0% found this document useful (0 votes)
126 views1 page

Underside of Beam: Option 1A Option 1B

This document provides two options for addressing the size gap between a concrete masonry unit (CMU) wall and a concrete beam. Option 1A involves using an A-shaped block at the top course of the wall. Option 1B involves cutting out the face shell of the CMU and replacing it after grouting, with the height varying. Both options call for using 1/4 inch thick by 6 inch wide steel plates welded to the beam after CMU placement for shear transfer, and bonding the beam at the second course from the top with through-bolting or lag bolting for additional shear transfer.

Uploaded by

UALU333
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
126 views1 page

Underside of Beam: Option 1A Option 1B

This document provides two options for addressing the size gap between a concrete masonry unit (CMU) wall and a concrete beam. Option 1A involves using an A-shaped block at the top course of the wall. Option 1B involves cutting out the face shell of the CMU and replacing it after grouting, with the height varying. Both options call for using 1/4 inch thick by 6 inch wide steel plates welded to the beam after CMU placement for shear transfer, and bonding the beam at the second course from the top with through-bolting or lag bolting for additional shear transfer.

Uploaded by

UALU333
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

OPTION 1A

OPTION 1B

SIZE GAP FOR DRIFT & DEFLECTION


OF BEAM FOR TYPE I HYBRID; OR
FILL GAP W/ DRYPACK FOR TYPE II
OR TYPE III HYBRID
OPTION 1A: A-SHAPED BLOCK AT
TOP COURSE; OR OPTION 1B: CUT
OUT FACE SHELL AND REPLACE
AFTER GROUTING; HEIGHT VARIES

1/4 THK x 6 WIDE PLATES FOR


SHEAR TRANSFER; WELD TO
BEAM AFTER CMU PLACEMENT
THROUGH-BOLT OR LAG BOLT AS
REQD FOR SHEAR TRANSFER
BOND BEAM AT SECOND
COURSE FROM TOP
GROUT & REINFORCING
AS REQD

UNDERSIDE OF BEAM
DETAIL 02.120.1201

OPTION 1
REV. 03/02/09