0% found this document useful (0 votes)
111 views3 pages

Infra Schedule

This document contains a schedule for infrastructure works with 115 tasks over 20 days from February 11th to March 2nd. The tasks include drainage works like excavation and concreting perimeter drains. Other tasks include gravel verge works, road works involving excavation, laying crusher run and premix, and pavement works. Miscellaneous tasks at the end involve installing pipe supports, staircase stumps, an economizer platform and light poles to finish the project.

Uploaded by

mhdfhm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
111 views3 pages

Infra Schedule

This document contains a schedule for infrastructure works with 115 tasks over 20 days from February 11th to March 2nd. The tasks include drainage works like excavation and concreting perimeter drains. Other tasks include gravel verge works, road works involving excavation, laying crusher run and premix, and pavement works. Miscellaneous tasks at the end involve installing pipe supports, staircase stumps, an economizer platform and light poles to finish the project.

Uploaded by

mhdfhm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ID

Task
Mode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57

Task Name

Duration

Start

Finish

INFRASTRUCTURE WORKS
Milestones
Drainage
Drainage Start
Drainage Finish
Gravel Verge
Gravel Verge Start
Gravel Verge Finish
Road Work
Road Start
Road Finish
Pavement
Pavement Start
Pavement Finish
Premix
Premix Start
Premix Finish
Perimeter Drainage
Perimeter Drain Deaerator East

20 days
20 days
15 days
0 days
0 days
15 days
0 days
0 days
16 days
0 days
0 days
13 days
0 days
0 days
5 days
0 days
0 days
15 days
4 days

11/2/14
11/2/14
11/2/14
11/2/14
25/2/14
14/2/14
14/2/14
28/2/14
14/2/14
14/2/14
1/3/14
15/2/14
15/2/14
28/2/14
26/2/14
26/2/14
2/3/14
11/2/14
11/2/14

2/3/14
2/3/14
25/2/14
11/2/14
25/2/14
28/2/14
14/2/14
28/2/14
1/3/14
14/2/14
1/3/14
28/2/14
15/2/14
28/2/14
2/3/14
26/2/14
2/3/14
25/2/14
14/2/14

1 day
1 day
1 day
1 day

11/2/14
11/2/14
12/2/14
13/2/14

11/2/14
11/2/14
12/2/14
13/2/14

Concreting Drain Wall


1 day
Perimeter Drain Deaerator North 4 days
East
Excavation
1 day
Casting Lean Concrete
1 day
Concrete base
1 day
Drain Wall Formwork Erection 1 day
(with curve wall)
Concreting Drain Wall
1 day
Perimeter Drain Boiler
4 days
(Right/North side)
Excavation
1 day
Casting Lean Concrete
1 day
Concrete base
1 day
Drain Wall Formwork Erection 1 day

14/2/14
15/2/14

14/2/14
18/2/14

15/2/14
15/2/14
16/2/14
17/2/14

15/2/14
15/2/14
16/2/14
17/2/14

18/2/14
14/2/14

18/2/14
17/2/14

14/2/14
14/2/14
15/2/14
16/2/14

14/2/14
14/2/14
15/2/14
16/2/14

Concreting Drain Wall


Perimeter DrainBoiler
(Right/North side Exit)
Excavation
Casting Lean Concrete
Concrete base
Drain Wall Formwork Erection

1 day
4 days

17/2/14
18/2/14

17/2/14
21/2/14

1 day
1 day
1 day
1 day

18/2/14
18/2/14
19/2/14
20/2/14

18/2/14
18/2/14
19/2/14
20/2/14

Concreting Drain Wall


Perimeter Drain Boiler
(Left/South side)
Excavation
Casting Lean Concrete
Concrete base
Drain Wall Formwork Erection

1 day
4 days

21/2/14
22/2/14

21/2/14
25/2/14

1 day
1 day
1 day
1 day

22/2/14
22/2/14
23/2/14
24/2/14

22/2/14
22/2/14
23/2/14
24/2/14

Concreting Drain Wall


Close Drain C/W R.C Sump
WTU to Boiler (L=6.95M)
Excavation
Casting Lean Concrete
Concrete base
Drain Wall Formwork Erection

1 day
5 days
4 days
1 day
1 day
1 day
1 day

25/2/14
11/2/14
11/2/14
11/2/14
11/2/14
12/2/14
11/2/14

25/2/14
15/2/14
14/2/14
11/2/14
11/2/14
12/2/14
13/2/14

Concreting Drain Wall & Top


WTU to Boiler (L=15M)
Excavation

1 day
5 days
1 day

11/2/14
11/2/14
11/2/14

14/2/14
15/2/14
11/2/14

Excavation
Casting Lean Concrete
Concrete base
Drain Wall Formwork Erection

Project: Infra Schedule 17_02_1


Date: 17/2/14

Text1

11/2
25/2
14/2
28/2
14/2
1/3
15/2
28/2
26/2
2/3

Task

Summary

Manual Progress

Milestone

Progress

Critical

Page 1

February
March
19/1 26/1 2/2 9/2 16/2 23/2 2/3 9/3

ID

Task
Mode
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99

100
101
102
103
104
105
106
107
108
109
110

Task Name

Duration

Start

Finish

1 day
1 day
2 days

11/2/14
12/2/14
11/2/14

11/2/14
12/2/14
14/2/14

1 day
12 days

11/2/14
15/2/14

15/2/14
26/2/14

1 day

15/2/14

15/2/14

Concreting Pavement
Remaining Pavement Boiler
North Side
Concreting Pavement
Remaining Pavement Boiler
South Side
Concreting Pavement
Pavement
Maintenance Track (Main)
Access Pickup Track WTU West
Side
Access Pickup Track Laku Tank

1 day
1 day

15/2/14
18/2/14

15/2/14
18/2/14

1 day
1 day

18/2/14
26/2/14

18/2/14
26/2/14

1 day
4 days
3 days
3 days

26/2/14
19/2/14
19/2/14
19/2/14

26/2/14
22/2/14
21/2/14
21/2/14

1 day

19/2/14

19/2/14

Access Pickup Track Demin


Tank
Access Pickup Track BFW
Access Pickup Track
Condensate
Gravel verge
Gravel verge at FG piperack
Leveling to finish level 9.8m
laying of crusher run
Gravel verge at WTU
Leveling to finish level 9.8m
laying of crusher run
Gravel verge at Boiler
(left/South side) yard
Leveling to finish level 9.8m
laying ofcrusher run
Road
FDT
Road work (WTU north side)
Excavation/Leveling
Laying of Crusher run
Road work (WTU tank South
Side)
Excavation/Leveling
Laying of Crusher run
Road work (Deaerator East Side)

1 day

20/2/14

20/2/14

1 day
1 day

21/2/14
22/2/14

21/2/14
22/2/14

15 days
5 days
2 days
2 days
5 days
2 days
2 days
8 days

14/2/14
14/2/14
14/2/14
17/2/14
18/2/14
18/2/14
20/2/14
21/2/14

28/2/14
18/2/14
15/2/14
18/2/14
22/2/14
20/2/14
22/2/14
28/2/14

3 days
3 days
16 days
1 day
3 days
1 day
1 day
4 days

21/2/14
24/2/14
14/2/14
14/2/14
14/2/14
14/2/14
16/2/14
17/2/14

25/2/14
28/2/14
1/3/14
14/2/14
16/2/14
15/2/14
16/2/14
20/2/14

1 day
1 day
4 days

17/2/14
18/2/14
19/2/14

19/2/14
20/2/14
22/2/14

Excavation/Leveling
1 day
Laying of Crusher run
1 day
Road work (Boiler North Side)
4 days
Excavation/Leveling
1 day
Laying of Crusher run
1 day
Road work (Boiler tank South
4 days
Side)
Excavation/leveling
1 day
Laying of Crusher run
1 day
Premix
5 days
Road work (WTU north side)
1 day
Road work (WTU tank South Side) 1 day

19/2/14
20/2/14
21/2/14
21/2/14
23/2/14
26/2/14

21/2/14
22/2/14
24/2/14
23/2/14
24/2/14
1/3/14

26/2/14
27/2/14
26/2/14
26/2/14
27/2/14

28/2/14
1/3/14
2/3/14
26/2/14
27/2/14

28/2/14

28/2/14

1 day
1 day

1/3/14
2/3/14

1/3/14
2/3/14

5 days
0 days

17/2/14
17/2/14

21/2/14
17/2/14

Casting Lean Concrete


Concrete base
Drain Wall & Culvert Formwork
Erection
Concreting Drain Wall & Top
Remaining Pavement (Around
perimeter drain)
Remaining Pavement Deaerator

Road work (Deaerator East Side) 1 day


Road work (Boiler North Side)
Road work (Boiler tank South
Side)
Micellenous
Start

Project: Infra Schedule 17_02_1


Date: 17/2/14

Text1

pending for FDT test

17/2

Task

Summary

Manual Progress

Milestone

Progress

Critical

Page 2

February
March
19/1 26/1 2/2 9/2 16/2 23/2 2/3 9/3

ID

Task
Mode

Task Name

Duration

Start

Finish

2 days

17/2/14

18/2/14

111

Pipe / structure Support stumps

112
113

Staircase stumps
1 day
Stumps for economiser platform 1 day

19/2/14
20/2/14

19/2/14
20/2/14

114

Light Pole installation

1 day

21/2/14

21/2/14

115

Finish

0 days

21/2/14

21/2/14

Project: Infra Schedule 17_02_1


Date: 17/2/14

Text1

Pending for MIE dwg position of pole


21/2

Task

Summary

Manual Progress

Milestone

Progress

Critical

Page 3

February
March
19/1 26/1 2/2 9/2 16/2 23/2 2/3 9/3

You might also like