the 12 Blending bunkers are fitted with a weigh feeders of capacity of feeding max.
150TPH of coal each, except feeders of bunker no. 11 and 12, they have capacity of 50TPH.
The tonnage of coal flow from these feeders can be adjusted, the purpose is to supply
desired/designated coal in prefixed quantity in the blend. These feeders feed coal to belt Y3
and Y3A which run parallel to YJH3JH. Y3/Y3A belt feed coal to Y4 belt which runs from
YJH3JH to YJH4JH. Y4 belt also has one EMS3 (Electro Magnetic Separator No. 3) so that
if any metal piece that might have come in the belt from bunkers is removed from the belt.
Y4 feeds coal to Y5 belt which runs from YJH4JH to Coal Crushing station. Y5 belt also
has ILMS1 (In Line Magnetic Separator) placed at its driver end pulley. ILMS removes any
small metal piece that may have not been removed by EMS. Y5 belt feeds coal to HammerMill Bunker. Purpose of hammer-mill bunker is not only to store coal but also to feed coal
to hammer-mill crushers. All the coal in hammer mill is to be crushed to a crushing index of
80-84% <3.2mm.Three nos. of RPG (rack and pinion gate) one for each crusher, is provided
at the discharge point of the bunker. RPG opens only when crusher has started running.
Three nos. of VF (Vibro-feeder) one for each crusher is provided after RPG to maintain
uniform flow of coal into the crushers. There are three nos. of Hammer Crushers in
COB#11, which crushes the coal by the impact of hammers to desired fineness and prepares
a homogeneous blend of different type of coal. Two nos. of Hammer Crusher remain
operational at a time and one is kept stand-by. 80-83% of coal less than 3.2mm in size is
desired for charging in coke oven. After crushing coal, Hammer Crushers feed the blended
coal to Y6 belt which runs from coal crushing station to YJH4AJH. A water sprinkler line is
provided in Y6 belt to maintain moisture level in the blend at 7-8% which is desired for
charging in battery. Y6 belt also has a metal detector (MD), so if a metal piece comes on the
IISCO Steel Plant
129
Coke Ovens
belt; it immediately stops the belt giving a chance to remove the piece before charging in
battery. Y6 belt feeds blend coal to Y10, which runs to YJH5JH. An Auto Sampling Unit
(ASU) is provided on Y10 belt which automatically collects the sample and stores it for
collection. Y10 feeds coal to Y11 belt which takes coal to Coal-Tower. Y11 belt can feed
coal to belts Y12 and Y13 belt using a diverter gate. Y12 and Y13 are reversible shuttle
conveyor which can feed four sets of bunkers in coal tower. Thus both the belts can feed
coal tower having a capacity of 4000T blend and crushed coal.
130
Coke Ovens
131
Coke Ovens
132
Coke Ovens
4. Major equipment & installation in Coal Handling Plant of COB#11:
Sl. No.
Name of equipment
1.
Conveyor Belts
44
2.
10
3.
12
4.
Belt Feeder
5.
6.
Diverter Gates
11
7.
8.
9.
Sample Cutter
10.
Metal Detector
11.
12.
13.
14.
Stacker (Nos.)
15.
Stacker (Capacity)
16.
17.
Travelling Trippers
18.
19.
Vibro-Feeder
20.
Hammer-mill Crushers
21.
22.
23.
24.
600TPH
2
1400TPH
1.6LAKH T
12
15000T
133
Coke Ovens
25.
4000T
Name of Belt/Belts
WT-3BFA/ WT-3BFB
C1C1/ C1C2
C1RSCA/ C1RSCB
C2C1/ C2C2
C3C1/ C3C2
CST-1
CST-2
C4C1
C5C1
C6C1
C7C1/C7C2
C8C1
CDIC1
YJH1C1
Y1
Y2
Y2A
Y3/Y3A
Y4
Y5
Y6
Y10
Y11
Y12/Y13
Capacity(TPH)
Width(mm)
Length(m)*
1400
1400
1400
1400
1400
1400
1400
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
2000
1600
1800
1600
1600
1600
1600
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1200
1400
5.5
447.3
9.2
80.9
84.9
379.9
379.9
392.8
392.8
392.8
389.4
309.4
110.0
237.7
12.3
102.1
100.4
120.2
89.1
84.4
151.2
189.1
82.0
9.5
Length given is the distance between centre of driver and driven pulley.
134
Coke Ovens
Coke Sorting Plant is of 250TPH capacity and will handle coke from COB11 and COB10.
Thecoke sorting plant sorts out the coke into four fractions e.g. 60-80 mm, 30-60 mm, 15-30
mm and0-15 mm.
1. Coke De-dusting Unit
Coke from Coke Dry Cooling Plant is transported to Coke Dedusting Unit byconveyors K-1
& K-2. Below Surge hoppers 2 numbers of Rack & Pinion gates RPG-1 & RPG-2are
provided to control the flow and 2 nos. of Diverter gates DG-12 & DG-13 are provided
todivert the material either to conveyor K3 or K4. Coke from conveyor K3 & K4 is fed
intoDedusting chutes from where the dedusted Coke is conveyed to Coke Crushing Station
byconveyors K5 & K6.
135
Coke Ovens
Coke fed on the Reversible conveyor P1RCA & P1RCB can either be fed to
conveyorJ9BC1/J9BC2 in Junction House P1. These conveyor J9BC1 & J9BC2 can either
convey thecoke directly to J9B building or deposit coke on Emergency Coke storage area
with the help ofMobile trippers (TT-3 & TT-4) provided over conveyor J9BC1 &
J9BC2.Presently J9BC1 isbeing used to convey material to Coke loading station (CLS) and
J9BC2 to emergency coke yard(ECY).From emergency coke storage, coke can be fed to
J9BC3 by pay loader through 3 groundhoppers GH1, GH2 & GH3.
In J9B, conveyor J9BC1 feeds coke to J10C1, J9BC2 feeds coke to J10C2 and conveyor
J9BC3can either feed to J10C1 or J10C2 by positioning diverter gate DG-17 provided
below conveyorJ9BC3. From J9B, coke will be transported to Blast furnace via Junction
House J10 byconveyors KC5 & KC6 where J10C1 will feed to KC5 & J10C2 will feed to
KC6.However dueto delay in blast furnace operation two additional conveyors KC7 & KRC
were installed after1conveyor KC5 so as to store coke into two bunkers of 400 Tons
capacity each. Wagon loadingarrangement has been made to transport this stored BF coke to
sister plants.
In Coke screening station, (-) 30 mm Coke fraction will be collected over conveyor K13
fromRS3 & RS4 and transported to Junction House P2. In Junction House P2, the conveyor
K-13discharges coke to conveyor K-14. Conveyor K-14 transports the Coke to Reversible
conveyorK-15 which in turn feeds over to 15mm Vibrating screens (VS1 & VS2 of capacity
150 TPH)through vibro feeders VF-8 and VF-9. Screened coke i.e.0-15 mm and 15-30 mm
fractions willbe filled into two separate bunkers. Each bunker is provided with twin outlets
at the bottom suchthat 1 opening will be operated with Rack & Pinion gate and other with
Sector gate (SG-1 & SG-2). Below the Rack & Pinion gates (RPG-3 & RPG-4) vibro
feeders (VF-10 &VF-11 of capacity200 TPH) are provided to feed the coke to conveyor
P3C1 which in turn discharges to JNT1C1at Junction House P3.The bunker having sector
gate opening can be emptied out usingtipper/dumper, this coke is transported to back shunt
yard.
136
Coke Ovens
From existing COB-10, coke will be transported to existing Screen House by conveyor KC2over which Metal detector MD2 is provided to detect the metallic materials in the Coke
flow.From existing screen house the coke will be transported to Junction House KTP1 by
conveyorKC-3 from where it will be discharged to conveyor KC-4 which in turn convey the
Coke to Newcoke crusher house and feeds over to a 80mm Roller screen (RS7). The
oversize coke fractionwill be fed into a Double roll crusher CR3 so that it can be crushed to
(-) 80 mm and will befilled into bunker of capacity 25 m3 below which 1 no. Rod gate RD21 & 1 no. Vibro feederVF-5 shall be provided. Vibro feeder VF-5 will feed the coke to a
Pipe conveyor of cap 200 TPHwhich convey the coke from New coke crusher house to CP3
building , which in turn fill abunker below which 1 no. Rod gate (RD-22) and 1 no. vibro
feeder VF-6 shall be provided toconvey the coke to Junction House KP1 by conveyor
KP1C1. In Junction House KP1 conveyorKP1C1 will feed the coke to KP2C1 which will be
conveyed to Junction House KP3 byconveyor KP3C1 via Junction House KP2. At Junction
House KP3 the conveyor KP3C1discharges the Coke to KP4C1 which in turn fills a RCC
coke bunker of 100 tonne storagecapacity with twin out lets shall be provided over the
conveyors K-9 & K-10 for storing cokecoming from the existing coke plant. Each outlet
will be provided with a Rod gates (RD-16 &RD-17) and a 100 TPH capacity belt weigh to
feed conveyors K9 &K-10.
4. Dust Extraction system is provided in the coke de-dusting unit (CDU). The system
comprises of dust extraction air blasting unit, suction hoods on the coke de-dusting chute,
ducting network, electrically operated dampers, bag filter unit, centrifugal fans, stack
electrics & control. One spark arrestor & one multi-cyclone are provided in the ducting
network at the inlet side of distribution chamber of bag filter unit. Spark arrestor prevents
smoldering particle from entering into bag filter while cyclone separator collects coarser
coke particles thereby preventing them from entering into bag filter. Bag filter unit consists
of distribution chamber, filtering chamber with filter bags & fitting for the bags, outlet
chamber, dust collection hopper with rotary air lock valves & dust storage cum disposal
hopper with rack & pinion gate and disposal chute, structural stair case and platform, timers
etc. Two suction ducts of the ducting network are provided with electrically operated
dampers and manually operated dampers are provided at ducts above conveyor K1 to K6.
IISCO Steel Plant
137
Coke Ovens
While running the CDU, air blasting unit fan sucks ambient air through air intake louver
&transition piece and blast/supply the air into the CDU through the ducting network. The
dustdisposal from bag filter, multi-cyclone& spark arrestor is through discharge into a
centralpneumatic system (through dust storage hopper).
138
Coke Ovens
139
Coke Ovens
140
Coke Ovens
D) By-Product Plant in COB # 11 Complex
The objective of By-product plant in COB # 11 is to clean the raw coke oven gas generated
from coke oven battery with removal of impurities like tar, ammonia, hydrogen sulphide
and naphthalene to the extent as it can be effectively used as fuel.The impurities thus
removed from the system are separated in the form of saleable products viz. Crude Coal Tar,
Ammonium Sulphate, Sulphur (99% pure) & Naphthalene. The coke oven gas is available
at 300C at the outlet of byproduct plant.
Sulphuric Acid
ii.
Solar Oil
iii.
Caustic
iv.
Catalyst
Coal Tar
ii.
Ammonium Sulphate
iii.
Naphthalene
iv.
Sulphur
The By-product plant is equipped with adequate flexibility from the point of view of
design, operation and maintenance. Adequate standby facilities are ensuredfor
uninterrupted and smooth operation of the plant.
IISCO Steel Plant
141
Coke Ovens
PGC
(2W + 1S)
Co
nd
en
sat
e
De-acidifier
(1W+1S)
De-acidified
Water
142
C. O Gas
(To Network)
Vapour
Co
al
W
at
er
Combined Stripper
(1W+1S)
Enriched
Water
Stripped
Water
St
ea
m
Ca
ust
ic
So
da
AMMONIUM SULPHATE
ETP
(1W+1S)
Gas Exhauster
(1W+1S)
Excess
Coal Water
Down comer
Gas
NH3/Coal Water
Storage (1W)
Naphthalene Recovery
Plant (1W)
NAPHTHALENE
Coke Ovens
Cooling tower & chilled water plant have been installed for catering the requirement
of primary gas cooler and Heat-exchangers of other units. The chilled water plant is
housed in a separate room. Cooling tower & chilled water plant have standby
provision.System of hot tar-liquor emulsion flushingis there for each PGC for removal
of naphthalene deposit on outside of water tubes. Arrangement of LP steam &
Nitrogen purging to PGC are also made.
b. Electrostatic Tar Precipitator
Electrostatic Tar Precipitators (E.T.P.) is required to remove the remaining tar fog of gas
& the same installed before exhauster. Arrangement for removal of deposited tar in the
ETP tubes is provided. Insulator boxes are provided with electrical heating arrangement.
Inert atmosphere by allowing N2 flow in Insulator boxes is to be maintained
c. Exhauster
Electric Motor driven exhauster sucks the coke oven gas leaving ETP and discharge the
same with a positive head. The discharge head shall be worked out depending upon the
pressure drops in the downstream equipment and desired pressure (700 mm to 1000
mmWG) of CO Gas at the Battery Limit of By-Product. The temperature of CO Gas at
143
Coke Ovens
the discharge of exhauster should be kept minimum. Suction requirement for upstream
of exhauster upto battery is 500 mm WG (indicative).
d. Tar &Ammoniacal Liquor Circuit
The coke oven gas in Gas collecting main is cooled to 820C by spraying
flushing/Ammoniacal liquor. The Ammoniacal Liquor flows in a closed cycle from
down comer to Solid Decanter; to Tar Decanter, Coal water tank and then back to Gas
collecting main via Ammoniacal/flushing liquor pump. Part of coal water is used for
HPLA system in battery. Excess coal water is sent to Ammonia stripper via Gravel filter.
Major portion of tar content in Coke oven gas is condensed in Gas main by flushing
liquor/ Ammoniacal liquor. The tar together with flushing liquor, gas condensate and
coal fines from coke oven flowing through gas collecting main goes to solid decanter.
The coal fines mixed with tar & flushing liquor is known as sludge. The solid decanter
serves to separate sludge from Ammoniacal liquor and tar by settling. Sludge being
heavier, settle at the bottom of solid decanter and sludge is continuously scrapped off by
scrapping conveyors into barrel/ trolley from where it is removed by a dumper/truck.
The Ammoniacal liquor and tar from the decanter overflows into tar decanter. The
Ammoniacal liquor from tar decanter goes to gas mains of battery. Part of this liquor is
used for HPLA system also. Surplus Ammoniacal liquor is generated due to moisture
present in the coal. This excess Ammoniacal liquor is sent to Ammonia stripper via
Gravel Filter.The tar from the tar decanter flows continuously to the Tar Storage Tank
for dispatch.
e. Major Technological Equipment/Facilities for Gas Condensation Plant
This plant comprises of the following major technological equipment
144
Equipment
Primary Gas Cooler
2W+1S
1W+1S
1W+1S
Capacity
24000 Nm3/Hr
for Each PGC
47500 Nm3/Hr
Coke Ovens
Flushing Liquor Pumps
2W+1S
E.T.P
1W+1S
Centrifugal Pumps for transferring tar, 1 W + 1 S
liquor etc
Tar Storage Tanks
1W+1S
Cooling Tower
2W+1S
Cooling Water Pump
4W+3S
Chilled Water Plant
2W+1S
Chilled Water Pump
1W+1S
Gravel Filter
1W+1S
Heat Exchanger
525 Nm3/Hr
47500 Nm3/Hr
1600 M3
To prevent gaseous emission from various vessels, tanks equipment & vents, a suitable
pollution control measures are taken.
145
Coke Ovens
by means of caustic solution. The upper part of the column receives the deacidified
solution from deacidifier & coal water (excess flushing liquor) from gravel filter unit
after pre heated by outlet liquor of column. The stripped off NH3 enter the deacidifier.
The deacidifier strips off NH3, H2S, CO2, HCN from the rich solution received from
H2S scrubber. These vapours from the deacidifier shall enter to the Ammonium
Sulphate plant after proper cooling.
c. Ammonium Sulphate production through Bubbler type saturator route
Ammonia, Hydrogen sulphide gas, CO2& HCN from deacidifier is led to Saturator
where Ammonia is recovered in the form of Ammonium sulphate. Ammonia and H2S
enters in saturator from top and bubbles through a bath of mother liquor where a
constant acidity is maintained by continuous addition of sulphuric acid. Sulphuric
acid is stored in separate storage tanks. The sulphuric acid is fed to the saturators by
gravity from overhead tank. Sulphuric acid is pumped to the overhead tank from
ground level storage tank. The mother liquor is kept under constant circulation by
centrifugal pumps to maintain uniform bath acidity and obtain uniform well
developed crystals from the Saturator. From the Saturator the Hydrogen sulphide with
HCN & CO2 enters the acid catcher, where the liquor droplets entrained in gas is
removed.
Ammonium sulphate crystals produced in the Saturator isejected out together with
mother liquor to the crystal receiving tank. Ammonium sulphate slurry flows from
crystal receiving tank by gravity to the centrifuge continuously for the separation of
mother liquor and salt. Ammonium sulphate from the centrifuge is conveyed by belt
conveyors to the dryer. Drying of ammonium sulphate is carried out in a stainless
steel rotary drier by means of hot air operating with steam and through forced draft
fans. From the drier, spent hot air with entrained dust particles is extracted by suction
fan through cyclone separator and wet scrubbing unit to remove the fine ammonium
sulphate salt before venting to atmosphere. Ammonium sulphate is transferred to the
bagging bunker by a bucket elevator. Dried ammonium sulphate is bagged, weighed
in automatic bagging and weighing machine and then sent to storage or dispatched by
146
Coke Ovens
rail and road. The provision for both railway wagon loading and road truck loading
are kept. Mechanized system for loading of bags is provided.
The Saturator, acid catcher and mother liquor tanks is of special steel alloy as per
DIN 1.4465 or similar in order to resist corrosion. All process pumps are of Alloy-20
construction.
d. Sulphur Recovery Unit
H2S/HCN/CO2vapor coming from drop separator (acid catcher) of saturator enters to
Catalytic Oven Reactor for burning.
The operation of the cracking reactor is characterized by partial burning of sour gas
with air to provide the required temperature for the catalytic cracking stage. Most of
the nitrogen compounds are burnt and reduced to elemental nitrogen and passes the
catalyst bed to crack the remaining ammonia and hydrogen cyanide.
Process gas leaving the catalytical area is post-burnt by providing secondary air, so
that the required ratio of SO2/ H2S is adjusted before the gas is cooled in the waste
heat boiler system (Process Gas Cooler). At the same time the first portion of
elementary sulphur is generated, which is separated in the outlet area of the boiler.
The boiler is used to cool the process gas down to 250 to 2800C. A partial flow is
taken between the Crack-Reactor and the boiler and mixed with the outlet of the LP
boiler to obtain the correct inlet temperature for the Claus reactor. The boiler is
equipped with an internal sulphur separator, where the liquid sulphur that has been
built, is separated from the process gas.
The process gas leaving the boilers is directed to the first of two claus reactors. Both
reactors are filled with alumina based catalyst. The conversion of sulphur dioxide and
hydrogen sulphide to sulphur takes place by the selected temperature of 2500C.
As the Claus reaction is of exothermic natures, the process gas is cooled after the 1st
Claus reactor stage in the Sulphur Condenser, followed by a sulphur separator and
IISCO Steel Plant
147
Coke Ovens
directed to the 2nd claus reactor stage. Before the process gas is led into the 2nd claus
reactor stage, it is re-heated to enter the claus reactor with the required temperature.
The process gas, leaving the 2nd Claus reactor stage is also cooled in the sulphur
condenser, released from liquid sulphur in the 2nd sulphur separator and directed as
tail gas to the crude gas main ahead of the primary coolers. By this mode of operation
the combined process is free from emissions.
Capacity
1W
47500
Nm3/Hr
Gas Processing
NH3 Scrubber
1W
47500 Nm3/HrGas
Processing
148
1W+1S
1W+1S
1W+1S
Coke Ovens
Final Cooling Pump
1W+1S
2W
Heat Exchangers
6W+3S
Ammonia stripping & Deacidification Unit
De acidifiers
1W + 1 S
Combined Stripper
1W + 1 S
1W + 1 S
1W + 1 S
1W
1W+1S
1W
1W+1S
1W
1W + 1 S
Heat Exchangers
8W+8S
1W + 1 S
Thickener
1W
Centrifuge
1W + 1 S
1W
Bagging system
1W
1W + 1 S
1W
Seal pot
1W
Sulphur Recovery Unit
1W
Claus reactors
2W
1W
Sulphur Condenser
1W
1W
COG Blower
1W + 1 S
149
Coke Ovens
Air Blower
1W + 1 S
Vapor Blower
1W + 1 S
1W
1W + 1 S
The vapour coming out from Naphthalene stripper contains Naphthalene with oil &
water vapour which is condensed in water cooled condenser. Naphthalene rich oil
getting separated from water in a separator is allowed to cool in water jacketed
Naphthalene tray. Naphthalene crystallises by indirect cooling. The oil content in the
150
Coke Ovens
Naphthalene is 1 % max. Contaminated water from separator goes back to tar separator
unit.
c. Major Technological Equipment/Facilities Naphthalene Scrubbing unit)
Equipment
Capacity
Naphthalene Scrubber
Naphthalene Scrubber
1W
47500
Nm3/Hr
Gas Processing
Solar Oil Circulation Pumps
4W
1W
1W+1S
1W
1W+1S
1W
Heat Exchanger
1W
Naphthalene stripping Unit
Stripper
1W
1W
Condenser
1W
Separator
1W
Heat Exchanger
2W+2S
d. Technological Parameters
i.
ii.
gas
Processing Capacity.
2. Exhauster Have 1.15 times of gas Processing Capacity.
3. Other units of by-product plant like H2S, NH3& Naphthalene Scrubber have
1.07 times of gas Processing Capacity.
4. Gas Velocity in gas line is 16 to 20 m/sec.
151
Coke Ovens
iii.
iv.
Raw Coke Oven Gas Composition & Impurities at the inlet of By-Product Plant
(Indicative):
Hydrogen
52-59
Carbon monoxide
6-7
Carbon dioxide
3-4
Oxygen
0.3-0.7
Methane
24-28
Nitrogen
4-7
CnHm
1.5-2.5
100-120
Benzol Hydrocarbons
30-36
Hydrogen Sulphide
3-4
Ammonia
10-12
Naphthalene
8-10
3. Impurities in clean Coke Oven Gas (At the outlet of By-Product plant)
Residual Impurities
gm/Nm3
Tar
0.02 (Max.)
Hydrogen Sulphide
0.80 (Max.)
Ammonia
0.03 (Max.)
Naphthalene
0.05 (Max.)
Benzol Hydrocarbons
28-34
9-9.5
IISCO Steel Plant
Coke Ovens
Suspended Solids
<100 ppm
Pressure
5-6 kg/cm2
Temperature
80-82
33.83 kg/TDC
Ammonium Sulphate
15.04 kg/TDC
Elementary Sulphur
1.05 kg/TDC
Naphthalene
0.11g/TDC
Specific gravity at 40 0C
1.18
Ammonium Sulphate
As Per IS 826
Sulphur
99 % Purity
Naphthalene
7. Chemical Consumptions:
Sulpuric Acid
1.55 T/Hr
49 Kg/hr
Caustic Soda
415 Kg/hr
153
Coke Ovens
1. Basic Principle Of The BOD Plant:
a. Physical Treatment
b. Chemical Treatment
c. Biological Treatment
(Three Stage Biological System 1st Stage Activated Sludge Process, Followed by
Nitrification and De-Nitrification Processes)
154
Coke Ovens
SKIMMED
TAR/OILTar
+ LiquorSKIMMED TAR &
TAR/OIL
SEPARATION TANK
OIL SUMP
EQUALISATION TANK
WITH SKIMMER
NaOH
DISSOLVED AIR
FLOATATION UNIT
pH ADJUSTMENT
TREATED SEWAGE
TREATED EFFLUENT
BACTERIAL CULTURE
MAGNESIUM
CARBONATE
SETTLING TANK-II
PREPARATION TANK
BACTERIAL CULTURE
PREPARATION TANK
AERATION TANK-II
SETTLING TANK-I
SLUDGE SUMP-I
EXCESS
SLUDGE
SLUDGE SUMP-II
AERATION TANK-
OVERFLOW
SLUDGE THICKNER
DENITRIFICATION
TANK
AMMONIA FIXING
CUM pH
ADJUSTMENT TANK
SLUDGE
RECIRULATION
OVERFLOW
UNDER
FLOW
THICKNED SLUDGE
SUMP
EXCESS
SLUDGE
METHANOL
ACID
NUTRIENT
SLUDGE
RECIRULATION
UNDER
FLOW
AMMONIA
STRIPPING TOWER
TANK-1
SETTLING TANK-III
AERATION TANK 1
SLUDGE SUMP-III
155
Coke Ovens
2. Major Units Of BOD Plant:
i.
ii.
Equalization Tanks
iii.
iv.
v.
pH Adjustment Tank
vi.
vii.
viii.
Aeration Tank I
ix.
Settling Tank I
x.
Aeration Tank II
xi.
Settling Tank II
xii.
De-Nitrification Tank
xiii.
xiv.
xv.
Sludge Sumps
xvi.
Thickener
xvii.
xviii.
Chemical House, MCC Room, PLC Room, Office, Laboratory, Chemical Dosing
Units
xix.
xx.
xxi.
a. Technical Features
Capacity: 40 m3/hr Un-treated Effluents from BPP and COB # 11 and 50 m3/hr Treated
Sewage Water from STP.
b. Treatment Scheme
Effluents generated from Coke oven and By-Product Plant (COB#11 complex) contains
pollutants such as Ammonia, phenol, Tar & oil, cyanide etc. Main function of BOD Plant
156
Coke Ovens
is to remove tar and oils by physical and chemical systems and subsequent biological
degradation of Phenols, Ammonia and cyanide.
Initially effluents are received in tar & oil separation tank. The capacity of the tank is
suitable for one hour detention period. The effluent collected in this collection sump
pumped to subsequent tar-oil separator. Tar-oil separator unit is provided with skimming
facilities. From this unit effluents flow by gravity to equalization tank.
The equalization tank capacity with residence time of 24 hours for designed flow of 40
m3/Hr. The equalization tank consists of three compartments, two compartments each
having six hours holding while the third compartment having twelve hours holding
capacity. The equalization tank is provided with necessary tar/oil skimming arrangement,
and epoxy painting in the inside faces of each compartment.
From the equalization tank effluents are pumped to dissolve air floatation unit for
removal of emulsified oils. This unit consists of recirculation pump, air compressor and
all other required accessories. A skimmed tar & oil sump is also provided for collection
and storage of skimmed tar & oil.
Since the skimmed tar & oil contains major portion as water, this skimmed tar & oil is
pumped to slop oil tank for separation of water & tar / oil. In the slop oil tank skimmed
tar & oil allowed to remain for few days for separation of tar and oil. Tar/oil floating on
the top surface is taken out through tapping connection provided for this and
sent for
secondary use. Water from the bottom of the tank taken out and sent back to the
treatment plant.
From the dissolved air flotation unit effluents flow by gravity to pH adjustment tank.
Alkali
is added to raise the pH around 11. This tank is provided with agitator and pH
157
Coke Ovens
The ammonia stripped effluents from collecting basin sent to ammonia fixing cum pH
adjustment tank. The residual free ammonia is fixed and pH is brought down to neutral
pH by addition of sulphuric acid. The tank is provided with agitator and pH indicating
instrument. Effluents form ammonia fixing tank are pumped to 1st stage aeration tank i.e.
aeration tank-I. Under normal operation condition part of treated effluent or treated
sewage
water is added at the outlet of ammonia fixing cum pH adjustment tank at the
rate of 40 m3/hr before entering into the biological treatment facilities. The aeration tankI is aerated along with the return sludge by mechanical surface aerator. The tank is made
of RCC and necessary arrangements are provided in the tank for receiving the return
sludge and required nutrients.
The effluents from aeration tank-I flow to settling tank-I where solid particles are settled
out. Overflow from settling tank-I flow to aeration tank-II whereas the underflow is taken
to sludge sump-I. The settling tank is of RCC construction and provided with necessary
scrapping arrangement, overflow weir, inlet and sludge outlet pipes, constant bleed
arrangement and all other accessories required. From the sludge sump-I sludge is
recirculated to aeration tank 1 and excess sludge is disposed to sludge thickener inlet.
The aeration tank-II is used as 2nd stage of the activated sludge process. The tank
consists
of aerators and other facilities for receiving the return sludge and required
aeration tanks.
Effluents from aeration tank-II flow to settling tank-II. The settling tank-II is similar to
settling tank-I. Facilities for collecting settled sludge from settling tank-II and pumping it
to aeration tank-II & sludge thickener inlet, sump is
from aeration tank-II flow to nitrification tank. The tank is operated under anaerobic
condition. Requisite quantity of methanol is added as carbon source. Effluents from denitrification tank flow to settling tank-III. The settling tank-III is similar to settling tank-I.
Similar facilities for collecting settled sludge from settling tank-III and pumping it to
sludge thickener inlet, sump, and pumps provided.
158
Coke Ovens
From the de-nitrification tank, effluent flow to aeration tank-III, where surface aerators
are provided in the aeration tank to supply required dissolved oxygen in the treated
effluent before disposal.
A sludge thickener is provided for thickening the excess sludge received from different
sludge sumps. The thickener is provided with sludge collection arrangement and all other
accessories. The overflow from sludge thickener is fed at the inlet of aeration tank-I
The underflow from sludge thickener is collected in a thickened sludge sump from where
it is pumped to sludge drying bed unit for dewatering of the sludge.
c. Design Specification
Inlet Concentration
Outlet Concentration
7.5 to 9.0
6.0 to 8.0
Temp.
50 - 60 Deg. C
Ambient Temp
Phenol
500 mg/l
1 mg/l
Cyanides
50 mg/l
0.2 mg/l
10 mg/l
500 mg/l
Ammonical N2 :50mg/l
SS
100 mg/l
BOD
30 mg/l
COD
250 mg/l
pH
Total Ammonia
159
A) Introduction
Energy Management Department looks after the Management and judicious
distribution of various liquid and gaseous fuels in the plant. The department
comprises the following sections.
1. Energy Monitoring Centre
2. Gas Safety
3. Laboratory
4. Additional Gas Boosting Station (AGBS)
5. Mixed Gas Boosting Station (MGBS) For Mills
6. Coke Oven Gas Boosting Station (CGBS) For Sinter Plant
7. Mixed Gas Boosting Station For LDCP
8. Gas Mixing Station For Mills
9. Gas Mixing Station For Sinter Plant
10. Gas Mixing Station For LDCP
11. BOF Gas Holder Operation
12. Energy Accounting And Conservation
13. Indenting And Planning Cell
14. Maintenance ( Mechanical And Electrical)
C) Gas SafetySection
This is very important section of the department. The main objective of this section is
as follows:
160
ii.
To create awareness among all working people about the basic principle of
gas safety.
iii.
Scheduled and emergency monitoring of gas prone areas of the plants for
presence of carbon monoxide gas in the atmosphere. Maintenance and
repair of oxygen breathing apparatus / gas mask.
iv.
D) Laboratory
Some regular and intermittent gas analysis is done to find the percentage of
constituents of the gas. Followings are the analysis jobs done at the laboratory.
i.
ii.
iii.
iv.
161
162
ii.
iii.
iv.
v.
163
A) Introduction
In any integrated steel plant, the importance of an Electrical Repair Shop can very well be
envisioned as it is considered as the Heart of the plant. It is one of the major service shops
which executes repair of all kinds of electrical equipments/machines used inside the plant.
There are various kinds of electrical machines of different ages and specification installed
and running continuously since many years, in different processes of production in IISCO
Steel Plant. General maintenance like cleaning, greasing and physical inspection /
checkups is done by concerned shops where the machines are used. All major repairs like
winding repairs, mechanical repairs, modification in existing winding, periodic
overhauling and innovative repairs etc. are being carried out by Electrical Repair Shop
B) Scope of Repair
Electrical Repair Shop carries out repairs of motors, generators, welding machine, brake &
control coils of all types and capacities.
Repairs from outside agencies are arranged strictly on need basis. Certain repairs like core
staggering, shaft change etc. for which repair facilities are not available in ERS are off
loaded to outside agencies. The repairs are limited in number and applicable for big size
and critical machines only.
C) Manpower Employed
ERS has a present manning of 61 non-executives and 6 executives of various grades. The
shop is headed by DGM (EM) ERS.
165
Hot Box
Electrical or
mechanical
Fitting Section
ect
ctric
Winding Section
Ele
Test Bed
Section
Test Bed
Fitting Section
Def
Coupling Section
Test Bed
al
Fitting Section
Mechanic
al Defect
Mechanical Section
problem
2. New ERS
a. AC LT and DC distribution (PDB & MCC) under ERS control.
b. Operation of Maintenance pump & compressors.
c. Operation of Maintenance of EOT crane in ERS & under ERS control.
d. Transfer car & battery Maintenance.
e. Area & Building illumination under ERS control, including street light, tower
light & high Mast light.
f. Earthing system of ERS including fire fighting & alarm system.
g. Maintenance of motor installed in ERS and under ERS control.
h. PLC controlled panel & other control panel of new ERS.
167
2. Machine Shop
The section caters to the need of all the mechanical repairs of the machines. It is
engaged in repairs like thread repair, key way repair, coupling boring, mica cutting
etc. The section is equipped with lathe machine, shaper machine, drilling and
punching machines. It is assisted to the welding section, which has both Arc
welding and gas welding facility. This section also makes the small mechanical
parts needed for the repair in case of mechanical defect.
3. Coupling Section
When a Motor with a Pulley/ Coupling Fitted to its shaft, comes to ERS for repair,
coupling section removes the coupling / pulley from its shaft and the motor is sent
to the dismantling & assembly section for dismantling. When motor is repaired and
assembled again, it is sent back to coupling section where coupling/pulley is fitted
again to the shaft and motor is sent to the receipt and issue section for dispatch.
4.
168
After successful repair of both the mechanical and electrical parts the machine is
then assembled here .The assembly sections takes those components of a machine
for assembly which are ready in all respects. Before assembly the components are
thoroughly checked to ensure whether all the repairs as mentioned in work order or
as noticed by assembly group are carried out or not. In case there is some
omission, it is sent to concerned section for further repair. After assembly, the
machine is sent to testing section again for final test.
Assembling and dismantling activities are carried out at two different sections.
i.
ii.
DC FITTING SECTION
This section handles the Dismantling & assembly of DC machines only.
The machines which are sent to this section are DC motor, Traction motor,
Traction generator etc.
5. Winding Section
As the very name signifies, winding of stators, rotors, armatures, coils etc are
carried out in this section. When a burnt component is taken up for rewinding, first
the number of poles, insulation class and connection is noted from the name plate.
Then winding is opened and end connection scheme, coil pitch, coil turns, No. of
slots, wire size etc. are noted precisely. One sample coil is removed and is kept for
preparing new coils. Now the old winding is removed, slots are cleaned properly
and slot insulation like Nomex or Manilex paper is provided. Then new coils are
IISCO Steel Plant
169
The liquid varnish is nothing but a thermo setting resin, when it is kept in furnace
the polymerization reaction takes place and varnish dries up like a moulded thermo
plastics. This provides a perfect bracing of the conductor in the slots. It protects the
winding against the mechanical vibration which develop during operation of the
machine.
After varnishing the component is sent to assembly section for further activity.
This section is engaged in repair activities of all the defective commutators and
slip ring. Here first the end cones are opened, then commutator segments and mica
insulation is checked meticulously for any damage. If required the copper
segments are changed or mica insulation is also changed, end cone Micanite ring
insulation is also developed. Then it is completely assembled after drying, it is sent
for High voltage test to ensure the quality of repair.
Slip rings are also repaired here. Generally the epoxy insulation gets damaged
under adverse operating conditions. Here the defective insulation is removed and it
170
6.
Testing Section
The primary objective of testing an electrical machine is to ensure whether it is
suitable for and capable of performing the duty for which it is designed. Testing
section of ERS assures quality of the machine which is successfully repaired.
Testing of electrical machines is carried out in accordance with the provision of
different International and National standards like B.I.S, IEEE etc.
Testing section conducts the following tests on all repaired machines on no load at
ERS besides conducting a set of tests on all machine components in intermediate
stages.
Rewound stators and rotors of a machine are subjected to 1000 V flash Test to
check insulation. They are also subjected to Drop test to check whether the all
Phase are balanced or not. If test is ok then Stator/ Rotor is sent for varnishing.
When Machine is received after repairing, then machine is tested for No Load
Test. In this machine is tested at its rated voltage without any load for few minutes
and its current and voltage drop is noted down. Its test data is noted down in Test
Report Book.
171
If the component does not comply with the testing norms, then they are sent for
necessary repair and rectification. Good components are sent for final assembly to
the assembly section. After assembly machines are received again at testing
section for final test. Final test includes No Load Run Test and Load test.
Store issues a spare part when requested by the concerned section for replacement.
It keeps a record of the spare parts issued and spare parts received from other
stores. When an item is about to finish, then store issues a request to buy the item
through indent and request is sent to the Material management department for
further process. When item is received from general store then Store updates its
record of the item. Store also prepares a monthly consumption report and based on
this report, it prepares planning for the next month for the better and timely
availability of the spare parts.
172
A) Introduction
ETL, Electro Technical Lab department of IISCO Steel Plant deals with PLC & Drive
automation, Electronic panels and power system protection & HV testing in the plant.
The department has been playing a key role by involving in successful commissioning
of automation and power system protection schemes in our upcoming new plant and
maintaining them effectively.
Our new plant has state of the art automation technology and automation systems
form an integral part of the processes. Any problem in the automation system
may result in the total stoppage of the particular process. Hence, ensuring
trouble-free functioning of automation systems is very much essential for the
smooth running of our plant. On the other hand IISCO Steel Plant has numerous
types of electrical equipment operating at different voltages. These include high
tension equipment at LBDS & Main Receiving Station (MRS) from where power
is distributed to different units of plant via different Substation units (LBDS) in the
plant. The power system protection equipment in these areas are very critical for safe
operation & preventing damage to the equipment.
The custodians of these equipment are the shops and departments concerned, who are
responsible for their day-to-day operational and maintenance activities. ETL
department
maintain them.
ETL provides
including HV testing, PLC & Drive automation system and electronic panels like
UPS, Micro controllers etc. in order to ensure smooth operation of the plant.
Modifications and additions for better performance of the equipment are
done by
ETL. ETL also ensures that shops adhere to the technological norms in the operation
of the equipment. The important roles of ETL are enumerated below:
i.
Periodic
testing
of
protective
devices
of
electrical
equipment
173
iii.
iv.
v.
vi.
vii.
Technical
support
to
the
different
shops
in
preparation
of
ix.
x.
xi.
xii.
xiii.
competitive edge.
xiv.
xv.
174
ETL has been divided into section specialized for specific work. ETL has three groups
looking after different areas. These are as follows:
a. Power Systems & High Voltage Group
b. PLC Automation & Drives Group
c. Electronics Lab & instrument Repair
The above mentioned group is further divided in to sub groups. Each sub group is
assigned a particular set of areas. Though ETL primarily works on equipment at
site, it has well developed test laboratories
for
all
the
above
sections,
having the latest testing equipment and diagnostic tools. In addition to the
requirements of the plant, ETL also provides support for maintenance of medical
equipment in Burnpur Hospital. The detailed working of each of the above groups is
enumerated below:
B) Power Systems & High Voltage Group
This group deals with EHT, HT and LT equipment at our main step
down substations, captive power plants (PBS) and LT substations , the high voltage
testing requirements HT equipment and high voltage safety appliances. The main
functions of this group are as follows:
1. Periodic testing of protection system at all our EHT, HT and LT
substations, captive-power plants and HT equipment like HT motors,
turbo generators and transformers. This is to ensure the reliable operation
of protective devices so, that there is no equipment damage, and minimum
disruption in power supply.
2. Periodic checking of islanding schemes for our captive power plants,
voltage regulators of turbo generators and static exciters of synchronous
motors.
3. Attending breakdowns in the above areas for quick liquidation.
IISCO Steel Plant
175
high
voltage
testing
of
motors,
transformers,
circuit
checking
of
the
operating
VVVF drives.
6. Taking drive parameter backup periodically for archiving.
7. Support shop electrical for Preventive maintenance and breakdown
maintenance of drives for quick liquidation of fault.
8. Proactive measures like recording and documentation of parameters of
different
parameters.
9. Investigation of recurring problems in the drives area and their
rectification.
10. Carrying out innovative modifications in the Automation schemes to achieve
better equipment utilization, energy savings and less equipment downtime.
11. Retrofitting of obsolete PLC and Drive system.
12. Support shop electrical for Preventive Maintenance and troubleshooting of
UPS system.
13. Support shop electrical for Preventive maintenance and troubleshooting of
different electronic controllers.
D) Electronics Lab & instrument Repair
This group deals with the repair of complex electronic cards & modules, testing &
calibration of electrical measuring instruments used all over the plant. This was
IISCO Steel Plant
177
and
de-soldering
stations and
other
diagnostic
tools. Repair
of
electronic cards at ETL has resulted in substantial savings for the plant.
178
Instrumentation
INSTRUMENTATION
A) Introduction
Instrumentation department at ISP is a new department that came into existence on the 11 th
March, 2011 as essential need for an independent Instrumentation department was
envisaged for smooth running of the new state-of-the-art 2.5 MT Expansion project.
During this brief period, the department has grown in line with the Plant needs and the
evolution process is still on. Earlier, the Instrumentation needs of the old Plant were
catered by T&I Department.
Instruments in the industry are basic sense organs and provide information about the
process, production, quality and standard parameters. They also process the information
into workable logics and deliver necessary outputs to meet the quality norms.
Instrumentation Department at ISP is a centralized department and is geared up to meet the
Control & Instrumentation requirements of both old and new plant.
The department is divided into 15 sections to cater to the process monitoring and control
needs of different shops of IISCO Steel Plant. Each section has a team of engineers and
technicians working in close tandem with the operation personnel on a round-the-clock
basis for meeting the department objective.
B) Department Objective
To ensure 100% availability & reliability of Process Parameter Measurements, Interlocks,
Protections and Control Systems for safe operation and resource optimization leading to
enhanced quality and productivity in all sections of the Plant
ii.
Control
room
instruments
(indicators,
recorders,
controllers,
Scanners,
Annunciators etc.)
iii.
179
Instrumentation
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
Flame Detectors/Scanners
xii.
xiii.
xiv.
xv.
Dip type temperature measurement systems (Temperature tips & Oxygen Tips)
xvi.
Positioners, I/P Converters, Air Lock Relays, limit switches etc. of Pneumatic
Control Valves/Power Cylinders
xvii.
xviii.
Mechanical Workshop
xix.
Maintenance of Analysers (Oxygen, CO, CO2, H2, H2S, SPM, SOx-NOx, SWAS,
SILICA)
xx.
Turbovisory Systems
xxi.
180
i.
ii.
iii.
iv.
v.
vi.
BOF Instrumentation
vii.
Instrumentation
viii.
Mill(WRM/BM/USM) Instrumentation
ix.
x.
xi.
xii.
2. Old Plant
i.
ii.
iii.
181
Instrumentation
C) Lime Dolomite Calcination Plant Instrumentation
This shop produces calcined lime and heated dolomite for steel melting shop and sintering
plant respectively.
Following main parameters are measured and controlled through ABB 800 xA DCS
System:
1. Kiln temperature Measurement & Control
2. Draught Measurement
3. Waste gas Pressure Control system
4. Electronic Weighing System
182
1.
2.
3.
4.
Instrumentation
5.
6.
7.
Amanoscope
8.
9.
10.
CV Analysers
2.
3.
4.
5.
Cryogenic Measurements
6.
G) BOF Instrumentation:
At BOF, steel is made from pig iron produced in Blast Furnace#5. LD process is employed
for this purpose. Steel made here is sent to Continuous Casting Plant for making
Billets/Bloom/Beam.
The major Control and Instrumentation parameters are:
1. Siemens PCS based Instrumentation &Control System
2. Vibro-feeder weighing System for weighing additives(Sartorius)
3. Liquid Steel Temperature Measurement using throwaway type thermocouples
(ElectroNite)
4. Blow time control
5. Flow and pressure measurement/control of blowing oxygen
6. Lance Height Position Measurement
7. Gas Cleaning Plant and Gas Holder related Instrumentation Systems
IISCO Steel Plant
183
Instrumentation
8. Converter Gas Analysers for O2, CO, CO2
184
1.
2.
3.
4.
5.
O2 analysers
6.
7.
8.
Profile Gauge
9.
10.
11.
CV Analysers
Instrumentation
J) Power and Blowing Station#2 Instrumentation:
This section is involved in maintaining Control & Instrumentation system of 3 nos Oil/Gas
fired Boilers, 3 nos. Steam Turbo Generators, 3 nos. Steam Turbo Blowers, 1 no. Back
pressure Turbo Generator and DM Plant. max DNA DCS System (BHEL) controls and
monitors all Instrumentation parameters:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
2.
3.
4.
Moisture Detectors
5.
185
Instrumentation
type Thermocouples and RTDs have also been developed. In the Precision Machine Lab,
all types of precision and mechanical parts and items related to instrumentation are
fabricated. All the test equipment (calibrators) are calibrated in the Instrumentation
Laboratory against measurement standards traceable to national/international standards to
meet the requirement of ISO: 9001: 2008 Quality Management system.
2.
3.
4.
Turbogenerator Instruments
5.
DM Plant Instrument
186
1.
2.
3.
4.
Instrumentation
5.
6.
7.
Oxygen Enrichment
187
Marketing Department
MARKETING DEPARTMENT
A) Functions
Primary products of SAIL units are sold by network of CMO Branches spread all over
the country. However, apart from the prime products, each SAIL unit also generates
many secondary materials/products like Melting scrap generated in Blast Furnaces,
Steel Melting Shop, Rolling Mills ,Coal Chemicals (Benzene, Benzol, Toluene, SB
Oil) and Ammonium Sulphate (SOA) from Coke Oven activities .
Marketing Deptt of ISP is responsible for disposal of Secondary Products, disposal
of idle assets and disposal of defective structural and semis generatedat IISCO Steel
Plant.
Secondary materials shall include materials arising from different processes involved
in Iron and Steel making such as:
a. Melting scrap generated in the Blast Furnaces, Steel Melting Shop, Rolling Mills,
Engineering shops, foundries etc.
b. Re-rollable Steel items/arising like defectives, rejects, cobbles, cuttings &
shearing generated in the Rolling Mills, Continuous Casting department (CCD),
Steel Melting Shop (SMS) etc.
c. Secondary products/By products/Fertilizers/Coal Chemicals generated from Coke
making, screening & transportation activities.
d. Other industrial arising generated in works area like Zinc dross, used rollers,
lubricants, bricks, maintenance /wear scrap, turning/boring scrap etc.
e. Used graphite electrodes, sludge and waste materials including cinder, Mill scale,
Flue dust, Blast Furnace Sludge ,Coal rejects etc.
f. Industrial gases including Nitrogen, Oxygen, Argon etc.
188
Marketing Department
i.
ii.
iii.
iv.
v.
Proposal for approval of H-1 price (highest price received in the auction)
by marketing department.
vi.
vii.
C) Mode of disposal
To sell all the items covered under the scope in a fair and transparent manner and get
maximum price, any of the following methods may be adopted:
i.
Electronic auction
Electronic auction through Internet.
189
Marketing Department
ii.
iii.
iv.
Secondary Products are Sold through e- auctions which are conducted by Mjunction
Services Pvt. Ltd.
Ammonium Sulphate and BF Granulated Slag are sold through free sale notice issued
time to time. B F Granulated Slag is also supplied to Local Cement Manufacturers on
the basis of free sale notice rate.
Marketing Department
Reserve price shall be fixed before conducting electronic auction for the sale
of material. The reserve Price can be revised, if even on second time of
auctioning, H-1 bid received is lower than the limit followed by Plant which
should not be less than 90% of the Reserve Price. . No bid received against
any particular lot during auctioning shall also be reckoned as an attempt for
sale for the lot.
ii.
The highest bid (H-1) received, if is equal to or more than the Reserve Price,
Material shall be sold to the H-1 party after receipt of the approval of the
competent authority.
iii.
If the H-1 offer is lower than the Reserve price and is more than or equal to
the limit followed by ISP which is subject to a lower limit of 90% of the
Reserve price , the material may be sold toH-1 bidder depending upon market
condition, after receipt of the approval of the competent authority.
iv.
If H-1 offer is less than 90% of the reserve price, the case may be reauctioned.
v.
In case the H-1 party backs out before or after accepting the sale order, its
EMD may be forfeited and appropriate action as per the terms and conditions
of the electronic auction may be taken. In such cases H-2/H-3 party may be
asked to accept the H-1 rate one by one, after receipt of approval of competent
authority. In case, H-2, H-3 parties do not accept the H-1 rate, re-auctioning
may be resorted to.
191
Marketing Department
i.
If the highest offer (H-1) received, is equal to or more than the Reserve price,
order may be placed on the H-1 party without conducting the negotiations.
ii.
If the H-1 offer is lower than the Reserve price and is more than or equal to
the limit followed by ISP which is subject to a lower limit of 90% of the
Reserve price, negotiations may be conducted with the approval of the
competent authority to bring the offer at par or above the reserve price before
placement of order. However, if negotiations do not succeed to bring the price
at a par with the Reserve price but since the quoted price /negotiated price is
within the specified limit, the order depending upon market conditions may be
placed on H-1 party on quoted /negotiated price.
iii.
If the offer received is less than 90% of the reserve price, negotiations may be
conducted with the approval of the competent Authority .After conducting the
negotiations if the price is not brought within the specified limit, the case may
be re-tendered. However, if the negotiated price is within the limit, order
depending upon market condition may be placed on H-1 party.
iv.
In case the H-1 party backs out before or after accepting the sale order, its
EMD may be forfeited and appropriate action as per the terms and conditions
of the electronic auction may be taken. In such cases H-2/H-3 party may be
asked to accept the H-1 rate one by one, after receipt of approval of competent
authority. In case, H-2, H-3 parties do not accept the H-1 rate , re-auctioning
may be resorted to.
In case more than one party becomes H-1 and found eligible for placement of
order/negotiations, negotiations may be conducted with all of them separately after
receipt of approval of competent authority and order to be placed on the revised H-1
party.
In case, even after negotiations, more than one party remains H-1, the order may be
placed by draw of lot in presence of all H-1 parties at revised H-1 price.
192
Marketing Department
Idle assets are those, which are no longer required of intended purpose and/or retired
from active use. These may be categorized as assets becoming idle:
i.
ii.
iii.
The major reasons for items becoming idle could be either /or a combination of the
factors
including
technological
up
gradations/modernization
of
ii.
Then the asset is surveyed by the Standing Survey Committee which sends it
for concurrence of Finance and approval of CEO. The Standing Survey
Committee at ISP comprises of members from finance, Drawing &Design
department, and concerned department and headed by GM (Mechanical).
iii.
iv.
v.
vi.
After getting auction report from mjunction a proposal is put up for approval
of auction price by Marketing department.
193
Marketing Department
vii.
viii.
ix.
x.
194
Sl. No.
Scrap Steel
36000
97130
Benzol
588
Benzene
823
Toluene
106
L. S. Naphtha
59
306
28554
26861
10.
10266
11
7961
12
Elemental Sulphur
898
13
Naphthalene Crystal
94
14
Nut Coke
42500
15
Breeze Coke
37200
16
383333
17
56000
18
BOF Slag
69317
19
Idle Assets
---------(20 Crores)
Medical Services
BURNPUR HOSPITAL
General Medicine
ii.
General Surgery
iii.
iv.
Ophthalmology (eye)
v.
ENT
vi.
Orthopedics
vii.
Paediatrics
viii.
Dermatology (Skin)
ix.
Psychiatery
x.
Dental
xi.
xii.
xiii.
xiv.
xv.
Anaesthesia
xvi.
Pathology
xvii.
Radiology
xviii.
Medical Stores
iii.
iv.
v.
Dialysis unit
vi.
195
Medical Services
vii.
Leprosy clinic
viii.
Nephrology clinic
ix.
x.
xi.
xii.
Chhottadigari Dispensory
xiii.
xiv.
xv.
D) Investigation facilities
i.
Pathology lab
ii.
Biochemistry lab
iii.
Haemotology lab.
iv.
Microbiology lab
v.
Blood Bank
vi.
Radiology
vii.
viii.
ix.
x.
ECG
xi.
Holter Monitor
Haemodialysis Machine
ii.
iii.
Auto Analyser
iv.
Cell counter
v.
TURP
vi.
Auto Refractometer
vii.
viii.
196
ix.
x.
Medical Services
xi.
xii.
xiii.
Haemodiaysis machines
xiv.
xv.
xvi.
Defibrillators
xvii.
xviii.
xix.
xx.
F) Administrative Section
i.
Hospital Administration
ii.
Account cell
iii.
iv.
v.
Mediclaim
G) Service function
i.
Ambulance Section
ii.
iii.
iv.
Mechanised Laundry
v.
Modern Kitchen
vi.
4 cabinet Morgue
H) Allied Service
i.
ii.
Telephone exchange
iii.
I) OHS Centre
197
Medical Services
For employees of plant curative, investigation & preventive for occupational hazards.
Also conduct programs onawareness on health measures. Periodical camps also
carriedout.
iii.
Works Clinic attached to OHS centre at ISP works, functioning round the clock.
iv.
v.
vi.
Helps CSR department in holding regular medical camps & medicines arebeing
supplied by Burnpur Hospital.
vii.
Hospital is catering medical services to the retired employees and their spouses.
viii.
ix.
x.
xi.
xii.
xiii.
xiv.
xv.
We give coverage to employees of our Kolkata and New Delhi ISP Offices.
198
Medical Services
199
Materials Management
Materials Management
Purchase requests are raised by each department to register its requirement and same
is translated into indent for further procurement action after necessary scrutiny by
200
Materials Management
screening committee and respective planning sections. Approximately 2000 indents
are raised in a financial year.
Consumables with predictable pattern of consumption and preferable having more
than one user are declared as Automatic Procurement items (AP Items). Indents for
AP items are raised by MMIS section of MM division based on past consumption
pattern. However, any special requirement of a department needs to be
communicatedto MMIS so that same are includedwhile raising indents.
2. Purchase
Purchase department is organized on the basis of nature of items e.g. Refractory, Raw
materials, Rolls, Electrical consumable, Electrical spares, General consumables etc.
Mechanical spares are however dealt on the basis of shops e.g. Coke oven spares,
Blast Furnace spares and so on.
Indents are normally processed through Single tender, Limited tender, Open/global
tender. Others modes of procurement are Rate Contracts/ MOU, Inter plant stock
transfers, DGS&D Rate contracts. Offers received against tenders are technically
evaluated. Order is placed on lowest technically acceptable vendor.
Total 2500 purchase orders valuing Rs. 200 Crore are issued by purchase department
for stores and spares. Orders for more than Rs. 300 Crores are issued for raw
materials. These will go up significantly with the commissioning of new plant.
201
Materials Management
5. Stationery Stores- Handles Stationery items.
6. Medical stores- Handles items related to hospital and is located in Hospital
premises.
Each item is having and Bin Card where receipt and issues are recorded. More than
one lakh bin cards are available in stores. Total inventory available in stores is more
than Rs 130 crores.
GRIN (Goods Receipt and Inspection Note) is the document which is generated for
acceptance or rejection of material.
Users can get the materials issued against Stores Issue Voucher.
Inspection department checks the quality of incoming materials. Materials are
normally checked after receipt at stores. In some cases, inspection is carried at
vendors premises before dispatch. In some critical cases, third party is appointed for
carrying out inspection.
Most of the activities of Materials Management are computerized and Users have an
access to Integrated Maintenance and Materials Management Integrated System
(IMMMS). Various transactions related to creation of item code, vendor code,
generation
generation of purchase orders, Day book, GRINs etc are being done through IMMMS.
This section is also responsible for bringing out various MIS reports for effective
monitoring of performances.
There will be a big jump in responsibilities of Materials Management with the
commissioning of new plant. Material division is gearing up to fulfil additional
responsibilities.
202
Operation Garage
OPERATION GARAGE
A) Introduction
Operation Garage department provides support service to various units of ISP, Burnpur.
Operation Garage is categorised into two sections.
i.
ii.
Removal of wastes from THF-I, THF-II, Duplex area & Stipper shed by
Crawler Loader & Dumpers.
ii.
iii.
iv.
v.
vi.
vii.
viii.
Removal /dozing of slag boulder from blast furnace slag pit area (BF).
ix.
Removal of mill scale from BBM, HSM, LSM&WRM from dumper & loader.
x.
Shifting of coke nuts at different size from breeze bunker and emergency
bunker to back shunt area at COB#11.
xi.
xii.
Collection of breakdown spares from mills and other unit to fitting section by
Dumper and general cleaning of plant by Loaders, Shovel &Dozer.
203
Operation Garage
ii.
iii.
iv.
v.
vi.
vii.
204
Operation Garage
viii.
ix.
x.
Dumper
20
Excavator
Mobile Crane
Water Sprinkler
Service Van
Diesel Browser
Lime Tanker
205
Operation Garage
Flue Dust Tanker
Tripper 10t
Rail
Crawler Crane
Truck
87
2.
3.
4.
5.
6.
7.
8.
9.
206
Operation Garage
C) Central Garage Section:
Vehicles of garage section are mainly utilised to coordinate the various activities of all
departments of plant (such as govt. auditor duty, plant control, laboratory, Dakcollection
& despatch, break down jobs as wells as material such as spares, tools & tackles etc).
The jobs done by Central Garage in general are as follows:
i.
ii.
iv.
v.
Vehicles ( Jeep , Mini Bus, Mini Truck, School Bus & Motor Cycle) to be
provided to CISF unit.
vi.
Vehicles are also given in Election Duty and Judiciary Duty on demand.
vii.
viii.
ix.
Department has also entered into Centralised rate contract of various types of
vehicles.
b. Trucks / Tippers
Used mainly for transportation of spares / consumable of stores and also for various
operational requirements. Used mainly for transportation of spares / consumable of
stores and also for various operational requirements. The trucks are required for
IISCO Steel Plant
207
Operation Garage
operation in the following department on regular basis: Coke Oven Battery, RMHP,
Sinter Plant, MRD & Refractory etc. The tippers are deployed majorly in OHP, Raw
Materials, Civil Maintenance and PME Departments.
c. School Bus
These are used on fixed deployment basis for school bus service of five schools which
are in the close vicinity of the plant. It facilitates daily transportation of office
employees. It caters the commuting of Management Trainees, ACT and OCT for plant
and HRD trainings. The facility is also used for Mahila Samaj Function and other
cultural events of plant etc. In addition to plant duty, buses are also used for Election
Duty and Judiciary Duty on demand.
d. Cash Van
These vans are used for secure monetary transactions between Finance/Account
Department and other Financial Institutions (Banks etc.).
JEEP
SCORPIO
TATA SUMO
TATA SPECIO
MARUTI SWIFT
CAS VAN
AMBULANCE
MINI BUS
BUS
208
Operation Garage
TRUCK
17
TRIPPER
PLATFORM TRUCK
FOAM TENDER
MOTOR CYCLE
11
TOTAL
75
209
Operation Garage
HOD
DGM (OPERATION GARAGE)
210
Oxygen Plant
OXYGEN PLANT
A) Introduction
Oxygen Plant comes under Utilities Department in our 2.5 MT IISCO Steel Plant.
Oxygen plant has two Air separation units each having a capacity of 750 ton per day
(TPD) of Oxygen. The main products are Oxygen, Nitrogen and Argon which are
supplied to other units in our Steel Plant.
Oxygen is primarily used in Basic Oxygen Furnace (BOF) for converting Hot metal
into Steel. In Blast Furnace (BF) oxygen is used for enrichment of blast air.
Nitrogen is used for quenching in Coal Dry Cooling Plant (CDCP) and for purging,
sealing purposes in other units.
Argon is mainly used in Secondary Refining Unit for refining purpose.
Apart from these, there is a provision for filling Oxygen, Nitrogen and Argon in
cylinders and in tankers at 2 x 750 TPD Oxygen Plant as per following pressures:
i.
ii.
iii.
iv.
v.
vi.
B) Process Description
The basic principle of the process is to separate liquid air into its various components
by cryogenic rectification using the different boiling points of the air gases. For the
production of gaseous oxygen the corresponding liquid product is pressurized by
pumps, warmed up and evaporated in the main heat exchanger and distributed to the
lines.
Liquid products are LOX, LAR and LIN
The air separation plant consists of the following parts and sections:
i.
ii.
Molecular sieve station for the removal of water vapour, most of hydrocarbons
and CO2.
211
Oxygen Plant
iii.
Heat exchangers for cooling down the process air close to its dew point and
for warming up the products.
iv.
Booster Air Compressors (BAC) for the additional compression of the process
air before entering the main heat exchanger (MHE).
v.
Refrigeration
vi.
Rectification
vii.
In the evaporation cooler the dry and pressure-less nitrogen absorbs part of the
injected cooling water. The required heat for the evaporation is provided by the water
which is cooled down by this effect. This water is called chilled water.
The water losses of this system due to evaporation will be recovered by cooling water
out of the cooling water system.
212
Oxygen Plant
While one absorber is purifying the air, the other absorber is regenerated. During the
heating cycle the regeneration gas (waste nitrogen gas from the cold box) is heated by
an electrical heater (2602.17.BE1) and desorbs water and CO2 from the molecular
sieve. During the cooling cycle the heater is switched off and the adsorbent is cooled
down with cold dry waste nitrogen gas. After the completion of the regeneration
sequence, the adsorber is pressurized before being switched over to the adsorption
cycle.
The regeneration cycle consists mainly of:
Heating; Cooling; Pressurizing; Depressurizing.
The regeneration gas coming from the rectification unit as waste gas is heated up in
the regeneration gas electrical heater 2602.17.BE1 at heating period. At cooling
period the heater is bypassed. An important indication for sufficient regeneration is
the regeneration peak temperature which appears during the cooling cycle. At the end
of the regeneration cycle the regenerated absorber is set into operation and the other
one starts with a new regeneration cycle.
The cycles are automatically controlled by a program.
E) Process Refrigeration
The dry and purified process air after the molecular sieve unit 2601.01A/B.BA1 splits
into two streams. The first stream is not compressed further. It is cooled down in the
main heat exchanger (3002.16.BE1), to about liquefaction temperature while the cold
gaseous oxygen and nitrogen streams coming from the columns are heated up. The air
is fed to the bottom section of the pressure column (3001.11.BT1).A second stream
splits in two. One is from BAC intermediate stage and other is the BAC final stage
discharge. The BAC intermediate stream cools down in the MHE before entering into
the Expansion Turbine (3401A/B.71.BX1). After expanding in turbine the stream is
fed into the rectification column 3001.11.BT1 .Liquid which appears in the separator
3002.32.BD1 is fed into the rectification column 3001.12.BT1. The BAC final stage
discharge stream is expanded in the rectification column 3001.11.BT 1 after passing
through the MHE 3002.16A/B/C.BE1.
213
Oxygen Plant
F) Refrigeration
The refrigeration requirement of the plant is due to insulation losses, heat exchanger
losses and removal of cold liquid out of the Low temperature section. These losses are
met by the Adiabatic Expansion (valve etc.) and by nearly isentropic expansion of the
air in the Expansion Turbine 3401A/B.71.BX1. The Expansion Turbine
3401A/B.71.BX1 is connected with the generator 3402A/B.20.CG1 which serves as
the brake for the turbine.
214
Oxygen Plant
Gaseous impure nitrogen stream leaves the top of low pressure column, warms up in
the sub cooler and in the main heat exchanger. After that it serves partly as cooling
gas for evaporation cooler and partly as regeneration gas for the mol sieve station.
J) Plant Components
1. Main Air Compressor (2 Units)
Process gas
Air
Operating Point
Units
Guarantee Minimum
Flow Rate
Nm3/hr
111700
81000
Suction Pressure
Bar a
0.993
0.993
215
Oxygen Plant
Discharge Pressure
Bar a
5.6
Make
ATLAS COPCO
5.6
Air
Flow rate
Nm3/hr
62660
Operating Point
Units
Section 1
Section 2
Suction Pressure
Bar a
5.3
32.5
Discharge
Bar a
32.5
58
Pressure
Make
ATLAS COPCO
Air
Operating Point
Units
Guarantee
Minimum
Flow Rate
Nm3/hr
25800
16000
Inlet Pressure
Bar a
32.3
32.4
Outlet Pressure
Bar a
5.3
5.3
Inlet Temperature
-109
-117
Outlet
-173
-174
427
220
Temperature
Power
at KW
Generator
Coupling
Make
216
CRYOSTAR
Oxygen Plant
217
Oxygen Plant
Product
Source
Flow min
Flow max
Pin
P out
m3/hr
m3/hr
Bar
Bar
20000
20000
20
7-10
Consumer
(PRMS)
OXYGEN
1
PGOX (2)
LOX IC+
PRV
PGOX(1)
LOX IC+
ENRICHMENT
20000
20000
20
12-19
PRV
3
HPGOX(5)
LOX IC/
BF FOR
76000
40
18-22
BOF
2000
4000
40
12-17
CCP &
BACK UP
4
HPGOX(4)
LOX IC/
BACK UP
GENERAL
PURPOSE
HPGOX (3)
(BUFFER)
10000
10000
40
7-10
BF
LIN IC/
13000
13000
31
31
BOF/CCP
18000
18000
12-
12-17
12-17
NITROGEN
1
HPGAN
BACK UP
2
MPGAN
N2Comp
17
3
MPGAN (1)
BACK UP
9000
9000
31
THROUGH
VAPORIZER
ARGON
1
GAR
BACK UP
3500
16
16
218
Oxygen Plant
219
Oxygen Plant
Liquid nitrogen is pumped from Liquid Nitrogen tank up to 160 bar and after passing
through atmospheric vaporiser, filled in cylinders and given to customers. LIN tanker
filling pump installed in LOX tank area pumps up to 28 kg/cm2 to fill LIN Trucks.
Liquid Argon pump installed in LAR tank area, pumps up to 160 bar and after passing
through atmospheric vaporiser, filled in cylinders and given to customers. LAR tanker
filling pump installed in LAR tank area, pumps up to 28 kg/cm2 to fill LAR Trucks.
Density of Oxygen is more than air and it will accumulate in pits and trenches.
So avoid entering in pits, trenches near area with possible oxygen leakage and
if it is necessary, always check with oxygen meter before going in.
ii.
iii.
Any manual valve in Oxygen service must be open slowly. Never strike on
pipes or valves in Oxygen service with hammer or iron rod.
iv.
Liquid Oxygen causes cold burn if it is allowed to come in contact with skin.
v.
Oxygen enrichment can enhance the combustion process. Any type of burning
or smoking is forbidden in Oxygen plant.
vi.
If you have been in oxygen enriched atmosphere you must ventilate your
clothing in the open air for at least 15 minutes before smoking or going near a
source of ignition.
2. Nitrogen/Argon:
i.
Nitrogen and Argon are non-toxic but dont support life and acts as
asphyxiates.
ii.
Rooms where these gases are handled or stored must have good ventilation.
iii.
iv.
When liquid nitrogen/ argon evaporate the gas produced is very cold and is
much heavier than air. Thus it can collect in low-lying areas and confined
spaces such as pits and trenches where they may be slow to disperse. If any
person going inside such places, may face oxygen deficiency.
220
Oxygen Plant
N) Plant Performance Data
1. Process Air
Parameter
Unit
Case A (Guar.)
Case B
Mixed Mode
GAS Mode
111000
110600
box)
Pressure
Bar(a)
5.37
5.41
Temperature
24
24
2. Oxygen
Parameter
Unit
Case A (Guar.)
Case B
Mixed Mode
GAS Mode
HPGOX
Flow
Nm3/h
11000
12000
Pressure
Bar(a)
40.20
40.20
Temperature
24.2
23
Purity
Vol. % O2
99.5
99.5
Flow
Nm3/h
1000
Pressure
Bar(a)
1.20
1.20
Temperature
-183
-183
Purity
Vol. % O2
99.5
99.5
Flow
Nm3/h
10000
10000
Pressure
Bar(a)
20.6
20.6
Temperature
24.2
23
Purity
Vol. % O2
99.5
99.5
LOX
PGOX
3. Nitrogen
Parameter
Unit
Case A (Guar.)
Case B
221
Oxygen Plant
Mixed Mode
GAS Mode
HPGAN
Flow
Nm3/h
6500
6500
Pressure
Bar(a)
31.4
31.4
Temperature
24.2
24.2
Impurities
ppm O2
Flow
Nm3/h
9000
9000
Pressure
Bar(a)
16.70
16.70
Temperature
40.1
40.1
Impurities
ppm O2
Flow
Nm3/h
500
Pressure
Bar(a)
1.10
1.10
Temperature
-195
-195
Impurities
ppm O2
PGAN
LIN
4. Argon
Parameter
Unit
Case A (Guar.)
Case B
Mixed Mode
GAS Mode
LAR
222
Flow
Nm3/h
790
790
Pressure
Bar(a)
1.10
1.10
Temperature
-185
-185
Impurities
ppm O2
ppm N2
223
ED (P&A)
GM (P&A)
GM (HRD)
DGM (PL-OD)
DGM (PL-NW)
GM (TS)
DGM (CSR)
AGM (PR)
AGM(TS) Elect.
Dy.Mgr.(TS) Civil
AGM (PL-Non Works)&
LO for OBC
SM (PL-Maint &
Services)
SM (Mills, Shops &
Welfare)
DGM (PL-Welfare)
DGM (PL-Central
Function)
224
2. Plant Personnel
Most important area in the Plant Works area (Operation, Maintenance &
i.
Services)
ii.
iii.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
ii.
225
The Section is headed by DGM (PL-CL& I/c Sports) which deals with
statutory compliance related to contract labour of entire plant and matters like:
ii.
Issuance of gate-pass
iii.
Union pass
iv.
v.
4. Central Functions
i.
ii.
iii.
Sends IR reports to CO
iv.
v.
vi.
Mediclaim
vii.
5. HRD
Organizing training for
i.
New recruits
ii.
Existing employees
iii.
6. Legal Cell.
Deals with cases
i.
ii.
at Industrial Tribunals
iii.
7. Estate
226
ii.
iii.
8. Security
Takes care of security in the township including vital installations and Hospital
ii.
iii.
Electricity Supply
ii.
Water Supply
iii.
Sanitation
iv.
Road construction
v.
Street lighting
11. Education
Takes care of all the Company Schools
i.
ii.
iii.
iv.
v.
ChottodighariVidyapeeth
vi.
ii.
227
Providing basic needs like roads wells / tube wells for water, solar lamps for
light, community halls etc.
ii.
iii.
14. Sports
The major responsibilities of the department include:
i.
ii.
iii.
ii.
iii.
Quiz
iv.
Counseling of employees
v.
vi.
vii.
viii.
Collective Bargaining
ix.
x.
xi.
228
A) Preface
Power & Blowing Station-2 (P&BS-2) is a captive power plant for supplying power to
the different shops in the ISP to facilitate the power requirement and to cater emergency
load in case of grid failure.
ii.
To provide required continuous cold air blast for the blast furnace
iii.
iv.
v.
vi.
b.
c.
CDCP Boiler (4 Nos. Waste Heat Recovery Boilers for dry quenching of hot coke)
d.
e. Steam Turbo Blowers ( 2 working+1 standby, Capacity: 3810 Nm3/hrs at 5.2 kg/cm2)
IISCO Steel Plant
229
g.
h.
i.
1. DeMineralization Plant:
De Mineralization Plant generates make-up feed water for Power & Blowing
Station 2 Boilers. At first raw water is filtered through Clarifier & RO. Then it is
passed through mechanical filters viz. Dual Media Filter and Activated Carbon
Filters followed by Strong Acid Cation Exchanger, Strong Base Anion Exchanger
and Mixed Bed. Capacity of the DM Plant is 150 T/hr.
230
ii.
iii.
iv.
As a process steam in Coke Oven by-product plant and Blast Furnace after
reducing pressure and temperature at 9 ata and 13 ata respectively.
i.
ii.
iii.
Air Preheater:It consists of 2 sections. Air flows across the tubes and flue gas
through the tubes downwards. This is of Tubular Type. Here heat from waste
gas is recovered by the fresh air for combustion.
iv.
v.
FD Fan:Two nos. FD Fans serve to supply air through air preheater for
combustion. Capacity of each FD Fan is 27.4 m3/sec max.
231
ii.
BOF Gas
iii.
iv.
CBM Gas
v.
i.
Oil System consisting of oil Pumps, Oil Tanks, Oil Coolers to supply bearing
lube oil and control oil.
ii.
iii.
Regenerative feed water heating system by low pressure and high pressure
heaters.
iv.
Surface Condenser with 2 pass, cooling water flow capacity 3250 m3/hr and
cooling surface area 1370 m2for cooling exhaust steam of turbine.
232
v.
vi.
vii.
Rankine Cycle:
Boiler uses feed water and converts this water to superheated steam. The
superheated steam after doing work in Turbine exits in the condenser. The exciter
exhaust steam Turbines of Turbo-Blowers & Turbo-Generators are cooled by the
cold water from cooling water system and are converted to water in the condenser.
This water is again sent as feed water to boilers. Thus P&BS-2 operates with steamwater cycle like all conventional power plants taking a small percentage (2-3%) as
make up water (DM water) to compensate the losses in the cycle. The name of this
steam-water cycle is Rankin Cycle.
ii.
8. Control System
The main equipment and related Auxiliaries of P&BS-II are controlled by a state of
the art distributed control system called Max DNA system. The Blower supplied by
MAN Turbo is controlled by their proprietary control system called Turbolog
However Turbolog is completely integrated with Max DNA control system for
smooth control of Turbo blowers. All the control panels are connected by intra plant
bus. Work stations with PCs are provided for operation and control of the whole
plant.
9. Power Distribution
Power is generated at P&BS-II from STG and BPTG at 11 KV. The same is stepped
up to 33 KV and connected to double bus 33 KV GIS switchboard. Synchronization
between power generated at power plant and grid power is done at 33 KV level at
P&BS-II. Power from grid is received at 220 KV level through two nos. 220 KV
feeders at MRS. Grid power is then stepped down to 33 KV at Main Receiving
Station (MRS) by transformers. P&BS-II is connected to MRS by two nos. of 33
KV feeders called Tie-I & Tie-II.
Power is distributed to different plants at 33 KV& 6.6KV feeders. P&BS-II feed the
vital consumers like:
234
i.
Coke Oven
ii.
Blast Furnace
iii.
iv.
v.
1. Boilers
No of Boilers
3 (2 Working + 1 Standby)
Capacity
Working Pressure
66 Kg/cm2
Steam Temp.
4905C
No of Super Heaters
Furnace Depth
8839 mm
Furnace Width
10973 mm
514 m2
Furnace Volume
988 m3
Fuel
Pressure
Max. Flow
CBM
3 Kg/cm2
COG
700 mmWC
BFG
600 mmWC
BOF
LDO
15 Kg/cm2
235
No. of FD Fans/Boiler
2 Nos.
Capacity
27.4 m3/s
Motor Power
175 KW
Speed
1480 rpm
466 mmWC
Control
No. of ID Fans/Boiler
2 Nos.
Capacity
80 m3/s
Motor Power
525 KW
Speed
980 rpm
426 mmWC
Control
750 PST
236
Total No of tubes
3456 Nos.
6060 m2
Width
3155 mm
Length
7485 mm
Height
4550 mm
Dia of tube
63.5 mm
Quantity
4 Nos. (2W+2S)
148.5C
Design Flowrate
272 m3/Hr
Discharge Pressure
104.19 Kg/cm2
Operating Speed
2980 rpm
Power Consumption
1300 KW
Voltage
6.6 KV
Pump Head
1135 mm
487 SVTL
7. Compressor
Make
Kirloskar Pneumatic
Model
TBTDRM
No of compressor
2 Nos.
Operating pressure
7.5 kg/sqcm
2 Nos./Boiler
10 Nos./Boiler
14 Nos./Boiler
Pressure
30 kg/cm2
Temp.
348C
Flow
8 T/Hr
Travel
0.9 m
Travel Speed
2.9 m/min
237
9. Dozing System
a. Ammonia Dozing Pump
4 Nos.
Type of Pumps
Positive Displacement
Make
Stroke
100/minute
Discharge Pressure
9.0 Kg/cm2
Flow
4 Ltr./Hr
Positive Displacement
Make
Stroke
100/minute
Discharge Pressure
9.0 Kg/cm2
Flow
8 Ltr./Hr
238
Type of Pumps
Positive Displacement
Make
Stroke
150/minute
Discharge Pressure
94.0 Kg/cm2
Flow
17 Ltr./Hr
Make
Omega
Total No.
2 Nos.
Motor
Capacity
Travel height
9000 Meter
Travel Speed
0.7 Meter/Sec
239
16.7 ata
62 ata
5 ata
DEA
1.77 ata
STG
LPH
16.7 ata
5 ata
HPH
DEA
1.77 ata
LPH
13
ata
9 ata
Terminal
Point
Point
62 ata
BPTG
13 ata
9 ata
13ata
PRDS
9 ata
Terminal
Point
9ata
PRDS
Steam Line Scheme for Running Boiler, STB, STG& BPTG (Diagram No.2)
240
HPH
BOILER#3
BOILER#2
HPH
BFP4
BFP3
HPH
BOILER#1
BFP2
BFP1
HPH
HPH
HPH
Feed Water Line for Boilers (Diagram No.3)
241
1. STGs (3Nos.):
Capacity
3X18 MW (2W+1S)
Steam temp.
485C
Steam press.
-62 ata
8470 RPM
2. STB(3Nos.):
Capacity
3X228,600 NM/hr.(2Working+1Standby)
62 ata.
5803 RPM.
3. BPTG(1No.):
Capacity
8.275 MW
RPM of Generator
1500
Pressure
62 ata
Temperature
485C
8800 RPM
Design pressure
(shell side)
IISCO Steel Plant
(tube side)
109605-01
Flow
40 m/h
Head
45.5 m
RPM
2900
NPSH
1.6
Flow
30.6 m/h
RPM
2900
Head
43.6m
NPSH 2.5
d. AOP & MOP: (for STG & STB) 12 Nos.
Make
Sulzer
Model
ZE80-2315
Serial No 109622-04/02
Flow
70 m/h
Head
102.3 m
RPM
2945
NPSH
2.0 meter.
243
138m/hr.
Head
107.3 m
RPM
2945
NPSH 4.6 M.
LPM
9, Pressure: 100kg/cm2.
RPM
1450 Motor-3.7KW.
Model
OTC- 2-02-137.
Make
GmbH.
10000 rpm.
2 kg/dm3.
Maximum
heavy
liquid 1 kg/dm3
separation
.
h. Oil Coolers for STGs (6Nos.)
Type
Quantity of oil
48.26Cu.m/Hr.
Surface Area
85sq.m.
No.of
tubes 436.
/cooler
Make
F.
Item
Side
design
pressure
temperature
Surface m2: 46. Radiography & Stress Nil.
relief
j. Oil Filters-Duplex Type- (6+6+2 Nos.): For STG, STB & BPTG.
Technical details:
Make
EPE
Process
filters
&
accumulators
Pvt.
Ltd./HYDAC/HYDAC
Model/Type
12-F10-0300-h10*L-50-3-4,1279887/3509171,
1295837/3458882.
1-0120-HIo*-4-00-0-P.
Sr. No.
Working Pressure
Flow Rate
Degree of filtration
10 micron.
245
Capacity
Charge
14.71cubic meter
Capacity
Make
Model No
LP-10.25
Capacity
RPM
2880
BHP
0.22
Set Pressure
100mmwc.
5. Condensate System:
a. Condensate Extraction Pumps: (for STG)
Make
KSB
Type
WKTR-100/005
Discharge 74 m/h
Head
Speed
73 m
1460
246
Make
KSB
Type
WKTR-125/003
IISCO Steel Plant
73 m
Speed
1470
UP150/53F
Type
WKTR-125/003
Discharge
429.3 m/h
Head
75 m
Speed
1470 rpm
150/200mm
d. Steam Jet Air Ejectors &Main Steam Ejectors: (6 Nos. & 12 Nos.)
Steam Quantity
750kg/hr.
13 atm.
(shell side)
(tube side)
(shell side)
(tube side)
247
1370 sq.meter.
No. of passes
02.
Exhaust Pressure
0.105 ata.
6. Heaters for STGs & STBs (HP & LP-06 Nos. each)
a. HP heater:
Design pressure
20 kg/cm(shell side)
b. LP heaters:
Design pressure
(shell side)
(tube side)
80
33.0M2
Weight
1850
1281M3/Hr.
IISCO Steel Plant
65.2MWC.
RPM
1480.
Jyoti Ltd.
750 M3/Hr.
Head
40 MWC.
RPM
960
Power
55 amp./525KW
.
c. COOLING WATER PUMPS FOR STBs 4 Nos.
Make
5400 M3/Hr.
Head
34.8 MWC.
RPM
740.
750 M3/Hr.
Head
40 MWC.
RPM
960.
Tower Model No
10 RC-U-182-C.
No. Of Cells
(9W+ 1S)
2800M3/hour.
FRP
HUB
MS hdg
249
SS 304.
Model No
B 228
50 liters.
Lubrication
Splash.
Type of Coupling
Flexible, Non-lubricated
Capacity
35Ton / 5Ton
Span
24 meter.
Height
Lift
Operation
Push Button Pendent.L T Gear Box, C T Gear Box, Main & aux. Hoist
Gear Boxes. Other integrated Mechanical part including wheel
carriage system & rails.
Location
250
Recirculation line
Control
valves
CONDENSER
HOTWELL
CEP-1
Motorized
valve
strainer
NRV
valve
GSC
Disch
Valve
CEP-2
Ejector (2Nos.)
CST
NRV
CTP-1
IISCO Steel Plant
251
CTP-2
ii.
252
iv.
v.
M/S VOLT AMP TRF. LTD.MAKE POWER TRANSFORMER- PTR 3 5 MVA, 33/6.9 KV, ONAN, Dyn11: 1 no.
vi.
M/S VOLT AMP TRF. LTD.MAKE POWER TRANSFORMER- PTR 4 12.5 MVA, 33/6.9 KV, ONAN, Dyn11: 1 no.
vii.
M/S
INTRA
VIDYUT
LTD.
MAKE
STATION
AUXILIARY
c. Lighting Transformers:
M/S SEEKO LTD. MAKE LIGHTING TRANSFORMER 100 KVA,
i.
415/433 V :1 No
M/S SEEKO LTD. MAKE LIGHTING TRANSFORMERS 250 KVA,
ii.
415/433 V: 2 Nos
BPTG
POWER
253
31.5
KA/3
Sec.consists
of
Breakers(2500Ax4nos,
potential
transformers,
relays,
Nos.
of
Marshalling
boxes(extension) and other electrical components for smooth operation of the GIS
Switchboard.
4. 11 KV HT Panel
M/S Arevamake VCB breaker & panel (1250Ax1no, 40KA, 3 Sec) and other
electrical components for smooth operation of the breaker panel: 1 No.
M/S BHEL make P&BS main switchboard (59 panels), 6.6kv, 50 Hz, 3 phase,
3150
A,
40
KA/3
sec.
consists
of
VCB
Breakers(3150Ax3nos,1600Ax2nos,630Ax43nos),isolators,earthing switches,
current transformers, potential transformers, relays and other electrical
components for smooth operation of the P&BS main Switchboard
M/S BHEL make Emergency Switchboard (16 panels), 6.6kv, 50 Hz, 3 phase,
1250
A,
40
KA/3
sec.
consists
Breakers(1600Ax3nos,630Ax8nos),isolators,earthing
of
VCB
switches,
current
6.6 KV, 630A Load Isolating breakers for station aux. transformers: 8 nos.
415V M/S L&T Make following Panels consists of 128 Nos.Air circuit
Breakers(4000Ax12nos,2000Ax4nos,1600Ax3nos,800Ax109nos),
isolators,
415V M/S C&S MAKE- BLT (BOILER) MCC (3 nos.). Consists of 9 Nos.Air
circuit Breakers (800A), isolators, MCCBs, MPCBs, isolating switches,
contactors, timers, current transformers, potential transformers, relays and
other electrical components for smooth operation of the LT Switchboard. Each
BLT MCC has 2 incomers, 1 bus coupler, and 112 outgoings
415V, 4000A TPN Bus Ducts and accessories for 8 Nos. Station Aux.
Transformers: 8nos
255
7. 230V AC Panels:
UPS DB-1 Panel (2 Nos. incomings & 90 outgoings),
UPS DB-2 Panel (2nos. incomings & 95 outgoings) &Illumination panels and
distribution boards.
.
8. UPS
9. 230V DC Panels:
DCDB-1 (2 Nos.Incomings & 60 Nos.Outgoings) & DCDB-2 (2 Nos.Incomings
& 109 Nos. Outgoings) 7.5kw, 220v Scanner Air Fan DC Motor starter panels:
3nos
10. M/S C& S Make 11 KV CT& PTSP (Power Transformer And Surge
Protector) Cubicle Panel, CT&NG Cubicle Panel and 11 KV Bus Duct &
Accessories for STG-1, 2 & 3.
CT&PTSP cubicle:
CT&PTSP cubicle consists of 12 nos. of CTs, 6 nos. of PTs, 3nos of Surge
capacitors and 3 nos. of Lightning Arrestors.
PT(11 KV primary, 110 V secondary, 50 Hz), CT (Rated Voltage 11 KV, 50
Hz, Ratio (1500/1), Surge Capacitors (18 KV, 50 Hz, 0.25 F 10%),
Lighting Arrestors (12 KV, 10 KA for 8/20 s)
CT&NG cubicle:
CT&NG cubicle consists of 1 no. of Neutral Grounding Transformer, 6 nos.
of Current Transformer and 1 no. of Loading Resistor. Secondary of Neutral
Grounding Transformer is connected with Loading Resistor
256
made
of
Aluminum.
Bus
support
insulators
are
made
of
257
panels
consist
of
Digitalvoltmeters,ammeters,MWmeter,MVARmeter,MVAmeter,PFmeter,Frequen
cy
meter,
Null
voltmeter,
Analogue
dual
volt
&
frequency
contact
multiplication,hooters,check
synchronization
IISCO Steel Plant
ii.
Reverse power
iii.
iv.
v.
Under frequency
vi.
vii.
Generator differential
viii.
Stator E/F
ix.
x.
Loss of excitation
xi.
xii.
xiii.
Over current
xiv.
Dead machine
xv.
Pole slipping
xvi.
Phase impedance
xvii.
xviii.
259
xx.
Over fluxing
xxi.
xxii.
xxiii.
260
i.
ii.
Reverse power
iii.
iv.
v.
Under frequency
vi.
vii.
Generator differential
viii.
Stator E/F
ix.
x.
Loss of excitation
xi.
xii.
xiii.
Over current
xiv.
Dead machine
xv.
Pole slipping
xvi.
Phase impedance
xvii.
xviii.
xix.
xx.
Over fluxing
xxi.
xxii.
ii.
Reverse power
iii.
iv.
v.
Under frequency
vi.
vii.
Generator differential
viii.
Stator E/F
ix.
x.
Loss of excitation
xi.
xii.
xiii.
Over current
xiv.
Dead machine
xv.
Pole slipping
xvi.
Phase impedance
xvii.
xviii.
xix.
xx.
Over fluxing
xxi.
xxii.
xxiii.
261
b. CWPH crane: M/S Eddy Cranes Engineers Pvt. Ltd make. 15/5T, 8.5M
SPAN: 1 No.
Motors: 4
VFD drives control. (Make- TOSHIBA-VF S11)- 4nos.
19. Lifts
M/S Omega elevators make lift: 2Nos. Motor: 3-phase, 50 HZ, 10 HP, 960 RPM.
Capacity: 544kgs.
VFD Drive: M/S Delta make, Model: VFD-VE, FOC Control: 2 Nos.
Total
No
(BFP 4)
3 squirrel Cage induction motor, 6.6 KV , 62.5 A, S1,
2
Boiler ID Fans
05(Boiler 2B)
3 squirrel Cage induction motor,
3
Boiler FD Fans
6.6 KV , 20 A, S1,
06(Boiler 2B)
3 induction motor, 6.6 KV , 57.5 A, S1, 525 Kw, 989
4
CW
pump
Blower
for
263
Export
Feed
Water
Motor( to CDCP)
Portable
water
3 induction motor,
supply
pump
3 induction motor,
10
11
rpm, 50 5% Hz , IP 55, Ins.cl-F,Temp- 45 , temp classT6, Frame- 71.M6, Rajendra Electricals Make, Sl No.-11D-
108
3 Squirrel Cage induction motor, 415 10%V , 0.98 A,
12
13
Hydrazine Stirrer
264
16
17
18
19
20
21
22
23
Agitator
Motor
for
CW
for
CW
Chlorination evaporator
Motor
for
CW
Acid
dosing pump
Motor
for
Acid
unloading pump
Motor for Bio dispersant
dosing pump
Motor for Anti scalant
dosing pump
Motor
for
Polymoric
Motor for AOP for hyd S1, 1.1 Kw, 1410 rpm, 50Hz 5%, IP 55, Ins.cl-F/8 Rise,
coupling of BFP
26
27
28
Motor for
Motorised
Valve
Motor
for
Motorised
for
Motorised
Valve
Motor
Valve
Motorised Valve in BFP
main Discharge
11
24
16
3 induction motor,
29
30
31
for
Valve
Scoop Control
Motor
Valve
68
oil
pump
Motor
Blower(AOP/MOP)
(TB1/MOP),
(TB2/MOP),
90024193
(TB3/MOP),
33
34
35
Oil centrifuge motor for 1.1 Kw, 2850 rpm, 50 Hz, IP 55, Ins.cl-F, temp-50 , ABB
Blower-3
80B20038-DNV-LR-ABS-GL-RINA BV)
37
38
Oil centrifuge motor for 1.1 Kw, 2850 rpm, 50Hz, IP 55, Ins.cl-F, temp-50 , ABB
Blower-1
266
Blower(For oil inlet & Kw, 1405 rpm, 50Hz, IP 55, Ins.cl-F, Frame- 80, Bharat 6
Outlet pump)
Motor
40
condensate
extraction
pump
for
Blower
41
42
43
44
45
Motor
for
Motorised
for
Motorised
for
Motorised
for
Motorised
Sl No.- L0905637(TB1/CEP2),
for
Motorised
45
24
Lube oil pump drive 250 L, CG Make, Sl No- NADT 99601 ( STG 1- MOP),
Motor for STG
Motor for Jacking oil ND 112 M, CG Make, Sl No- HLAM 13689 ( STG 1-JOP
pump for STG
1), INJ 11127 ( STG 1-JOP 2), GKG 10179 ( STG 2-JOP
1), INK 11541 ( STG 2-JOP 2), HLAM 13690 ( STG 3-JOP
1), INK 11536 ( STG 3-JOP 2)
48
Turning
Gear
drive
Make,
Sl
No-
N8/64123494
Frame-180L, 3
(STG
1),
267
Motor for Oil vapour S1, 0.37Kw, 2880 rpm, 50Hz 5%, IP 55, Ins.cl-F/B Rise,
temp-50 , Temp Cl- T6, Frame-80, Bharat Bijlee, Type-
1ST Oil centrifuge motor 1.1 Kw, 2850 rpm, 50Hz, IP 55, Ins.cl-F, temp-50 , ABB
for STG
80B20038-DNV-LR-ABS-GL-RINA BV)
Oil centrifuge motor for 3 induction motor,
51
STG(For
oil
inlet
Outlet pump)
Motor
52
for
STG
3 induction motor,
53
Motor for CEP pumps 1460 rpm, 50 Hz ,IP 55, Ins.cl-F/B, temp-50 , Framefor STG
55
56
57
58
Motor
for
Motorised
for
Motorised
for
Motorised
for
Motorised
for
Motorised
12
24
BPTG MCC
268
Lube
59
oil
pump
Motor
drive
for
BPTG(AOP/MOP)
60
3 induction motor,
2960 rpm, 50 Hz 5%, IP 55, Ins.cl-F, temp-50 , FrameND280M, CG Make, Sl No.-NADV 96700 ( AOP ), NADV
96699 ( MOP)
3 induction motor, 415 V 10%, 34 A, 19.5 Kw, 1463
rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 ,
Frame- 1
61
Motor for Oil vapour S1, 0.37Kw, 2880 rpm, 50Hz 5%, IP 55, Ins.cl-F/B Rise,
extraction fan for BPTG
M0911980
62
63
Motor for oil inlet & oil 1485 rpm, 50Hz 5%, IP 55, Ins.cl-F/G, temp-50 ,
outlet
K0937422 (Outlet)
Motor for Condensate 3 induction motor, 415 V , 2.1A, S1, 0.75Kw, 1485 rpm,
64
collection trfr pump for 50Hz , IP 54, Ins.cl-F, temp-50 , Wilo Make, Sl No.- 2
BPTG
65
66
67
68
69
70
Motor
4024289/0610/22800
for
Motorised
for
Motorised
for
Motorised
for
Motorised
for
Motorised
for
Motorised
269
Blowers
EOP
drives Kw, S1, 2900 rpm, IP 55, Ins.Cl- F, temp-50 , MTG- B3,
motor(DC)
Frame AF 82253,
STG
EOP
motor(DC)
DASH 5265 (STG 1), DASH 5264 (STG 2), DASH 5263
(STG 3)
DC Motor, Field Voltage - 220 V, Field Current- 0.55 A,
73
BPTG
EOP
motor(DC)
74
PMCC-04
75
76
77
270
L,
Bharat
Bijlee
Make,
Sl
No.-
dampers / Air Heater Kw, 1400 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , Frame- 6
Bypass damper
79
80
for
Drum
continuous / intermittent
blowdown valve
81
82
83
12
Motor for Main steam 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 4 Kw,
vent-reg valve
Motor for SH SPRAY 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 1.2 Kw,
control bypass valve
Motor
for
SB
Bypass vavle
Motor for LDO LOPCV 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 0.102
84
LOFCV
valves
85
86
87
Motor for CBM FCV 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 7.5 Kw,
Bypass vavle
Motor
for
valve
Motor for Bypass ECO 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 0.09
inlet valve
Motor for Drain Valves -
88
ECO /
89
Motor for Main steam 3 induction motor, 415 V,, S2-15Minutes, 50 Hz, 4 Kw,
vent valve
271
90
92
93
94
95
96
drive
for
ID
Fan(handling system)
Hoist
drive
for
FD
Fan(handling system)
Motor
for
Light
oil
pumps
3 induction motor,
97
98
30
UML-75P-395
99
Motor
Blowers
for
ROTARY
DM PLANT
3 Squirrel Cage induction motor, 415 V , 14.5 A, S1, 7.5
100
Motor for Air blower for Kw, 1440 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , FrameET
272
Motor for Effluent feed Kw, 1450 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , Framepump
10565900041
102
103
104
105
106
415 V ,
50 Hz , Mod- V13,
Frame-D 90 L, 2
Motor
1 induction motor,
for
Coagulant
dosing pump
107
Motor for MGF feed Kw, 1450 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , Framepump
10565900047, 10565900048
108
109
Motor
for
MGF
blower
115642990002
110
Motor
Agitator
for
Caustic
111
112
113
V-230, Hz-50, Make- Milton Roy India Pvt. Ltd., ModelB-92, Max OP- 10.0 (LPH), Max PR-4.0(Kg/sq.cm), Sl. 2
No.-3926,3921.
V-230, Hz-50, Make- Milton Roy India Pvt. Ltd., Model-V11, Max OP- 5.0 (LPH), Max PR-4.0(Kg/sq.cm), Sl. No.- 2
26720,26721.
V-230, Hz-50, Make- Milton Roy India Pvt. Ltd., Model-B91, Max OP- 6.0 (LPH), Max PR-10.0(Kg/sq.cm), Sl. No.- 2
3923,3924.
3 induction motor,
114
Motor for High pressure 2950 rpm, 50 5% Hz , IP 55, Ins.cl-F, temp-50 , Framepump
200
L,
Siemens
Make,
Sl
No.-
N8/64278284,
N8/64278285, N8/64278286
3 squirrel Cage induction motor, 415 V , 52.4 A, S1, 30
115
Motor for DMF Feed Kw, 1470 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , Framepump
DV
200
L,
Marathon
Electric
Make,
Sl
No.-
1056049S0005, 1056049S0006
116
Motor
for
Chemical
cleaning pump
117
Motor
for
Backwash
pump
225
S,
Marathon
Electrical
Make,
Sl
No.- 3
118
Motor for Air blower for Kw, 1445 rpm, 50Hz , IP 55, Ins.cl-F, temp-50 , FrameDMF
115642980002
119
274
120
200
L,
Marathon
1056011SP0001,
Electrical
Make,
1056011SP0002,
Sl
No.- 4
1056011SP0003,
1056011SP0004
3 squirrel Cage induction motor, 415 V , 27.1 A, S1, 15
121
Motor for Air blower for Kw, 1460 rpm, 50 Hz , IP 55, Ins.cl-F, temp-50 , FrameMB
115642970002
122
123
Motor
for
Regeneration pump
1056613P0001
124
125
Motor
for
Caustic
unloading pump
126
Motor
for
105645800001,
105645800002
3 induction motor,
275
Motor for Agitator of S1, 0.37 Kw, 910 rpm, 50 5% Hz , IP 55, Ins.cl-F, temp50 , Frame-ND 80,CGMake, Sl No.- JFG 10943, FG
SMBS dosing
17593
129
130
DM Traqnsfer Pump
Frame-ND 200L,
NADM 31890
131
132
Frame-G- 2
Condensate
Transfer
Pump
between
Tower(MCC
CWPH & CT )
Electric
Make,
Sl
Frame-DV225S, 3
No.-1056037SP0005,
1056037SP0001, 1056037SP0006
AC & VENT
3 Sqirrel cage induction motor, 415 V 10% , 34 A, S1,
136
276
NADM 26953
138
139
STG
Ventilation
Motor
140
141
L1300251
142
LT
Ventilation
Motor
Pump
143
HT
Switchgear
motors
54A
EOT Crane(TG Building)
3 Squirrel Cage induction motor, 415, 40 A, S4 - 40%,
144
2956381V0002
3 Squirrel Cage induction motor, 415, 1.13 A, S4 - 40%,
145
277
295661220012
3 Squirrel Cage induction motor, 415, 6.7 A, S4 - 40%,
147
295661150002, 295661150002
EOT Crane(CWPH Building)
3 induction motor, 415 10% V , 15.91 A, S4, 7.5 Kw,
148
150
151
3)
(MCC between CWPH & D 160 M, Marathon Electric Make, Sl No.- J10567200001,
CT )
IBD
153
(For
J10567200003
3,4,5,6 3 squirrelCage induction motor, 415 V , 14.3 A, S1, 7.5
Pumps
Boiler
&
(MCC between CWPH & D 132 S, Marathon Electric Make, Sl No.- 105645810001,
CT )
LDO Unloading Pump ( 3 induction motor, 415 10% V , 7.56 A, S1, 3.7 Kw,
154
278
155
LDO
Delivery
Pump
From
Frame-E 112 M, CG Make, Sl No.3 induction motor, 415 10% V , 13.7 A, S1, 7.5 Kw,
156
157
Kw, 960 rpm, High torque Lift Duty Motor as per IS 8151, 2
Ins.cl-F, Frame- 160, OMEGA Make, Sl No.3 squirrel Cage induction motor, 415 10% V , 267 A,
158
Compressor Motors
motors, 2 chiller water motors, 2Cooling tower fan motors & 3Air
28. Illumination
All inside and outside illumination (AC&DC) of PBS-2 complex excluding DM
Plant
Sl. No.
Recessed mounting type down lighter suitable for false ceiling mounting 40.000
Quantity
279
84.000
iii
Industrial type fixture suitable for surface mounting on wall or ceiling & 30.000
1x36W fluorescent tube
iv
Industrial type fixture suitable for surface mounting on wall or ceiling & 228.000
2x36W fluorescent tube
36.000
vi
Recess mounting type decorative lighting fixture with 2x36W florescent 443.000
lamps, copper blast ,starter & power factor improvement capacitor
vii
64.000
viii
Industrial well glass luminary suitable for 1x70 HPSV lamp with non- 439.000
integral control gear
ix
Street lighting fixture suitable for 125W HPSV lamp with optic reflector & 54.000
acrylic cover
Industrial High bay fixture suitable for 125W HPMV Lamp High bay 40.000
fixture
xi
Industrial High bay fixture suitable for 250W HPMV Lamp High bay 114.000
fixture
xii
Street lighting fixture suitable for 250W HPSV lamp with optic reflector & 12.000
acrylic cover
Grand Total
280
1584.000
281
G) DM Plant
1. List Of Major Equipment:
TAG No.
DP-108-A/B
DT-108-A/B
DP-109-A/B
DT-109-A/B
DP-110-A/B
DT-110-A/B
DP-111-A/B
DT-111-A/B
P-102-A/B
P-103-A/B
P-104-A/B
T-101-I/II/III
SC-112
HRSCR-113
CWS-114
MGFFP-115A/B/C
SCP-116
STP-117-A/B
ET-106
P-107-A/B
AB-105-A/B
MGF-201-A/B
AB-202-A/B
DP-203-A/B
DT-203-A/B
DP-204-A/B
DT-204-A/B
DP-205-A/B
DT-205-A/B
MCF-206-A/B/C
HPP-207-A/B/C
282
Description
NaOCl dosing pump
NaOCl dosing Tank
Polymer dosing pump
Polymer dosing Tank
Coagulant dosing pump
Coagulant dosing Tank
Lime dosing pump
Lime dosing Tank
IBD
Drain
transfer
pump
IBD
Drain
transfer
pump
IBD
Drain
transfer
pump
IBD Drain transfer sump
Stilling Chamber
Clarifier
Clarifier water sump
MGF Feed Pump
Sludge collection Sump
Sludge transfer pump
Equilisation sump
Size/Cap.
10 LPH @ 4 Kg/cm2
0.5 m diaX 0.8 hos
100 LPH @ 4 Kg/cm2
1.1 m dia X 1.5 hos
50 LPH @ 4 Kg/cm2
0.8 m dia X 1.4 hos
1 cum/hr @ 4 Kg/cm2
1.3 m dia X 1.6 hos
60cum/hr @ 3 Kg/cm2
MOC
PP
MSRL
PP
MSRL
PP
MSRL
PP
MSRL
CS
Qty
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
2 (1w+1S)
30cum/hr @ 3 Kg/cm2
CS
2 (1w+1S)
30cum/hr @ 3 Kg/cm2
CS
2 (1w+1S)
40/40/90 cum
2.1X1.5X2.5 HT
10DX4.8 HT
10X10X3.5 m-0.5 mFB
80cum/hr @ 2.5 Kg/cm2
RCC
RCC
RCC
RCC
Cl
3
1
1
1
3 (2w+1s)
RCC
Cl
RCC
1
2 (1w+1s)
1
Cl
Cl
MSEP
Cl
2 (1w+1s)
2 (1w+1s)
2 (1w+1s)
2 (1w+1s)
PP
2 (1w+1s)
MSRL
2 (1w+1s)
PP
MSRL
PP
MSRL
SS
2 (1w+1s)
2 (1w+1s)
2 (1w+1s)
2 (1w+1s)
3(2w+1s)
SS
3(2w+1s)
5x5x3.5 m HOS
10cum/hr @ 1.5 Kg/cm2
10.8X13.5X4.5 m -0.8
mFB
Effluent Feed pump
160cum/hr @ 1.5 Kg/cm2
Air blower for ES
250cum/hr @ 0.5 Kg/cm2
Multi Grade Filter
3400 dia X 2200 hos
MGF air blowers
4.33cum/hr
@
1.5
2
Kg/cm
Scale inhibitor dosing 101 LPH @ 4 Kg/cm2
pumps
Scale inhibitor dosing 0.7 dia X 1.2 ht
tanks
SMBS dosing pump
101 LPH @ 4 Kg/cm2
SMBS dosing Tank
0.6 dia X 0.9 ht
Acid dosing pump
5 LPH @ 4 Kg/cm2
Acid dosing tank
0.45 dia X 0.65 ht
Micron cartridge filter
80 cum/hr (20 NO
CATR)
High pressure pumps
77.2
cum/hr
@
283
CDT-510-A/B
CDT-511
AMT-512
NP-513
PT-514
NWTP-515-A/B
MB
Caustic dilution tank for
MB
Caustic dosing tank for
NP
Acid dosing tank for NP
Neutralization pit
Priming tank
Neutralized
transfer pump
FRP
2 (1w+1s)
FRP
1
1
1
2
(1w
+1s)
285
Backwash
Lime dosing
Polymer dosing
NaOCl dosing
IBD
Coagulant dosing
3 nos. pumps
Coagulant dosing
EQUILISATION
SUMP
CLARIFIER
WATER
SUMP
CLARIFIER
STILLING
CHAMBER
SLUDGE
TRANSFER TANK
3 nos. pumps
Blower
Scale inhibitor
dosing
BACK WASH
SUMP
MULTI
GRADE
FILTER
Blower
Acid dosing
Sodium Meta Bisulphate
dosing
CHEMICAL
CLEANING TANK
3 nos. h.p
pumps
ACTIVATED
CARBON FILTER
(2 nos.)
R.O
SUMP
DUAL MEDIA
FILTER
(2nos.)
REVERSE
OSMOSIS
MICRON
CARTRIDGE
FILTER
2 nos. pumps
blower
blower
STRONG ACID
CATION (2
nos.)
2 nos. DM
transfer pumps
Amine
dosing
blower
286
DEGASSER
(2 nos.)
STRONG BASE
ANION (2 nos.)
IISCO Steel
MIXEDPlant
BED
(2 nos.)
DM WATER
STORAGE
TANK
To
2 nos. Regeneration pumps CST
287
37
63
170 m
2950 r.p.m.
415
30 bar
6312 C3
6312 C3
56 m3/hr.
7.5
IISCO Steel Plant
14.3
25 m
2850 r.p.m.
6208 ZZ
6207 ZZ
o. MB Blower:
Capacity
66 m3/hr.
KW
15
Ampere
27
Pressure
0.4 Kg/cm2
Speed
1460 r.p.m.
DE side bearing no.
6309 ZZ
NDE side bearing no. 6209 ZZ
6205 ZZ
6205 ZZ
96 m3/hr.
20.96
55
2960
3
6308
6308
289
Lith. Based
V0100/400 + CPC
140 m3/hr.
50 m
1450 r.p.m.
37 KW
NWTP-1190
290
S1
50 DEG. C
315
415
2010
50
37
50
65
1470
92.5%
0.86
6313
6312
Power Distribution
POWER DISTRIBUTION
A) Introduction
Power distribution At Power Distribution Department is an important Electrical
department of SAIL-ISP which provides power to different shops for their operation in
2.5MT new plant, 0.5MT old plant and Township ISP
DVC (Damodar Valley Corporation) is the main supplier of power to SAIL-ISPthrough
DVC substation located at Burnpur. It is part of DVC grid and connected to Mejia
thermal power station, capacity of 1340 MW. Other than Mejia it also gets power from
kalyanesweri substation, which are interconnected and in parallel.
i.
There are two 220kV incomers to MRS (Main Receiving Station) at new 2.5MT
Steel plant, ISP and two 33kV incomers to old plant from DVC s/s at Burnpur.
ii.
There are two Captive Power Plants which are named Power and Blowing
Station(PBS #1 & PBS #2)
PBS #1: Capacity 2X10MW + 1X20MW (20MW in Service)
PBS #2: Capacity 3X18 MW + 1X8.275 MW (18MW in Service)
The Total Maximum load as expected of 2.5 MT new steel Plant is of order220MW
(approx.). Total power imported from DVC is around 170MW and captive power plants
generation is around 50MW.
New Plant receives power from DVC through two 220kV lines at MRS (Main Receiving
Station).This power received in MRS is stepped down to 33kV level through 4
transformers. The total load from Different Shops of New 2.5 MT Steel Plant is catered
through 10 number 33kV level substations named as LBDS (Load Block Distribution
Stations). Power supply to various LBDS is from MRS through 33kV cables.At LBDS
the power is again stepped down to 6.6kV level and then distributed to various
shops.There are also 4 Tie lines two each from PBS 1 & 2 at 33kV level in MRS. There
are 6.6kV tie lines at LBDS #1, 2,4,5,8 for emergency from PBS #2 it also supplies
291
power to LBDS #1, 2 which are essential load at 33kV level. In case of DVC grid failure,
PBS is islanded and Emergency power is supplied at 6.6kV level through PBS #2.
B) The 220 kV Scheme at MRS
There are two incomers from DVC named I/C-1 & 2 which are fed into Bay-4 & Bay-6
known as the Incomer Bays. Bay-4 & 6 feed the power into the two main buses and the
transfer bus denoted as Bus-A, Bus-B & Tr. Bus respectively in the above scheme. From
the main buses power is fed to Bays 1, 3, 5 & 7 which are called the Transformer Bays.
These bays feed power to the four 80/100MVA transformers which step down the voltage
level to 33KV from 220KV for distribution to the various LBDSs. Bay-2 is called the
Bus Transfer Bay and Bay 8 is the Bus Coupler Bay. Bay-8 is used to synchronize Bus-A
and Bus-B. The bus transfer bay is used to re-route power between the bays when any
equipment of any of the bays requires maintenance or repair.
292
Power Distribution
C) The 33 kV Scheme at MRS
The output of each transformer at the MRS goes to a 33KV bus as shown above. All four
transformers have an individual output bus. Each of these buses are coupled with each
other so that one may draw current from the other. As shown in the circuit above the
33KV bus at MRS has outgoing feeders to LBDS 1, 2, 3, 4, 5, 7, 8 & 9 and tie lines to the
old and new CPPs.
Substation name
LBDS #1
LBDS #2
LBDS #3
LBDS #4
LBDS #5
LBDS#6 & 7
LBDS #8
LBDS #9
LBDS #10
Shop
Blast Furnace
Coke Oven,BPP, CHP & CDCP
Sinter Plant
BOF-CCP
USM
RMHP
WRM & BM
Oxygen Plant
LDCP
293
294
Power Distribution
D) Connectivity at a glance:
1. Two 33KV tie lines exist between MRS and Old CPP.
2. Two 33KV tie lines exist between MRS and New CPP.
3. LBDS#1 has two 33KV feeders from New CPP, one 33KV feeder from MRS, one
6.6KV feeder from New CPP and a 33KV tie line with LBDS#2.
4. LBDS#2 has two 33KV feeders from New CPP, one 33KV feeder from MRS, one
6.6KV feeder from New CPP and a 33KV tie line with LBDS#1.
5. LBDS#3 has two 33KV feeders from MRS.
6. LBDS#4 has two 33KV feeders from MRS and one 6.6KV feeder from New CPP.
7. LBDS#5 has two 33KV feeders from MRS and one 6.6KV feeder from New CPP.
8. LBDS#6 has two 33KV feeders from LBDS#7.
9. LBDS#7 has two 33KV feeders from MRS.
10. LBDS#8 has two 33KV feeders from MRS and one 6.6KV feeder from New CPP.
11. LBDS#9 has two 33KV feeders from MRS.
12. LBDS#10 has two 33KV feeders from LBDS#5.
295
ii.
iii.
Isolators
iv.
Lightning Arrestors
v.
vi.
vii.
viii.
ix.
x.
Earthing Transformer
xi.
Lightening Transformer
xii.
Battery Bank
296
i.
ii.
25/31.5MVA Transformer:
iii.
iv.
Current Transformers
v.
Potential Transformers
vi.
vii.
Battery bank
Power Distribution
G) Protection Schemes at MRS:
297
Power Distribution
b. O/C AND E/F PROTECTION(50/51 & 50N/51N)
5. 6.6 KV INCOMER FROM 33/6.6 KV TRAFO.
a. PROTECTION RELAY-MiCOM P632 AND MiCOM P111
b. O/C AND E/F PROTECTION(50/51 & 50N/51N)
c. DIFFERENTIAL AND REF PROTECTION(87T & 64R)
d. STAND BY EARTH FAULT PROTECTION
e. WTI, OTI, PRV, OSR, BUCHHOLZ
6. 6.6 KV BUS COUPLER
a. PROTECTION RELAY-MiCOM P132
b. O/C AND E/F PROTECTION(50/51 & 50N/51N)
7. 6.6 KV TRAFO. FDR.
a. PROTECTION RELAY-MiCOM P122
b. O/C AND E/F PROTECTION(50/51 & 50N/51N)
8. 6.6 KV MOTOR FDR.
a. PROTECTION RELAY-MiCOM P220
b. O/C AND E/F PROTECTION(50/51 & 50N/51N)
c. THERMAL OVERLOAD PROTECTION
d. EXCESS LONG START
e. LOCKED ROTOR
299
A) Introduction
Production Planning & Control (PPC) Department is the overall coordinating
department of Works & acts as the nerve centre of information pertaining to its
various activities. The office of the Chief Executive Officer & the Head of Works is
dependent on PPCD on the first hand/ real time happenings & important data
associated with the Works functions.
The main functions of PPC Department are managed by five different sections viz.:
a. Plant Control
b. Planning
c. Statistical & Management Information System
d. Sales Co-ordination & despatch
e. Road weigh-bridge operation
B) Plant Control
Plant Control runs on 24 x 7 on 365 days basis and continuously does the real-time
monitoring of Plant Activities. Its main function includes:
a. Continuous monitoring on safety & fire related issues.
b. Collection of data on hourly basis related to production, despatch &
forecast on incoming commodities.
c. Follow-up on Mechanical & Electrical breakdowns/ delays, its analysis,
expected time of recovery & co-ordination with the related agencies.
d. Co-ordination with Head of Works, GMs/ DGMs, Line Managers & Shift
in-charges.
e. Day end reporting at 6:00 am on major issues to ED (W) & other senior
executives.
f. Periodic detail reporting to ED (W)
g. Conducting daily tele-conferencing at 08:30 am on weekdays between ED
(W) & all HODS.
h. Preparation of detail report based on above & uploading into intra-net for
information of all employees of ISP.
300
ii.
iii.
iv.
v.
vi.
vii.
b. Short Term
i.
ii.
Monthly shut down programmes & Capital repair plans of each production
departments.
iii.
iv.
ii.
Daily Flash Report, monthly special steel & quarterly performance reports for
Corporate Office Delhi
iii.
iv.
v.
vi.
301
Monthly sales co-ordination meeting at the end of the month for the
succeeding month being chaired by ED (W) in the presence of ED CMO
(LP), SAIL, CMO, SRM, Mills collective, RCL, Traffic & PPCD.
ii.
iii.
Based on above, daily meetings are conducted for monitoring & follow-up
& for rake formation.
ii.
1 No. 80Mt computerised Pit type near Vehicle gate: Weighing of Coke
Fractions, Scraps, granulated slag, Boiler ash..
iii.
2 Nos. 100 Mt Pitiless type near Sanmara gate: For despatches from new plant
units.
302
Projects Department
PROJECTS DEPARTMENT
1. Project Execution
The scope of project execution includes the following activities:IISCO Steel Plant
303
Projects Department
a. Expansion of ISP
b. AMR Schemes
c. Township Development
The ongoing 2.5 MTPA expansion project comprises 32 Main Packages, 25 Auxiliary
Packages, 47 Auxiliary packages andover 125 enabling infrastructure packages.
These packages are in various stages of implementation. The project jobs mainly
comprises of the following activities which are mostly common to all packages:
a. Construction Planning, Progress Monitoring & Allocation of resources
b. Space allocation for equipment, Construction materials, Offices etc.
c. Site supervision for conformity with drawing and specification including Onsite
quality
control
and
co-ordination
with
Construction
Agencies,
304
i.
Tender Documents
ii.
iii.
Negotiations
IISCO Steel Plant
Projects Department
iv.
v.
vi.
Closure of contracts
b. Import License.
c. CAPEX Procurement, Coordination with PAG etc
d. Consultancy Contracts
e. Contract administration
f. Issuance of waybill, Sales Tax: C- form
g. Budget for expansion projects, Coordination with M-Junction
h. Procurement and contract finalization for AMR cases /Non-Plant CAPEX cases
like Town, Hospital etc.
i. Coordination jobs for Investment Planning and PAG clearances.
3. Project (Finance)
a. Verification and passing of bills and accounting thereof.
b. Re conciliation of Taxes & duties for free issue of steel
c. Returns of TDS and Works contracts,C-Form related jobs
d. Monitoring of Bank Guarantees, correspondence for BGs with Bank
e. LC related jobs etc,Capital budget for AMR schemes and Expansion schemes
f. Custom Duty payment
g. All other finance related matters relating to screening of Tender documents and
awarding of contracts
305
Projects Department
5. Project Safety
a. Providing Safety induction training to 100% executives, non-executive, contract
labours
b. Ensuring conducting of periodical safety meeting
c. Monitoring &enforcement of safety
d. Monitoring protocol of erection jobs, commissioning jobs etc
e. Conducing safety checks
f. Safety administration as per statute.
g. Liaison with safety inspectors, etc
8. Surveyors
At present there are no surveyors in Projects. A Survey team consists of minimum of
4 Survey Officersand 4 non-executives. Surveyors will be required for the Projects
and need to be recruited.
Projects Department
307
RMHP
RAW MATERIAL HANDLING PLANT (RMHP)
A) Introduction
This department has come up under 2.5 MT modernization programme of ISP in 2012.
With this Burnpur got bedding / blending facilities for raw materials for the first time
along with facilities of unloading of all raw materials at one location except coking coal
for coke oven battery no10 and boiler coal of old plant.
1. Salient features of RMHP
Under 2.5MT Expansion of ISP, the principal scheme and material flow in RMHP
comprises the following:
i.
Unloading, of all raw materials for the plant except Coal of existing Coke Ovens
(COB#10).
ii.
Bedding/Blending and Reclaiming facilities in a big stock yard of all Iron ore,
Flux materials, Mn ore, Quartzite.
iii.
iv.
Preparation of Base mix and bedding with required proportion including crushing
& screening of Flux and Coke.
v.
vi.
Ensuring safe & Pollution free working environment inside the plant and its
surrounding area.
Material
Source
No.
1
308
Haldia
RHMP
4
Chasnalla
CDI Coal
Haldia
Imported/ Kuteshwar
Imported
Dalgaon
Dalgaon
2. Objective
a. To reduce interference of internal traffic movement and to Unload Raw materials at
the periphery of the plant, by avoiding detention of railway wagons.
b. Bedding of raw materials in different bed by making homogeneous pile of raw
materials received from our captive mines/other sources so as to achieve consistent
quality.
c. Keeping buffer stock of raw materials & their uninterrupted supply to different
consuming units.
d. Preparation of Base Mix & dispatch of the same to Sinter Plant.
Paddle Feeder
Stacker
309
RMHP
Barrel Reclaimer/Bucket
Wheel Reclaimer
Transfer Car
Screen
Rod Mill
Impact Crusher
Conveyor Belts
The Raw Material Handling Plant (RMHP) department can be broadly divided into two
main areas namely Ore Handling Plant, OHP (where unloading, stacking and reclamation
of raw material is done), and Base mix Handling Plant, BMP (where Base mix
preparation, stacking, and reclamation is done).
4. Customers of RMHP
310
i.
ii.
Sinter Plant
iii.
LDCP
RHMP
B) Ore Handling Plant (OHP)
OHP - Flow Diagram
IRON ORE FINES, LIME STONE, DOLOMITE, MN ORE, QTZ
BF #5
BASE
MIX
LS (LDP)
LS (SP)
EXISTING
PLANT BF-2
FLUX
SCREENING
Dolo
(LDP)
Mn
DOLO (SP)
I/O Lump
COAL BED
ORE
SCREENING
WT-2
WT-1
TRACK HOPPER
LDCP
Depending on the types of wagons, raw materials rakes supplied by the mines by means
of Railways are being placed either in wagon tippler or track hopper for unloading. The
types of wagons for unloading in wagon tippler and /or track hopper is as given below
For wagon tippler - BOXN, BOXC, BOST, NBOY
For track hopper - BOBS, NBOBS.
311
RMHP
is to be to be unloaded at Track Hopper by means of opening & closing of doors of the
Wagons.
The Wagon Tipplers shall be of Rota Side Discharge Type (Please refer to section A for
Wagon Tippler details) capable of unloading BOXN and BOY wagons up to a gross
weight as stipulated in IS: 10095 2001 with provision of Locomotive to pass through.
The rated unloading capacity shall be 20 Tips/hour. The placement of rakes shall be done
by Side arm chargers which are rail mounted, capable of handling a full rake of wagons.
The Track hopper (for unloading Iron ore lumps only) of 200m hopper-length (length
excludes maintenance area); capable of unloading BOBR/BOBRN wagons, shall have
four (4) paddlefeeders to extract material from track hopper bunker table and discharge
onto the conveying system underneath. The paddle feeders are rail mounted.
From the Wagon Tipplers WT-1/2, the raw material is conveyed through a series of
conveyors, Junction Houses and stacked on to Beds to prepare a stockpile. The three
single-boom stackers (Please refer to section 1.1.3 for Stacker details) over yard
conveyors stores the raw material in the designated place of the yard in bed nos 1 to 6.
Flexibility is in-built in the intermediate Junction Houses to ensure stacking is trouble
free.
From Track Hopper the Iron ore lump is conveyed through series of conveyors and
Junction Houses and at Junction House J2B screening of Iron ore Lump & fines is
provided with two hoppers to collect the fines of (-) 8 mm size materials and suitably
send it to the fines beds (bed no. 1 and 3) time-to-time. The lumps (+) 8 mm size
materials shall go online to the beds (bed no. 2 and 4) for storage. Please refer to Figure 1
for OHP flow diagram.
Suitable interchangeability shall be provided below Wagon Tipplers and Track Hoppers
for conveyors by providing Diverter gates. Electro-Magnetic Separators, In-Line
Magnetic Separators, Metal Detectors, Belt-Weigh-Scales, are provided to make the
system complete and the operation/maintenance smooth.
312
RHMP
Wagon Tippler is used for unloading wagons. It holds the wagon from the top (with the
help of Clamps) to a section of track (fixed to the tippler table) and rotates the track and
wagon to discharge the contents in the wagon in the hoppers provided on to the side.
ELECON
Design / Model
MARK III
Wagon
Handled
Max. Weight Of Shunting Loco At 8
130 T
Sr. No.
Type Of Wagon
Overall
Overall
Overall Length
Gross
Tare
Height
Width
Over Coupling
Weight (T)
Weight
(mm)
(mm)
Centres (mm)
(T)
1.
BOX/BOX C
3161
3136
13729
81.3
25.0
2.
BOXN MARK-
3225
3200
10715
81.3
24.28
3735
3136
10715
81.3
24.28
II
3.
BOXN
313
RMHP
Railway Gauge
Rail Size
60 Kg/m
Time Cycle:
i.
10 Sec.
ii.
Tipping/Forward Rotation
47 Sec.
iii.
Pause
06 Sec.
iv.
Reverse Rotation
47 Sec.
v.
10 Sec.
vi.
120 Sec.
20 Rated
Approval)
Overall Dimensions of Tippler
97 T (Approx.)
Weight
Clamping Arrangement
Hydraulic
68 T (Approx.) Total
Natural Rubber
Nos. Of Clamp
6 Nos.
Auxiliary Current
314
Power Supply
RHMP
Technical Specifications of Wagon Tipplers installed in RMHP
SL. No.
PARAMETERS
SPECIFICATIONS
Side Discharge
Material Handled
Quantity
3 (WT-1, 2, 3)
Gross Weight of each wagon 110 Ton Max. as per RDSO G33
handled
BOX/BOX C, BOXN
20
Clamping arrangement
Hydraulic
Number of Clamps
10
Tippler Drive
315
RMHP
Technical Specifications offside Arm Chargers installed in RMHP
SL. No.
1
PARAMETERS
SPECIFICATIONS
58 No.s loaded Wagons with Max. 110 T
Hauling Capacity
Quantity
Travel Drive
Arm
Movement
Coupler release
316
a. Capacity
b. Quantity
04 Nos
c. Material to be Handled
d. Total travel
200 m
10000 T
4 Nos.
h. Carriage Speed
1.5 m/min
j. No. of Blades
06
k. Liner of Blades
4000 mm
n. Anti-collision Devices
Infrared Sensor
1 Cu. M.
400
RHMP
4. Stacker
A stacker is a rail mounted machine used to make stockpile on beds provided on either
side of the rail track by travelling to and fro along the length of the beds. In RMHP the
stackers make stockpile by CHEVRON method. The entire control and operation of the
machine is done from operators cabin provided on the machine through PLC system.
Please refer to Table for Technical Specifications of Stackers.
Technical Specifications of Stackers installed in RMHP
SL.
PARAMETERS
SPECIFICATIONS
No.
1
Type
Material Handled
Quantity
Stockpile height
Rated Capacity
Travel Drive
Boom
Conveyor
width
8
Slewing Drive
Luffing Mechanism
10
Lubrication System
11
Weighing
317
RMHP
RHMP
homogenization of single/different source of same raw materials over a full length of
pile/bed.
Bed numbers 1, 2, 3, and 4 (bed no. 4 partially) uses Barrel cum Blender Reclaimer
(Please refer to section 1.3.2 for Barrel Reclaimer details) for reclaiming the stored
material from the beds. For reclaiming material from these four beds two barrel
reclaimers are provided with a transfer car to transfer the reclaimers as and when required
from one bed to the other. Two nos Bucket-wheel reclaimers are envisaged for bed nos
4 (partly), 5, and 6.Please refer to section 1.3.3 for Bucket Wheel Reclaimer Details. The
rated capacity of all stacking line conveyors, feeders and stackers etc. is 1400tph and a
designed capacity of 1680tph. The rated capacity of all reclaim line equipment is 1200tph
and a designed capacity of 1440tph.A repair bay, with a closed cover shed is envisaged at
the end of the transfer car bay after bed no. 6 where maintenance for Barrel cum Blender
Reclaimers is taken up.
Reclamation from OHP takes place in the following circumstances
1. Feeding of Iron ore Lumps to Blast Furnace (BF#5) stock house.
2. Transporting Limestone/Dolomite (SP grade) and Iron-ore fines for Base mix
preparation to BMP.
3. Transporting SMS grade Limestone/Dolomite (-) 25mm to Base mix Preparation
plant (BMP), after screening.
4. Transporting Limestone/Dolomite (SMS grade) (+) 25mm to Lime Dolo Calcinations
Plant (LDCP) storage bunkers.
5. Transporting of Iron ore Lump and Dolomite to existing Blast Furnace (BF#2)
through Pipe Conveyor (Please refer to Section 1.3.4 for pipe conveyor details).
Two sets of Auto sampling unit for collecting samples of iron ore have been provided,
one at J2B building and the other at J1 building. The samples collected from samplers are
taken manually for testing purpose. At J2B auto sampling unit the material unloaded at
Track Hopper complex (Iron ore Lumps) is taken for sampling and similarly at J1 auto
sampling unit, the material unloaded at Wagon Tipplers (Iron ore fines, Limestone,
Dolomite, etc.) is taken for sampling.
319
RMHP
8. Barrel Reclaimer
A Barrel Reclaimer is a rail mounted machine used for blending and reclaiming the
stacked material from a longitudinal stockpile area of the bed and delivers it to the yard
conveyor. The machine is rail mounted and operates in conjunction with fixed reclaim
conveyors. The machine is centrally controlled from the control desk provided in the
operators cabin on the machine. Please refer to Table 4 for Technical Specifications of
Barrel Reclaimer.
9. Bucket Wheel Reclaimer
A Bucket Wheel Reclaimer is a rail mounted machine used to reclaim the stacked
material on the beds provided on either side of the rail track by travelling (rail mounted)
along the length of the beds and deliver the material to the yard conveyor. Reclamation in
RMHP is done by Block-cutting method. The entire control and operation of the Bucket
Wheel Reclaimer is done from operators cabin provided on the machine through PLC
system. Please refer to Table for Technical Specifications of Bucket Wheel Reclaimers.
Technical Specifications of Barrel Reclaimers installed in RMHP
SL. No.
PARAMETERS
SPECIFICATIONS
1
2
3
4
5
6
Type
Material Handled
Quantity
Stockpile height
Rated Capacity
Travel Drive
7
8
9
10
320
RHMP
Technical Specifications of Bucket Wheel Reclaimers installed in RMHP
SL. No.
1
PARAMETERS
Type
SPECIFICATIONS
Rail Mounted, Self Propelled, Boom type, Luffing &
Slewing Bucket Wheel Reclaimer
Material Handled
Quantity
Stockpile height
Rated Capacity
1200 MTPH
Travel Drive
1200mm
Slewing Drive
Luffing Mechanism
10
Lubrication System
11
Weighing
12
13
Bucket Capacity
321
RMHP
Since the capacity of the Coke oven battery (COB#11) is inadequate for the Blast Furnace
(BF#5), the balance coke is transported from the existing batteries after screening/sizing to
the new coke sorting plant through pipe conveyor and belt conveyors. Since the topography
of the area from existing plant to the 2.5MT expansion unit is not feasible for normal belt
conveyors, a pipe conveyor has been installed to transfer Coke from existing coke sorting
plant. In addition to the coke pipe conveyor, another pipe conveyor is installed for conveying
Iron ore lump and limestone/dolomite required for the existing Blast furnace (BF#2) which is
under RMHP.Daily requirement of BF#2 (i.e. 1200 tonnes of Iron Ore Lump and 150 tonne
of dolomite) will be met through Ore pipe conveyor.
A common gallery for both pipe conveyors of open type with walkways on both side of the
conveyors and one walkway in-between, except for receiving and discharge ends, where
closed gallery is provided above the open conveyor. Drives for pipe conveyors are electromechanical type with VVVF. Please refer to Table below for Technical details of Pipe
conveyors
Technical details of Pipe Conveyors
SL. No.
PARAMETERS
COKE
IRON ORE/FLUX
CONVEYOR
CONVEYOR
Rated Capacity
200 TPH
600 TPH
Length
1485m
1355m
Pipe Diameter
300mm
300mm
Temperature
<120C
Ambient
12.6m
4.3m
receiving end)
322
Belt Width
1100mm
1100mm
315KW
355KW
1236
1151
RHMP
Before going into the details of Base mix handling plant (BMP), it is advisable to
understand the basic requirement of the internal customer (Base mix Handling Plant) as
well as external customer of RMHP. Please refer to Table below for Base mix plant
requirement and Table 8 for Sinter plant requirement.
Requirement of internal customer (Base mix plant, BMP)
SL. No.
RAW MATERIAL
SIZE RANGE
10140
(-)10 mm - 100%
(-)8 mm - 90%
Flux material
2000
(-)3 mm - 90%
(-)5 mm 100%
800
(-)3 mm - 90%
(-)5 mm 100%
390
(-)3 mm
MATERIAL
SIZE RANGE
160
(-)3 mm - 90%
(-)5 mm - 100%
200
dolomite
3
Base mix
(-)3 mm - 90%
(-)5 mm - 100%
13500
(-)8 mm
323
RMHP
There are two stacking and storage beds in Base mix yard, with a storage
capacity of 8 days maximum and size being 200m X 32m X 12m.
ii.
Two Slewing Stackers and two Barrel type blender reclaimers are provided
dedicated for each bed.
iii.
One Transfer Car is provided for shifting Barrel Reclaimer from One bed to
the other or to the repair bay.
iv.
Three Rod mills are provided for crushing Coke at a rate of 50 TPH each.
v.
Six Hammer Crushers are installed for crushing Flux material at a rate of 150
TPH each.
vi.
Four Flip Flow screens are provided in Flux screening building for screening
crushed flux material at a rate of 250 TPH for Primary screening and 300 TPH
for Secondary screening.
vii.
Two Flip Flow screens are provided in Coke Crushing building for screening
coke at a rate of 100 TPH.
viii.
There are twenty bunkers in Mixing Bin (MB) building with a storage
capacity based on the volume of 285cu.m for storing various raw materials.
ix.
There are eight bunkers in Flux Bin (FB) building of 200cu.m.Volume with a
storage capacity of 320 Ton each.
x.
There are six bunkers in Coke Breeze (CB) fines building of 200cu.m. volume
with a storage capacity of 100 Ton each.
324
RHMP
Various fines of different materials are mixed based on the process requirement of
Sinter Plant and the resulting mixture, whichis called as Base mix, is conveyed to
open storage beds with the help of stackers and then blended with barrel reclaimers
and finally sent to Sinter plant. The Base mix is a homogeneous mixture of IOF,
crushed Coke, crushed Flux (Lime stone & Dolo fines),mill scale, Flue dust etc mixed
in a certain proportion. The standard proportions of various raw materials for
preparation of Base mix are shown in Table below:
2. Raw material mixing proportions for preparation of base mix
SL. No.
RAW MATERIAL
PERCENTAGE
78%
Flux Fines
14%
Coke Fines
05%
03%
Operation of Base Mix Plant is best understood by considering Mixing Bin building
(MB) as an epicenter and analyze the material in-flow to and out-flow from MB,
since all types of Raw materials required to prepare Base mix flow into the MB and
come out of MB as a mixture (Base mix). Please refer to Table 10 for Mixing Bin
building details.
Mixing Bin Building details
Sl.
Material
No.
Number
Volume
of Bins
(Cu.M.)
Tonnage
Net Capacity In
Tons
285
627
627 x 8= 5016
Flux fines
285
456
456 x 4= 1824
Coke fines
285
142.5
142.5 x 4= 570
Mill scale
285
513
513 x 2= 1026
Sinter fines
285
513
513 x 2= 1026
325
RMHP
326
RHMP
by MB building. One is being Coke Sorting Plant of Coke Oven and the other
Blast Furnace Stock House. Coke conveyed by either of the above two
sources will be conveyed to the Coke Breeze (CB) fines building. In CB, 6
nos bunkers of effective storage volume (capacity) of 200cu.m. each has been
provided to store Coke fines. As and when required, the stored coke fines can
be carried to Coke crushing building (KCB) where 2 No.s of Flip Flow
Screens (FF-1,2) and 3 No.s of Rod Mills (RM-A, B, C) are installed for
crushing Coke. After screening, the Coke fines (-) 3mm size is fed to MB
Building.
d. Sinter Fines
Sinter fines which are returned from Blast Furnace Stock House is directly fed
to MB bins.
i.
Make
: Pennsylvania
ii.
Location
iii.
Type
iv.
Material Handled
v.
Quantity
: 6 Nos.
a.
Primary
: 3 Nos.
b.
Secondary
: 3Nos.
vi.
Crushing Capacity
: 150 TPH
vii.
Crushing
: 1200 rpm
viii.
Feed Size
: 25 mm to 50 mm
327
RMHP
ix.
Product Size
: 3 mm (80%)
x.
Make
: Mcnally Sayaji
ii.
Location
iii.
Type
: Rod Mill
iv.
Material Handled
: Coke Breeze
v.
Quantity
: 3 Nos
vi.
Capacity
: 50 TPH
vii.
Mill Speed
: 14.7 RPM
viii.
: 3 RPM
ix.
Feed Size
x.
Product Size
xi.
xii.
Rod Size
328
RHMP
In addition to Base mix, Coke fines (Coke Crushing Building) and Flux fines
(Flux Screening Building) are sent to Sinter Plant for fine tuning.
f. Yard equipment
The equipment which are installed on the storage yard/beds are generally termed
as Yard equipment which are of M/s Elecon make. Although the details of these
equipments have already been elucidated in various sections, the Table 11 below
would be a ready reference of the details of these yard equipment installed in
RMHP. The numbers in the brackets are the machine numbers designated for that
particular machine.
Ohp Area
(411,
Bmp Area
Capacity In Tph
Two
412, 415)
BMP = 1200
413)
2
Two
(419, -
OHP = 1200
420)
3
Barrel
type
blender Two
(421, Two
Reclaimer
422)
424)
BMP = 1200
Transfer Car
One (425)
One (426)
NA
D) Utility Section
329
RMHP
The Utility section can be best understood if both OHP area and BMP area utilities are
studied separately.
1. OHP Utilities
Major divisions in OHP Utilities are elucidated below:
2. Fire Protection System
There are two Pump Houses in OHP area namely, Pump House-1 which is dedicated
to Fire Protection System, and Pump House-2 which is dedicated to mainly Dust
Suppression and Make-up Water System in the area.
The Fire Protection System consists of following Sub-Systems:
a. Hydrant System (installed as per TAC fire protection manual) with fire
network covering OHP (with 299 Hydrant points), BMP (with 359 Hydrant
points), Sinter Dispatch Conveyors, Water Treatment Plant, and LBDS-6.
Please refer Table 12 for Pumping arrangement of Hydrant System.
b. Medium Velocity Water Spray System (MVWS) for cable cellar and cable
tunnels for LCSS-1A (DV-1), LCSS-2A (DV-2), LCSS-3A (DV-3), LCSS-4A
(DV-4), LCSS-5A (DV-5), and LCSS-6A (DV-6 & 7) using Deluge Valves.
Please refer Table 13 for Pumping arrangement of MVWS System.
c. Clean Agent (Inergen Gas based) system for Dispatcher, PLC Rooms at
LCSS-5A, and Wagon Tippler control room. Inergen is a blend of inert
atmospheric gases that contains 52% nitrogen, 40% argon, 8% carbon dioxide,
used for fire suppression system agent. It is considered a clean agent for use in
gaseous applications.
d. Portable fire extinguishers at various locations as follows: -
330
i.
Electrical rooms.
ii.
Administration building.
iii.
Pump Houses.
iv.
RHMP
Pumping arrangement of Hydrant System
Sl.
Pump Details
Drive
Quantity
No.
Capacity
Remarks
(Cu.M. /Hr.)
Electric Motor
273 at 88 mwc
Stand-by Pump
Diesel Engine
273 at 88 mwc
Jockey Pumps
Electric motor
20 at 88 mwc
For
pressurizing
the entire
system
Pump Details
Drive
Quantity
No.
1
Capacity
Remarks
(Cu.M. /Hr.)
Main Fire Pumps
Electric
273 at 88 mwc
Motor
2
Stand-by Pump
Diesel Engine
273 at 88 mwc
Jockey Pumps
Electric
20 at 88 mwc
For
motor
pressurizing
the entire
system
331
RMHP
4. Dust Suppression
The Dust Suppression and Make-up Water System consist of following Sub-systems:
i.
DS-1 which is Plain Water Dust Suppression System for Track Hopper. 2
Nos Pumps are installed at Pump House-2 for this purpose.
ii.
iii.
iv.
v.
PW-1 which is Potable Water System for Wagon Tippler Control Room,
Administrative Building, Canteen Building, FLD-1, LDB, LDS, LCSS1A, LCSS-2A, LCSS-3A, LCSS-4A, LCSS-5A, LCSS-6A, Toilet-1,
Toilet-2, Toilet-3. 2 Nos Pumps are installed at Pump House-2 for this
purpose.
vi.
MW-1 which is Make up water system for Air washer of the Ventilation
System & AC Cooling Tower at Wagon Tippler Control Room, LCSS-1A,
LCSS-2A,LCSS-3A, LCSS-4A, LCSS-5A, LCSS-6A.2 Nos Pumps are
installed at Pump House-2 for this purpose.
vii.
SP-1 which is Sump Pump arrangement for Track Hopper Sump Pit (4
Nos), Wagon Tippler Sump Pit (2Nos), Sump pit at J0 Building (2Nos),
and 2Nos Portable pumps for miscellaneous usage.
There is an RCC Storage Tank (RCC TANK-II) near Pump House-II which will get
continuous Industrial Water Supply by IISCO at Location N-9952/E-7358 @
255 cu.m. /Hr. at 1 to 1.5 Kg/Sq.cm. pressure. This RCC Storage Tank will supply
water to the Dust Suppression System for DS-1 to DS-6, DFDS-1, and MW-1.There
is another RCC Storage Tank (RCC Tank-III) near Pump House-II which will also
get continuous Drinking Water Supply by IISCO at location N-9952/E-7358 @ cu.m.
332
RHMP
/Day at 1.5 to 2 kg/Sq.cm. pressure. This RCC Storage Tank will supply water to the
Potable Water System (PW-1).
5. Ventilation System
Air washer type pressurized ventilation (supply and Exhaust) has been considered for
Cable vault & Switch gear rooms at LCSS-1A, 2A, 3A, 4A, 5A, 6A.Please refer to
Table 14 and Table 15 for Ventilation Exhaust and Suction fans details and their
locations installed in OHP area.
Ventilation Exhaust Fans
SL.No.
LOCATION
INSTALLED
CAPACITY
QUANTITY
(Cu.m. /Hr.)
Track Hopper
82500
J0 Building
86000
J0 Tunnel
86000
65000
65000
Location
Installed Quantity
Capacity
(Cu.M. /Hr.)
Track Hopper
74000
J0 Building
78000
J0 Tunnel
78000
58000
58000
6. BMP Utilities
333
RMHP
Major divisions in BMP Utilities are elucidated below along with the schedule of
pumps mentioned in Table below:
Capacity
Application
(Cu.M.
Quanti
ty
/Hr.)
1
DFDS-1A/1B
12
Suppression System
2
DFDSC-
850
DFDS Compressor
70
Stockpile Dust
1A/1B/1C/1D/1E/1F
3
SPDSP-1A/1B
Suppression System
4
FHDSP-2A/2B
18
Suppression System
5
SW-3A/3B
Service Water
PWP-4A/4B
Potable Water
CWP-5A/5B
16
Cooling Water
7. Dust Suppression (DS) and Dry Fog Dust Suppression System (DFDS):
Plain water type dust suppression system is considered for Base mix stockpile, fixed
hoppers & Dust/Scale. Plain water type sprinkler type dust suppression system is used
for the stockpiles shortly called as SPDS. Plain water spray type dust suppression
system is used for Emergency coke storage yard and fixed hoppers near emergency
coke storage area.
334
RHMP
Dry fog type DS system is used for controlling the fugitive dust generated during the
handling of material in all transfer points and other buildings.
8. Service Water Flow
Service water pump located in Pump House-C will take industrial water from RCC
tank located adjacent to the Pump House-C and supplies to the overhead PVC service
water storage tanks at control rooms, administrative buildings, workers rest room,
canteen& coke crushing station. This water from overhead tank is delivered to toilets
of MCC rooms, make-up water required for water cooled PAC units and for air
washer units of respective MCC rooms by gravity.
9. Potable Water Flow
Potable water pump (OWP-4A/4B) located in Pump House-C will take potable water
from RCC potable water tank located adjacent to the Pump House-C and supplies to
the overhead PVC storage tanks at Control rooms, administrative buildings, workers
rest room, canteen & coke crushing station.
10. Cooling Water Flow
Cooling water pump (CWP-5A/5B) located in Pump House-C will take cooling water
RCC water tank located adjacent to Pump House-C and supplies this water to the Rod
Mill Bearings in KCB building. The return hot water from Mill bearings will be
routed through the conveyor galleries and will be drained to RCC tank near Pump
House-C, while dissipating heat along the travel length of approximately 470m.
11. Air Blasters
In each bunker, 8 number of air blasters of capacity 150lt. each is provided for
blasting compressed air to loosen the sticky material inside the bunkers. Two screw
air compressors are installed in the compressor house. Please refer to Table 17 for list
of buildings for which Air Blaster system has been considered, along with the
capacities of their respective Air Blast Compressors (ABC) at BMP.
335
RMHP
Air Blasters details
Sl.
Air Blaster
Number Of
No.
Compressor
Air Blasters
Location/Building
Cubic Feet
Per Minute
(Cfm)
ABC-6A/6B
160
162.5
ABC-7A/7B
48
125
336
RHMP
i.
Each conveyor is protected against damage to the edge of the belt due to
excessive sidewise movement by providing an adequate number of belt sway
switches at an interval of 100m. The belt sway switches are of addressable
type, i.e. that particular switch which was operated can be traced from Central
control room.
ii.
For emergency stop, adequate numbers of pull cord switches are provided at
an interval of 30m. Additionally each conveyor is provided with one Zero
speed switch for sensing beltspeed. In case the speed of belt goes below preset
value, it will trip the conveyor. The pull cord switches are also of addressable
type.
iii.
Chute Block Switch is provided at each leg of chute & will trip the conveyor
in case of blockage of Chute.
iv.
Limit Switches like end limit switch, for Wagon Tipplers, Side Arm Chargers,
Stackers, Bucket Wheel Reclaimers, Barrel Reclaimers, Shuttle Conveyors,
and position limit switch for Shuttle Conveyors etc. are provided.
v.
vi.
Anti collision switches for moving equipments like yard equipments are
provided to avoid collision of equipment running simultaneously in
same/different beds.
vii.
viii.
Suitable interlocks are provided in all possible equipment to ensure men and
machine safety.
1. All OHP area equipment are PLC controlled and all BMP area equipment are DCS
controlled.
337
RMHP
2. VFDs are installed for Belt Weigh feeders of BMP area, Travel drives of Stackers,
Barrel Reclaimers, Bucket Wheel Reclaimers, and Barrel drives of Barrel Reclaimers
for speed control.
3. There is a Central Control Room at LCSS-5A near E.D. (Works) building for
operation of complete processes of Ore Handling Plant (OHP) area.
4. There is a Central Control Room at LCSS-2C for operation of complete processes of
Base mix handling plant (BMP) area.
5. Addressable type Pull cord Switches (PCS) and Belt sway switches (BSS) are
installed in all conveyors by which the location of operated PCS/BSS can be traced
from Central Control Room.
6. There are six Load Control Sub-Stations (LCSS) at OHP and three LCSSs at BMP
area.
7. An Administrative building for RMHP is situated near BMP area in which View
monitors are installed for 24 hrs monitoring of processes in both OHP and BMP
areas.
338
Rolling Mills
ROLLING MILLS
A) Introduction
RollingMills Complex is the last processing unit in an integrated steel plant where
steel is given shape in to structural, coils, rebars, bars etc as per market requirement.
Old Rolling Mills Complex at ISP was having Blooming Mill, Billet Mill, Heavy
Structural Mill, Light Structural Mill and Merchant Mill. All these mills were phased
out on 31.03.2014.New Rolling Mills Complexconsists of Wire Rod Mill, Bar Mill
and Universal Section Mill under 2.5 MT Expansion and Modernisation programme
of ISP. Facilities available in these mills are as follows:
339
Rolling Mills
2. Flow Diagram of Wire Rod Mill
Steel Grades
Carbon steel
Spring steel
Electrode quality
Ball bearing quality
Free cutting
Cold heading
Low alloy
Forging quality
Rebar
Rolling Mills
5. Product Tolerance
Product
Plain Wire Rod
Rebar
Size (mm)
5.5 22.0
6.0,8.0,10.0 & 12.0
Tolerance (mm)
(+/-) 0.10
IS 1786:2008
Ovality
70 %
6. Coil Characteristics
Actual
situation
Outside
Dia
(mm)
1250
Inside Dia
(mm)
850/900
1250
850/900
Height before/and
after compacting
& tying (mm)
2000/1500
(plain wire rod)
2800/1800 (rebar)
Weight
(kg)
No
straps.
2000
2000
115 m/s
76.4 %
97.0
0.135kg/t
0.270 G Cal/t
100t/hr
341
of
Rolling Mills
Walking beam type reheating furnace consortium comprising of M/s
BricmontInc, USA, M/s Micco,India. The furnace has an inside effective
length of 19350 mm and width of 12900 mm.
Description
Bar Mill
Type of furnace
2
3
4
5
6
7
8
9
10
11
12
13
Fce capacity(tph)
Discharge temp (max)
Fuel
CV of gas
Air temperature
No of burners
Maximum scale loss
Automation
Combustion system
Gas pressure
Air pressure
Nitrogen pressure
Cold billets are placed on charging grid by means of magnet fitted EOT
cranes. Hot billets are charged directly from CCP on to the charging roller
table. Billet is being stopped at the entrance of the furnace. The piece is then
crowded to ensure that it is cantered on the charging roller table. The piece is
342
Rolling Mills
positioned inside the furnace by in-furnace charging roller table. Once the
billet has been placed inside the furnace, the walking beam lifts and advances
the product inside the furnace. The maximum walk length is 225 mm. When
the billet is requested by the mill and a piece at the discharge end of the
walking beam mechanism, the door will open, the walking beam will move
one walk and place the heated billet on to the discharge roller table. The
discharge rolls will accelerate and advance billet in to the mill.
Two combustion air blowers are provided to supply combustion air to the
furnace. Only one is required to operate for the furnace combustion system,
the second is provided as standby.The air is preheated in two pass dual bundle
type recuperator. The temperature of the combustion air from recuperator is
controlled by the furnace control system by adjusting the position of the hot
air bleed valve. By bleeding hot air out of the system more cold air enters the
recuperator and affectively lowers the temperature to avoid damage of
recuperator. The safety circuit monitors the furnace combustion system and
shuts down the furnace when unfavourable condition exists.
The furnace pressure control system maintains a slightly positive pressure at
the discharge door by automatically adjusting the position of the waste gas
damper to maintain a set point near +0.06 mbar.
The furnace level-2 system takes information from the base control system
(level-1) to optimize furnace efficiency. Furnace operation is being controlled
from HMIs located in furnace control pulpit.
c. Mill Area
i.
343
Rolling Mills
344
ii.
Descaler
Billets before entering in to the mill is descaled by means of high pressure
water descaler (250 bar max) during its travel on the roller table.
iii.
iv.
Finishing Blocks
At the exit stand of pre-finishing mill (stand -16), the rolled stock is
conveyed to the 2-passes+8-passes Fast Finishing Blocks. Each finishing
block is driven through a single motor shaft and consists of rolling units
with tungsten carbide rings arranged at 900 one in comparison to other for
rolling without torsion to get high quality finished products.
Rolling Mills
v.
vi.
vii.
viii.
Laying Head
Laying head provides formation of regular and constant shape and size
ofthe wire rod loops falling on to the roller conveyor.
ix.
x.
345
Rolling Mills
two trestles are mounted on a rotating platform to allow the above
operating cycles alternatively. The trestle in discharging position is tilted
900and the coil is picked up and transferred in a horizontal position to the
hook of the C-Hook conveyor. The C-Hook conveyor brings the coil to the
compacting and tying machine. Compacting and tying is done by
SundBirsta tying and compacting machine.
d. Water Treatment Plant
Water treatment plant for wire rod and bar mill is designed for catering the
process water for both the mills. It is a centralized water supply unit which
houses all the water supply equipment and treatment processes.
The basic purpose of the water treatment plant is to provide a suitable quality
of process water at desired flow rate and pressure and also to apply essential
treatment to the water in order to keep that quality maintained. These
treatments include physical filtration and chemical dosing.
It not only provide centralized water supply but is also highly automated. It is
capable of being controlled remotely from a single station HMI (human
machine interface). This water treatment plant is equipped with highly
automated systems which are governed by PLC (programmable logic
controller). PLC is programmed with set of logics which, during the operation
of the plant governs the running of several equipment according to the changes
in various parameters.
Besides the supply of water to mill it also take care of minimal wastage of the
process water by recycling of the waste water. It has got state of the art waste
water treatment facility which allows the recycling of the waste water from
even sludge.
Main Pump House Area consists of:
i.
ii.
29 pumps
iii.
4 blowers
iv.
v.
Rolling Mills
i.
Motor cooling
ii.
iii.
iv.
Inter-cooling in compressor
This water called non-contact water or indirect cooling water because it cools
these components without making direct contact with it. It flows in closed
coils or circuits and picks up the heat via metallic conduction. It mainly carries
heat and less physical impurities.
Its treatment includes physical filtration through self-cleaning filter and
chemical dosing for conditioning of water.
f. Contact water circuit
These circuits are meant for supplying water for:
i.
ii.
iii.
For descaling.
iv.
v.
This water is called contact water because it directly sprays over the
components it is supposed to cool. It carries a big amount of scale and other
physical impurities and is requires rigorous treatment for its cleaning and
reusability maintenance.
This water called contact water or direct cooling water because it cools
components by making direct contact with it. It sprays over the rolls and hot
metal and picks up the heat via direct contact. It carries heat and a lot of
physical impurities including scale, oil etc.
Its treatment includes physical filtration by settling scale and skimming oil in
scale pit and longitudinal settling basin. Its treatment also includes
conditioning of water by chemical dosing.
347
Rolling Mills
Rolling Mills
Bar Mill consortium comprising of M/s Danieli, Italy, M/s Danieli Engineering
Limited, India, M/s Shriram EPC, India, and Mecon Ltd, India as consultant. Installed
capacity of Bar Mill is 0.90 MT/ year. Bar Mill having equipment facilities similar to
stand 16 of WRM. One additional facility is available in between descaler and pinch
roll is Endless Welding Rolling Machine. This machine allows rolling of an endless
bar eliminating billet gap time. Material yield increases 2.0 % and production
increases approx 5.0 %. Stand 14 is a convertible stand and can be used as horizontal
or vertical as per rolling schedule. Slit rolling technique is used for rolling bars from
8.0 mm to 18.0 mm. Slit bar after stand 16 goes to two 6-passes Fast Finishing Block
where roll units are arranged at 450 for rolling without torsion.
349
Rolling Mills
1. QTB
After the blocks a QTB water quenching line for making rebars. QTB is a surface
quenching and self-tempering process. The first stage is a drastic water cooling
operation applied to the bar as it leaves the last stand. At the end of this operation, the
bar surface has the martensite layer an austenite core and an intermediate layer
composed of a mixture of martensite and austenite. In the second stage, the bar leaves
the area of water cooling and is exposed to air. The core reheats the quenched surface
layer by conduction and the martensite formed during the first stage is subjected to
self-tempering which ensures adequate ductility while maintaining a high yield
strength. The third stage occurs on the cooling bed. The product of this transformation
is a mixture of ferrite and pearlite or ferrite, pearlite, bainite.
2. Rotary Flying Shear
At cooling bed inlet, a continuous rotary flying shear cut the rolled stock to a multiple
lengths.
3. Double Twin Channel
Double Twin Channel bar delivery system brakes and discharges one bar per notch of
the cooling bed. Start/stop walking beam type cooling bed collects and cools the bars.
At cooling bed exit side the layer of bars is cut to final length on static mode by a
heavy duty cold shear equipped with a gauge beam. An additional roller table after
bar counting area is provided to recover short bars.
350
Rolling Mills
Size (mm)
8.0-40.0 mm
Rebar
Tolerance (mm)
IS 1786:2008
Ovality
8. Bundle Characteristics
Length (m)
6-9-12
Weight (kg)
2000-5000
Tying with
wire
2-3-4
40 m/s
76.4 %
96.5
0.200 kg/t
0.293 G Cal/t
163 t/hr
351
Rolling Mills
D) WRBM-Roll Shop
Roll Shop is the heart of the Rolling Mills. The objective of having Roll Turning
Shop is to provide turned Rolls & Tungsten Carbide Rings to Rolling Mills.
Additionally, for supporting the production of TMT bars, notching & branding
operation on Rolls & Tungsten Carbide(TC) Rings are also carried out in Roll
Turning Shop. All these turning, notching & branding operations on Rolls & Tungsten
carbide Rings are done by Computerised Numerically Controlled (CNC) machines
supplied by M/s ATOMAT, Italy.
Another important operation performed at Roll Shop is Labyrinth Ring fitting for
bearing fitting. For which Labyrinth Ring, Inner Ring & Spacers are cleaned properly,
heated with some special electrical heating device & fitted to cleaned Roll neck.
Computerised Numerically Controlled (CNC) machines are used for machining i.e.
turning/grinding, notching & marking operations on Rolls and Tungsten Carbide
Rings as per the pass design to roll different sizes of plain rounds and TMT barsat
WRM as well as Bar Mill . The following machines are commissioned at WRBM roll
Shop CNC Machines Installed
Sl.
No.
CNC machines
No.
CNC
of
Software used
1.
AT 830E CNC
2.
AT 830NTE CNC
CNC
3.
AT 710E CNC
4.
AT 710EN CNC
5.
6.
Control
WORK
There are altogether 4 CNC lathes (AT830E & AT830 NTE) for machining rolls. The
AT830E CNC Machines are used for turning of Rolls and AT 830NTE CNC
Machines are used for turning, notching & branding of Rolls. Similarly, AT 710E
CNC machines are used for grinding of T.C Rings and AT 710EN CNC is a combined
352
Siemens
Rolling Mills
grinding, notching & branding machine for T.C Rings. Guide rollers redressing are
also done in the AT 710 series of machines with the help of special attachment.
Other than the CNC machines, the conventional machines that are installed in the
Roll Shop are as follows:
i.
ii.
Shaping machine
iii.
iv.
v.
vi.
Knife Grinder
The above mentioned machines can be used for performing various machining
operations at Roll Shop. To mention a few, the Shaping machine is a general purpose
shaper, suitable for cutting plane and formed surface of medium and small size workpiece of various kinds whereas Universal Horizontal Lathe is able to take operation
like internal and external cylindrical turning, facing and other sorts of turnings; and is
able to cut Metric, Inch, Module and D.P threads; to drill, ream and broach grooves.
In addition to the above operations, gap-bed lathe is able to turn flat-type and
irregular-shaped work-pieces.
353
Rolling Mills
To run the above mentioned sophisticated machines a group of operators have been
trained in different Roll Shops in India as well as abroad.
E) Chiller Plant
The chiller plant is a centralized unit for air conditioning in the various rooms in both
B.M. and W.R.M. It chills the water circuit through its evaporator to create cooling of
the air circuit which runs in the rooms where the cooling is required.
The chiller plant consists of 6 chiller unit which provides centralized service. These
chiller unit are compact and consisting of partial automation. The operators interface
is a console where operator can manage the parameters and take the information about
the running process. Besides the chiller units the chiller plant also consists of other
components like water pumps, cooling towers etc. it houses the whole system in a
single housing.
The chiller plants centralized placement is connected to various rooms to be cooled
via a network of chilled water pipes. The water goes to the components called AIR
HANDELING UNIT or AHU. These AHUs are responsible for the cool air in the
ECRs and pulpits. The AHUs cools the air with the help of chilled water circuit.
There are 10 air handling unit in wire rod mill.
Housing
Cooling coils
Air blower
Air filters
Housing: it is a box like structure that is installed with other mentioned
components.
ii.
Cooling coils:these are finned stacking of coils in which the chilled water,
supplied from the chilled water pumps, run. These coils are finned to increase
354
Rolling Mills
the surface area of contact with air hence, increasing the heat transfer. The air
comes through the coil and gets cooled.
iii.
Air blowers: these are the blowers which send air into the cooling space and
suck the air in AHU rooms. Air that comes into AHU rooms is the returning
air from the cooling space that is carrying back the heat. The air goes to the
cooling space via duct arrangement.
iv.
Air filters: these are fabric strainers for air. They are mounted in a matrix form
on the housing, right outside the cooling coil arrangement. The air that goes
through the cooling coils first gets filtered by these air filters.
ii.
iii.
iv.
v.
vi.
vii.
Steel Grade-
Steel & high tensile steel grade, SAILMA, Corrosion resistant steel ,DMR
Steel grade
viii.
Yield
100%
1.5%
1%
Finishing losses
Production yield
1%
96.5%
2. Input Materials
Beam Blank
Blooms
355
Rolling Mills
Bloom Size: 200x280 mm will be used for Equal Angles & Blub Bars sections.
3. Product Mix:
Product
Size Range
Input Material
240 750
H Beam (HE)
200-450
Channels
200-400
Equal Angles
150-200
Special Sections
(Sheet pile, Z Section
etc)
Total
Annual
Production
1, 50,000
(25%)
1,
50,000(25%)
1,
30,000(21%)
1,
50,000(25%)
20,000 (3%)
6, 00,000(100
%)
Rolling Mills
The beam blanks or blooms will be charged to the reheating furnaces into two
ways:
i.
ii.
From the hot charging roller table or from the cold charging grid the beam blanks
will be transferred to the reheating furnace. A weighing scale will be installed in
the charging roller table for measuring the weight of the individual beam blanks.
The furnace discharge roller table will feed the starting material to a high pressure
(opp. Pr. At nozzles of abt. 205 bar) water descaler.
Afterwards the materials will be delivered to the reversing roughing mill stand
where the leader section for the tandem mill will be produced. Shifting & centring
units in front of & behind the roughing mill stand will guide the material to the
roll groove according to pass schedule. Based on the various starting sizes mainly
5 to 7 runs (max. 9 runs) will be rolled on the BD Mill Stand.
Downstream the roughing mill there is foreseen space for installing a crop saw for
cropping bended head ends to avoid troubles during biting in the tandem mill.
Behind the crop saw, the material will be transferred to the Universal Tandem
Mill with the stand arrangements:UR - E - UF
Whereby,
UR/UF = Universal Stands
E
For automatic changing of rolls and guides the operator side housing including the
complete roll set with guide will be shifted out of the mill line. After a side shift of
the shifting platform the completely assembled new roll & guide set cartridge will
be connected with the stand housing and both together will be shifted into mill
line.
Downstream the tandem mill, there will a hot saw which will serve for cropping
and sample taking.
The cooling bed is designed as a combined walking beam type/ chain type cooling
bed.
IISCO Steel Plant
357
Rolling Mills
Straightening of the sections behind the cooling bed is carried out by a double
support CRS- Roller straightening m/cs.
Behind the straighter the sections will be collected on a layer collecting bed for
performing cutting of layers. The layers will be cut by cold saws
Two by two fixed strap type bundling machines are behind the straightening m/cs
for automatic bundling.
358
Rolling Mills
Process Flow Chart in USM
Shifting &
Centering Device
Layer Collecting
Device
Weighing System
Breakdown Mill
Horizontal Roller
Straightener
Reheating Furnace
Cooling Bed
De-scaler
Online Measuring
Device
Charging System
Hot Saw
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
359
Rolling Mills
Furnace Charging System
Reject Roller
Table
Cold
Charge
Grid 1/2
Hot
Charging
from CCP
Run in
Roller
Table
Breakdown
Mill Area
Furnace
D/Roller Table
Walking beam
furnace
Weighing
System
Inlet R/Table
Discard
Mechanis
m
b. BD Mill Area
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
Two high Reversing B.D Mill stand with syn. Motor (4000KW @ 360960 rpm)
360
xi.
xii.
Rolling Mills
Double Roll
Changing
Device
Work &
Extension Roller
Descaler
Table
Grip Type
tilter &
shifting
device
Reversing & 2
high BD mill
Stand
Grip Type
tilter &
shifting
device
Work &
Extension Roller
Table
Tandem
Mill Area
iii.
iv.
v.
vi.
361
Rolling Mills
vii.
viii.
ix.
Pendulum Hot sawTo cut-off crop ends of finished product entering cooling bed
Saw Blade dia- 1650-1800 mm; Blade thickness -12 mm
ii.
iii.
Sample Grid with pusherTo remove and collect samples at the exit side of Hot saw.
iv.
ii.
iii.
iv.
v.
vi.
362
i.
ii.
Rolling Mills
iii.
iv.
v.
vi.
vii.
Scale disposal system- Scale will be disposed to flume with the help of
pump.
viii.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
ii.
iii.
iv.
v.
IISCO Steel Plant
Rolling Mills
Length -33 m; No of R/Table-17; Roller Table Speed 0-2.5 m/s
Drive-individual by Geared motor & coupling
vi.
vii.
viii.
Pilling System
ii.
iii.
Pilling Machine
iv.
ii.
iii.
iv.
v.
j. Auxiliary System
364
i.
EOT Cranes
ii.
Water System
IISCO Steel Plant
Rolling Mills
iii.
Hydraulic System
iv.
Lubrication System
v.
Grease system
vi.
vii.
Media Lines.
viii.
Ventilation System
ix.
Despatch bay
4 nos of 20 T capacity
Finishing bay
2 nos of 20 T cap
1 no of 20 T cap
Bloom storagebay
2 nos of 20 T cap
Mill bay
1 of 50 T cap,1 of 30 T cap
Auxiliary system
Covering area
Hydraulic System
Hydraulic system 1(130 bar)
B D mill area
365
Rolling Mills
Central grease lubricating system III
T D mill area
1 no
H P water system II
Sump pump
6. Water System
a. Indirect cooling water circuit
b. Direct cooling water circuit
c. Pump houses:a. Main pump houses
b. Primary scale pit pump house
c. Secondary scale pit pump house
d. Fire-fighting pump house
d.
Cooling tower
e.
366
Rolling Mills
LBDS 5
ECR-2
ECR-1
3
PCC
FED.FROM 6
2MVA TXF.
FROM 2
TXF
OF
2MVA
ECR-3
2 TXF
FOR
LDB
2 PCC
FED
FROM 4
TXF OF
ECR-4
1 TXF FOR CB
ROLLER
TABLE
&
AUX.
2 TXF OF 2 MVA
FOR 1 PCC.
2MVA
1TXF FOR
BDM MOTOR,1
TXF FOR
BDMROLLER
2 TXF FOR
SHARING LOAD
IN FURNANCE.
367
A) Introduction
Accidents in a plant affect productivity, and morale of workforce. All accidents,
regardless of their consequences, are symptoms of production inefficiency. Accident
free production is regarded as an efficient production. Many activities and processes
in a steel plant can present situations which involve risk to safety and health of
employees, and risk of damage and loss to plant equipment and product. Hence it
is a moral, economic as well as legal duty of all especially the front line
executives - to prevent, control or guard against such risks and their possible ill
effects. With an objective to achieve elimination of human suffering, damage to
material and equipment, and resultant loss of production.
The erstwhile Indian Iron and Steel Company (IISCO), one of the oldest steel plants of
the country has been amalgamated with Indias largest steel maker, Steel Authority of
India Limited (SAIL) with effect from 16th February 2006. Following merger, IISCO
has now been renamed as IISCO Steel Plant (ISP). ISPs annual hot metal production
capacity is envisaged to go up to 2.5 million tonnes (MT) from a level of 0.35 MT in
2004-05. The plant which was earlier written off is now being written about. The
spotlight is now on ISP, the fifth integrated steel plant of SAIL.
ISP, one of the oldest integrated steel plants, started production of iron away back in
1870 in its Kulti Works of Bengal Iron Works Company. ISPs Burnpur Works was
incorporated on 11th March 1918, started iron making in 1922 and steel making in
1939.In the early 1960s, it expanded further to become a million tonnes steel plant.
ISP has got an integrated steel plant at Burnpur, Captive collieries at Chasnalla, Jitpur
and Ramnagore. It produces a wide range of products, starting from pig iron to finished
steel products, mainly heavy, medium and light structural and special sections. ISP has
pioneered the production of centre-still Z section used in the production of wagons and Z
type sheet pilling section used in construction of barrages, bridges foundations and other
projects and colliery arch section used for roof support in collieries. Its Merchant Mill &
Heavy Structural Mill is equipped with ISO: 9001, and the Rolling Mill complex has
acquired ISO: 14001.
368
B) Safety Policy
IISCO Steel Plant is committed to:
i.
The safety of its employees and the people associated with it, including those
living
ii.
C) Guiding Principles
i.
ii.
All employees are responsible and accountable for maintaining laid down
safety standards.
iii.
iv.
v.
vi.
We shall perform all works in consonance with the local, State and Central
Acts, and Rules and Regulations on Safety.
vii.
viii.
369
Apprising the managers where they are falling short of safety standards.
ii.
iii.
iv.
v.
b.
Reporting of Accidents:
i) All the accidents resulting in injuries are reported to ED (Works)
ii) In case of serious/fatal accidents and dangerous occurrences, after the
Investigation, immediate information is sent to CEO/ED (Works).
iii) As soon as the occurrences of such serious / fatal accidents or immediately
after the knowledge of such accidents, the messages are forwarded to the legal
authorities.
371
ii.
iii.
d.
Review:
Safety aspects discussed daily by senior management team during morning
conference. Departmental Safety Committees are reviewing various safety issues
during their meetings held regularly. Safety issues are also discussed at the
monthly meetings of Zonal Joint Production /Maintenance Committee. Central
Committee for S.H.E. reviews the safety aspects in their quarterly meetings.
H) Joint Participation
Various committees are formed eg. Departmental Safety Committee and SHE (Safety,
Health & Environment) committee as a member to discuss safety related problems
and arrive at solutions to strengthen Safety.
I) RAIL-ROAD SAFETY:
1. Checking of road worthiness of contractors' transport vehicles inside the
plant.
2. Monitoring of rail traffic at rail road crossings inside the plant.
3. Conducting special campaigns to enforce use of crash helmets by two
wheeler riders inside plant.
4. Surprise checks for 100% presence of LOCO Crews.
5. Vehicle speed limits checking by Speed-gun.
6. Blinker light checking at all level crossings and blind corners.
7. Road Illumination checking on regular basis.
8. Conducting Rail-Road safety awareness programmes.
9. Fencing of unauthorised routes.
372
2.
3.
4.
To make the employees aware about safety aspects, hazards of the work environment
and risk involved in it, the safety posters are very beneficial tool. Safety posters
depicting the general and specialized safety aspects are pasted at strategic locations
373
5.
6.
7.
374
8.
Joint Participation
a. Inspection of Shop- Inspection is a routine job for SED and its review of working
condition are the key job to prevent the accident
b. Conducting
Apex
Safety
Committee
Meeting
and
implementing
the
9.
Inspection Committees
i.
Cable gallery inspection committee ensure the vital electrical installation inside
the plant, every month and take necessary action against the any unsafe
condition.
ii.
Oil Cellar Inspection Committees inspect and ensure the safe condition inside the
oil cellars, every month.
iii.
10.
Statutory Provisions
375
376
A) Existing Shops
The existing shops play the vital role of supplying spares for the works since the central
workshop is now under construction. The major units of the existing Shops are given
below.
1. Machine Shop
2. Structural shop
3. Forge Shop
4. Foundries
a) LMS/Foundry
b) Ingot Mould Foundry
c) Steel Foundry
B) Main Activities
i.
ii.
iii.
iv.
C) Flow Process:
A brief description of the process of spare manufacture from the order stage to the
dispatch stage is given below:
Work order for a job is placed on the shops by the concerned department based on the
monthly job list as finalized at the end of every month at the monthly meetings. Jobs are
categorized in the order of priorities. The plan is processed for execution by the shop
planning section. The jobs are then scheduled on various machines/equipment as per the
sequence of operation. The completed jobs are collected by the ordering department.
D) Machine Shop
Machine Shop is divided into the following Sections
IISCO Steel Plant
377
The machining section carries out machining operation of various new and reclaimed
spares. The general purpose machine tools available for performing the above are as
follows:
a) Lathes
b) Shapers
c) Planning Machines
d) Slotter
i.
Dia 48 Inch)
ii.
iii.
iv.
The section has two bays Heavy and light bays having EOT cranes of 15T and 3T
respectively for material handling.
2. Assembly Section
Performs the following functions:
a) Planned manufacture of new assemblies
b) Repair/Re-conditioning of parts/sub assembliesof various departments on
regular basis and during scheduled repairs, capital repair or at breakdown
378
15T Capacity
Max
150
DegCelsius
e) Radial Drill & Shaping Machine
E) Structural Shop
This section performs the following important functions:
a)
b)
c)
d)
b)
c)
d)
Plasma Cutting Machine : can cut Stainless Steel Plate of thickness max 12 mm
e)
Welding Transformers
f)
g)
F) Forge Shop
This shop makes various forgings from cut billets as raw material for machining after
getting orders from planning sections.
The equipment available in this section are:
a) 1 Ton Capacity Pneumatic Hammer Machine
1 No.
1 No
4 Nos.
e) Blower
2 No.
379
2.
3. Steel Foundry
Produces Cast Steel Slag Pots for our own Blast Furnace and Steel Melting
Shop.Recently we supplied BSP and DSP Slag Pots also. Cast Steel slag pots are
poured directly with liquid steel received from SMS 1. It is also equipped with one
sand Mixer (capacity 500 Kg) for making prepared sand.
H) Major Achievements
1. Total 777 Nos. of bent Crane rails (CR 80: 50 Nos., CR 100: 297 Nos. and
CR 120: 430 Nos.) straightened for our new project during the period from
2010 2011 to 2013 2014.
2. Manufactured 9 Nos. of BSP Slag pots Cap 16 Cu. M) and 12 Nos. of DSP slag
pots (Cap 12 Cu. M) in 2013 2014.
3. Fabrication of Stainless Steel Heat Shield for CDCP
4. Stainless Steel Cone for CDCP Mill fan inlet line
380
I) Central Workshop
The central workshop is being constructed under 2.5 MT expansion project of ISP to
cater to the need of heavy duty and critical spares for BF, coke oven, BOF-CCP,
universal mill, W & R mill etc. The shop layout area is 120 m X 74 m and consisting of
the following sections:
1. Heavy Machine Area
2. Light Machine Area
3. Assembly Area
4. Fabrication Area
5. Forging Area (Future Plan)
6. Heat Treatment Area (Future Plan)
7. Stock Yard And Scrap Yard
8. Raw Material Space
9. Office, Store, Conference Room, PDB Room Etc.
J) New Equipments
The following new equipment will be installed in the Central Workshop:
1.
2.
3.
381
5.
6.
7.
8.
CNC Lathe
K) Future Plan:
1. Balancing Facility
2. Hydraulic Lab
382
1.
1 No
2.
1 No
3.
1 No
4.
1 No
5.
1No
6.
1No
IISCO Steel Plant
1 No
In addition to the above it is proposed to procure the following equipment for material
handling to various sections:
1.
2.
383
Sinter Plant
SINTER PLANT
A) Introduction
The old plant was operating without Sinter with most outdated technology with old
equipment through the ingot route resulting in low yield and high cost of production at SAILISP. As a part of corporate plan 2012, Capacity Expansion of ISP is being taken up by
installation of a new stream of 2.5 MTPAcapacity Crude Steel in the green-field area.In the
2.5 MTPA new stream expansion, a Blast furnace of 4060 m useful volume will be installed.
In order to cater to 80% sinter requirement as prepared B.F. burden, a state of art sinter plant
complex comprising of 2 x 204 m sinter machines along with associated facilities have been
envisaged to produce 3.88 MTPA gross sinter.
Iron ores size (-8 mm) generated during various stage of mining and screening at mines are a
major source of iron ore fines. The technology of Sintering was started in 20 th century as a
mean to utilize these undersize iron ore fines and other metallurgical waste. Now it is a major
source of feed to blast furnace due to its excellent metallurgical properties.
Sintering is basically an agglomeration of iron ore fines, coke breeze and flux at high
temperature (1050C to 1150C). Sinter is produced as a combined result of locally limited
melting, grain boundary diffusion and re-crystallization of iron oxides.
ii.
iii.
iv.
v.
vi.
384
Sinter Plant
c. Decrease in coke rate
d. Increase in productivity
B) Design Parameters:
Unit
Value
2
no. x m
Productivity
ton/m /hr.
2 x 204
1.2
RatedDesign
1.4
Ton
3,877,500
mm
5-40
days x hr.
330 x 24
mmWC
1600
mm
700
Cooler area
202
Hr.
800-850
Cold Sinter
< 100
< 50
mg/Nm
C) Raw Materials
The various raw materials used for producing sinter are as follows
Sl.No.
Material
Size(mm)
T/yr
-8 mm
3386000
Lime stone
-3 mm
267000
Dolomite
-3 mm
263500
Coke breeze
-3 mm
253200
385
Sinter Plant
5
Flue dust
Mill scale
-3 mm
Calcined lime
-1 mm
69800
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
Common Stacks for waste gas ESP & Plant De dusting ESP unit 1 & 2
x.
xi.
xii.
xiii.
xiv.
xv.
Chiller plant
xvi.
DG set building
xvii.
Cooling tower
xviii.
xix.
xx.
xxi.
xxii.
xxiii.
xxiv.
386
Sinter Plant
Sl. No.
Material
Size
(mm)
No.
of
bins
Each bin
Volume,
Moisture,
Storage
(Effective)
Capacity, t
m3
Storage
capacity, hr
(approx)
1.
Blended mix
-8
500
5.4
4500
15.6
2.
Lime Stone
-3
300
2.0
960
284
3.
Coke breeze
-3
300
1.0
360
58
4.
In plant
-5
200
340
3.0
-1
50
100
Sinter returns
5.
ESP dust
All bins are provided with single outlets. The bins for blended mix are lined with SAIL
HARD liner and SS lining is provided in conical portion for bins for Calcined lime fines.
The bin for sinter returns is of stone box construction. Air blasters is provided for smooth
flow in base mix. Bin aerations systems is provided for bins of ESP dust and Calcined
lime.
387
Sinter Plant
The proportioned raw mix constituents from bins is extracted by means of belt weigh
feeders on corresponding dosing conveyors and fed to a combined mixing and nodulising
drum. The return fines bin with single outlet is equipped with standby trolley mounted
weigh feeder. Mixer/ Granulator is provided below bin below ESP dust.
3. Flow- Diagram
Bag filters of
suitable capacity is provided at the top of lime bins for dedusting purpose. Lime fines from
lime tankers is pneumatically transported to lime bins.
The Mixing and nodulising unit comprisesof combined mixing and nodulising drum proper,
girth gear & pinion, steel tyres, support & thrust roller assembly, water spraying arrangement,
grease/ oil lubrication system, discharge chute & hood with fume stack, complete with
mounted electrics & instruments.
388
Sinter Plant
The combined mixing and nodulising drum of size 4m x 15 m long with a coefficient of
filling of 15% is mounted on steel tyre support rollers and have a atomized water spray
arrangement with pipes projecting into the drum to provide water addition in mixing and
nodulising portions of the drum. The drum is complete with drive, gear box, lubrication
system and automatic spray lubrication system for the girth gear and pinions with associated
services etc. The drum with rubber lined conical mixing section have replaceable lifter for
through mixing in first section and nodulising.
C V of gas
2000 Kcal/Nm3
Type of gas
Duty
24 hours continuous
Burner Mounting
Side wall
The ignition furnace is designed for providing optimum ignition time and with necessary
IISCO Steel Plant
389
Sinter Plant
instrumentation and control & regulation system etc& safety device. Negative pressure
ismaintained inside ignition furnace. Post heat hood is located after ignition furnace which
will
avoid sudden chilling of sinter. Cooler hot air at 350 400 deg. C is used in post heat hood as
well as combustion air in ignition hood.
390
Type
600 tph
Pallet width
3.0 m
Pallet length
1.0 m
204 m2
40 - 50 mm
650 mm
700 mm
Speed range
1 4 m/ min
164 + 10 (spares)
Type of drive
Sinter Plant
houses
combustion air fans, hot air fans & multi cyclone, etc.
Hot air at 350 400 deg. C coming out from first section of hot sinter receiving section
of cooler is supplied to ignition furnace for use as combustion air. The hot air is cleaned
in a multi cyclone and pressurized by combustion air fans before supplying to the ignition
furnace.
Hot air coming out from the second section of hot sinter receiving section of cooler is fed
to post heat hood to avoid sudden chilling of raw mix after ignition by the hot air fan.
Duct work from cooler to ignition furnace and post heat hood will be complete with
fixed/ sliding supports & compensators, air intake valves and other instruments.
390 t/h
Area
202 m2
Mean diameter
22.5 m
Trough width
3.5 m
1.6 m
Bed height
1.5m (max)
391
Sinter Plant
Hot sinter temperature
800-850 deg. C
100 deg. C
Retention time
1 hour (approx.)
Annular ring girder is fabricated from rolled steel sections to form main rotating
support structure for the cooler.
ii.
Cooler support rollers (two per cooler draft) are mounted on forged steel shafts.
iii.
Two circular cooler tracks is provided on which the rotating structure of cooler is
supported. One track is on either side of the ring girders. The ring girder are
mounted on RCC circular walls.
iv.
At the discharge point of the cooler, the inner and outer rail tracks are dip
allowing pallet segment trailing edge to dip, thus causing the sinter material to
discharge off the grate into the receiving hopper.
v.
Sinter receiving hopper is of stone box type design to prevent excessive wear.
vi.
vii.
Two sets of friction pulleys and pressure pulleys drive the cooler friction plates.
The friction pulley is driven by helical gear box motor drive unit.
viii.
ix.
x.
Cooler guide rollers is provided and equally spaced about the outside ring girder
of the cooler to ensure smooth rotation of the structure along the circular path,
during operation.
xi.
xii.
392
Sealing arrangement
IISCO Steel Plant
Sinter Plant
xiii.
The sealing arrangement consists of laminex & rubber, cover plates and steel
parts.
xiv.
xv.
Dust hoods are provided over the feed and discharge points of the cooler are
connected to the dedusting unit.
xvi.
Vibro-feeder
xvii.
The discharge of sinter from the hopper to the heat resistant belt conveyor is by
means of a VVVF controlled vibro feeder for control of level on the discharge
hopper of cooler. The belt conveyor feeds cold sinter to the cold sinter crusher in
cold sinter crushing building.
xviii.
xix.
7. Plant De-dusting
The dust laden air from the discharge ends of cooler and sinter machine discharge end,
proportioning bins (except base mix, calcined lime bins), sinter screens, vibro feeders, and
all other dust generating points like conveyor transfer points, etc. are connected to ESPs of
plant dedusting system before being discharged to the atmosphere.
393
Sports Department
SPORTS DEPARTMENT
A) Introduction
With the revival of IISCO Steel Plant after its merger with SAIL, it was our
responsibility to infuse life in Social and Cultural milieu of Burnpur. Sports being
the major driving force for youth, it was appropriate to use it as a fulcrum to
revive Burnpur have lost glory in the field of Sports. With the full support of
higher management and guidance from SAIL Corporate Sports, the Sports
Department of ISP started taking lead and since then Sports activities started
making their presence and importance felt to the people of Steel Township.
Recently after a gap of 33 Years National Boxing Championship was organized
by ISP at Burnpur in which around 400 Participants and Officials from different
States and Units took part. For the first time ISP organized National (Inter
Institutional) Table Tennis Championship at Burnpur which was widely covered
by Media at National level. The Highlights of the Sports at ISP are as under.
B) Our Objective
1. To create and develop a strong base of sports.
2. To contribute to employees welfare by providing sports facilities.
3. To project a positive image of the Organization and enhance the sense of pride
through laurels in national sporting events.
4. To promote sports & games in Steel Township as well as in schools.
C) Our Focus
1. To be pioneer centre in Bengal and on the Indian Corporate scene.
2. To assist employees wards for achieving excellence in sports.
3. To encourage the voluntary Organizations / Clubs specializing in sports in and
around Burnpur.
4. To provide quality input, Infrastructures, coaching and motivation.
5. To be in the front line of sports / games.
394
Sports Department
D) Our Initiatives
1. Coaching
a. Coaching camp for junior boys and girls invarious disciplines under the
concept - Catch them young
b. Sporting talents
c. Intensive coaching to raise the performance standard up to National / International level.
d. Providing standardized playing equipments for training.
e. Selection of teams at sub-junior / junior andsenior level for various
competitions.
2. Organizing
a. Local tournaments round the year in various disciplines.
b. National / State / Dist. / Sub-divisional / Inter steel and SAIL Inter Plant
Sports competitions in various disciplines.
c. Guidance / assistance to local organizations in holding Divisional / District
/ Zonal / National level tournaments.
d. Assistance to ISP Schools for preparation of teams / organizing
competitions.
3. Area of Activities
Outdoor
Indoor
Athletics
Badminton.
Basketball
Bridge
Boxing
Table Tennis
Hockey
Chess
Cycling
Weight Lifting.
Football
Power Lifting
Cricket
Body Building
Handball
Kabaddi
Volleyball
395
Sports Department
Mountaineering
Gymnastic and Yoga
ii.
iii.
iv.
v.
vi.
b. Burnpur Stadium
i.
Football Ground
ii.
ii.
iii.
Fitness Center
e. ISPBoxing Stadium
i.
Boxing Ring
ii.
Wrestling Arena
iii.
Gymnastic Arena
iv.
Yoga Center
396
i.
Cricket Pitch
ii.
Volleyball Court
iii.
Basketball Court
IISCO Steel Plant
Sports Department
iv.
August 2009
Cadets
Venue
Coaching
Age Group
Between 12 to 16 Years.
Performance
Target
397
Sports Department
i. Strength of Academy
A residential Academy with total strength of 34 Cadets selected from
different parts of the country by a panel of experts consisting of ExNational and International players.
j. Facilities
i.
Free fooding,lodging,training,education, medical facility ,
ii.
iii.
398
iv.
v.
Telecommunication Department
TELECOMMUNICATION DEPARTMENT
A) Introduction
Telecommunication
plays
an
important
role
in
our
life
today.
Generally,
In steel industries telecommunication plays a vital role for effective, safe, smart,
competent & speedy production of steel & other steel products.In SAIL-ISP,
Telecommunication department mainly looking after two areas:
a. Telecommunication
i.
ii.
iii.
399
Telecommunication Department
iv.
v.
Walkie-Talkie Monitoring
vi.
vii.
viii.
ix.
b. Railway Signaling
B) Telecommunication
1. Intercom Landline Telephone
a. Plant Telephone Exchange
For the 2.5 MT new stream of expansion project for the deployment of a fully
Modular & Non-blocking, Distributed Architecture based SIP (Session Initiation
Protocol) based Communication Server to provide telephony services along with a
SIP based audio conference bridge.
Plant Telephone Exchange has been equipped with 3000 subscriber lines, wired
with 6000 subscriber lines &extendable up to 12000 subscriber lines.
400
Telecommunication Department
Along with Call Servers in New Server Based Telephone Exchange there are also
following Servers connected to this Exchange through switches.
b. Audio Conference Bridge - Omni Touch Team Work Server
OmniTouch My Teamwork is an application enabling employees to collaborate
remotely with colleagues or external participants. SIP based Audio Conference
Bridge of 150 ports fully integrated to the Telephony system.Maximum 150
Subscriber can be included in one Conference.Daily Morning Conference of
senior executives has started from Feb, 2014 through Server based Conference
system.
401
Telecommunication Department
and telecommunication cost tracking. It is a software tool for the maintenance &
monitoring of features & facilities provided to the subscribers.
e. Remote Maintenance Access RMA
The RMA (Remote Maintenance Access) system is an external server used to
perform configuration and maintenance operations. Maintenance is performed
locally or remotely, via the modem.
g. Township Exchange
There is an Alcatel Lucent make Server Based Telephone Exchange installed in
Township Exchange which comprises of 3 call servers (Back up for Call Servers
installed in Plant Exchange).Township Exchange has been equipped with 1000
subscriber lines & extendable up to 2000 subscriber lines.
Telecommunication Department
i.
ii.
Existing Plant Zone: Covering areas Coke Oven Battery#10, Old CHP,
Gates, Machine Shops, Blast Furnace#2, Old Power Plant, Safety, Fire,
Environment, General Offices, Stores andall other establishments
functioning in existing area.
iii.
403
Telecommunication Department
TELEPHONE EXCHANGE FULL NETWORK OF SAIL-ISP
Plant
Exchange
Main Electric
Room (440V)
B1
B2
CABLE
ROOM
MDF
AS
FCBC
CALL
SERVERS
Main
Circuit
Breaker
1
UPS
Bt-1
Bt-2
ES
Township
Exchange
CS
DS
(1 Nos.)
(8 Nos.)
ES
ES
RLU
SUBSCRIBERS
ES
AS
DB
404
MDF
PCS
MG
1 - 14
SUBSCRIBERS
MG
LIU
Telecommunication Department
LIU - Light Interface Unit, AS - Alcatel Switch, CS - Core Switch (1 Nos.), DS - Distribution
Switch (8 Nos.),DB - Distribution Box, ES - Edge Switch (LIU is present within ES only), MDF
- Main Distribution Frame, MG - Media Gateway, RLU - Remote Location Unit, FCBC - Float
cum Boost Charger (O/P = 48 V DC, 50 Hz), Bt-1, Bt-2 -Battery Back-Up for UPS (O/P = 220V
AC, 50Hz), B1, B2 - Battery Back-Up for FCBC
Note: From Township Exchange the lines are given to the subscribers in the same manner as
given in the Plant Exchange through MDF & Cable Room present in Township Exchange.
5. Walkie-Talkie Monitoring
For the efficient & fast production of Steel Walkie-Talkie facility has also been
provided by Telecommunication Department. Maintenance of Walkie-Talkies is
looked after by Telecommunication Department.
6. Close Circuit Video Monitoring
IISCO Steel Plant
405
Telecommunication Department
Telecommunication Department is looking after the Close Circuit Video Monitoring
through CCTV cameras for surveillance as well as monitoring purpose. These CCTV
cameras have been installed at different locations in plant.
For Surveillance purpose there are presently 10 nos. of CCTV cameras have been
installed at Gates & Weigh Bridges.
Nos. of
Type of cameras
cameras
1.
Tunnel Gate
Fixed
2.
SCOB Gate
Fixed
PTZ
3.
Vehicle Gate
Fixed
4.
Sanmara Gate
PTZ
Fixed
PTZ
5.
All these cameras except at Sanmara gate are being viewed through Fiber Optic
network. Sanmara Gate is yet to be connected with Fiber Optic network.
For monitoring purpose there are approx. 234 nos. of CCTV cameras are to
beinstalled in the modernization site. Presently, following nos. of CCTV cameras
have
Sl. No.
Location
Qty
Make/Model
1.
Sinter Plant
11
Bosch/LTC 0455/51
2.
WRM
10
Pelco/CC3651H-2X
3.
Bosch/LTC 0455/51
4.
10
Pelco/C10DN-6X
been
installed.
406
Telecommunication Department
LSIS stands for Loudspeaker Intercommunication System & LSBC stands for
Loudspeaker Broadcasting System. These two have been used for the announcement
at work sites from a control roomand also from different locations of that unit. LSIS
is based on two way communication whereas LSBC is based on one way
communication. Telecommunication Department provides the support maintenance
for these two systems of communication.
C) Railway Signalling
In a steel plant, timely and efficient supply of raw materials and dispatch of finished
goods is very essential. For this, we require railway yards to be functioning smoothly.
Thus, Railway Signaling Scheme plays a vital role in the supply chain of steel
production.In the old plant, changing of tracks and giving of signals to train are done
manually. As a result, more manpower is required and efficiency as well as safety
decreases. In the new plant, the railway yards are being automated using the state of the
art Panel Interlocking technology based on Indian railways pattern which reduces
manpower and improves safety.
The Railway Signalingschemeat Damodar Yard (Raw material Handling Yard) is looked
after by Telecommunication Department. The Railway Signaling Scheme at this yard
incorporates Route Relay Interlocking system which provides for the failsafe operation of
Signals and point machines for the smooth movement of locos.
IISCO Steel Plant
407
Telecommunication Department
Main equipments at Damodar Yard consist of:
a. Electric Point machine:There are 31 point machines which are used for movement of
tongue rails.In the event of a power failure or emergency the point can be operated
manually.
b. Relays:Signaling relays have applications such as Route Relay Interlocking, Panel
Interlocking, Automatic Signaling, Point Operation and Track Circuiting. There are
around 1780 nos. of indoor and 231 nos. of outdoor relays.
c. Track circuit: There are 62 track circuits to detect the correct position of railway
engine/ wagon on the track and thereby giving signal accordingly.
d. Signals: There are various types of signals like main, routing, shunt and calling on
signals to display stop or move signals to loco driver.
e. Control cum indication panel: It has push buttons for setting of route, setting of
individual point machines and giving of signal. There is also provision for emergency
cancellation of set routes. Whenever a route is set all the point machines on that route
are automatically set and set route is shown by yellow LEDs on the Indication
panel.When the loco arrives,itsmovement is shown by transformation of yellow LED
to red LED showing occupied track and subsequently clears the section in rear as it
moves on.
408
A) Introduction
T&RM department is concerned with the transportation of incoming raw materials,
inter-process materials and outgoing finished products. This transportation involves
both the intra-plant movement and railway rake movement.
a. Railway rake movement can be either inward rake movement for supply of
raw materials or empty rake for dispatch of the materials from the plant.
b. For dispatch & receipt of rakes ISP has three railway sidings;
i.
ii.
BCME sidings - Inward coal receipt & dispatch of coke and pig iron
from old plant.
iii.
ISP Burnpur is the only plant of SAIL which is served by two different zones of
Indian Railways; South Eastern Railways (SER) through its division at Adra and
Eastern Railways (ER) through its division at Asansol.
The key areas of working can be summarized as
a. Planning and procurement of raw materials
b. Placement and withdrawal of wagons.
c. Up keeping of the tracks for movement.
d. Maintenance of the Diesel Locomotives used for hauling.
e. Attending to disruptions & derailments.
Based on the above key functions; T&RM department has been divided into five sections;
a. Raw Material.
b. Movement.
c. Permanent Way (PW).
d. Diesel Loco Maintenance.
e. Carriage & Wagon.
409
Item
No
Source
Consuming Unit
Remarks
Meghataburu, Kiriburu,
1
Gua,
Manoharpur,Kalta,
Sinter Plant
For use in BF
Barsua, Bolani
Meghataburu, Kiriburu,
2
Gua, Manoharpur,
Kalta,
BF#2,BF#5
Barsua, Bolani
3
Lime Stone
Kuteshwar
Sinter Plant
Lime Stone
Jaisalmer, Imported
LDCP
Dolomite
BISRA
BF#2
Dolomite
Dalgaon, Bhutan
Quartzite
Local Purchase
BF
LD Slag
BSL
BF#2
Coking Coal
Chasnalla
Coke Oven
Haldia, Dhamra,
(Australia Hard)
Paradip Ports
Haldia, Dhamra,
(US Hard)
Paradip Ports
Haldia, Dhamra,
Paradip Ports
Haldia, Dhamra,
(Australia Soft)
Paradip Ports
Haldia, Dhamra,
Paradip Ports
Boiler Coal
ECL Mines
10
11
12
13
14
15
410
For use in BF
For use in
Steel Making
Sinter Plant,
For use in
LDCP, BOF
Coke Oven
Coke Oven
Coke Oven
Coke Oven
Coke Oven
Boilers
IISCO Steel Plant
The iron ore lump for BF#2 is received at Transit Bunker through ISPB siding by
S.E.Railway. However, the iron ore lump for BF#2 may also be received at Track
Hopper of new plant for sending to BF#2 of old plant.
The iron ore fines and iron ore lump rakes required for Sinter Plant and BF#5 are
received at Damodar Yard through S.E.Railway and unloaded in Tippler#301(Fines)
and Track Hopper (lump).
411
Dolomite for BF#2 is procured from BISRA Stone & Lime Co. Ltd, Birmitrapur. For
Sinter Plant and use in LDCP/BOF Low Silica Dolomite is procured from Dalgaon,
Bhutan.
For Quartzite procurement ISP has taken procurement action to get the quartzite in
wagons through Rail Route.
5. Boiler Coal:
Boiler Plant gives its annual coal requirement. Based on that monthly requirement and
plan is given to CCSO, Dhanbad, under Operations, Corporate Office, NewDelhi. The
allotment of coal rakes are taken from ECL, Headquarters on weekly/10 days basis for
supply to BCME siding, ISP.
412
STEEL SECTION
IRON SECTION
NORTH YARD
SOUTH YARD
DAMODAR YARD
Connected with
ER
through
HSME
for
C/Coal, B/Coal,
Flux
Rake
reception
for
existing plant,
Feeding
of
empty wagons
supply to PCM,
Coke Loading.
Connected with
SER
through
Burnpur for I/Ore
lump
rake
reception
for
existing
plant,
feeding of B.F.
Coke
through
high line & power
house coal for
power plant
Connected
with
SER
through
Damodar
for
reception of raw materials
and caol for the New Plant.
Equipped with three nos. of
tipplers & one no. of Track
Hopper
WestYard
B. Fce Yard
Connected with EC Railway
through HSME for reception of
empty rakes for steel, Pig Iron &
G. Slag loading and despatch.
The principal role of T&RM department comes under movement section. The whole
transportation i.e. from incoming materials to products which has to be dispatched is looked
upon by this section.
IISCO Steel Plant
413
1. Traffic (Iron):
Traffic (Iron) is mainly concerned with the movement of incoming raw materials i.e.
coal, iron ore and flux materials such as limestone, dolomite etc. Moreover, intraplant
movement of various output of the existing B.Fce and Coke Oven are also monitored
by this section. Dispatching of pig iron and coke are the prime area of outward
movement of this section.
In Order to make sure on monitoring of movement, Traffic (Iron) has been further
divided into the following yards which are: Damodar Yard, South Yard and North
Yard.
a. Damodar Yard
Damodar yard is built to cater the needs of new plant. Its connected to South Eastern
Railways through Damodar Station Main Line & it will handle the entire inbound
loaded rake to new plant. It has ten lines named in the numerical sequence & total
running length of yard is 24 Km. Damodar yard is equipped with the advanced Route
Relay Interlocking system (RRI) to prevent conflicting movements through an
arrangement of tracks such as junctions or crossings & for this it has a total of thirty
one motorized points that can be operated from RRI cabin.
For the first time in the history of SAIL, Indian Railways will bring their loco inside
the plant. To facilitate the movement of railways electric locomotive, all the lines are
electrified by OHE of 25 KV.
All loads will go over the in motion weigh bridge of 150 ton capacity provided at the
main entry side of Damodar yard for weighing all in coming raw material rakes.
414
There are three tipplers & one track hopper for the unloading of loaded rakes. Coal &
flux are unloaded in tipplers while iron lumps are unloaded in track hopper. Track
hopperof length 200 meter connected with line no: 01 & 02 can handle up to 18
wagons at a time. Tippler 302 connected with line no: 09 & 10 is specifically for
unloading of coal rakes while tippler 301 connected with line no: 06 & 07 is for
unloading of fluxes, iron fines & coal rakes. Tippler 300 connected with line no: 04 &
05 is specifically for unloading of iron ore fines rakes. A sick line (line no: 11) has
been provided near the out haul of tippler 302 for attending sick wagons.
c. South yard:
This Yard is directly connected to South Eastern Railways through Burnpur Station.
Different storage space has been provided in this yard for handling and storing
different raw materials and products of the existing plant, i.e.
i.
Limestone
ii.
Dolomite
iii.
LD Slag
iv.
Mn Ore
v.
BF Coke
vi.
Nut Coke
vii.
Lump Iron Ore rakes are directly placed from Burnpur Station to South yard on track
hoppers. Iron ores are unloaded in the bunkers from which these materials are directly
415
d. North Yard:
North yard is connected to Eastern railways through Asansol Divisions Hirapur
Exchange Yard (HSME). Like South yard, it also handle&Store differentstocks like:
i.
Coking Coal
ii.
Coke Breeze
iii.
Nut Coke
iv.
v.
Wagons containing Coking coal are placed in Box tippler for unloading to feed
existing Coke Oven Batteries. Through this yard pig iron and coke rakes are also
dispatched to different destinations.
An electronic weigh bridge as well as a Mechanical Weighbridge have also been
installed in this yard to check the weighments.
2. Traffic (Steel)
This section has also been divided into two yards
i.
ii.
West Yard
a. East Yard:
It caters to the requirement of existing Steel Melting Shop, Rolling Mills and partly of
Blast Furnace for its feeding of raw materials, disposal of liquid steel, steel ingots and
disposal of waste materials like furnace jam and steel scraps arising from SMS., mill
scale, scrap generated from mills, defective structural etc.
b. West Yard:
This yard is modernized with the idea of catering to the requirement of despatch from
New Plant. It has got 12 lines measuring about 17 KM and 6 nos. of WDS-6AD
Locomotives are there to cater to the New Plant requirement.
.
416
Provision has been made in the Yard to facilitate for direct reception of Inward Traffic
e.g. Empty Rakes & Billets etc by Railway Pilot through full length OHE
arrangement in Line #8 	 with switchover facility. Provision has also been made to
draw the loaded outbound Rakes by Railway Pilot.
In the New Plant this yard will cater to the job of receiving Empty Rakes & feeding of
empties to various Mills, Pig Machines and Granulated slag for loading, receiving
loaded wagons, regrouping them, rake formation and hand over the rakes to Railways
after completion of Field Commercial formalities.
Rails
ii.
Sleepers
iii.
Fittings &fastenings
iv.
Ballasts
v.
417
ii.
high
carbon
or
iv.
Switch: Pair of tongue and stock rails with necessary connections and
fittings form a switch.
v.
Points: Pair of tongue rails with their stock rails is termed as points.
vi.
418
i.
Preventive Maintenance
ii.
ii.
iii.
iv.
v.
vi.
Conducting monthly safety meeting & counseling with last injured person
Damodar Yard
25 Km
In Plant
18 Km
West Yard
15Km
Blast Furnace
7km
4km
South Yard
8.5km
North Yard
9.6km
West Yard
10km
4km
3.5km
419
AREAS
FOR
REGULAR
AS
WELL
AS
CONTRACTUAL
EMPLOYEES.
BEFORE
STARTING
THE
OPERATION/PRODUCTION/CONCERN
JOBS
ON
DEPARTMENTS
RAIL-TRACKS,
ARE
BEING
INFORMED IN ADVANCE & RED FLAGS ARE BEING FIXED AT BOTH ENDS
OF THE TRACKS.
INSPECTION OF TRACKS ARE CARRIED OUT DAILY & NEXT DAYs JOBS
ARE PLANNED ACCORDINGLY.
420
ii.
Our mottos:
i.
ii.
To cater to the requirement of 2.5 MTPA plant under modernization and expansion,
12 Nos. of diesel locomotives have been purchased and these have been deployed as
follows:
Sl.
Yard Location
No.
Locomotive
Type
Nos.
Functions
Deployed
1.
Damodar Yard
WDS6AD
Yard operation
2.
West Yard
WDS6AD
Yard operation
421
BHEL - SPP
CCP Area
Torpedo Ladle
movement
CAPACITY
QTY.
GE - Single Unit
235 HP
2 Nos.
GE - Double Unit
600 HP
9 Nos.
350 HP
2 Nos.
700 HP
4 Nos.
BHEL - SPP
700 HP
3 Nos.
DLW - WDS6AD
1350 HP
9 Nos.
29 os.
Regular Servicing
Schedule Major Maintenance
Capital Repair
422
i.
Regular Servicing.
ii.
Schedule Maintenance.
iii.
Engine Overhauling.
iv.
v.
vii.
Capital Repair.
viii.
423
424
How can water resources be managed sustainably while meeting an ever increasing
demand?
Freshwater accounts for only 2.5% of the Earths water, and most of it is frozen
inglaciers
andcaps.
The
remaining
unfrozen
freshwater
is
mainly found
asgroundwater, with only a small fraction present above ground or in the air.
ii.
iii.
iv.
v.
Fire fighting.
1. Carrier of Heat
Most of the water in a steel plant is used for removal of heat as in the
following processes
i.
ii.
425
3. Gas Seals:
As gas seals in Gas Cleaning Plants and Gas Holders to prevent the escape of
gases to atmosphere.
4. Generation of Steam:
Used for generation of heat in Power Plants, Waste Heat Boilers and
evaporation cooling systems.
5. Fire Fighting:
In an integrated steel plant there are many fire prone areas like Liquid Fuel
Station, Oil Cellars,Cable Galleries, Oil & gas pipelines, Chemical Plants,
Coal Feeders, Conveyors, etc. Fire Hydrants(indoor & outdoor) are provided
for fire fighting all over the plant. Most of the fire hydrants in ISP use
industrial water.Different systems are adopted for circulation of industrial
water in an industry.
The water can be collected after use and re-used (re-circulation system) or can
be discharged back tothe natural streams / rivers (once through system). For
the latter the source should be sufficientlylarge enough for the continuous
supply of water throughout the year. This system is hardly used now days as
there is an ever increasing demand of water and source of water to meet huge
demands isvery rare. Also, the government is enforcing stringent pollution
control regulations & restrictions oneffluents discharged.
In steel plants re-circulation schemes are adopted. Re-circulation schemes can
be broadly classified as
426
ii.
In central re-circulation system, most of the plant units draw water from one
singlesystem anddischarge water back into the system. In the local recirculation system,each of the plant units draw only the make-up water
required from the central source and the water is re-circulated within the unit
itself. Centralised system is adopted in the old IISCO PLANT and Local
recirculation system is adopted in the new plant.
Listed below are some important points in the contract with DVC.
i.
The existing contract with DVC envisages that up to 12MGD the cost of
drawing water from Damodar is free and an exceeding this amount water
charges are to be paid at Rs one per cum.
ii.
Although from Oct12 DVC has terminated the above contract and demanding
formation of a new contract which will scrape the free water supply and water
charges will rise to Rs 5.7/cum. But since no new agreement has been signed
so far this proposal is under negotiation.
Water required for ISP is drawn by the intake pump house located at River
Damodar.
D) A Brief of existing Intake pump house &Old and New pump house.
427
ii.
428
particularly 12, 18 & 24 are supplying the water to Town department and 27
line supplying the water to the reservoir at Burnpur Works. Through 24 line
water can also supply to the reservoir by diversion at Booster pump House near
tunnel gate.
There is a Pressure filter plant to supply the water Riverside colony and park
(Nehru Park) , Pump houses and Pump house colony . The raw water is directly
taken from settle Tank No-4 through 27 Line to the tank. From tank raw water
lifted through the pumps to the clarifiers and from there water goes to the pressure
filters and from pressure filters it is taken to the Overhead Tank by high lift
pumps.
There are 04 No of pumps 02 (1W+1S) for supplying water to clarifier and the
rest two numbers of pumps (1W + 1S) supplying water to the overhead tank.
429
Pump house
b. New Pump House.
Purpose
Pumps
Alum Dosing
To improve clarity.
Settling Ponds
430
Pump House
Pipeline
431
100 cum/hr
In ISP drinking water is supplied to the old plant and the town ship in the form of filtered
water and industrial water is supplied into the central recirculating system.
In the new plant drinking water and makeup water is supplied from the water treatment
plant and make up water is supplied to the local recirculation systems of the individual
units.
10%
CCP
16%
5%
4%RHF 2%
2% PCM
18%
TPP-TPS
BLAST
FURNACE
RMHS
15%
BOF
16%
The major requirement of makeup water in steel plant is for the units such as BOF, BF,
RMHS, CCP AND TPP-TPS.
432
H) Reservoirs:
ISP has 2 nos. of cooling ponds in the OLD plant and two nos. of reservoirs in the new
plant , the capacity of the reservoirs in the new plant is 160000 cum and 120000
cumrespectively. The capacity of the two reservoirs in the old plant is .9 lakh cum and 4.5
lakh cum.
433
ii.
iii.
iv.
K) Distribution Network
434
435
436
Title
Requirement
m3/h (Max)
RMHS 01A
RMHS 01B
Hours
working
288
5180
210
5180
115
5180
26
8760
8760
Remark
Schematic
diagram for
service water &
Potable water
system
RMHS 01C
Schematic
diagram for
SW/PW & CW
system
Coke oven
water
battery
consumption
and water
removal data
CDCP
UG network of
water supply &
sewerage Flow
diag
By product
P&ID for
plant
cooling water
Sinter plant
8760
UF & RO having
system
capacity-32m3/hr
P&ID for
RO-having capacity 7
utilities-Water
system
122
7920
437
P&ID Cooling
water
system(1/5)
are stored in
722
8760
CDI
Flow diagram
for cooling
8760
water system
Pig Casting
Process Flow
process losss-
Machine
diagram of
water
70
2190
circulating
15m3/hr, no water is
drain out
system
HMHS
Flow diagram
of industrial
water for
8760
HMHS
USM
Water mass
Blowdown of ICW
balance for
is no blowdown in
85
6000
DCW, Dewatering
system is also
planned, no water is
drain out
RHF
Design Criteria
Blowdown goes to
of Auxiliaries
RO-having capacity
157
6800
12 m3/hr, Lamella
clarifier is provided to
dewater the waste of
filtration plant
438
Process Flow
Blowdown goes to
Diagram
RO having capacity100
6000
20 m3/hr, Treatment
unit is provided to
dewater the waste of
filtration plant
Air
Process flow
Separation
diagram of
Plant
cooling water
RO Plant having
180
7920
21
8160
capacity of 22m3/hr
for treating blowdown
system
Top pressure
Cooling water
recovery
system control
Turbine
flow chart
Power &
Water Balance
Blowing
diagram
Blowdown goes to
506
8160
Station
LBDS
RO (having capacity
155m3/hr)
Tech Data
sheet of pumps
27
8760
8760
8760
8760
335
8760
for LBDS
GA of pumps
for LCSS
IPPL
Intermittent
requirement for
filling up U
Seal, Flare
Stack, Etc
BOD Plant
Water
requirement
LDO Storage
As Discussed,
no water is
required
Package 11-
Make-up water
14 - CCP
requirement in
Blowdowngoes to
SST, hence utilised in
439
CCP Area
system
Package 11-
Make-up water
Blowdown goes to
14 - BOF
requirement in
area
BOF Area
375
8760
Lime &
Schematic
Dolomite
Flow Diagram
plant
for Cooling
10
8760
Tower
Centralised
Integrated
Compressed
Air station
supply system
ACVS
MW FOR CCP
Chiller Plant
Blowdown 7.5m3/hr
54
8760
16.2
8760
25
8760
8760
8760
8760
100
8760
25
8760
MW for
ventilation &
AC Consumers
of BOF Shop
proper
Data Sheet of
cooling Tower
MRS
P&ID FOR AC
SYSTEM
P&ID FOR AC
SYSTEM
Drinking
Water
Misc
440
441
442