Koh Pich Construction Company: Elite Town Iii Project Work Report

The daily report from Koh Pich Construction Company provides details of construction work completed on January 2nd, 2017 at the Elite Town III project site. Work that day included setting coordinates for pile foundations, installing reinforcement for pile caps at two blocks, excavating soil at one block, repairing a pile, and breaking the head of a pile. Tomorrow's scheduled work includes pouring concrete for pile caps, installing more reinforcement, backfilling soil, and excavating soil for another block's foundation. Photos document the day's progress on pile work and soil movement. An attendance report lists 134 workers on site from the main and subcontractors.

Uploaded by

Ket Chanthul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views7 pages

Koh Pich Construction Company: Elite Town Iii Project Work Report

The daily report from Koh Pich Construction Company provides details of construction work completed on January 2nd, 2017 at the Elite Town III project site. Work that day included setting coordinates for pile foundations, installing reinforcement for pile caps at two blocks, excavating soil at one block, repairing a pile, and breaking the head of a pile. Tomorrow's scheduled work includes pouring concrete for pile caps, installing more reinforcement, backfilling soil, and excavating soil for another block's foundation. Photos document the day's progress on pile work and soil movement. An attendance report lists 134 workers on site from the main and subcontractors.

Uploaded by

Ket Chanthul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Koh Pich Construction Company

ELITE TOWN III Project


Name

Work Report

Daily Report

Details of performance
Today's Work Description

January 2nd, 2017 (Monday) Weather (Fine )


Work time: From:700am
To:5:00pm

Setting out of coordinates for Footing Pile Work


Installing pile cap reinforcement at Block B1&A2
Soil Excavation at Block B1
Pile Repair at Block B1
Pile head breaking at Block B1
Lean concreting

Message and Work Schedule for Tomorrow


Pile Cap concreting at Block B1
Pile cap reinforcement installation at Block B1
Lean concreting
Soil Backfilling at Block A2
soil arrangement for basement slab at A1&A2
Soil Excavation for Block B2

Concerns & Troubles

Daily Work Report has to be mailed at the end of the today's work.

Construction Photos(Fix Points)

2-Jan

Fix Point 1

2-Jan

Fix Point 2

2-Jan

Fix Point 3

Construction Photos (Today's Work)

2-Jan

Pile head breaking at Block B1

2-Jan

Fabricating pile cap reinforcement at Block B1&A2

2-Jan

Soil Excavation at Block B1

2-Jan

Pile Cap Concreting at Block A1

KOH PICH CONSTRUCTION CAMPANY


ELITE TOWN III PROJECT
Date : January 2 nd, 2017

Daily Attendent Report


No

Site
Engineer

Draftsman

M &E
Engineer

Admin

Warehouse Survey

Safetyag
Foremen Drivier
ents

Skill
Worker

Common
Worker

Others

32

11

Main Contractor

48

Sub Contractor

10

80

18

134

3
4
5
6
7

Project Manager

Ket Chanthul

Prepare by :

Sophat Pisey