DETERMINING PROBABILITY / LIKELIHOOD GUIDANCE CRITERIA
If almost no gap exists in control of the identified Environmental Aspect / impact as technology, operational
1
Highly unlikely (HUL)
control, measurement monitoring, competence in place
2
Unlikely (UL)
If there is any minor gap / weakness in control of the identified Environmental Aspect / impact
Likely (L)
There are unreasonable/ major gaps in the control of the identified Environmental Aspect / impacts with respect
to adoption of technology, operational control, measurement monitoring and competence
Very likely (VL)
There are almost no control in place in controlling the identified Environmental Aspect / Impact
DETERMINING LEVEL OF CONSEQUENCE GUIDANCE CRITERIA
Level of Harm /
Rating
Reference on Controls
Consequence
Effect on Environment
Slightly harmful
No control measure is required
Confined to the equipment / source
area
Harmful
Control measure may be required /
considered
Spread to the section limit
Very harmful
Control measure is certainly required
Spread beyond section limit
urgently
Extremely harmful
Control measures are required
immediately
Spread beyond factory limits / soil
contamination / contamination of
drains
Consumption of Resources
Controls are well established with
effective bench-marking (No
opportunity for further reduction)
Controls are established however yet
an opportunity for improvement
(Random opportunity for further
reduction)
Controls are in place however largely
ineffective (Reasonable opportunity
for further reduction
No Control at all including Huge
Generation of waste (Substantial &
continual opportunity for further
reduction)
DEFINITION OF LEVEL OF IMPACTS
Impact
Level
Impact Level
Action and Time Scale
1,2,3
TRIVIAL
No action is required and no documentary record needs to be kept.
4,6
TOLERABLE
No additional controls are required. Consideration may be given to a more cost-effective solution or improvement
that imposes no additional cost burden. Monitoring is required to ensure that the controls are maintained.
8,9,12
SUBSTANTIAL
Work should not be started until the impact has been reduced. Considerable resources may have to be allocated
to reduce the impact where the impact involves work in progress, urgent action should be taken.
16
INTOLERABLE
Work should not be started or continued until the impact has been reduced. If it is not possible to reduce impact
even with unlimited resources, work has to remain prohibited.
Develop a list of Environmental Aspects and Impacts:
Example:
Condition
Activity / Sub-activity
Environmental Aspect
Adequacy of
N/AN/E
Charging of Raw material in to
day bins
Consumption of electricity
- Operation of dust collector
Consumption of filter bags
Consumption of air
Generation of Hazardous
Waste - Waste mix RMs
Generation of Hazardous
Waste - Waste filter bags
Generation of noise
1. Workplace noise is below 90 dB
2. Regular PM being done
3. Oiling / Greasing is a part of CLIT
Noise Pollution
Dusting from day bins
charging ports
AN
1. PM of ID fan being done regularly
2. Replacement of filter bags every six
month
Air pollution
Fire due to mix of different
RMs
1. Compatibility study conducted
2. Daily frequency of empty out
collected mix RMs from dust collector
Air pollution
CASE: Actual / Normal
Emission from stack within
- No Gap in existing
limits
control
CASE: Actual / Normal Emission from stack within
- Gap in existing control limits
CASE: Potential / Emission from stack
Abnormal beyond limits
AN
CASE: Actual / Emission from stack
Abnormal beyond limits
AN
Existing
Gaps, if any
Impact
D/I
1. Power consumption being
monitored
2. Regular PM of ID fan / blower
Approved standard make filter bags
being used. Life expetency is 6 month
as per OEM
PM of ID fan being done regularly
1. Waste mix RMs extracted from
dust collector being tracked
2. Hazardous waste being disposed
off as per defined SOP
1. Approved standard make filter
bags being used. Life expetency is 6
month as per OEM
2. Hazardous waste being disposed
off as per defined SOP
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
Filter bags not
approved laboratory
replaced in last PM
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
Resource Depletion
Resource Depletion
Resource Depletion
Disposal of Hazardous
Waste by Incineration
Disposal of Hazardous
Waste by Incineration
Air pollution
Air pollution
Air pollution
Air pollution
Likelihood - Consequen Total = L x
L
ces - C
C
Classification
of Impact
Over-riding factor
(LC)
Control Measures
Develop a list of Environmental Aspects and Impacts:
Exercise: 05
Condition
Activity / Sub-activity
Environmental Aspect
D/I
N/AN/E
Adequacy of
Existing
Gaps, if any
Impact
Likelihood - Consequen
Classification of
Total = L x C
L
ces - C
Impact
Over-riding factor
(LC)
Control Measures
Evaluate & Prioritize Environmental Aspects and Impacts:
Example:
Activity / Sub-activity
Environmental Aspect
Condition
D/I
N/AN/E
Charging of Raw material in to
day bins
Consumption of electricity
- Operation of dust collector
Consumption of filter bags
Consumption of air
Generation of Hazardous
Waste - Waste mix RMs
Generation of Hazardous
Waste - Waste filter bags
Generation of noise
Dusting from day bins
charging ports
Fire due to mix of different
RMs
Likelihood - Consequen
Classification of
Total = L x C
L
ces - C
Impact
2
Trivial
Resource Depletion
Trivial
Resource Depletion
Trivial
Disposal of Hazardous
Waste by Incineration
12
Substantial
Disposal of Hazardous
Waste by Incineration
Trivial
1. Workplace noise is below 90 dB
2. Regular PM being done
3. Oiling / Greasing is a part of CLIT
Noise Pollution
Trivial
AN
1. PM of ID fan being done regularly
2. Replacement of filter bags every six
month
Air pollution
Tolerable
1. Compatibility study conducted
2. Daily frequency of empty out
collected mix RMs from dust collector
Air pollution
Tolerable
Air pollution
Tolerable
Air pollution
Substantial
Air pollution
Tolerable
CASE: Actual / Normal Emission from stack within
- Gap in existing control limits
AN
1. Power consumption being
monitored
2. Regular PM of ID fan / blower
Impact
CASE: Actual / Emission from stack beyond
Abnormal limits
Gaps, if any
Resource Depletion
CASE: Actual / Normal
Emission from stack within
- No Gap in existing
limits
control
CASE: Potential / Emission from stack beyond
Abnormal limits
Adequacy of
Existing
AN
Approved standard make filter bags
being used. Life expetency is 6 month
as per OEM
PM of ID fan being done regularly
1. Waste mix RMs extracted from dust
collector being tracked
2. Hazardous waste being disposed off
as per defined SOP
1. Approved standard make filter bags
being used. Life expetency is 6 month
as per OEM
2. Hazardous waste being disposed off
as per defined SOP
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
Filter bags not
approved laboratory
replaced in last PM
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
1. Monitoring of stack emission being
done on month basis by MoEF
approved laboratory
2. Filter bags being replaced every six
month during PM
Air pollution
12
Substantial
Over-riding factor
(LC)
Control Measures
SOP/EMP:
1. QIP to be taken for
chemical scrap reduction
OSEP
LC
SOP/EMP:
Filter bag to be replaced eery
six month and noted in log
book
LC
SOP/EMP:
1. Filter bags replacement
frequency to be revised to 03
months
2. Improved dust collector
bfilter bags to be explored
3. Improved design of dust
collector to be procured
Evaluate & Prioritize Environmental Aspects and Impacts:
Exercise: 06
Date of Aspect Impact Study:
Risk Assessment Carried out by:
Version No.:
Activity / Sub-activity
Environmental Aspect
IDENTIFICATION OF ENVIRONMENTAL
ASPECTS AND EVALUTAION OF IMPACTS
Condition
D/I
N/AN/E
Adequacy of
Existing
Gaps, if any
Impact
Likelihood - Consequen
Classification of
Total = L x C
L
ces - C
Impact
IMSM 4.3.1/R01
Over-riding factor
(LC)
Control Measures
List of Aspect Imapct:
Aspect Category
Resource Use
Material Use
Air Emissions
Release to Air /
Water / Land
Aspect List
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Resource Depletion
Consumption of Engineering Material -*
Consumption of Chemical - *
Air Emission: Dust
Air Emission: Fumes
Air Emission: Vapours
Air Emission: Flue gas from stack
Air Emission: Vehicular emissions
Resource Depletion
Resource Depletion
Air Pollution
Air Pollution
Air Pollution
Air Pollution
Air Pollution
Generation of Condensate
Fire
Water Pollution
Land Pollution
Reuse of condensate (+ve)
Water Pollution
Land Pollution
Recycle of treated effluent in gardening (+ve)
Air Pollution
Water Pollution
Land Pollution
Air Pollution
Water Pollution
Land Pollution
Environmental Damage
Generation of Noise
Generation of Heat
Generation of Radiations
Generation of Vibrations
Generation of Odour
Environmental Nuisance
Environmental Nuisance
Environmental Nuisance
Environmental Nuisance
Environmental Nuisance
Generation of Effluent
Spillage
Leakage
Environmental
Nuisance
Impact List
Use of Electricity
Use of Water
Use of Natural Gas
Use of Diesel
Use of Furnace Oil
Use of Coal
Use of Steam
Use of Air
Use of Nitrogen
Consumption of Raw Material - *
Waste Management Generation of Hazardouse Waste - *
Generation of Bio-medical Waste
Generation of e-waste
Generation of Waste Lead Acid Batteries
Generation of Non-Hazardous Waste - *
Generation of Food Waste
Disposal of Hazardous Waste to Landfill
Disposal of Hazardous Waste by Incineration
Disposal of Hazardous Waste to Authorised Recycler
(+ve)
Disposal of Bio-medical Waste to Common BMW
Incineration
Final Impact for Waste Disposal
Land Pollution
Air Pollution
Conservation of Resources (+ve)
Air Pollution
Disposal of e-waste to Authorised Recycler (+ve)
Conservation of Resources (+ve)
Disposal of Waste Lead Acid Batteries to Authorised
Recyclers (+ve)
Conservation of Resources (+ve)
Reuse / Recycle of Non-Hazadrous Waste to Authorised
Traders (+ve)
Conservation of Resources (+ve)
Recycle of Non-Hazardous Waste by Re-work
Conservation of Resources (+ve)
Disposal of Food Waste by Cattle Feed (+ve)
Conservation of Resources (+ve)
List of RMs, HW, Non-HW:
Consumption of Raw Material - *
Generation of Non-Hazardouse Waste *
Bladder
Rubber
Carbon Black
Silica
Oil
Sulphur
Other Chemicals
Others - Indirect Material
Textile
Steel Cord
Generation of Hazardouse Waste - *
33.3-Discarded containers - empty containers / drums
Compound
Conveyor Belt
Electrical Scrap
Fabric
Flaps
33.3-Discarded containers - empty liners bags
34.3-ETP Sludge
5.1-Used Spent oil
3.3-Sludge and filters contaminated with oil
Garbage
Green Tyre
Liner bags
Liner MS drums
21.1-Waste / residue - Dust collector bags
21.2-Filler residues - Spent slurry from mixing
23.1-Waste / residue - Waste chemicals from mixing
Bead Wire
Liner Paper drums
Liner PVC Can
Liner PVC drum
MS Scrap
Non-Ferrous Scrap
Paper
Plastic
Rubber
Steel
Tubes
Tyre
Wooden Scrap
5.2-Waste/residue containing oil - Cotton waste / Used PPEs
33.1-Chemical containing residue from decontamination Chemicals from spillage / floor cleaning
34.1-Flue gas cleaning residue - Boiler / DG stacks
34.2-Residue from used ion exchange material in water
purification
34.5-Sludge from cooling water treatment
15.2-Discarded asbestos
Class D-Waste / residue containing sulphur (>50000 mg/kg)