Data Center Best Practices Guide PDF
Data Center Best Practices Guide PDF
Introduction.....................................................................................................1
i
ii Data Center Design Guidelines
Introduction
Data centers can consume 100 to 200 times as much electricity as standard
office spaces. With such large power consumption, they are prime targets for
energy efficient design measures that can save money and reduce electricity use.
However, the critical nature of data center loads elevates many design criteria
-- chiefly reliability and high power density capacity far above efficiency. Short
design cycles often leave little time to fully assess efficient design opportunities
or consider first cost versus life cycle cost issues. This can lead to designs that
are simply scaled up versions of standard office space approaches or that re-
use strategies and specifications that worked good enough in the past without
regard for energy performance. This Data Center Best Practices Guide has
been created to provide viable alternatives to inefficient data center design and
operating practices and address energy efficiency retrofit opportunities.
Based upon benchmark measurements of operating data centers and input from
practicing designers and operators, the design guidelines are intended to provide
a set of efficient baseline design approaches for data center systems. In many
cases, the design guidelines can also be used to identify cost-effective saving
opportunities in operating facilities. No design guide can offer the one correct
way to design a data center, but the design guidelines offer efficient design
suggestions that provide efficiency benefits in a wide variety of data center design
situations. In some areas, promising technologies are also identified for possible
future design consideration.
From the level of the data center owners and tenants, to the designers and
equipment manufacturers, there are many key players involved when forming a
new or retrofitting an old data center. A careful collaboration between all data
center stakeholders is essential for establishing persistent energy efficient data
center operation.
Data center design is a relatively new field that houses a dynamic and evolving
technology. The most efficient and effective data center designs use relatively
new design fundamentals to create the required high energy density, high
reliability environment. The following best practices capture many of the new
standard approaches used as a starting point by successful and efficient data
centers.
Introduction 1
2 Data Center Design Guidelines
1. Information Technology (IT) Systems
Efficient power supplies usually have a minimal incremental cost at the server
level; however, management intervention may be required to encourage
equipment purchasers to select efficient models. The purchasers need to be
given a stake in reducing operating cost and the first cost of the electrical and
conditioning infrastructure, or at least be made aware of these costs, in order
to make a rational selection. The impact of real operating loads should also be
considered to select power supplies that offer the best efficiency at the load level
at which they are expected to most frequently operate.
Principles
Specify and utilize high efficiency power supplies in Information Technology
(IT) computing equipment. High efficiency supplies are commercially
available and will pay for themselves in very short timeframes when the
total cost of ownership is evaluated.
For a modern, heavily loaded installation with 100 racks, use of high
efficiency power supplies alone could save $270,000-$570,0001 per year
and decrease the square-footage required for the IT equipment by allowing
more servers to be packed into a single rack footprint before encountering
heat dissipation limits.
When ordering servers, specify power supplies that meet at least the minimum
efficiency recommendations by the Energy Star and 80 PLUS. Energy Star
rated servers are 30% more efficient than standard servers, on average.
When appropriate, limit power supply oversizing to ensure higher and more
efficient load factors.
Approach
The individuals specifying data center equipment should consider the efficiency of
this equipment. Frequently, there is little connection between the group selecting
data center equipment and the group that is aware of (and responsible for paying) the
equipments energy costs. Often, the department that selects and procures the data
center equipment deals with hardware and software deployment issues and has little
if any interaction with the department responsible for paying operating costs. With
no feedback regarding operating cost, energy efficiency is often overlooked by the
selectors unless, perhaps, they have had negative, usually expensive, experience
with overheating racks and the associated risk of equipment failure.
To encourage the use of more efficient servers, storage devices, network equipment
and power supplies, an organization must illustrate the clear connection between
equipment energy usage and operating cost to the people who make the equipment
purchasing decisions. With many types of equipment becoming commodity items and
with small differences in price heavily impacting the selection, it is essential that the
total cost of ownership of low efficiency IT equipment be recognized in the selection
process.
Efficient Servers
Rack servers tend to be the main perpetrators of wasting energy and represent the
largest portion of the IT energy load in a typical data center. Servers take up most of
the space and drive the entire operation. The majority of older servers run at or below
20% utilization most of the time, yet still draw full power during the process. Recent
improvements in the internal cooling systems and processor devices of servers have
been made to minimize this wasted energy.
When purchasing new servers it is recommended to look for products that include
variable speed fans as opposed to a standard constant speed fan for the internal
cooling component. With variable speed fans it is possible to deliver sufficient cooling
while running slower, thus consuming less energy. The Energy Star program aids
consumers by recognizing high-efficiency servers. Servers that meet Energy Star
efficiency requirements will, on average, be 30% more efficient than standard servers.
Consolidation
Hardware Location
Lower data center supply fan power and more efficient cooling system
performance can be achieved when equipment with similar heat load densities
and temperature requirements are grouped together. Isolating equipment by
environmental requirements of temperature and humidity allow cooling systems to
be controlled to the least energy-intensive set points for each location.
Power Supplies
Most data center equipment uses internal or rack mounted alternating current/
direct current (AC-DC) power supplies. Historically, a typical rack servers
power supply converted AC power to DC power at efficiencies of around 60%
to 70%. Today, through the use of higher-quality components and advanced
engineering, it is possible to find power supplies with efficiencies up to 95%.
Using higher efficiency power supplies will directly lower a data centers power
bills and indirectly reduce cooling system cost and rack overheating issues.
At $0.14/kWh, savings of $2,000 to $7,000 per year per rack (10 kW to 25 kW,
respectively) are possible just from improving the power supply efficiency from
75% to 85%. These savings estimates include estimated secondary savings due
to lower uninterruptible power supply (UPS) and cooling system loads. In most
cases, a more efficient power supply pays for itself in one year or less, even if its
manufacturing costs are doubled.
Figure 1.01:
Efficiencies at varying
load levels for typical
power supplies
(Source: Quantitative Efficiency
Analysis of Power Distribution
Configurations for Data centers,
The Green Grid)
References
1. Depending on cooling system efficiency and rack loading. Top end assumes
a rack load of 16.8 kW of server power and a cooling power use equal to
rack power use (lower quartile of cooling performance measured in recent
benchmarking).
Resources
Data Processing and Electronic Areas, Chapter 17. ASHRAE HVAC
Applications, 2007. The Green Data Center 2.0, Chapter 2, Energy-efficient
Server Technologies, 2009. Source: http://www.processor.com/editorial/
article.asp?article=articles%2Fp3008%2F32p08%2F32p08.asp.
http://www.efficientpowersupplies.org
http://www.80plus.org
http://www.hightech.lbl.gov
Modern data center equipment racks can produce very concentrated heat loads.
In facilities of all sizes, from a small data center supporting office buildings to
dedicated co-location facilities, designing to achieve precise control of the air
flow through the room that collects and removes equipment waste heat has a
significant impact on energy efficiency and equipment reliability.
Air management for data centers entails all the design and configuration details
that go into minimizing or eliminating mixing between the cooling air supplied
to equipment and the hot air rejected from the equipment. When designed
correctly, an air management system can reduce operating costs, reduce first
cost equipment investment, increase the data centers density (W/sf) capacity, and
reduce heat related processing interruptions or failures. A few key design issues
include the location of supply and returns, the configuration of equipments air
intake and heat exhaust ports and the large scale airflow patterns in the room.
Principles
Use of best-practices air management, such as strict hot aisle/cold aisle
configuration, can double the computer server cooling capacity of a data
center.
Removing hot air immediately as it exits the equipment allows for higher
capacity and much higher efficiency than mixing the hot exhaust air with
the cooling air being drawn into the equipment. Equipment environmental
temperature specifications refer primarily to the air being drawn in to cool
the system.
A higher difference between the return air and supply air temperatures
increases the maximum load density possible in the space and can help
reduce the size of the cooling equipment required, particularly when lower-
cost mass produced package air handling units are used.
Approach
Improved airflow management requires optimal positioning of the data center
equipment, location and sizing of air openings and the design and upkeep of the
HVAC system. While the application can vary widely, one overall objective is simple:
to remove hot air exhaust from the equipment before the exhaust, and the heat
it carries, is mixed with cool supply air and recirculated back into the equipment.
Countless design strategies can be used to achieve this objective. They include:
hot aisle/cold aisle rack layout; flexible barriers; ventilated racks; and optimized
supply/return grills and/or floor tiles. Energy savings are realized by extending
economizer savings into higher outdoor air temperatures (up to 80-85F) and/or
reducing fan airflow and power costs in spaces running at less than design cooling
capacity.
Fan energy savings are realized by reducing fan speeds to only supply as much air
as a given space requires. There are a number of different design strategies that
reduce fan speeds, but the most common is a fan speed control loop controlling
the cold aisles temperature at the most critical locations the top of racks for
underfloor supply systems, the bottom of racks for overhead systems, end of
aisles, etc. Note that many computer room air conditioners use the return air
temperature to indicate the space temperature, an approach that does not work
in a hot aisle/cold aisle configuration where the return air is at a very different
temperature than the cold aisle air being supplied to the equipment. Control of the
fan speed based on the server inlet temperature is critical to achieving savings.
ReturnAirPlenum
RaisedFloor
The potential for cooling air to be short-circuited to the hot aisle should be evaluated
on a rack-by-rack basis, particularly in lightly loaded racks. Floor tile leakage into
the hot aisles represents wasted cooling and lost capacity and should be regularly
checked and corrected. Operators should be properly educated on the importance
of conserving cooling air in the cold aisles, to prevent misguided attempts to fix
the hot spots, and to encourage correction of leaks in raised floor assemblies.
Operator education is very important since a hot aisle/cold aisle configuration is
non-intuitive to many data center personnel who are often trained to eliminate hot
spots, not deliberately create them in the form of hot aisles. The fact that only the
air temperature at the inlet of equipment must be controlled is the basis of good air
management.
The hot aisle/cold aisle configuration is rapidly gaining wide acceptance due to
its ability to serve high density racks better than traditional, more mixed flow
configurations. As the power consumption of a single loaded rack continues to climb,
exceeding 14 kW in some cases, the physical configuration of the racks cooling air
intake and hot air exhaust becomes crucial. Data center operators have discovered
that exhausting large heat loads directly onto a rack of equipment can lead to
overheating alarms and equipment failure regardless of the amount of room cooling
available. First and foremost, a hot aisle/cold aisle configuration is an equipment
layout that improves reliable operation.
Underfloor air supply systems have a few unique concerns. The underfloor plenum
serves both as a duct and a wiring chase. Coordination throughout design and into
construction is necessary since paths for airflow can be blocked by uncoordinated
electrical or data trays and conduit. The location of supply tiles needs to be carefully
considered to prevent short circuiting of supply air and checked periodically if users
are likely to reconfigure them. Removing tiles to fix hot spots can cause problems
throughout the system.
Light fixtures and overhead cable trays should be laid out in coordination with the
HVAC air supply to ensure no obstructions interrupt the delivery and removal of air to
the rows. Hanging fixtures or trays directly under an air supply should be avoided.
Flexible Barriers
Using flexible clear plastic barriers, such as plastic supermarket refrigeration covers
or other physical barriers, to seal the space between the tops of the rack and the
ceiling or air return location can greatly improve hot aisle/cold aisle isolation while
allowing flexibility in accessing, operating, and maintaining the computer equipment
below. One recommended design configuration supplies cool air via an underfloor
plenum to the racks; the air then passes through the equipment in the rack and
enters a separated, semi-sealed area for return to an overhead plenum. This
displacement system does not require that air be accurately directed or overcooled.
This approach uses a baffle panel or barrier above the top of the rack and at the ends
of the cold aisles to eliminate short-circuiting (the mixing of hot and cold air). These
changes should reduce fan energy requirements by 2025 percent, and could result
in a 20 percent energy savings on the chiller side.
With a downflow CRAC unit, combining pairs of racks with a permeable barrier
creates a system in which hot air can be immediately exhausted to the plenum.
Unfortunately, if the hot-cold aisle placement is reversed (with the cold aisles being
the ducted aisles), the working (human) spaces would be hotat temperatures up to
or even above 90F 3.
Such designs should be evaluated on the basis of their effectiveness in capturing hot
exhaust air with a minimum of ambient air mixing (typically achieved by placing the
capture opening very close to the hot exhaust) and factoring in any fan energy costs
associated with the systems. Exhaust systems typically have far higher fan energy
costs than standard returns, so the use of small diameter ducting or hoses and
multiple small fans should be carefully evaluated to ensure that additional fan power
cost does not seriously reduce or eliminate the savings anticipated from improved air
management.
Diffusers that dump air straight down should be selected and located directly in
front of racks, not above or behind. Unlike an office space design, diffusers should
be selected and placed in order to dump air directly to where it can be drawn in the
equipment, rather than to provide a fully mixed room without human-sensible drafts.
The thermostat should be located in an area in front of the computer equipment, not
on a wall behind the equipment. Finally, where a rooftop unit is being used, it should
be located centrally over the served area the required reduction in ductwork will
lower cost and slightly improve efficiency. While maintenance and roof leak concerns
may preclude locating the unit directly over data center space, often a relatively
central location over an adjacent hall or support area is appropriate.
DropCeiling
56F 80F
48F PoorlyPlaced
41FWater Diffusers,AirLeaks RaisedFloor
An existing data center room cooled by an underfloor system was having trouble
maintaining temperature. Chilled-water cooled Computer Room Air Conditioners
(CRACs) with a total capacity of 407 tons were installed and operating in the room. All
available floor space for CRACs had been used in an attempt to regain control of the
room. The chilled water loop serving the data center, a district cooling system with
an installed capacity of 4,250 tons, had the chilled water temperature reset down to
41F, primarily to assist in cooling this single data center facility. Measurements of
the room revealed the air flow condition seen in the figure below.
A lack of capacity was the suspect issue. However, air temperature measurements
quickly suggested that the actual problem was not the installed capacity, but the
airflow management. The majority of the CRACs were located at the end of the room
farthest from the highest heat density racks, and they used non-ducted through-the-
space returns.
CRACReturnAirTemperaturevs.Capacity
Figure 2.03:
75
CRAC Return Air
Return AirTemperature,F
Temperature vs Capacity
70
(Source: Created by Integral Group)
65
60
59F ReturnAir
Performance
55
50
0 50 100 150 200 250 300 350
TonsCooling
ReturnAirPlenum
80F
Figure 2.04:
CRACs Servers Alternate Airflow Solution
LowPower
Workstations (Source: Created by Integral Group)
72F
50F
44FWater RaisedFloor
In this situation, the ideal solution was not practical. Reconfiguring the data center
to implement a hot aisle/cold aisle design and moving the CRAC units closer to the
load would have been prohibitively expensive and would have required unacceptable
amounts of down time. An alternate solution was proposed to improve airflow as
shown below.
The main objective is to collect waste heat as close as possible to the source and
then isolate it from the space in the return air stream. Floor supply tiles are replaced
by solid tiles in the low load area to increase the air supplied to the farthest, and
largest, rack loads. The return air is no longer drawn through the space. Return air
travels through a ceiling plenum to avoid mixing with the cool air being served to the
room. Note that only stratification is being used to scavenge the hot rack exhaust,
resulting in a lower return air temperature than would be expected with a well
executed isolation strategy such as hot aisle/cold aisle.
This design literally doubles the cooling capacity of the installed CRACs and allows
the district plant chilled water temperature to be increased to 44F, which would
substantially increase the efficiency of the entire 4,250 ton district chilled water
system. In this case, correcting the airflow management offered a solution to cooling
problems when the traditional approach of adding more cooling equipment did not.
References
1. Compared to a standard system with no economizer and a return
temperature of 78 rather than 85.
Resources
Thermal Guidelines for Data Processing Environments, TC9.9 Mission
Critical Facilities, ASHRAE, 2008.
Data centers operate 24-hours a day with a large, constant cooling load that
is independent of the outdoor air temperature. Most nights and during mild
conditions, the lowest cost option to cool data centers is an air-side economizer.
Simply using a standard office system economizer offered on Title 24 compliant
units is not advised until a proper engineering evaluation of the local climate
conditions and the space requirements can be completed. Due to the humidity
and contamination concerns associated with data centers, careful control and
design work may be required to ensure that cooling savings are not lost because of
excessive humidification requirements.
Principles
An economizer can cut data center cooling costs by over 60% 2 using
standard, commonly available low-cost equipment. Depending on the
climate, the steady, 24-hour cooling load of a data center is well suited to
take advantage of seasonal and nighttime temperature variations to cool the
space.
Economization must be engineered into the air handling system. Small data
centers may be economically served by low cost, mass produced package
units. Larger data centers typically justify a more efficient chilled water
system with central air handlers.
Approach
An outdoor economizing system is best implemented starting at the schematic
design stage, where the required architectural accommodations can be made with
little or no additional cost. An air handler equipped with an air-side economizer
will draw outside air into the space when the outside air (OSA) is cooler than the
return air. During economization, the return air system operates as a heat exhaust.
Depending on the space load, at about 55F OSA or below, the compressor(s)
should not be required to run at all. During economization, the supply air picks up
heat from the space and is exhausted to the outside instead of being recirculated.
Energy is saved by simply exhausting the heat rather than removing it mechanically
via a compressor. Cooler outside air is then drawn in, cooling the space. While
economization is usually implemented with a central air handler configuration,
many Computer Room Air Conditioning (CRAC) units (direct expansion or water coil
cooled) offer optional economizers and controls.
Alternatively, in areas with long periods of cold, dry weather a somewhat more
complex humidity control system may be justified to maximize economization. As
described below, a sidestream adiabatic humidification system scavenging waste
computer heat may be suitable.
Humidity control algorithms should be designed to account for the local conditions,
in particular the rate of humidity change. In a data center situation, when a rapid
change in outdoor humidity is sensed, economization can simply be stopped and
returned to standard mechanical control usually in a matter of minutes. Rapidly
changing outdoor air humidity is more of a control problem in critical facilities
that do not have the option of closing the outdoor air dampers and returning to
a recirculation configuration, such as cleanroom fabrication plants with a high
exhaust air makeup requirement.
Economization hours can be efficiently extended into dry winter months if computer
waste heat is recovered to provide humidification energy. One approach is to use
an adiabatic humidifier to humidify a small amount of warm return air, which is
then injected into the supply stream. An adiabatic humidifier exposes water to the
air stream and uses the heat energy of the air stream itself to evaporate the water.
Water is usually exposed through the surface of a wet media, spraying through
mist nozzles or by producing an ultrasonic-generated fog. The return air carrying
the waste heat from the computers is cooled evaporatively as it is humidified
before it is introduced into the supply air stream; the common direct evaporative
cooler (or swamp cooler) widely used for greenhouses and in dry climates is a
form of adiabatic humidifier. Adiabatic bypass humidifiers can greatly extend the
use of and savings from, economizers for data centers in dry, cold climates.
Fan SupplyAirDown
Figure 3.01 : ToDatacenter
3
Rooftop Data Center 4
53F,68%RH,
System using an Adiabatic OutsideAir 42.9FDewpoint
50F,50%RH,
Humidifier 32FDewpoint,
(Source: Created by Integral Group) 25,000CFM
2 AdiabaticHumidifiedAir(ReturnBypass):
81F,95%RH,59FDewpoint,10,000CFM
Humidifier
Exhaust
dampers:
reject
datacenter
wasteheat
1
HotReturnAirUpDatacenter
85F,23%RH,42.9FDewpoint
1ExhaustDampers:RejectDatacenterWasteHeat.
2AdiabaticallyHumidifiedAir:Hotexhaustairisbothhumidifiedand cooledby
anadiabatichumidifier.
3 OutsideAirDamper: Coldanddryoutsideairispulledintoreplacethehot
returnairthatisexhausted.
4MixedAir:Theadiabaticallyhumidifiedairmixeswiththeoutdoorairtocreate
freecoldsupplyairatadewpointof42.9F,equivalenttothetargetminimum
humidityinthedatacenter.
Most data centers will require a reasonable level of filtration of outside air. Ideally,
the filtration system can be configured to filter outside air prior to combining it
with the recirculation air stream, to eliminate unnecessary filtering of the cleaner
recirculation air. The fan power required for filtration can be significant if care is
not taken to design low face velocity filtration and to use extended media filters.
Smaller data centers located in large office buildings may realize significant energy
efficiency by using the main office system during normal hours as a primary source
of cooling. In particular, data centers that are served by air-cooled split systems or
air-cooled computer room air conditioners (CRACs) present good opportunities for
energy savings. In California, due to Title 24 requirements, the main office system
probably has an economization capability. In addition, the larger house systems are
often more efficient than the standard, air-cooled data center systems, particularly
if the house systems use a central chilled water plant. During off-hours, the
dedicated computer room system can provide for data center cooling since the
main house system would typically be oversized for the small data center alone.
An air-cooled package unit was chosen to replace both the air-cooled chiller and
the associated chilled-water CRAC units. The package unit, shown to the right in
Figure 3.02, included full air-side economization capability. With this unit, exhaust
air is ejected from one end of the air handler, while outside air is drawn in from
the opposite end of the unit through louvers in the screen wall. This system had
multiple benefits for the data center: it replaced the failing chiller, allowed for
air-side economization, and eliminated all chilled water piping from within the
DXPackageUnitforuseonnightsandweekends
EconomizerCapable HouseAirSystem
Figure 3.03 : AirSideEconomizer&
Schematic Diagram of Air ChilledWaterSystem
Distribution System
(Source: Created by Integral Group) Fan
To From
Office Office
Space Space
This system also freed up floor space in the data center by removing the CRAC
units. The removal of the CRAC units effectively enlarged the space available for
computing equipment, reducing the need for costly future expansions of the space.
The data center can still be served from the central plant, but now through cooled
air from the house air handler rather than chilled water from the house loop.
The data center uses a hot aisle/cold aisle configuration to increase the return
air temperature, which both extends economizer operation into correspondingly
higher outdoor air temperatures and increases the amount of heat that is
exhausted during economizer operation (see Figure 3.03).
Measurements of the data center showed it to be lightly loaded overall at less than
30 W/sf. Hourly simulation of the data center was performed using a DOE2 model
and demonstrated total energy savings of 45% (254,000 kWh/yr). Approximately
one quarter of the savings (66,000 kWh/yr) was due to the economizer alone (the
balance of savings were from reduced fan power, pumping power, and integration
with the central house system). Addition of the economizer to the package unit was
a negligible incremental cost item in this project where the primary objective was
replacement of the failing chilled water system.
Related Chapters
Air Management
References
1. ASHRAE, 1999 HVAC Applications, pg 16.1
Resources
Data Processing and Electronic Areas, Chapter 17, ASHRAE HVAC
Applications, 2003.
Figure 4.01
Interior and Exterior Air
Handling Units
(Source: Integral Group)
Better performance has been observed in data center air systems that utilize
specifically-designed central air handler systems. A centralized system offers many
advantages over the traditional multiple distributed unit system that evolved as an
easy, drop-in computer room cooling appliance. Centralized systems use larger
motors and fans, and can be more efficient. They are also well suited for variable
volume operation through the use of Variable Speed Drives (VSDs, also referred to as
Variable Frequency Drives or VFDs). Most data center loads do not vary appreciably
over the course of the day, and the cooling system is typically oversized with
significant reserve capacity. A centralized air handling system can improve efficiency
by taking advantage of surplus and redundant capacity to actually improve efficiency.
The maintenance benefits of a central system are well known, and the reduced
footprint and maintenance traffic in the data center are additional benefits.
Principles
A central system allows redundancy to be implemented in a manner that
provides maximum reliability (a spinning reserve) and increases normal
operating system efficiency. System maintenance is also simplified through
centralization.
In most California climates, air handlers can be located on the roof (ideally
in a central location not directly over the data center the space), allowing
significant cost savings compared to computer room air conditioners
(CRACs) by reducing the data center floor space required by the air
conditioning.
While data center loads tend to be constant 24 hours a day, the loading
across the data center floor can vary significantly. A central system can
reduce fan power use and save energy by taking advantage of this variance.
A low-pressure drop design (oversized ductwork or a generous underfloor)
is essential to optimizing energy efficiency and long-term build out
flexibility.
Approach
Early in the evolution of data centers, the typical cooling system involved multiple
small air-cooled split systems with small vertical air handlers and independent
integrated controls that stood in the data center room and provided cooling. Such
a system was easy to install in existing buildings that were initially constructed
without consideration for the high density sensible heat loads of modern electronic
equipment. Now that the loads and conditioning requirements of data centers
are relatively well understood, purpose-built central air handler systems can be
designed to meet typical data center requirements with greater efficiency than the
traditional multiple distributed units design seen in the figure below.
ElevationView
CRAC
Unit
ServerRacks
CRAC CRAC
Unit Unit
ServerRacks
Section
ServerRacks
CRAC CRAC
Unit Unit
ServerRacks
PlanView
A centralized air handler system can be used to provide efficient data center cooling.
The typical approach to a centralized system for a data center is to use a single
supply air plenum fed by a few large air handlers. Depending on the size of the space
and frequency of data center load changes, variable airflow boxes may be used within
the distribution system to actively direct the airflow to the highest load regions.
Alternatively, the system may simply be statically balanced after every major change
in load. The figure below shows a centralized air handler system where the data
center distribution system is fed from above.
The distribution system must be designed for low pressure drop in order to maximize
energy savings. Ducts should be sized significantly larger than typical office systems,
since 24 hour operation of the data center increases the value of energy use over
time relative to first cost. Since loads often only change when new servers or racks
are added or removed, a static balance approach can be quite effective due to the
constant, 24 hour nature of most loads. The distribution system may be either
underfloor or a traditional overhead ducted configuration in determining the load
carrying capacity, proper air management is usually more important than the supply
configuration (see Air Management chapter).
ServerRacks
ElevationView
ServerRacks
ServerRacks
ServerRacks
ServerRacks
PlanView
This concept utilizes a smaller number of large premium efficiency motors, fans, and
variable frequency drives (VFDs) rather than many smaller motors and fans. Central
air handlers should be much larger than the units used in a conventional multiple-
distributed system using CRAC units. Larger fans and motors improve in efficiency
as they are scaled up; for example, a NEMA premium efficiency 10 hp motor is 91%
efficient or better, while a 30 hp motor with the same premium designation is 93%
efficient. In energy terms, for a 30 hp nameplate motor, a 2% efficiency difference
equals about 4,000 kWh per year in energy savings savings possible simply through
the consolidation of three small 10 hp motors into a single 30 hp motor 1.
The use of VFDs on data center systems offers significant savings, since oversizing
the air handlers, which is standard data center design practice, can actually result
in greater system efficiency. While oversized chiller or air-conditioner compressors
commonly prove detrimental to energy performance, oversized air handler systems
can provide surplus future capacity and redundancy, and can be designed to realize
significant part-load energy savings. Until the data center facility is fully built out
or loaded with more energy intensive devices, with all future expansion and safety
factors exhausted, the system will operate at part-load with surplus capacity
available. The surplus capacity offers the ability to save energy in two ways: Part load
operation allows the supply air volume to be reduced; and larger cooling coil areas
allow the chilled water system temperature to be increased in order to improve the
chiller plant efficiency.
Air handler fan speeds should be controlled in order to reduce the air volume
supplied during part-load conditions. Also, all air handlers, including redundant air
handling unit(s), should be configured to operate in parallel. Until the unit fans are
operating at the minimum speed allowed by the drive and motor, more operating
units result in higher air system efficiency. This also provides an always-on spinning
reserve that can seamlessly react to a fan failure while resulting in a lower total fan
power use 2. Improvements in fan system efficiency add up to significant savings.
The HVAC fan power consumption for a 100 w/sf design data center can range from
11 W/sf to over 22 W/sf 3. Reducing the supply air volume offers a large, non-linear
reduction of this fan energy use just a 20% reduction in airflow volume reduces the
power by 45-50%.
Using the larger coil area available during part-load conditions to increase the
chilled water temperature setpoint is discussed in the Cooling Plant Optimization
chapter of this document. A centralized air handler system in the data center should
use temperature sensors, located at the intakes of the IT equipment, where cooling
air is drawn into the racks and a standard temperature must be maintained in order
to meet the equipments operating requirements. The return air stream should not
be used as an indication of the space temperature. Due to the highly concentrated
loads common in data centers, correspondence between the return air temperature
and the cooling air being drawn into data center equipment is neither reliable nor
accurate. Temperature sensors can be mounted on appropriately located pillars,
UPSLosses
HVAC 13%
54% Lighting
Lighting
Lighting 1%
1%
2% HVAC
HVAC AirMovement
ChilledWater 9%
Plant
14%
References
1. The larger sizes of CRAC units commonly seen used in a multiple small unit
system configuration will often use three 10 hp motors driving parallel fans.
2. This can be somewhat counter intuitive, that operating three fans will
use less power than operating only two, but it is a natural result of power
requirements being related to the cube of the volume. Considering only the
pressure drop of the air handler, which typically is the highest pressure
drop component in the supply system, operating three 30,000 CFM air
handlers to provide 60,000 total CFM will require about half the total power
of operating just two air handlers for the same total 60,000 CFM flow. This
fan law relationship is not exact, but is a reasonable estimate of actual
performance.
Resources
Data Processing and Electronic Office Areas, Chapter 17, ASHRAE HVAC
Applications Handbook, 2003.
Figure 5.01:
Cooling Towers from a
Chilled Water Cooling Plant
(Source: Integral Group)
Principles
Design for medium temperature chilled water (55F) in order to eliminate
uncontrolled dehumidification and reduce plant operating costs.
Thermal storage can decrease peak electrical demand savings and improve
chilled water system reliability. Thermal storage can be an economical
alternative to additional mechanical cooling capacity.
For peak efficiency and to allow for preventive maintenance, monitor chiller
efficiency.
Approach
For large data center facilities, a chilled water system served by a central plant
is the most efficient approach to providing mechanical cooling. There are many
design decisions that impact the efficiency of a central plant; the issues discussed
here are selected due to their prevalence in typical data center operation.
constantCWTemp
CWT=78
1.0 CW temperatures
CWT=73
CWT=68
(Source: Created by Integral Group)
0.8 CWT=63
CWT=58
VFDchiller CWT=56
0.6
0.4
0.2
0.0
0% 20% 40% 60% 80% 100%
LoadFactor
PrimaryOnlyChilledWaterPumpingSchematic
Figure 5.03:
Primary only Chilled Water FlowMeter 55F
Pumping Schematic 55F
(Source: Created by Integral Group)
Bypassis 55F
normally
PInlieuof closed:
P flowmeter M Coil Coil P
Opens
CH2
CH3
CH3
forbypass onlyto
control maintain
minimum
flow
65F
Chillers 65F 65F
VFDEquipped
PrimaryPumps
Variable flow pumping is required in order to allow the chiller to operate at design
delta-T during part load conditions. Traditional chiller design maintains a constant
flow through the chiller, which inevitably results in the delta-T (the difference
between the warm water entering the chiller versus the chilled water leaving the
chiller) being directly proportional to the load. A 50% load will result in a delta-T
that is 50% of the design value. This type of operation results in unnecessary
pumping power use and often leads to inefficient chiller staging control, with an
additional chiller (and condenser water pumps and towers) being staged on before
the operating units are fully loaded.
Often chilled water pumping costs can be reduced by 30% to 50%. The staging and
control of a primary-only pumping system is no more complex than the traditional
primary-secondary approach, but it is different. ASHRAE publications and white
papers from chiller manufacturers are good sources of information on this
configuration.
Thermal Storage
Properly designed thermal storage can offer an efficient method of increasing
plant capacity without adding chillers and should be considered for critical
facilities. Thermal storage has three main benefits. First, it takes advantage of
off-peak electric rates which are typically significantly lower. Second, chilled
water systems operate more efficiently when outside air temperatures are lower.
Third, chilled water storage adds redundancy and can often substitute for one
or more back up chillers. Water storage is preferred over ice because water is
simpler, cheaper, more efficient, and more reliable although it requires more
space. Using multiple tanks will provide system redundancy and emergency
backup cooling potential. Thermal storage can be linked to free cooling systems,
such as water side economizers using cooling towers. In some dry climates, a
comprehensive system design can combine free cooling and thermal storage to
provide an almost full-time lifeline (maintaining space within the over-temperature
but permissible range) cooling backup to mechanical cooling.
Related Chapters
Air-Side Economizer
References
1. This is a rule of thumb. For more accurate data, consult the manufacturer of
your chiller for a comprehensive performance selection.
Resources
Variable-Primary-Flow Systems Revisited, Schwedler P.E., Mick, Trane
Engineers Newsletter, Volume 31, No.4, 2002.
ARI Standard 550/590- 2003, Water Chilling Packages Using the Vapor
Compression Cycle, Air-Conditioning and Refrigeration Institute, 2003
Direct liquid cooling refers to a number of different cooling approaches that all
share the same characteristic of transferring waste heat to a fluid at or very
near the point it is generated, rather than transferring it to room air and then
conditioning the room air. There are several approaches to implementing liquid
cooling for data center equipment. One option, currently available as an option
from many rack manufacturers, installs cooling coils directly onto the rack to
capture and remove waste heat. The underfloor is often used to run the coolant
lines that connect to the rack coil via flexible hoses. Many other approaches are
available or being pursued, ranging from water cooling of component heat sinks to
bathing components with dielectric fluid cooled via a heat exchanger.
Liquid cooling can serve higher heat densities and be much more efficient than
traditional air cooling. A high efficiency approach to cooling data center equipment
takes advantage of liquid coolings ability to efficiently move heat by transferring
the waste heat from racks to a liquid loop as close to the heat source as possible,
at the highest possible temperature. Currently, the most common approach is
to use a chilled water coil integrated in some manner into the rack itself. Liquid
cooling is adopted for reasons beyond efficiency; it can also serve higher power
densities (W/sf). Energy efficiencies will be realized when such systems allow the
use of a medium temperature chilled water loop (55-60F rather than 44F) and by
reducing the size and power consumption of fans serving the data center.
In the future, products may become available that allow for direct liquid cooling of
data center servers and equipment more directly, via methods ranging from fluid
passages in chip heat sinks to submersion in a dielectric fluid. While not currently
widely available, such approaches hold promise and should be evaluated as they
continue to mature and are commercialized for the data center equipment market.
Principles
Water flow is a very efficient method of transporting heat. On a volume
basis, it carries approximately 3,500 times as much heat as air.
Transferring heat from a small volume of hot air directly off the equipment
to a chilled water loop is more efficient than mixing hot air with a large
volume of ambient air and removing heat from the entire mixed volume. A
water-cooled rack is equivalent to an almost perfect hot aisle/cold aisle
configuration, where recirculation of waste heat is eliminated and the hot
aisle heat exhaust can be run at very high temperatures with no impact on
workers or equipment in the data center room.
Approach
A cooling system using water as the heat transport medium can conduct about
3,500 times more heat on a volume basis than a system using air. For example,
one gallon of water per minute (not a particularly large water flow) will remove
the thermal equivalent of a kilowatt with a seven-degree temperature rise. By
comparison, removing a kilowatt with air requires passing 140 cubic feet (1,050
gallons) of air per minute through the rack at a 23-degree temperature rise. In
addition, the low temperature rise of the water flow would allow for relatively
warm water to be used for cooling; modern cooling equipment is more efficient
when it is producing warmer temperatures, and use of free cooling or a water-side
economizer could eliminate high-energy-use compressor cooling from the cooling
system altogether. While liquid has a huge advantage in heat removal efficiency,
and was a common approach in the dawn of the mainframe era, the use of liquids
in data centers is a hotly debated issue. However, as chip power continues to
rise and equipment loads continue to increase in density, liquid cooling becomes
increasingly inevitable as a strategy for cooling the rapidly increasing equipment
load density (measured in W/sf).
One mature approach to direct liquid cooling is to use a rack provided with an
integrated chilled water coil. Figure 6.01 shows a rack with an open back panel. To
the left would be the back plates of the servers installed in the rack. To the right
is a hinged door that contains a cooling coil. The flexible hoses supply the coil in
the hinged door with cooling water. In use, hot air from the backs of the server
equipment would be blown out the coil (or drawn through by a fan) allowing it to be
cooled while it is at its highest temperature. When the rack is opened for service,
it would simply revert to using room air for cooling the room should be designed
to serve the load of a few racks running open to accommodate expected service
accesses.
Part 6: Direct Liquid Cooling 43
Figure 6.01:
Server Rack provided
with an integrated
Chilled Water Coil
(Source: Created by Integral Group)
The first cost of the coil option and additional required piping should be compared
to an analysis of expected energy, mechanical equipment, and/or architectural
savings. The most significant energy savings are achieved when the liquid cooling
system is paired with a water-side economizer or free cooling. Direct liquid cooling
directly replaces air handler or computer room air conditioner (CRAC) capacity.
A data center that fully utilizes direct liquid cooling can be served like a standard
office space by the air-side system. Architectural savings are less common, but
can be significant if the use of water cooled racks allows for a reduction in the
square footage of the data center by allowing a higher equipment density. In small
data centers serving existing buildings, water-cooling may allow a standard office
space to be used as a data center without the need for costly space retrofits.
Another configuration, shown in the figure below, consists of a water cooling coil
placed in the bottom of the rack. Small rack fans circulate hot air from the servers
down, through the coil, and then bring the cooled air back to the server intakes.
Rack-integrated water cooling places the coil directly in the path of the high
temperature air exiting the equipment. This positioning greatly reduces the volume
of air that must be moved by removing the waste heat before it is mixed into the
room. Rather than cooling 100 CFM of 78F air down to 60F, the coil can cool 50
CFM of 110F air down to 74F to remove the exact same amount of heat. Since the
air does not have to be cooled to as low a temperature to compensate for mixing
and heat recirculation, warmer water, possibly from a free cooling system (see
Free Cooling via Water-side Economizer), can be used.
Integrating cooling into the racks can allow for the ideal implementation of the
hot aisle/cold aisle configuration. Integrated chilled water coil racks are currently
available on the commercial market and use common, mature technologies. The
designs offered vary and range from simple chilled water systems with integrated
fans to systems that combine cabinet cooling with component coolers using
Many of these systems are designed with sophisticated leak and condensation
detection and mitigation systems that address equipment protection concerns.
They can be supported with redundant power sources and redundant fans. Some
are being designed to accommodate rapid exchange or replacement, in order to
further minimize the effects of downtime. A common design goal is to support
significantly higher power densities than are possible with standard room air
cooling systems, not only within the rack but over the entire data center floor since
large aisles for cooling air are not needed, nor are large, freestanding CRAC units.
Designs should be evaluated to ensure that efficiency has not been sacrificed; in
particular, the use of multiple small, constant speed fans or small liquid chillers
between the house chilled water plant and the rack coolant loop can reduce
system efficiency.
Figure 6.02
Fan Schematic of Integrated
Cooling in Server Rack
(Source: Created by Integral Group)
CoolAir
HotAir
IT
Equipment
inRack
Cooling
Coil
Chilled water systems are common in larger modern and legacy data centers, and
the cost of installation of chilled water cooled equipment systems in these types
of facilities is relatively low. Where existing chilled water systems support CRACs,
plant capacity would be unchanged, as the number of air conditioners would
naturally be reduced with the introduction of integrated cabinet cooling. However,
in centers with either no chilled water, or systems of limited capacity, the initial
cost of installation would be significant.
In many temperate climates, data center loads may not require any
dehumidification and should be served by medium temperature chilled water to
ensure dry coils and avoid uncontrolled dehumidification. Medium temperature
chilled water (55F or higher) should be used to eliminate any condensation
potential and avoid the need for insulation on hookup lines. To maximize
efficiency, medium temperature chilled water should be supplied from a loop
equipped with free cooling (water-side economizer), either directly or through
a close-approach heat exchanger. Depending on the climate at the location,
an evaporative free cooling system could supply the majority of a data centers
cooling hours without the need for an energy intensive chiller. The ideal
opportunity is a site where the mechanical cooling can be eliminated entirely,
potentially making the more efficient liquid cooling have the same or even a lower
first cost than a standard system.
One advantage of the cabinet mounted solution is that water is kept away from
the electrical components, yet it is still close enough to the equipment to provide
an efficient method of delivering cooled air. The fans used to move air across
the cooling coils and through the equipment can be made both redundant and
efficient, as they can be actively controlled to operate at variable speeds based
on the racks actual cooling demand. The air can be evenly distributed or actively
controlled across the rack, so that the temperature stratification within the rack
that is so evident in traditional raised floor or overhead distribution systems is
virtually eliminated. Poor airflow leading to stratification in the cabinet has been
cited as causing three times the rate of failure for equipment mounted at the top
of cabinets 2.
While a typical data center has the ability to cool loads of up to approximately 5
kW per rack, and careful airflow management can increase that capacity further,
integrated water cooled rack systems have demonstrated the ability to efficiently
cool loads up to 20 kW per rack 3. The advantages are obvious; end users are
able to cool far more equipment in smaller spaces while reducing their operating
costs for an equivalent amount of processing capacity. The more even distribution
of cool air through data center equipment increases the useful life of that
equipment. Further, maintenance costs of the cabinet integrated systems can be
significantly lower than the costs of maintaining traditional air systems capable of
supporting equivalent heat loads.
Beyond a traditional coil mounted on the rack to cool the exhaust airstream, other
approaches under development tend to keep liquid well away from the chips by
using various non-liquid-based methods to move heat from the electronics to
the liquid in an off-board or even outside-the-rack location. Heat pipes, carbon
fibers, and a few other non-liquid media can transfer heat to a backplane liquid
system, eliminating the need to have the water near the chips. Separating the
two helps relieve anxieties about mixing water, or any liquid, with electricity.
Direct liquid cooling of components is not currently available in the general, non
supercomputer, server market, but is also an approach that has a high potential
for realizing significant energy saving opportunities and may be used in future
commercial offerings. Direct liquid cooling through the use of chip heat sinks
with liquid passages, while not common commercially at the moment, is a mature
technology that can offer significant efficiency savings if available.
Related Chapters
Air Management
Air-side Economizer
References
1. Baseline study measurement of critical facility plants indicates that chiller
power represents approximately 70% of total energy consumption.
Resources
http://www.esmagazine.com/CDA/ArticleInformation/coverstory/
BNPCoverStory- Item/0,2500,158187,00.html
http://www.knuerr.com/web/en/index_e.html?service/faq/faq_cooltherm.
html~mainFrame
Figure 7.01
Use of a Cooling Tower
to provide Water-side
Economizer
(Source: Integral Group)
Data centers present an almost constant, 24-hour, internal cooling load. Free
cooling can be provided via a water-side economizer, which uses the evaporative
cooling capacity of a cooling tower to indirectly produce chilled water to cool the
data center during mild outdoor conditions (particularly at night in hot climates).
While a bin analysis using local weather data is required to properly assess
the potential, free cooling is usually best suited for climates that have wet bulb
temperatures lower than 55F for 3,000 or more hours per year. It most effectively
serves chilled water loops designed for 50F and above chilled water or lower
temperature chilled water loops with significant surplus air handler capacity in
normal operation. Often, existing data centers can capitalize on redundant air
handler capacity with chilled water temperature reset controls to retrofit free
cooling.
Table: 7.01.
Free Cooling Applicability
(Source: Integral Group)
Atleast3000hoursperyear Applicability
wherewetbulbtemperature
isbelow:
FreeCoolingSpecifiedAirHandlersorCRACs;
55F ManyLowTemperatureSystemswith
AppropriateChilledWaterReset
RetrofitReusingMostExistingAirHandlers
45F Designedfor42FChilledWaterWithoutNeed
forReset
Data centers require cooling 24 hours a day every day of the year even
when it is cold outside. This makes data centers very well suited to water-
side economization. For example, in San Jose, free cooling would be
expected to operate for over a third of the year, significantly reducing cooling
bills and noticeably reducing chiller run hours and maintenance costs.
Isolation between the space air and outside air is not impacted by water-side
free cooling, making it an alternative to air-side economization when this is
a concern.
A flat plate heat exchanger is used to isolate the chilled water loop from the
open tower condenser water to prevent fouling of coils.
Approach
Free cooling operates on the principle that during cool weather conditions,
particularly at night, data center cooling loads can be served with chilled water
produced by the cooling tower alone, entirely bypassing an energy intensive
chiller. In this scenario, the cooling tower produces low temperature water. A heat
exchanger is used to cool the building loop while keeping it clean and isolated from
the relatively dirty cooling tower water. Free cooling reduces or eliminates chiller
Data centers often have redundancy in their cooling tower plants. Through the
use of VFDs and common condenser water header systems and/or sumps, the
redundant tower capacity can be used to achieve a lower approach temperature.
With variable speed fans, it is efficient to operate as many towers as the tower
minimum flow requirements allow, maximizing the natural convective cooling while
achieving a lower approach capability.
Free cooling can also offer an additional level of redundancy by providing a non-
compressor cooling solution for portions of the year. In particular, free cooling can
often provide a backup to compressor chillers during cooler nighttime hours when
plant staffing may be lower. When the weather allows, free cooling replaces the
complex mechanism of a chiller with a simple, non-mechanical heat exchanger.
Use of medium temperature chilled water, in the range of 50F and higher,
maximizes the potential savings from a free cooling system. An efficient data center
system is likely to be designed for use of chilled water in this temperature range
already, since use of traditional (for office systems) 44F chilled water is likely to
result in uncontrolled dehumidification in high load areas (leading to artificially low
humidity or wasteful simultaneous dehumidification/humidification operation). A
typical data center maintained at 72F and 50% RH is susceptible to uncontrolled
dehumidification when the supply water temperature is lower than 52F.
New data center facilities that are specified for medium temperature chilled
water can be designed. Medium temperature chilled water systems also reduce
energy use and sometimes compressor sizing of normal chillers at the cost of
somewhat larger coils and piping. In existing facilities, free cooling operation
can be retrofitted and optimized through the use of an aggressive chilled water
temperature reset. Typically, data centers have surplus air handler capacity, in the
form of redundant units or overdesigned systems. The surplus capacity can allow
A cooling tower used for free cooling should be selected to provide an approach
temperature (leaving tower water temperature minus ambient wet bulb
temperature) between 5 and 7F (see Cooling Plant Optimization chapter). A lower
approach temperature generally results in a physically larger tower since more
surface area in the tower is required for the heat rejection process. A variable
speed drive (VSD) for the fan motor should be used in a free cooling tower to
minimize on-off cycling and maximize controllability and energy savings.
Figure 7.02:
Free Cooling Loop
Schematic
(Source: Created by Integral Group)
Figure 7.02 shows a typical free cooling setup. Note that the free cooling heat
exchanger is placed in line with the chillers. This allows for free cooling to support
a portion of the load while the chillers can provide the last few degrees of cooling
(referred to as integrated operation). A critical design element is that the chillers
automatically and seamlessly provide 100% backup to the free cooling system.
Free cooling requires that the cooling tower produce low temperature water,
often lower than a chiller will accept for condenser water. There are two common
design approaches to address this concern. One approach is to hydraulically
isolate a tower and dedicate it to free cooling only. This is the best approach, but
requires careful piping configuration and control valve placement and operation.
A redundant backup tower can be provided with automatic isolation valves and
used for free cooling. Since free cooling operates during low temperature weather
conditions, the chilled water plant load is often low enough that even non-backup
towers are available for free cooling use provided the proper automatic valves and
a control sequence that gives the chillers priority for tower use (in case of free
cooling failure) is implemented.
The other common approach is to share a single condenser water loop and towers
between free cooling and the chillers by running the loop at a low, free cooling
temperature and providing a bypass at the chillers, as shown in Figure 7.02.
Locating the tower bypass (a standard feature in cooler climates) at the chiller end
of the loop instead of at the cooling tower brings low temperature water into the
main plant area, in many cases greatly reducing the cost of piping to implement
free cooling. The bypass is used to mix warm condenser water leaving the chiller
with low temperature condenser water to produce a suitable condenser water
supply temperature the standard tower bypass control loop. In cooler climates,
a tower bypass is usually located directly next to the tower plant with an identical
control algorithm to allow starting up the chillers during cold temperatures with a
cold tower sump and chiller operation in very low temperatures. This approach is
popular in retrofit situations or where the pipe run to the cooling towers is too long
to economically allow a second set of pipes for free cooling. Some efficiency is lost
by producing lower temperature water for the chillers than is used, but typically
this is far outweighed by the reduced chiller compressor energy consumption.
Added costs for a water-side economizer result from controls, heat exchangers,
and piping. Some installations will also incur additional costs for additional plant
floor space or an additional pump. In a typical critical facilities installation, no
additional cooling tower capacity is required since the non-critical free cooling
system components do not require any redundancy.
%
%
60
40
80
0.0300
HumidityRatio(lbsH2Operlbsdryair)
=
=
RH
Figure 7.03:
RH
RH
0.0280
h=50Btu/lb
0.0200 h=40Btu/lb
0.0180
0.0160
RH=20%
0.0140
h=30Btu/lb
0.0120
0.0100
0.0080 h=20Btu/lb
0.0060
0.0040
0.0020
3200hoursminimumoffreecooling 50FWetbulbLine
0.0000
30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120
DryBulbTemperature(F)
Related Chapters
Air-side Economizer
References
1. Baseline study measurement of critical facility plants indicates that chiller
power represents approximately 70% of total energy consumption.
The redundancy level and environmental control of a data center determine the
potential energy efficiency of the data center infrastructure. Carefully consider
the acceptable availability and reliability levels for the data center as higher
reliability involves higher built-in redundancies at all system levels. The latter can
limit the maximum possible load factor, and therefore lower the efficiency, under
which some components operate. Data centers often over cool and over control
humidity, which results in no real operational benefits and increases energy use.
The first step in designing the cooling and air management systems in a data
center is to look at the recommended operating environments for equipment
set forth by the American Society of Heating, Refrigerating and Air-Conditioning
Engineers (ASHRAE) or Network Equipment Building System (NEBS). IT equipment
manufacturers often test for equipment functionality outside of these intake air
temperatures and moisture level ranges. For data center spaces where humidity
control is determined to be essential, widening the humidity setpoint range will
reduce fighting for control between adjacent CRAC units and make the control
less prone to humidity sensor drift. Low-energy humidification techniques can
replace electricity-consuming steam generators with an adiabatic approach that
uses the heat present in the air or recovered from the computer heat load for
humidification. Ultrasonic humidifiers, wetted media (swamp coolers) and micro
droplet spray are some examples of adiabatic humidifiers.
Modern servers do not require extremely tight humidity control and typical
data centers cannot actually provide tight humidity control due to sensor
drift.
Centralized humidity control can keep all units serving the same space in
the same humidification mode, eliminating simultaneous humidification
/ dehumidification common when using independent computer room air
conditioners (CRAC) controls.
Higher levels of air filtration incur a fan power penalty. MERV 11 filters
on outside air intakes (including air-side economizer intakes) should be
sufficient to keep particulates in the data center to an acceptable level. MERV
8 filters provide sufficient particulate filtration on recirculating units.
Approach
Availability/Reliability and Redundancy Options
Carefully consider the acceptable availability and reliability levels for the data
center. Uptime Institute has created a tier classification system as a benchmark
for reliable data center infrastructure design. They provide tier certification at
the design document and constructed facility stages. Systems built with very high
reliability involve built-in redundancy at all system levels. The level of built-in
redundancy influences efficiency by way of limiting the maximum load factor under
which some components will operate. For instance, designing an uninterruptible
power supply (UPS) system for 2N redundancy implies that each UPS likely
operates below 50% capacity; hence lowering its operating efficiency. Use only the
level of redundancy required to meet well justified availability requirements. Once
the acceptable redundancy level has been established, consider different electrical
distribution topology options. The best options minimize the power path and power
conversions while operating equipment at higher load factors.
Environmental Conditions
The first step in designing the cooling and air management systems in a data
center is to look at the standardized operating environments for equipment set
forth by the American Society of Heating, Refrigerating and Air-Conditioning
Engineers (ASHRAE) or Network Equipment Building System (NEBS). In 2008,
ASHRAE in collaboration with IT equipment manufacturers expanded their
recommended environmental envelope for inlet air entering IT equipment.
The revision of this envelope allows greater flexibility in facility operations,
and contributes to reducing the overall energy consumption. The expanded,
recommended and allowable envelopes for Class 1 and 2 data centers are shown
in Figure 8.01 and in Table 8.01 (for more details on data center type, different
levels of altitude, etc., refer to the referenced ASHRAE publication, Thermal
Guidelines for Data Processing Environments, 2nd Edition).
Table 8.01.
ASHRAE Recommended and Allowable Inlet Air Conditions for Class 1 and 2
Data Centers
(Source: ASHRAE Thermal Guidelines for Data Processing Environments, 2008)
High Temperature
80.6F DB 89.6F DB 95F DB
Limit
High Moisture Limit 60% RH & 59F DP 80% RH & 62.6F DP 80% RH & 69.8F DP
Another important factor to consider regarding the optimal server inlet air
temperature is that variable speed fans in the servers are usually controlled to the
internal server temperature. Operating the data center at server inlet air conditions
above the recommended range may cause these internal fans to operate at higher
speeds and consume more power. For example, a data sheet for a Dell PowerEdge
blade server indicates a 30% increase in server fan speed with an increase in inlet
Humidity Control
Humidity control is very energy intensive and should be minimized.
Dehumidification requires that the air be cooled to such low temperatures that
electric reheat is commonly used to maintain a supply temperature around 50-
55F. Removing moisture requires that a large amount of energy be removed,
about 1,000 Btu for every pint of moisture condensed. One thousand Btu is
equivalent to the energy required to heat all the air in a 100 square foot room from
32F to 100F. Beyond the large energy cost of moving that quantity of heat, using
energy to simultaneously heat and cool air is an inefficient but common part of the
dehumidification process. Standard humidification also adds to the data center
cooling load, adding in heat to essentially boil water and produce steam. Finally,
in a chilled water plant system, dehumidification can reduce the efficiency of the
entire plant by requiring a lower chilled water temperature.
Humidity requirements can and should be set to meet the actual equipment
specifications. Modern server equipment is designed to operate in a wide humidity
range, usually 20% to 80% relative humidity (RH). A somewhat tighter control band
is expected in order to allow for sensor error; however, specifying a tight humidity
band, such as +/-5% is very rarely justified and equally rarely achieved even when
specified. In a configuration where multiple computer room air conditioner (CRAC)
units are used with individual humidity control, it is common to find one CRAC
unit humidifying right next to another that is dehumidifying. This happens when
humidity ranges are tight as the humidity sensors inevitably drift over time. Precise
humidity control is not required by data center equipment, so poorly operating
humidity control systems, and their associated energy waste, are often unnoticed
or ignored. This and similar humidity control problems can be solved by:
Using the wider humidity and dewpoint temperature ranges, such as those
allowable by ASHRAE.
Barring high infiltration, most cooling systems will automatically control the
maximum humidity to about 60% to 70% RH due to the fundamental nature of
their operation. Supply air at 60F saturated with as much moisture as it can
possibly carry has a humidity of only 66% RH at 72F. Over-humidity problems are
more likely to indicate excessive infiltration (i.e., a broken outside air damper) or
malfunctioning humidifiers than a dehumidification control or capacity problem.
Concerns have been raised over high humidity levels causing the growth of
conductive anodic filament (CAF) on circuit boards and leading to potential
equipment failure. However, published research on CAF growth establishes that it
does not occur below 80% RH, under specific environmental conditions.
Humidity sensors are possibly the least stable sensor technologies in common
HVAC use. Without regular calibration, attempts to control to a tight humidity
band (1% - 2%) are not meaningful. The problem with expending large amounts
of energy to maintain a 50% RH +/-1% when the humidity sensor is off by at least
5% is clear. Even with a data center-appropriate control band such as 30-60% RH,
humidity sensors should be regularly calibrated. Humidity control consumes a
large amount of energy and requires costly equipment to achieve; if the first cost
was justified, then calibrating the humidity sensors should be considered as much
an operating cost as the electric bill in order to ensure the first-cost investment is
actually providing the desired space condition.
In situations where units have been added over time, there can also be a significant
amount of excess humidity control capacity, complicating control. Usually, the
initial cooling system is sized to meet the humidity load of the full envelope and
ventilation. The addition of equipment load through a gradual build out may result
in the need for additional CRAC units; however, no additional humidity load is
needed since data center equipment adds no humidity load. If the added units are
all installed with humidity control, perhaps intended to be identical to the original
equipment, then there can be a significant amount of surplus humidification
capacity. Too high a capacity can result in unstable humidity and inefficient
control if systems continually overshoot the setpoint. The control problem can be
greatly magnified when many independent CRAC control loops are involved. Many
humidifiers also tend to complicate control due to significant lag between the call
for humidification and the steam generator warming up.
In some cases, the humidification need may be so small that it is more economical
to eliminate humidification and simply lockout the economizer during very dry
outdoor air conditions. An economizer lockout should be based upon the outdoor
airs dewpoint temperature or humidity ratio, not the outside relative humidity. As
its name implies, relative humidity is relative to the temperature. Dewpoint and
humidity ratio are measurements of the water in the air that do not change when
the air is heated or cooled to the data centers operating temperature. A common
economizer lockout could be to override the economizer damper to minimum OSA
when the outdoor dewpoint is below 40F, a condition that would correspond to
summer peaks of 95F drybulb temperature and 15% humidity and winter lows
below 40F drybulb.
When a data center uses a properly controlled economizer, the latent load
(dehumidification or humidification) should be minimal. There are few sources in a
data center that add or eliminate humidity a high humidification load is likely due
to economizer control or unintended dehumidification from too low a chilled water
temperature (see Cooling Plant Optimization chapter). A dedicated outside air unit
should be used to dehumidify or humidify outside air before it is brought into the
building. Humidity produced in the space by operators can be easily controlled by
supplying outside air at a slightly lower humidity than the setpoint.
Air Quality
The air quality surrounding a site should be evaluated and strategies to deal with
concerns over particulates or gaseous pollutants should be determined. Mitigation
steps may involve filtration or other measures. Contamination concerns with salt
or corrosives and locations near pulp and paper mills or chemical plants should
be evaluated. Additional filtration increases the fan power required to either draw
outside air into or recirculate air within the data center space. A study by LBNL
found that particulate concentrations in data centers with air-side economizers
were a factor of 10 below maximum limits recommended by the International
Electrotechnical Commission (IEC). If MERV 11 outdoor air filters and MERV 8
recirculating air filters are used, particulate levels in data centers should be within
comfortably acceptable limits.1
Air-side Economizer
References
1. Data Center Contamination and Humidity Study, Lawrence Berkeley
National Laboratory, 2007 http://hightech.lbl.gov/documents/data_centers/
economizerdemoreport-3-13.pdf
Resources
Psychrometrics, Chapter 6, ASHRAE HVAC Fundamentals Handbook, 2005.
The combination of a nearly constant electrical load and the need for a high degree
of reliability make large data centers well suited for on-site electrical generation.
To reduce first costs, on-site generation equipment should replace the backup
generator system. It provides both an alternative to grid power and waste heat that
can be used to meet nearby heating needs or harvested to cool the data center
through absorption or adsorption chiller technologies. In some situations, the
surplus and redundant capacity of the on-site generation plant can be operated to
sell power back to the grid, offsetting the generation plant capital cost.
Principles
On-site generation can improve efficiency by allowing the capture and use of
waste heat.
Waste heat can be used to supply cooling required by the data center
through the use of absorption or adsorption chillers, reducing chilled water
plant energy costs by well over 50%.
Approach
Data centers typically require sufficient emergency generation capacity on-site to
support all the data center equipment and its infrastructure. Making this generator
capacity the primary source of power for the facilityusing efficient technologies
provides numerous benefits. The ideal primary power supply for a data center is an
on-site generation system with short and simple distribution paths, and double
redundancy at a minimum with waste heat recovered and used to power the
cooling system.
Using waste heat for cooling can increase site efficiency and improve reliability
for large data centers; in most situations, the use of waste heat is required to
make on-site generation financially attractive. While large data centers have
little need for space heating, waste heat from on-site co-generation can drive
thermally based cooling systems. This strategy reduces the overall electrical
Absorbers use low-grade waste heat to thermally compress the chiller vapor in
lieu of the mechanical compression used by conventional chillers. Rather than
refrigerant and a compressor, a desiccant that absorbs and releases water, in the
process absorbing and releasing heat, is used to remove heat from the chilled
water loop and reject it to the condenser loop. The electrically driven compressor
is replaced by a heat driven dessicant cycle. Single stage, lithium bromide
dessicant based chillers are capable of using the low grade waste heat that can
be recovered from common on-site power generation options including micro
turbines, fuel cells, and natural gas reciprocating engines. Although absorption
chillers have low coefficient of performance (COP) ratings compared to mechanical
chillers, utilizing free waste heat from a generating plant to drive them increases
the overall system efficiency. Absorbers are a very mature technology available
from several major manufacturers.
A potentially more efficient thermally driven technology that has begun making
inroads in the domestic market is the adsorber chiller. An adsorber is a desiccant-
based cooling system that uses waste heat to regenerate the desiccant and
cooling towers to dissipate the removed heat. An adsorption chiller minimizes its
auxiliary loads by eliminating the absorbent pump and decreasing the run times of
the vacuum and refrigerant pumps, thus further limiting the electricity requirements
while maintaining a similar thermal COP. The silica gel based system uses water
as the refrigerant and is able to use lower temperature waste heat than a lithium
bromide based absorption chiller. While adsorption chillers have been in production
for about 20 years, they have only recently been introduced on the American market.
The recommended system would typically be sized to cover the full site load (as
allowed by local utility and codes) and connected to the grid to ensure reliability
and to improve payback. The grid would serve as the backup to the on-site
generation plant. The key to successful connection with the utility is two very fast
circuit breakers or static switches on each generating bus to quickly disconnect
Any on-site generation system would need to be designed carefully to meet all
local codes and requirements, including air emission limits. Storage of backup fuel
for natural gas systems can also be a code and technical challenge, with propane
and dual-fuel capable generators often used to create an on-site emergency fuel
storage solution.
Frequently, on-site generation systems are sized to only supply a baseline quantity
of power, offering the benefits of waste heat reclamation at a reduced first cost.
However, depending on the specific generation equipment used, there can be a
significant delay between operation in a baseline mode with the utility grid always
used to top up to the actual required load, and operation in an island mode,
with standard backup generators or load shedding used in place of the grid. It is
the transfer time from operating in a grid connected mode to operating on the
generator plant alone that often necessitates the continued installation of UPS
systems.
Using waste heat from the data center can minimize losses by block heaters or be
used to extend ASHP operation and reduce the reliance on the electric immersion
heaters. Solar panels could be considered as an alternative source for generator
block heat. Another potential strategy is to work with generator manufacturers to
reduce block heater output when conditions allow.
References
1. Air Source Heat Pump for Preheating of Emergency Diesel Backup
Generators, Design & Engineering Services, Southern California Edison ET
08.02 Report, 2009.
Resources
Data Processing and Electronic Areas, Chapter 17, ASHRAE HVAC
Applications, 2003.
Figure 10.01:
Typical UPS units
(Source: Integral Group)
Principles
Select the most efficient UPS system that meets the data centers power
conditioning needs. Among double conversion systems (the most commonly
used data center system), UPS efficiency ranges from 86% to 95%. Simply
selecting a 5% higher efficiency model of UPS can save over $38,000 per
year in a 15,000 square foot data center, with no discernable impact on the
data centers operation beyond the energy savings. In addition, mechanical
cooling energy use and equipment cost can be reduced.
FactoryMeasurementsofUPSEfficiency
(testedusinglinearloads) Figure 10.02
100 Factory measurements
Efficiency(%)
80 Flywheel UPS
DoubleConversionUPS
75
DeltaConversionUPS
70
0 20 40 60 80 100
PercentofRatedActivePower Load
Figure 10.03:
An efficiency gain is
realized when operating
smaller UPS systems at
partial loads as opposed to
larger systems as partial
loads 1
Figure 10.04:
Measured Efficiencies of
UPS Systems 2
Notice the large efficiency range, from 86% to almost 95% at full load, and even
greater at partial loads where most systems are operated, among the double
conversion UPS systems tested. Double conversion UPS systems are the most
commonly used UPS in data centers.
For a data center, the UPS system should be configured to efficiently accommodate
operation at partial loads. For example, it is common for data centers to operate
at less than half of their full design load as the data center is populated. If the
UPS configuration shown on the left of the figure 10.03 is operating at 50% of
its design load (300 kW), each UPS is operating at a load factor of only 25% (150
kW). However, for the same total equipment load of 50% in the configuration on
the right, each UPS would need to operate at 33% (100 kW). An efficiency gain of
approximately 5% would be realized just from operating a UPS at 33% versus 25%
of full load. Both configurations maintain the same level of redundancy.
Table 10.01:
Battery UPS configuration Power Conditioning and Efficiency
(Source: Created by Integral Group)
Accurate IT equipment load estimates can prevent gross oversizing and the
resultant under loading of UPS systems. Data centers are often designed for two
to four times their actual measured operating equipment load. When designing a
data center, using actual measurements of the load of an equivalent operating data
center can help develop a rational design load, and a modular UPS system design
approach can easily allow for future growth and delay the first cost of additional
capacity until it is actually required. A modular UPS system can allow the total
operating capacity to be optimized to match the actual connected load.
The internal UPS system design, or topology, and how it conditions incoming
utility power has a large impact on the efficiency of the system. The most efficient
topology is a passive standby configuration, where the equipment loads are
connected directly to the utility power and only switched to the UPS systems
alternate power supply during a power failure. A topology that provides a degree
of continuous power conditioning between the utility and data center loads is a
line-interactive system. Finally, a double conversion configuration continuously
converts all incoming utility power to DC and then uses the inverter section of the
UPS system to convert it back to AC to supply conditioned power to the data center.
The Table 10.01 summarizes how these technologies generally compare in regards
to the relative degree of power conditioning they provide and their efficiency
potential.
As a general rule, the greater the power conditioning offered, the larger the
number of components involved, and the lower the efficiency. Data centers typically
require some degree of power conditioning this precludes the use of passive
standby UPS configurations for any critical data center equipment. However, most
mass-produced data center servers and equipment can operate through significant
power disruptions; most server power supplies have a specified input voltage range
of more than +/- 10% relative to the nominal voltage. Computing equipment power
supplies are often designed to operate in non-data center environments, and
therefore utilize internal AC to DC power supply converter designs that can accept
typical utility power disturbances. Data centers often specify double conversion
systems, the gold standard of power conditioning performance (and cost) by default
when line-interactive systems may be appropriate, more efficient, and reduce both
first costs and operating costs.
Beyond the traditional battery powered UPS, there are some technologies
currently being commercialized that eliminate the battery/inverter design
approach entirely, offering the opportunity for greater efficiency. One is the rotary
UPS, which utilizes a high speed, very low friction rotating flywheel coupled with a
backup diesel generator that can start up instantaneously to provide emergency
power. When power fails, the rotational energy of the flywheel is used to drive a
generator until the fast start generator can take over the load. Typically, flywheel
systems offer a shorter ride-through time than battery based systems, potentially
impacting the selection and redundancy of backup generators. Flywheel systems
offer the very high efficiency of line-interactive devices, in excess of 95%. The
reliability of these systems compared to inverter systems has not yet been fully
proven in the market, however the systems are commercially available and
rapidly gaining operating hours in a wide variety of critical facility applications.
This rapidly maturing technology should be considered when selecting an UPS
system.
EffectofHighEfficiencyModeonUPSEfficiency
(testedusingnonlinearloads) Figure 10.05:
100 Effect of High Efficient Mode 3
Efficiency(%
95
90
85
80
75 HighEfficiencyMode
70 DoubleConversionMode
65
60
0 20 40 60 80 100
PercentofRatedActivePower Load
In one test, transferring the power supply from the utility line to the batteries was
seen to cause only a very brief voltage sag (1/2-1 cycle). A UPS with an economy
mode (often referred to as a high efficiency or eco mode) is a good energy
efficiency option if the data center equipment can tolerate the switchover time of
the high efficiency mode, as most standard computer power supplies can. The
system should also be checked to verify its compatibility with the installed backup
generator system. Specifying double conversion UPS systems with economy
HighEfficiencyMode1cycle30%sag
OutputVoltage(volts)
switching from passive
standby mode to high 500
300
efficiency mode 3
200
250
100
0 0
100
250
200
30% sag&
500 3/4cycle
interruption 300
750 400
0 50 100 150
Time(ms)
Related Chapters
Information Technology (IT) Systems
On-Site Generation
References
1. Ecos Consulting, EPRI Solutions, LBNL, High Performance Buildings: Data
Centers, Uninterruptible Power Supplies (UPS), LBNL, 2005.
Resources
Data Processing and Electronic Areas, Chapter 17, ASHRAE HVAC Applications,
2003.
http://hightech.lbl.gov/ups.html
http://hightech.lbl.gov/server-ps-tool.html
http://www.energystar.gov/index.cfm?c=new_specs.uninterruptible_power_
supplies
Time of day usage patterns and unexpected events causing spikes in computing
demand are often addressed by over-provisioning IT resources and as a result,
over sizing cooling and electrical systems to meet peak computing demands.
Idle servers can use over 50% of full computational power, wasting both primary
electrical demand and cooling systems capacity. Dynamic resource allocation can
improve the efficiency of the data center hardware, operating system, applications
and storage systems by throttling resources up and down as demand dictates.
As the cooling and electrical power demands in the data center rise and fall, the
cooling system and electrical power chain components should be controlled to
respond to varying loads while maintaining energy efficiency.
Principles
Computing demand is often dynamic and yet idle servers can draw over 50%
of full power. Thus, huge savings can be realized by powering down idle
servers.
Variable speed motors on cooling system supply fans and chilled water
pumps allow the cooling system to deliver cooling to match the load and
maintain high energy efficiency.
Actively reset cooling system setpoints (e.g. supply air static pressure
or flow rate, water-side differential pressure, chilled water supply
temperature) to optimize cooling system efficiency in response to varying
loads in the data center.
Servers
Throttle-down drives are devices that reduce energy consumption on idle
processors. When a server is running below a set utilization percentage, a throttle-
down device will reduce the server electrical usage. This is also sometimes
referred to as power management. Many IT departments fear that throttling
down servers or putting idle servers to sleep will negatively impact server
reliability. However, server hardware is designed to handle tens of thousands
of on-off cycles. Server power draw can also be modulated by installing power
cycler software in servers. During low demand, the software can instruct
individual processors on the rack to power down. Potential power management
risks include slower performance and possibly system failure; which should be
weighed against the potential energy savings.
Network Equipment
As newer generations of network equipment pack more throughput per unit of
power, active energy management measures can be applied to reduce energy
usage as network demand varies. Such measures include idle state logic, gate
count optimization, memory access algorithms and input/output buffer reduction.
Storage
For Write Once, Read Occasionally applications, a massive array of idle disks
(MAID) system can be installed such that disk drives are spun up on demand,
rather than spinning continuously. This energy efficient measure is best applied
where significantly higher latency and significantly lower throughput are
acceptable tradeoffs for the reduced power demand.
Variable speed drives on CRAH and CRAC units allow for varying the airflow as
the cooling load fluctuates. For raised floor installations, the fan speed should
be controlled to maintain an under-floor pressure set point. However, cooling air
delivery via conventional raised floor tiles can be ill-suited for responding to the
resulting dynamic heat load without either over-cooling the space or starving some
areas of sufficient cooling 1. Variable air volume, air delivery systems are a much
better solution for consistently providing cooling when and where it is needed.
Supply air and supply chilled water temperatures should be set as high as possible
while maintaining the necessary cooling capacity.
On the chilled water plant side, variable flow pumping and chillers equipped with
variable speed driven compressors should be installed to provide energy-efficient
operation during low load conditions. Another option to consider for increasing
chiller plant efficiency is to actively reset the chilled water supply temperature
higher during low load conditions. In data centers located in relatively dry climates
and which experience relatively low partial loads, implementing a water-side
economizer can provide tremendous savings over the course of the year (see
earlier discussion on Water-side economizers).
Operational Parameters
References
1. Best Practices Guide for Energy-Efficient Data Center Design, United
States Department of Energy, Energy Efficiency & Renewable Energy
Information Center, 2010. http://www1.eere.energy.gov/femp/pdfs/
eedatacenterbestpractices.pdf
Resources
Design Recommendations for High Performance Data Centers. Rocky
Mountain Institute, 2003.
The original content was developed by Integral Group, in part, based upon work
by Lawrence Berkeley National Laboratory supported by the California Energy
Commission. The following authors participated in the development of the guide:
Integral Group:
Jeff Thomas, John Bruschi, Robin Anliker, Neil Bulger, and
Arunabha Sau, John McDonald, John Weale, Peter Rumsey
PG&E refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2012 Pacific Gas and Electric Company. All rights reserved.
These offerings are funded by California utility customers and administered by PG&E under the auspices of the California Public Utilities Commission.
October 2012 CTM-1012-1737